Cdot I 25 Value Engineering Study Draft Report 1
Cdot I 25 Value Engineering Study Draft Report 1
State of Colorado
Department of Transportation
DESIGN TEAM
January 25, 2013
Please find enclosed four (4) hard copies and two (2) CDs of our Value Engineering Report for the
proposed I-25 Managed Lanes Project. Using the Value Engineering “Job Plan” – Information, Function
Analysis, Creative, Evaluation & Development, the VE Team identified alternatives and design
suggestions that offer potential opportunities for reducing construction cost, expediting project delivery
and improving the flow of work during construction. All this was done without reducing the
functionality of the finished project or encroaching on key understandings with the stakeholders and
funding agencies.
We trust that you will find this report to be in proper order. It should be noted that the results of this
workshop are volatile in that they can be overcome by the events that accompany the expeditious
continuance of the design process. Accordingly, we encourage an equally expeditious implementation
meeting to determine the disposition of the contents of this report.
Please contact me at (919) 576-4017 should you have any questions regarding this submittal.
On behalf of our VE Team, we thank you very much for the opportunity to work with you and the hard
working staff members of the Colorado Department of Transportation and your design consultants.
Yours truly,
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY................................................................................................................................... 3
3.3 NOTES FROM THE KICK-OFF SESSION PRESENTATIONS BY CDOT AND PROJECT DESIGN TEAM ...............66
Page 2
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
1 EXECUTIVE SUMMARY
1.1 INTRODUCTION
This report is intended to recount the events and findings of the Value Engineering workshop that took
place at the North Holly office of the Colorado Department of Transportation (CDOT) in Denver, during
the period 14 – 17 January 2013. The subject of the VE workshop was the I-25 Managed Lanes Project
on the north side of Denver. The project is being designed by the team of Parsons Brinckerhoff, Atkins,
and APEX Design PC, out of the Denver offices of those three firms. At the time of the workshop, the
plans had just recently been through their Field Inspection Review (FIR) on 10 December 2012. The
plans and supporting documentation used by the VE Team for this study were in a state of transition,
since the design team was in the process of incorporating the comments from the FIR.
The North I-25 Managed lanes extension project involves the creation of managed lanes along I-25 from
US 36 to 120th Avenue by repurposing the existing inside shoulders of the roadway, both north and
southbound. CDOT will be responsible for the design and construction of the new facility as well as
maintenance of the facility and ITS infrastructure while the High-Performance Transportation Enterprise
(HPTE) will be responsible for the management and operation of the managed lanes including the tolling
system. It is planned that the E-470 Public Highway Authority will provide back office support to process
and issue tolls, as well as collect payment.
The project would provide meaningful relief for the most congested corridor in the Denver Metropolitan
area, currently traveled by 175,000 vehicles and 4,300 bus transit riders every day. Implementation of
the managed lanes will result in a more efficient use of available roadway capacity to improve traffic
flow and reduce travel times in the corridor. In addition, the managed lanes will support Bus Rapid
Transit (BRT) along the corridor and provide more consistent transit travel times for the many express
transit routes that currently serve the corridor.
Under the new managed lanes configuration all eligible user (HOVs, registered hybrid vehicles,
motorcycles, buses and toll-paying POVs) will be able to access the managed lanes at designated
ingress/egress points.
Page 3
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The proposed North I-25 managed lane system will offer more choices to commuters and make the best
use of available freeway capacity. The project has several key goals that include:
Utilize managed lanes to improve flow in the general purpose lanes and thereby improve travel
along the corridor for roadway users;
Provide a means for public transit to achieve better on-time performance by removing them
from the congestion in the general purpose lanes; and,
Encourage carpooling and alternative modes of travel by offering free use of the managed lanes
for public transit and HOV users;
Encourage the further economic growth in the corridor by providing a more efficient
transportation system.
All the usual concerns go along with this project. These concerns include:
Meeting the objectives and requirements of the very important federal Tiger Grant. These are
stringent and have a performance time frame which calls for the obligation of the funds by June
of 2013.
There are numerous stakeholders and fund sources involved in the execution of this project.
The various agreements and the EIS/ROD requirements weave together a strict route that must
be followed to deliver this project.
Among the stakeholders are the owners of the irrigation ditches that cross under the existing
right-of-way. Every effort has been made to make certain that the proposed project does not
impact these ditches.
There is also an important goal that calls for building all improvements within the existing
footprint of I-25. Negotiations are currently underway to obtain the temporary construction
easements necessary to construct the improvements.
Repairs to the existing noise walls and the inclusion of Noise Wall No. 2 in the project has been a
carefully tracked part of the negotiations with the local interest groups.
Page 4
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
1.4 FINDINGS
During the course of the VE workshop the team developed 14 Alternatives and 16 Design
Suggestions. Following this page is the table entitled, "VALUE ENGINEERING STUDY – SUMMARY OF
RESULTS". The cost results may not be added together as some of the alternatives are mutually
exclusive. One of the goals of the VE Team was to identify ways in which cost savings might be realized
while, on the other hand, indicating ways in which the resulting savings might be invested back into the
project to realize added value. A rough impression to be had from reviewing the Summary of Results is
that between $5 and $7 million in cost savings might be reasonable to expect from the implementation
of these alternatives. The team has also illustrated how nearly $800,000 could be put back into the
project, in the form of added acceleration, deceleration and auxiliary lanes; in order to improve the
operational performance of the proposed improvements.
The reader is encouraged to read over the summary table then look at the tabbed section of this report
entitled, "STUDY RESULTS", for a detailed accounting as to how these alternatives were documented.
The Design Suggestions can also be as important as the fully developed Alternatives.
