Time Schedule - RAYYAN VILLA

The document outlines the project activity plan for civil and MEP work for the Alrayan Majles farm project. It details various electrical, plumbing, HVAC, and other installation activities along with their scheduled start and finish dates. Key activities include marking and shipping of walls from June 10-26, 2021, installation of electrical first fixes from May 20-July 30, 2021, installation of GI ducts from June 20-September 15, 2021, plumbing installations from June 15-July 20, 2021, and testing/commissioning from October 15-November 15, 2021.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views2 pages

Time Schedule - RAYYAN VILLA

The document outlines the project activity plan for civil and MEP work for the Alrayan Majles farm project. It details various electrical, plumbing, HVAC, and other installation activities along with their scheduled start and finish dates. Key activities include marking and shipping of walls from June 10-26, 2021, installation of electrical first fixes from May 20-July 30, 2021, installation of GI ducts from June 20-September 15, 2021, plumbing installations from June 15-July 20, 2021, and testing/commissioning from October 15-November 15, 2021.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT NAME: Alrayan Majles farm

CLIENT Representive Dr. Ali Bin Smikh Almarri


CONSULTANT: Heratige
Date 12/6/2021
REV 0
PROJECT ACTIVITY PLAN for Civil and MEP work

Start Finish
Activity Names s
Date Date

marking for walls dry area Done


shipping for walls Dry area 10 10/6/2021 20/6/2021
marking for walls wet area 2 14/6/2021 16/6/2021
shipping for walls wet area 10 16/6/2021 26/6/2021
installation of electrical First Fix walls Ground floor 12 20/6/2021 2/7/2021
installation of electrical First Fix walls First floor 10 12/6/2021 22/6/2021
installation of electrical First Fix walls Pent floor 7 20/5/2021 27/5/2021
installation of electrical First Fix ceiling Ground floor 15 1/7/2021 15/7/2021
installation of electrical First Fix ceiling First floor 15 25/6/2021 10/7/2021
installation of electrical First Fix ceiling Pent floor 10 5/7/2021 15/7/2021
installation of electrical First Fix Floors Ground floor 5 20/7/2021 25/7/2021
installation of electrical First Fix Floors First floor 5 25/7/2021 30/7/2021
installation of electrical First Fix Floors Pent floor 5 25/7/2021 30/7/2021
installation of electrical second Fix walls Ground floor 5 20/7/2021 25/7/2021
installation of electrical second Fix walls First floor 5 25/7/2021 30/7/2021
installation of electrical second Fix walls Pent floor 5 25/7/2021 30/7/2021
installation of electrical second Fix ceiling Ground floor 15 5/7/2021 20/7/2021
installation of electrical second Fix ceiling First floor 15 10/7/2021 25/7/2021
installation of electrical second Fix ceiling Pent floor 10 20/7/2021 30/7/2021
installation of electrical second Fix Floors Ground floor 5 20/7/2021 25/7/2021
installation of electrical second Fix Floors First floor 5 25/7/2021 30/7/2021
installation of electrical second Fix Floors Pent floor 5 25/7/2021 30/7/2021
installation of Gi duct support 7 15/6/2021 22/6/2021
installation of GI duct ground floor 40 20/6/2021 30/7/2021
installation of GI duct First floor 30 1/7/2021 30/7/2021
installation of GI duct Pent house floor 20 1/7/2021 20/7/2021
installation of GI duct at risers 30 20/6/2021 20/7/2021
installation of GI duct External Lower Roof 45 1/8/2021 15/9/2021
installation of GI duct External Upper Roof 60 1/8/2021 30/9/2021
installation of PVC draiange pipes at ground floor 15 15/6/2021 30/6/2021
installation of PVC draiange pipes at First floor 15 30/6/2021 15/7/2021
installation of PVC draiange pipes at Pent house floor 10 10/7/2021 20/7/2021
instalaltion of Flush tank 10 from date of delivery
installation of embeded part for sanitry fixture 25 from date of delivery
Installation of water pipes for walls at ground floor 7 20/6/2021 27/6/2021
Installation of water pipes for walls at First floor 15 25/6/2021 10/7/2021
Installation of water pipes for walls at Pent house floor 5 1/7/2021 5/7/2021
Installation of water pipes for Ceiling at ground floor 15 1/7/2021 15/7/2021
Installation of water pipes for Ceiling at First floor 20 5/7/2021 25/7/2021
Installation of water pipes for Ceiling at Pent house floor 10 15/7/2021 25/7/2021
Installation of water pipes for Riseres 25 1/7/2021 25/7/2021
installation of AC package unite 15 15/7/2021 30/7/2021
installation of exhuast fan 5 15/7/2021 20/7/2021
PROJECT NAME: Alrayan Majles farm
CLIENT Representive Dr. Ali Bin Smikh Almarri
CONSULTANT: Heratige
Date 12/6/2021
REV 0
PROJECT ACTIVITY PLAN for Civil and MEP work

Start Finish
Activity Names s
Date Date

installation of silenceres 45 15/7/2021 30/8/2021


installation of water heater
installation of water pump
installation of water filter 10 20/7/2021 30/7/2021
installation of water cooler
installation of water water tank
instalaltion of roof cable trays 30 30/7/2021 30/8/2021
instalaltion of roof cables 20 10/8/2021 30/8/2021
instalaltion of roof Isolators with support 10 15/8/2021 25/8/2021
termination of isolators with mechanical equipments 5 25/8/2021 30/8/2021
installation od DB SMDB 15 15/8/2021 30/8/2021
instalaltion of ELV equipments with termination 25 1/9/2021 25/9/2021
Land scape work 30 1/9/2021 1/10/2021
conenction with municipilty ( water , drainage ,electrical , orreddo) 15 1/10/2021 15/10/2021
testing and commisioning 30 15/10/2021 15/11/2021