Page 5
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Net Cost
Life Cycle
Cost Original Cost Initial Cost Reduction
Cost
Design Alternative Reduction Including
Impact
LCC
ITS/TOLLING (IT)
Don't use lane control for the general
IT-1 $4,039,200 $571,200 $3,468,000 $3,119,769 $6,587,769
purpose lanes
Eliminate lane control for Northbound
IT-2 $9,506,400 $3,481,600 $6,024,800 $5,419,833 $11,444,633
Traffic
IT-3 Minimize signs and devices $8,527,200 $571,200 $7,956,000 $7,956,000
IT-4 Do not add extra fiber optic cable $301,376 $0 $301,376 $301,376
Use standard VMS in lieu of full color
IT-5 $2,448,000 $2,284,800 $163,200 $163,200
matrix signs
IT-6 Eliminate proposed CCTV cameras $13,600 $0 $13,600 $13,600
IT-7 Combine detection devices DESIGN SUGGESTION
Provide for coordination of traffic
IT-8 DESIGN SUGGESTION
management assets
IT-9 Maximize use of existing sign structures DESIGN SUGGESTION
Set objective to integrate this project
IT-11 DESIGN SUGGESTION
into area wide master plan for ATM
IT-14 Define enforcement concept DESIGN SUGGESTION
Implement incident management
IT-15 DESIGN SUGGESTION
concept
IT-16 Implement ramp metering for corridor DESIGN SUGGESTION
PAVEMENT (PV)
Provide auxiliary lane between
PV-4 $0 $512,088 ($512,088) ($512,088)
Thornton Parkway and 104th Avenue
On southbound I-25, provide parallel
PV-8 $32,849 $93,871 ($61,022) ($61,022)
acceleration lane from 104th Avenue
Provide 1000 foot parallel deceleration
PV-9 lane for the approach to Thornton $9,448 $171,516 ($162,068) ($162,068)
Parkway
Provide 500 foot parallel deceleration
PV-
lane for the approach to Thornton $9,448 $102,086 ($92,638) ($92,638)
9A
Parkway
PV- Re-stripe Thornton Parkway
DESIGN SUGGESTION
10 southbound ramp
Page 6
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Net Cost
Life Cycle
Cost Original Cost Initial Cost Reduction
Cost
Design Alternative Reduction Including
Impact
LCC
TRAFFIC CONTROL DURING CONSTRUCTION (TC)
MISCELLANEOUS (MI)
MI-1 Optimize conduit sizes DESIGN SUGGESTION
MI-2 Use shorter light standards $1,629,484 $1,150,560 $478,924 $478,924
MI-3 Reduce lighting coverage $2,479,416 $436,377 $2,043,039 $2,043,039
MI-4 Integrate lighting into barrier walls DESIGN SUGGESTION
Consider use of LED fixtures for
MI-6 DESIGN SUGGESTION
roadway lighting
Revisit possibility of new bridge at 88th
MI-7 DESIGN SUGGESTION
Avenue
MI-8 Replace in lieu of re-set the existing
DESIGN SUGGESTION
&9 guardrail
MI- Enhance definition of project
DESIGN SUGGESTION
10 requirements
Page 7
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
2 STUDY RESULTS
2.1 INTRODUCTION
The measurement of the success of Value Engineering study can be done in several important ways,
mostly depending on the nature of the project under review. In the current instance it should be
expected that the VE study would provide the I-25 Managed Lanes project delivery team from CDOT and
their design firms with a selection of alternatives. These alternatives offer opportunities for initial and
life cycle cost reductions, opportunities to reduce the project delivery time and a chance to enhance the
effectiveness of the design before it goes to construction. The VE team used these objectives as they
selected creative ideas to carry forward for development. The workshop resulted in full development of
alternatives that offer opportunities for significant first cost savings. These alternatives were selected as
being reasonable considerations for incorporation in the design. There were also Design Suggestions
that offer measures to simplify construction, provide various means for reducing costs (in these cases
these savings are hard to quantify), may help to improve the operational requirements for the finished
facilities, and reduce the construction duration.
The Value Engineering team members utilized the unit costs and quantities from the construction cost
estimates provided by the Design Team, wherever possible. This was done to make sure that
comparisons between original and alternative costs were handled consistently and fairly. When the VE
team deviated from this practice by providing their own unit costs, mostly for alternative materials, it
has been clearly noted in the cost calculations that accompany the developed alternatives. Likewise, if
there was a problem with either unit costs or quantities in the supplied estimates, these deviations were
clearly annotated in the VE Team's documentation.
The cost estimates provided by the VE Team in their documentation are intended to serve as general
indicators of the cost results should the alternatives be accepted as they are written. Some of the
alternatives are mutually exclusive so it is expected that the identified cost impacts cannot be added and
taken as the final, total cost conclusion for the VE workshop.
With regard to Life Cycle Cost analyses (LCC), the conclusions reached are based on a 4.2% annual
discount rate and zero percent inflation. This zero percent inflation is due to the use of "Constant
Dollar" analytical practice recommended for use on federally funded projects. Life cycle cost analysis
has impressive formulas that give the outward appearance of being very precise. However, many things
affect the outcome of LCC decisions, not the least of which is the uncertainty of dealing with bank rates
that may well be significantly different from that which was assumed, in a very short period of
time. Accordingly, LCC decisions should only be supported when they signal a very clear benefit that will
be experienced regardless of the ebb and flow of financial times.
Page 8
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The design calls for 99 lane control signs including locations on the managed and general purpose lanes.
Alternative:
The lane controls will be placed on the managed lanes only. This would reduce the number of signs down to
14 for the managed lanes.
Opportunities: Risks:
Technical Discussion:
This approach would provide the needed information for the drivers to navigate through the managed
lanes and fulfill the requirements of the project. The cost savings would be the result of reducing the
number of signs, sign structures, and utility services. This amounts to approximately $30,000 per sign. The
savings from this alternative could be used to add more pavement in the form of Acceleration and
Deceleration, and Auxiliary lanes to further support the efforts to reduce traffic incidents and enhance
traffic operations.
The ATM deployment might be better served by deploying it south of US 36 from downtown to the
northern terminus of this project.
Page 9
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 3
NO. OF NO. OF
ITEM UNITS COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS UNITS
$ $
Lane Control Signage EA 99 $ 30,000.00 $2,970,000 14 30,000.00 420,000
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Sub-
total $2,970,000 $ 420,000
Page 10
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ALTERNATIVE
PROJECT: Reduction in Number of Lane Control Signs NO. IT-1
Based on Eliminating Lane Control for GP Lanes
SHEET NO. 3 of 3
LIFE CYCLE
20 years 99 Signs 14 Signs
PERIOD:
INTEREST ESCALATION
4.20% 0.00% ORIGINAL ROPOSED
RATE: RATE:
A. INITIAL COST (Note - escalation shown as 0.0% since using 4,039,200 571,200
constant dollar LCC
Useful Life (Years) 10 10
analysis)
INITIAL COST SAVINGS 3,468,000
2. Maintenance
3. Energy
Page 11
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The design calls for a high density of devices along the northbound and southbound travel routes in order to
develop the ATM system. The overhead supports for the devices are located at one half mile intervals.
Alternative:
The current design would be modified by eliminating that portion of the ATM system not necessarily required
for the current operational plan. This is more adequately described as follows:
Eliminate the northbound overhead supports and devices except for those at stations 65+00 and 117+00.
Eliminate all side-mounted signs (VMS)
Reduce southbound locations to approximately one-mile intervals, to meet obvious needs such as exit
locations.
Opportunities: Risks:
Technical Discussion:
ATM is probably not needed as the northbound traffic is significantly lighter than the southbound traffic.
Side mounted signs can be installed once the need and purpose have been identified through day-to-day
use. Having the structures on one-half mile intervals, along with the proposed signage, may be more than is
required for the moment and will likely distract drivers from their attention to driving.
Page 12
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 3
NO.
NO. OF
ITEM UNITS COST/ UNIT TOTAL OF COST/ UNIT TOTAL
UNITS
UNITS
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Unit costs are primarily VE Team
Approximations $ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Page 13
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
2. Maintenance
3. Energy Not identified
Total Annual 475,320 174,080
Costs
Present Worth 13.3528 13.3528
Factor
Present Worth 6,346,845 2,324,453
of RECURRENT
COSTS
Present
C. SINGLE EXPENDITURES Year Amount PW factor Present Worth
Worth
ORIG PROP < Put "x" in appropriate box (original design or proposed design)
Page 14
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The design calls for 91 ITS signs for the six-mile corridor. This may represent a very high information
density from a driver’s perspective.
Alternative:
The intent of the project is to construct managed lanes that help to move the traffic through the corridor.
Consideration might be made to reducing the management and driver information density by affecting the
following changes:
Use eight existing cameras but do not install the four new cameras
Use the existing variable message signs but eliminate the VMSs and supplemental VMSs for ATM
Use the minimum signs and devices necessary to meet the project intent
Opportunities: Risks:
Technical Discussion:
This approach would provide the needed information for the drivers to navigate through the managed
lanes and fulfill the requirements of the project. The cost savings would be the result of reducing the
number of signs, sign structures, and utility services. Savings from this alternative could be used to add
more pavement in the form of acceleration and deceleration, and auxiliary lanes to further support the
efforts to reduce traffic incidents and enhance traffic operations. There would be additional life cycle
cost savings that have not been calculated.
Page 15
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 2
NO. OF NO. OF
ITEM UNITS COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS UNITS
$ - $ -
$ - $ - $ -
$ - $ -
$ - $ -
$ - $ -
Page 16
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Install new fiber optics line. 34,320 LF Northbound and 10,000 LF Southbound.
Alternative:
Do not place extra fiber line. Utilize what is already in place.
Opportunities: Risks:
Initial cost savings In the future, may not have enough lines
May expedite construction available
Technical Discussion:
There is an opportunity to utilize the remaining capacity with of the existing fiber optic facilities. The
adequacy of this capacity must be confirmed. If needed, can always add fiber optic cabling to meet needs
of that time.
ALTERNATIVE $ 0 $ $ 0
Page 17
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 2
NO. OF NO. OF
ITEM UNITS COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS UNITS
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ -
Sub-
total $221,600 $ 0
TOTAL $301,376 $ 0
Estimated Savings: $301,376
Page 18
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The current design calls for the use of 12 each full matrix, full color, 20 mm pitch, overhead variable
message signs. There are to be six in the northbound and six in the southbound traffic lanes.
Alternative:
Standard variable message signs would be used in place of the full color matrix signs.
Opportunities: Risks:
Initial cost savings by reducing IT cost for There would be no color options
driver/sign integration
Will reduce driver distractions Some redesign required
Technical Discussion:
The same messages can be communicated by the standard message signs as with the full color matrix
signs.
Page 19
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 2
NO. OF NO. OF
ITEM UNITS COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS UNITS
$
VMS Full Color (Overhead) EA 12 $ 150,000.00 1,800,000 $ - $ -
$ $
VMS LED (Overhead) EA $ - $ - 12 140,000.00 1,680,000
$ - $ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$
Sub-total $,800,000 1,680,000
$ $
Mark-up at 36.00% 648,000 604,800
$ $
TOTAL 2,448,000 2,284,800
Estimated Savings: $163,200
Page 20
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The design calls for CCTV cameras to monitor VMSs. There are two of them located at Stations 149+00
and 254+00.
Alternative:
The design would be modified to rely on the internal diagnostic devices to monitor the proposed
equipment.
Opportunities: Risks:
Technical Discussion:
The internal diagnostic devices that come with the proposed system equipment should be adequate to
monitor the system. Each of the cameras cost $5,000. The resulting cost savings would be $10,000 plus
$3,600 in project mark-ups.
There would some additional cost savings related to wiring and power provision. This is not included in
the numbers below as this is a fairly minimal cost.
ALTERNATIVE $ 0 $ $ 0
Page 21
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Throughout the project there are devices (RTMS, Doppler and others) deployed to measure
speed/occupancy, etc., for different CDOT user groups (DTS, ITS/TOLLS). These devices collect similar or
the same information.
Alternative:
There may be an opportunity to streamline and combine these devices. Perhaps the various groups could
get together and determine their various data needs and see how they overlap and find opportunities for
consolidation of devices to reduce the cost of construction and simplify data acquisition.
Opportunities: Risks:
Cost savings for initial capital outlay It will take time to provide for the
Reduce future maintenance and replacement communications between the various
costs stakeholders
Technical Discussion:
There is a potential for construction cost savings and simplification of the systems that must be serviced
over the years to come.
Page 22
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Similar to IT-7, there are redundant devices for traffic data collection.
Alternative:
Opportunities should be sought for consolidation of devices and the sharing of their data flow.
Opportunities: Risks:
Cost savings for initial and maintenance Time will be required to orchestrate this
capital outlay effort
Operations enhancements
Some redesign may be required
Technical Discussion:
There is a need for a standard data collection protocol to aid in the collection and dissemination of
data.
Page 23
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The ATM/Tolling project has almost 40 new structures for devices and signage.
Alternative:
Consideration might be given to seeking opportunities to reuse some of the existing structures for
mounting these devices and signs.
Opportunities: Risks:
Technical Discussion:
If this is possible, there could be significant benefits in terms of initial cost savings and in the
expedition of construction.
This design suggestion is a part of several design suggestions and alternatives that encourage
simplification of the data fed to drivers passing through this corridor. Spacing structures out along
the way would give the drivers time to digest the information provided to them from the last sign
array.
Page 24
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
ATM is employed for this six-mile project. It is being used to reduce congestion and improve
safety.
Alternative:
As this project is being deployed, it would be a good time to evaluate how the project is to be
deployed and to be sure that it is a part of the area wide master plan.
Opportunities: Risks:
Technical Discussion:
Much of the ATM deployment is geared toward queue detection and management. Based on
the quick analysis, the cost for this system is about $8 million. One of the questions about
deployment and implementation of this queue detection is what mechanism will be used to
manage queues. Will this be based on CDOT research of spaced harmonization or other
technical approach? Based on past studies/projects, the ATM could have significant impact on
this corridor if deployed from downtown to the northern limits of this project.
Page 25
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Technical Discussion:
The design calls for a buffered, separated configuration for managed lanes throughout the
corridor. This type of configuration raises enforcement questions. Is there an enforcement
plan and has it been worked out so that appropriate enforcement assets will be available when
needed?
Page 26
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Technical Discussion:
A “quick clearance program” should be developed as part of the existing incident management plan.
Establishing best practices for first responders and CDOT to deal with incidents will add significant
value to the current Incident Management Plan of detour/diversion. The quick clearance of
incidents should help minimize the impact on traffic.
Page 27
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Alternative:
Consideration might be given to deploying ramp metering for all ramps in the project.
Opportunities: Risks:
Technical Discussion:
Some locations may not have the necessary volume to warrant metering. However, from a corridor
perspective, it will allow for better coordination if the entire project has ramp metering on all ramps.
An important consideration for this suggestion is whether or not the existing operations system is
capable of accommodating the use of metering at the ramp locations not already metered.
Page 28
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Alternative:
The alternative would provide a full auxiliary lane between Thornton Parkway and 104th Avenue.
Opportunities: Risks:
Technical Discussion:
The existing on-ramp from Thornton Parkway merges onto Northbound I-25 then, as one approaches the
104th off-ramp, an exit ramp with two lanes is present for two vehicles to exit. The alternative would then
call for extending an auxiliary lane as noted.
ORIGINAL DESIGN $ 0 $ $ 0
Page 29
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
CALCULATIONS
DESCRIPTION: PROVIDE FULL AUXILIARY LANE BETWEEN THORNTON PKWY & SHEET NO.: 2 of 3
104TH AVE
Page 30
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 3 of 3
Sub-
total $ - $ 376,535
Mark-up at 36.00% $ - $ 135,553
TOTAL $ - $ 512,088
Estimated Savings: ($512,088)
Page 31
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Uniform 35:1 taper merge for two lanes coming onto mainline SB I-25 from 104 Ave. Length of taper =
855ft for two lanes.
Alternative:
Provide a 50:1 (620ft) taper to merge two on-ramp lanes onto one, then provide a 600ft parallel acceleration
lane, terminating with a 300ft lane termination taper.
Opportunities: Risks:
Technical Discussion:
The taper and parallel accelerations lengths are regularly used in the metro area and are consistent with
AASHTO guidance.
Page 32
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ILLUSTRATION
Page 33
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
CALCULATIONS
Page 34
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
CALCULATIONS
Page 35
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 5 of 5
Page 36
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The Thornton Parkway southbound off ramp starts at Station 215+50 with no deceleration lane. The
ramp is where deceleration is expected to occur. (See attached illustration)
Alternative:
The alternative would provide a 1000’ deceleration lane prior to the off-ramp entrance. (See attached
illustration)
Opportunities: Risks:
Technical Discussion:
There would be some significant advantages realized from adding this highly beneficial deceleration lane.
First, the vehicles exiting the mainline to take the Thornton Road off-ramp will be able to more safely
execute the maneuver. Since they will be able to move out of the mainline flow of traffic in order to
decelerate, this added lane should assist in maintaining the flow of traffic on the mainline.
Page 37
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ILLUSTRATION
Page 38
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
CALCULATIONS
Page 39
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 4 of 4
NO.
NO. OF
ITEM UNITS COST/ UNIT TOTAL OF COST/ UNIT TOTAL
UNITS
UNITS
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Sub-
total $ 6,947 $ 126,115
Page 40
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The Thornton Parkway southbound off ramp starts at Station 215+50 with no deceleration lane. The
ramp is where deceleration is expected to occur. (See attached illustration)
Alternative:
The alternative would provide a 500’ (preferred design length) deceleration lane prior to the off-ramp
entrance. (See attached illustration)
Opportunities: Risks:
Improved safety Moderate redesign will be required
Reduces the impedance of mainline traffic Additional construction cost
Technical Discussion:
There would be some significant advantages realized from adding this highly beneficial deceleration
lane. First, the vehicles exiting the mainline to take the Thornton Road off-ramp will be able to more
safely execute the maneuver. Since they will be able to move out of the mainline flow of traffic in order
to decelerate, this added lane should assist in maintaining the flow of traffic on the mainline.
Page 41
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ILLUSTRATION
Page 42
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
CALCULATIONS
Page 43
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 4 of 4
NO.
NO. OF
ITEM UNITS OF COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS
UNITS
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Sub-
total $ 6,947 $ 75,063
Page 44
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Alternative:
Opportunities: Risks:
Technical Discussion:
This re-striping can be done without adding any pavement. So, the result is a more effective
acceleration lane at very little extra cost, if any.
Page 45
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Phasing has median work being completed first, with milling and paving being completed in Phases
3a and 3b.
Alternative:
Re-sequence phasing so milling and paving are the final items to be completed along with tie-ins.
Opportunities: Risks:
Technical Discussion:
Phasing seems out of sequence. Milling and final paving should be the last item to be performed.
Try to reduce number of shifts. Avoid scarring on new pavement.
Page 46
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ILLUSTRATION
Phase 1a – Install drainage across I-25 (night work, lane closures as per Region 6 lane closure strategy)
Phase 3a – Complete all construction outside of the existing pavement. (original Phase 4a)
Phase 3b – Complete all remaining construction to complete the HOV/HOT lane connections. (original 4b)
Page 47
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The estimate quantity of concrete barrier (temp) to be used on the project is 46,000 LF.
Alternative:
Reduce the amount of barrier needed by constructing the shoulder in segments. Also construct the
median drainage improvements, sign structures and guardrail type 7 in segments.
Opportunities: Risks:
Impact to traffic Extra moves to reset barrier
Technical Discussion:
Build in segments to lessen the impact on traffic. Build approximately 1 ½ miles at a time. Reduce
concrete barrier to 16,000 LF.
Page 48
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 2
NO. OF NO. OF
ITEM UNITS COST/ UNIT TOTAL COST/ UNIT TOTAL
UNITS UNITS
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
Sub-
total $ 1,242,000 $ 352,000
Page 49
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
It is estimated that that there will be 450 TCI days associated with the duration of the project.
Alternative:
Reduce the TCI days to reflect the days needed for the project duration of 268 days (working days).
Opportunities: Risks:
Quantity adjustment will better fit expected and Need to make sure that there are
necessary TCI days enough TCI days to service the length
of the project
Technical Discussion:
This alternative calls for reducing the quantity of TCI days actually needed based on 268 working
days. The current quantity is too high, based on project duration. The quantity will reflect the TCI
days needed for weekends, holidays and potential non-chargeable weather days.
Page 50
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
SHEET NO.: 2 of 2
Sub-
total $ 53,100 $ 20,060
Mark-up at 36.00% $ 19,116 $ 7,222
TOTAL $ 72,216 $ 27,282
Estimated Savings: $44,934
Page 51
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The design identifies the cost of the mobile attenuators by cost unit “each”.
Alternative:
The pay item for the mobile attenuators should “days” (pay for each of the attenuators by day when
they are being used on the job site).
Opportunities: Risks:
More flexibility as to how the attenuators can be Cost tracking by engineer is more
used and their costs tracked complicated
More accurate cost estimate
Technical Discussion:
Even if this was not a CDOT standard to pay by day per attenuator as it is used on the job site, it is
more accurate to use this cost approach in the design and the construction phases.
It should be noted that the VE team feels that the cost for the attenuators will actually be significantly
higher than what is currently reflected in the estimate. Suggest that this be checked as the design and
estimate move to the next level.
Page 52
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Alternative:
Use approximately sized lighting conduit. (2” conduit may satisfy requirements).
Opportunities: Risks:
Smaller conduit is easier to work with Will not be able to add more wiring in
Save cost with smaller size future
Technical Discussion:
Is 3” plastic conduit needed? A smaller size may be more appropriate. Some of the conduit may need
to be bored, resulting in different pricing. The sizing may result in a cost savings. This will likely be
more apparent as the design progresses.
Page 53
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The current design calls for 77 each, 70 foot high light standards with triple headed, 1000 W fixtures.
Alternative:
The alternative would call for the use of 134 each, 40 foot high light standards with double-headed, 400 W
fixtures.
Opportunities: Risks:
Initial cost savings Significant redesign will be required
Significant Maintenance and energy cost savings
Reduced light pollution
Technical Discussion:
The use of the 70 foot high standards would require heavy foundations that will difficult to accommodate in
the median. The 40 foot high standards will go up quickly and not require significant measures to
accommodate and protect in the median.
The VE team assumptions include going from three heads for 70 foot standards to two heads for 40 foot
standards. Also, it will take twice as many 40 foot standards to replace the 70 foot standards ( must be
confirmed). Also, assumed that the caisson savings would offset the additional cost for the alternative
conduits.
Page 54
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ILLUSTRATION
Page 55
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 3 of 3
Sub-
total $1,198,150 $ 846,000
Mark-up at 36.00% $ 431,334 $ 304,560
Page 56
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The current design calls for 77 each, 70 foot high light standards with 1000 Watt light fixtures. The project site is in
a transition area from dense urban to light urban land use, with interchange spacing at approximately one mile.
Alternative:
The VE came upon the question – does the project require roadway lighting to supplement high mast lighting at
interchanges? Is this a requirement from the EIS? Could the focus of the lighting on this project be on the area
one mile north of U.S. 36 only, or specific areas where lighting needs have been identified. The documentation
says, “proposed project is to reduce roadway lighting one mile north of U.S. 36”.
It appears that it might be possible to reduce the lighting requirement from 30,000 LF of lighting to 5,280 LF.
Opportunities: Risks:
Initial cost savings Pavement will not be lit as well
Significant Maintenance and energy cost savings Moderate redesign required.
Reduced light pollution Need to reconstruct median barrier if median
roadway lighting is needed in the future
Technical Discussion:
Taken to its conclusion, the obvious question is whether or not the intent is to illuminate the entire corridor.
Perhaps, the noted reduction in lighting deployment could be a good place to stop for this time.
Page 57
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
COST WORKSHEET
SHEET NO.: 2 of 2
Page 58
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
The existing design calls for concrete barrier walls in the medians.
Alternative:
The alternative would call for down lighting to be integrated into the barrier walls.
Opportunities: Risks:
Technical Discussion:
LED lighting may be a good candidate for providing this integrated lighting.
Page 59
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
DESCRIPTION: CONSIDER USE OF LED FIXTURES FOR ROADWAY LIGHTING SHEET NO.: 1 of 1
Original Design:
The current design calls for High Pressure Sodium (HPS) type light fixtures to illuminate the roadway.
Alternative:
Opportunities: Risks:
Technical Discussion:
The current trend is to move toward greater utilization of LED light fixtures in most industries. For each
application contemplated one must research the availability of appropriate LED fixtures and determine their
unit costs. It is understood that roadway lighting with LED fixtures is in its infancy and is not immediately
reassuring. Attached the reader will find a brochure that should help in deciding whether the alternative
should be implemented. The usual conclusions should be that a more natural light color rendition results
for LED vs. HPS lighting. The life of the LED bulbs exceeds that for HPS lighting. Since the bulbs do not need
replacement as often, the maintenance crews do not have to get out into high traffic areas so often. This is
a real plus. LED lights are more expensive but, due to their longer life, they generally prove out on a life
cycle cost basis.
Page 60
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Currently, 88th Avenue passes over the existing I-25 Mainline. This situation has been studied carefully and,
due to cost considerations, it was decided to lower I-25 mainline in order to get the required overhead
clearance between the mainline pavement and the bottom chord of the bridge.
Alternative:
Opportunities: Risks:
Some minimal re-design
Should improve safety
Should improve traffic operations
Technical Discussion:
This re-striping can be done without adding any pavement. So, the result is a more effective acceleration
lane at very little extra cost, if any.
Page 61
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Original Design:
Alternative:
Consideration should be given to replacing the existing Type 3 with new Type 3 or cable rail where possible.
Opportunities: Risks:
Significant redesign required
This will enhance safety aspects of project
Will reduce maintenance cost
Technical Discussion:
The cost to reset guardrail can actually be more than if new guardrail is used. In addition, resetting Type 3
guardrail can much more labor intensive and difficult than using the new.
Cable rail is an efficient barrier. When impacted, it minimizes the damage to people and property.
Although cable rail cannot be used throughout much of the project, due its deflection during an incident,
but should be considered for isolated areas of application. Some of the deflection can be dealt with during
the design stage.
Page 62
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Technical Discussion:
When the Value Engineering team was working their way through the Function Analysis Phase, they
arrived at the conclusion that this interesting project is not easily pigeonholed like many projects. The
popular title of the project, “I-25 Managed Lanes”, tells only part of the story. The project is also a pilot
program to test the application of some intensive Active Traffic Management, Tolling and other
sophisticated tools on a critical corridor. It is a corridor that has some of the heaviest traffic congestion
in the State. Accordingly, many eyes will be observing the rollout of this project and its resulting
benefits as measured in the near future.
It is suggested that CDOT capitalize on the knowledge to be gained from this project by establishing a
well-defined series of measures for its operational parameters. The following might be asked in
developing the success measures for the different elements of this project:
One of our known goals is to reduce congestion. How do we define our goals so that we can
measure our success or failure?
Will we develop an idea of the optimal density of information that we can pass on to the driving
public without becoming a potentially dangerous distraction?
Are we going to be able to correlate safety results within the project boundaries with other similar
corridors that might serve as a control group for this pilot project?
In short, there is an opportunity here to provide the basis for new lessons learned in the future. These
observations could provide insights that will be beneficial for years to come.
Page 63
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
3 PROJECT DESCRIPTION
The North I-25 Managed lanes extension project involves the creation of managed lanes along I-25 from
US 36 to 120th Avenue by repurposing the existing inside shoulders of the roadway, both north and
southbound. CDOT will be responsible for the design and construction of the new facility as well as
maintenance of the facility and ITS infrastructure while the High-Performance Transportation Enterprise
(HPTE) will be responsible for the management and operation of the managed lanes including the tolling
system. It is planned that the E-470 Public Highway Authority will provide back office support to process
and issue tolls, as well as collect payment.
The project would provide meaningful relief for the most congested corridor in the Denver Metropolitan
area, currently traveled by 175,000 vehicles and 4,300 bus transit riders every day. Implementation of
the managed lanes will result in a more efficient use of available roadway capacity to improve traffic
flow and reduce travel times in the corridor. In addition, the managed lanes will support Bus Rapid
Transit (BRT) along the corridor and provide more consistent transit travel times for the many express
transit routes that currently serve the corridor.
Under the new managed lanes configuration all eligible user (HOVs, registered hybrid vehicles,
motorcycles, buses and toll-paying POVs) will be able to access the managed lanes at designated
ingress/egress points.
The proposed North I-25 managed lane system will offer more choices to commuters and make the best
use of available freeway capacity. The project has several key goals that include:
Utilize managed lanes to improve flow in the general purpose lanes and thereby improve travel
along the corridor for a roadway users;
Provide a means for public transit to achieve better on-time performance by removing them
from the congestion in the general purpose lanes; and,
Encourage carpooling and alternative modes of travel by offering free use of the managed lanes
for public transit and HOV users;
Encourage the further economic growth in the corridor by providing a more efficient
transportation system.
Page 64
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
All the usual concerns go along with this project. These concerns include:
Meeting the objectives and requirements of the very important federal Tiger Grant. These are
stringent and have a performance timeframe that calls for the obligation of the funds by June of
2013.
There are numerous stakeholders and fund sources involved in the execution of this project.
The various agreements and the EIS/ROD requirements weave together a strict route that must
be followed to deliver this project.
Among the stakeholders are the owners of the irrigation ditches that cross under the existing
right-of-way. Every effort has been made to make certain that the proposed project does not
impact these ditches.
There is also an important goal that calls for building all improvements within the existing
footprint of I-25. Negotiations are currently underway to obtain the temporary construction
easements necessary to construct the improvements.
Repairs to the existing noise walls and the inclusion of Noise Wall No. 2 in the project has been a
carefully tracked and rehearsed part of the negotiations with the local interest groups.
Maximizing use of available roadway capacity
Match driver expectancy
Minimize delays to the RTD bus operations
Minimize toll revenue losses
Maximize enforcement efficiency; and,
Integrate seamlessly with the reversible lane segment
In order to do this it will be necessary to deploy key components that are subjects of carefully
orchestrated protocols developed between the operating agencies. Some of the key components in
tolling facilities, ITS and tolling integration, HOV lane management, courtesy patrol and snow plow
operations, incident management capabilities, managed lane enforcement, enhanced Active Traffic
Management (ATM) elements, Variable Message Signs (VMS), CCTV, Microwave Vehicle Radar Detectors
(MVRD), Travel Time Indicators (TTI), Ramp Meter Stations (RMS) and Automatic Traffic Recorders (ATR).
All of these, coupled with integrating communications make this a very complex project.
Part 3.4 of this narrative includes some drawings that will give the reader some understanding of the
extent and detail of this important project.
Page 65
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
3.3 NOTES FROM THE KICK-OFF SESSION PRESENTATIONS BY CDOT AND PROJECT
DESIGN TEAM
In the corridor there is a lot of congestion. Basically, traffic is at a standstill during heavy use
hours.
North 25 EIS -- approximately 2003 -- ROD was signed in 2009. The record of decision sealed a
lot of the decision making process and set the pace for the rest of the project.
Idea was to use some unused space on the typical section by inserting one new managed lane
each way on the inside shoulder. This was a very direct way of making use of an existing asset
to minimize cost and provide additional required traffic capacity.
A federal Tiger Grant was applied for and the resulting funds have made it possible to expedite
this project. Originally, this project was not seen as possible for years to come. With the added
financial assets, this served to energize the other stakeholders to step up to the plate and help
to fund this project. As a result, there are a lot of stakeholders (eight or nine) that are providing
funds to make this happen. The Tiger Grant requires obligation of the funds by June of this
year. CDOT expects to have this done by May.
Must re-stripe lanes -- got design exceptions to go to 11.5 foot lanes and 4 foot inside
shoulders. The outer two lanes are kept at 12 feet to accommodate truck traffic.
This project will expedite bus traffic.
Some new noise wall, pavement repair and tolling/ATM facilities have been made an integral
part of the project.
Safety was a big part of the Federal Tiger Grant.
FIR meeting was held in December. FOR is due in March.
Budget $44.3 million. Now at $60 million. Major elements, including ATM, tolling, etc. affect
the bottom line dramatically. It appears that current funding commitments could be stretched
to cover the $60 million. Could not accept a bottom line that is higher than this.
Project will be design-bid-build.
Concern was raised by FHWA about the status of the integration of the technology deployment
and having a cradle-to-grave plan that must be approved by FHWA before the project can be
approved to go forward. This will be addressed in part during the VE workshop.
Page 66
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Noise Wall No. 2 is a work in progress. The plans for this Noise Wall is separate from the current
plans because it was in the project, taken out, and is now back in the project. The details are
being worked out.
Other documentation includes the comments on the FIR plan set which was covered on 10
December 2012.
May 18, 2013 -- advertising date for bids. Construction is expected to begin in the fall and is
believed to last for about 22 months.
Action Items from the FIR meeting:
Couple of options on the south side with regard to how the managed lanes would be connected.
Ditches -- had to adjust by concurrences with owners of the ditches.
Noise Walls -- currently proceeding with all noise walls as shown on the plans.
Working within the confines of what is currently in the field -- i.e., staying within the current
footprint/Right-of-way.
Currently dealing with the need to define construction easements. Results of this research is
expected shortly.
Environmental -- pulling together the noise wall, air quality, hazmat and other features that
dictate the final compliance scheme for the project.
Drainage is fairly well along. Got concurrence to break the grade at the shoulder to simplify the
design and enhance the drainage away from the mainline, on the inside of the travelways.
Pavement calls for reconstruction of the shoulders in order to be able to handle the traffic. This
is a full-depth replacement.
With regard to scope changes -- lowering I-25 at 88th Avenue -- requires some additional
phasing/costs, adding some lighting in the median for the entire project.
Some of the constraints that are seen as necessary:
Noise walls -- needed
At 88th Avenue -- elected to lower the interstate. Since the bridge has been hit a few times
consideration was given to the use of new bridge. Rejected due to much greater costs to put in
a new bridge.
Page 67
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 68
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 69
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 70
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Generally, the most important ingredient in the conduct of a Value Engineering workshop is to have the
VE team composed of seasoned, highly knowledgeable personnel. The team members must be very
skilled in the discipline they represent while serving on the team. In the instance of this VE study we had
the privilege of support from the following key personnel from the Colorado Department of
Transportation and the Federal Highway Administration:
The Value Engineering team was led by Charles R. McDuff, PE, CVS-Life, CCE, LEED AP of Atkins. The
team would also like to thank several of the key players in preparing for and lending support throughout
the VE effort. These include:
Page 71
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
The Value Engineering team followed the six-step Value Engineering job plan as promulgated by SAVE
International. This six-step job plan includes the following:
Information Phase – during this phase of the team’s work, the team received a briefing from the
design team and representatives of the Colorado Department of Transportation. This briefing
included discussions of the design intent behind the project, the cost concerns, and was
followed by a general discussion and Q & A session for all the participants. In the working
session that followed, the VE team developed cost models from the cost data provided by the
designers and familiarized themselves with the construction drawings and other data that was
available to the team. An excerpt from the cost estimate and the included cost model are
enclosed, immediately following this introductory narrative.
Function Analysis Phase – during this phase the team reviewed the project from the simplest
perspective by asking the questions of “What is the project supposed to do?” and “How is it
supposed to accomplish this purpose?”. In the Value Engineering vernacular, the answers to
these questions are cast in the form of active verbs and measurable nouns. These verb/noun
pairs form the basis of the function analysis that distinguishes a Value Engineering effort from a
potentially damaging cost cutting exercise. The team developed a Function Analysis System
Technique (FAST) diagram that depicts the flow of functions within this project. The FAST
diagram is also enclosed.
This brainstorming session initially identified numerous ideas that were then evaluated in the
next phase. The reader will find the creative worksheets enclosed. These same work sheets
were also used to record the results of the Judgment or Evaluation Phase.
Judgment or Evaluation Phase – Once the team identified the various creative ideas, it was
necessary to decide which alternatives should be carried forward. This is the work of the
Judgment or Evaluation Phase. The team reflected back to the project constraints and
objectives shared with the team by the owner’s representatives, in the kick-off meeting on the
first day of the workshop. From that guidance, the team settled on the following values as
measures of whether or not an alternative had enough merit to be carried forward in the VE
process:
o Construction Cost Savings
o Support for Environmental Objectives
o Ability to Implement the Idea
Page 72
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Based on these measurement sticks, the VE team evaluated the alternatives and graded them
from 5 (Excellent) down to 1 (Poor). Other notes about the alternatives are annotated at the
bottom of the enclosed creative and evaluation sheets, including the inclusion of two other
ratings – Design Suggestion (DS) and Already Being Done (ABD)
Development Phase – This is the section of the report in which the alternatives are explained,
sketched, documented and put to cost and technical tests to determine their suitability for
implementation and for their impact on the project.
Presentation Phase – As noted earlier, the team made a final, informal out-briefing on the last
day of the workshop, designed to inform the Owners and the Designers of the initial findings of
the VE workshop. A copy of the summary table and the rough draft of the results section of the
report were left with the project delivery team. This written report is intended to formalize
those findings.
As noted earlier, this report section includes supportive narratives, cost data and cost models, and other
useful information. In order of appearance this documentation consists of:
Page 73
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Turnpike Conference Room located at 4670 North Holly Street Denver, CO 80216
Page 74
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 75
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 76
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 77
4.6
HOW? WHY?
ADD
CAPACITY
CDOT INTERSTATE 25 - MANAGED LANES
IMPROVE LENGTHEN
RAMP ACCEL/DECEL
ACCESS
FAST DIAGRAM
Page 78
FOR
ENHANCE I-25 MANAGED LANES
REDUCE
DRIVING
TRAVEL TIME
SAFETY PROJECT
REDUCE
CARBON
FOOTPRINT
INFORM POST
TRAVELERS INFORMATIVE
SIGNS
SCOPE OF STUDY
VALUE ENGINEERING REPORT
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
ITS/Tolling (IT)
IT-1 Don’t use lane control for general purpose lanes 5
IT-5 Use standard Variable Message Signs (VMS) in lieu of full color matrix signs 4
IT-8 Provide for better coordination of traffic management assets on the alignment DS
IT-11 VE Team Question – is the current design configuration an integral part of an area- DS
wide traffic operations management concept?
IT-12 Reduce the number of traffic management devices to the minimum See IT-3
Page 79
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
PAVEMENT (PV)
Northbound Lanes
PV-2 Continue fifth lane from Project Start to 84th Avenue for lane continuity (4,000’) 4
PV-4 Use full auxiliary lane between Thornton Parkway and 104th Avenue 4
Southbound Lanes
Page 80
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
PV-10 Re-stripe pavement at on-ramp for Thornton Road(accommodate parallel accel. lanes) DS
EARTHWORK (EW)
EW-1 Reduce excavation See PV-3
MISCELLANEOUS (MI)
MI-1 Optimize conduit for lighting system DS
Page 81
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
MI-5 Put lighting on outside shoulders (note downrated due to being placed in clear zone) 3
MI-8 Replace guardrail in lieu of re-setting existing guardrail (potential added value) DS
Page 82
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 83
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 84
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 85
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 86
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 87
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 88
CDOT INTERSTATE 25 - MANAGED LANES VALUE ENGINEERING REPORT
Page 89
CDOT – North I-25 Managed Lanes
Summary of Value Engineering Responses
The following table identified in summary format the results reported in the attached, more detailed
report that was generated as a result of the implementation meeting for the above referenced project.
Where some of the results are still under study, the facilitator of the VE study has provided a
conservative estimate of the value expected to be received from the alternative in question.
Pavement (PV)
Alternative PV-4 Provide auxiliary lane Not Accepted None
between Thornton
th
Parkway and 104 Avenue
Alternative PV-8 On SB I-25, provide Not Accepted None
parallel acceleration lane
th
from 104 Avenue
Alternative PV-9 Provide parallel Not Accepted None
deceleration lane – 1000’
approach to Thornton
Parkway
Alternative PV-9A Provide 500’ parallel Not Accepted None
deceleration lane for the
approach to Thornton
Parkway
Alternative PV-10 Restripe Thornton Accepted Minor cost additive
Parkway – Southbound
Ramp
Miscellaneous (MI)
Design Suggestion MI-1 Optimize conduit sizes Will Consider Not cost identified at this
time
Alternative MI-2 User shorter light Not Accepted None
standards
Alternative MI-3 Reduce lighting coverage Not Accepted None
Design Suggestion MI-4 Integrate lighting into Not Accepted None
barrier walls
Design Suggestion MI-6 Consider use of Led Will Consider Will increase cost but cost
fixtures for roadway not identified at this time
lighting
Design Suggestion MI-7 Revisit possibility of new Not Accepted Note – schedule will not
th
bridge at 88 Avenue permit
Design Suggestion MI-8 Replace in lieu of resetting Will Consider May reduce cost
existing guardrail
Design Suggestion MI-10 Enhance definition of Will Consider Will flesh this out as
project definitions project progresses – no
cost identified
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
The following responses to the Value Engineering Study Report were prepared by the following:
Parsons Brinckerhoff: David Ungemah, Les Jacobson, Dave Poling, Jeff Wilson, Jim
Bumanglag, Larry Nechanicky
Apex Design: Scott Thomas
ITS/TOLLING (IT)
Alt No IT-1 Description: Don’t use lane control for the Recommendation: Decline
general purpose lanes
Recommendation Discussion:
The primary purpose of ATM is to be able to provide back of queue protection across all lanes.
There will be more collisions in the general purpose lanes than in the managed lanes. Showing
lane control and speed warning just over the managed lanes would not provide significant
benefits.
Recommendation Discussion:
This is a viable alternative, especially with the results of the modeling of the alternative
configuration for ending the managed lane in the vicinity of 120th northbound. The alternatives
are to have full ATM northbound, no ATM northbound, or a less intensive ATM northbound that
could take the form of a small number of VMS signs only (on the order of 3 to 5) only, or a
combination of more widely spaced ATM gantries with shoulder mounted speed advisories
between the ATM gantries. We can discuss the less intensive ATM options and approaches in
more detail, if CDOT is interested, or we can cover it in the ConOps. Not installing ATM NB at
all is a viable and operationally justifiable option.
Recommendation: Accept this part of the alternative and do not implement full ATM in the NB
direction at this time. Rather to recommend that full ATM be deferred until additional growth in
the corridor occurs and conditions would support that level of investment.
1
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
In the meantime, it is suggested that CDOT apply the queue warning aspect of ATM in locations
where there is the highest likelihood of congestion or collisions. We believe that there are two
locations for VMS placement that will support this concept. The first is just north of the US 36
interchange to cover congestion approaching 84th. There is already a VMS in the design at that
location, so this one is covered. The second is in advance of the 120th St Interchange, probably
about a mile in advance, to cover the end of the managed lane and the drop lane to 120th. If we
forecast that the congestion would be severe or would occur often, we would recommend either
multiple signs in advance or a sign further upstream than 1 mile. However, in this situation, we
think a 1-mile advance works well. This also puts the VMS at the same location as the mile
advance guide sign for the 120th exit. Finally, in the full ATM design, there would be a full ATM
gantry at this location so it would support the full ATM build out at a later date. The savings is for
all NB ATM elements except the VMS in advance of the 120th exit and the VMS north of US 36
approaching 84th. Our estimate for these two signs is $210,500 each for sign, structure,
controller, and cabinet. Total savings is about $3,670,000.
The preliminary design shows an overhead VMS on every other ATM gantry (approximately 1
mile spacing for overhead VMS). On the gantries without overhead VMS, we are showing side
mount DMS on both sides of the roadway. This was based on the WSDOT design. They are
very happy with this design, but we can certainly look at alternatives that would provide the
needed capabilities at a lower cost. It is very important that the system provide reasons to the
drivers for why there are lane closures or reduced speeds recommended. It is also very
important that the reasoning is given reasonably close to the slowdown or lane
closure/blockage. If these conditions aren’t met, the credibility of the system suffers, many
drivers will not take the action recommended, and the effectiveness of the system is
compromised.
Recommendation Discussion:
This alternative eliminates ATM altogether. Improving safety is a key element of the project and
the TIGER grant. ATM treatments, such as queue warning, are being incorporated into the
project to address safety by reducing rear-end collisions. Therefore, it is recommended that
ATM remain a project component to help achieve the project safety goals.
2
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Alt No IT-4 Description: Do Not Add Extra Fiber Optic Recommendation: Decline
Cable
Recommendation Discussion:
We checked with CDOT ITS (Jill Scott) on the existing fiber allocation and there is only one
buffer tube (12 fibers) not in use. The additional ITS/ATM/Tolling equipment will require an
additional cable, so we feel this is needed.
Recommendation Discussion:
This alternative deals directly with the large overhead VMS, proposed on every other gantry.
Full color is not necessary for these signs. However, the cost difference between full color and
monochrome is shrinking. Full color provides much more flexibility in the messages and types
of messages provided. The savings for this alternative were estimated to be $163,200 for 12
signs, or just under 7 percent of the cost of the signs. It is the preference of CDOT to have full
color capabilities.
Recommendation Discussion:
The proposed CCTVs on the south end are primarily for tolling purposes and will be used to
view the gates sets and roadway simultaneously. The newly added CCTVs on the rest of the
corridor are to provide better surveillance coverage for the additional ATM elements.
The alternative design suggests using the internal diagnostics to monitor the system. Internal
diagnostics work very well for most things that an operator would want to see. However, there
are a few things that the cameras provide in lieu of sending someone out in the field for things
the diagnostics can’t do. These include:
3
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Testing. When the signs are first installed in the field, they will have to be tested. This
includes testing the diagnostics. Conditions in the field are different than in the factory or
at a test facility. It is not good practice to test a system with the system itself. Having
operators be able to see the signs as they post messages is very valuable.
Concerns over sign visibility. In Les Jacobson’s experience, it is not unusual for the
public to call in about the visibility of a sign message. Call outs to the field can be saved
with the cameras. Over the life of the system, this can provide a substantial savings.
Independent confirmation of messages. Although the diagnostics should cover the
question of what message is on the sign, there are times when communication to the
field is down or there is a discrepancy between a report from the public or field personnel
and what the diagnostics display. The ability to independently check the message on the
sign can be very valuable in these cases, both in terms of responsiveness and in terms
of saving a call out to the field.
Recommendation Discussion:
The detection devices being designed for this project consist of MVRD (side-fire radar units),
TTI (toll tag readers), and DTD ATRs. Ramp Meters are also along the corridor and utilize
MVRD units. The MVRD for ITS will provide lane-by-lane volume, speed, and occupancy that
will feed into the ATM system. The ITS and Ramp Meter MVRD units will be combined to cut
down on field devices. The TTI readers will provide travel time over the segments throughout
the corridor for the GP and managed lanes. The DTD ATR utilizes a Diamond counter.
Recommendation: Accept. As the design progresses and the ATM infrastructure is finalized, we
will revisit the device locations and needs, and look for ways to combine detection devices.
Recommendation Discussion:
Every attempt is being made for opportunities for sharing gantries, detectors, CCTV, etc. for the
items needed by the managed lanes features.
Recommendation: Accept. This alternative was used in the design of the systems
4
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Recommendation Discussion:
The design has included extensive consideration for every way possible to share gantries and
use existing where possible and feasible without compromising the operation of the system.
Recommendation: Accept. This alternative was used in the design of the systems.
Recommendation Discussion:
We agree with this suggestion. This alternative is used in the design of the systems.
Recommendation: Accept.
Recommendation Discussion:
Recommendation: Accept.
Recommendation Discussion:
There is an incident management plan for this corridor. Although it is not currently scoped for
this project the IMP could benefit by being revisited. For now it will be mentioned in the Concept
of Operations as a consideration.
5
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Recommendation Discussion:
Southbound: All SB on-ramps within the corridor have ramp meters, with the exception of 120th
Avenue. The SB on-ramp at 120th does not have a ramp meter because RTD and CDOT
agreed to not induce delay for buses leaving the park-n-Ride. There is not room to easily widen
the ramp to include an HOV/bus bypass lane due to a retaining wall to the west.
Northbound: Along NB I-25, there is a ramp meter at 84th. NB ramp meters at Thornton and
104th are not warranted and it is CDOT’s practice to only install ramp meters at locations where
there is an anticipated benefit.
PAVEMENT (PV)
Alt No PV-4 Description: Provide Auxiliary Lane Between Recommendation: Decline
Thornton Parkway and 104th Avenue
Recommendation Discussion:
This alternative may help traffic flow and should probably have a modeling analysis performed
to verify if there is a benefit. Essentially it adds additional paved surface and cost. Adding
additional paved surface also may affect how the project is viewed environmentally as it is a
departure of staying within the existing footprint of the interstate.
Recommendation Discussion:
This alternative may help traffic flow but as with PV-4 it adds additional paved surface and cost.
Existing ramp metering helps overall traffic flow in the peak hours to sort itself out for entering
onto I-25.
6
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Recommendation Discussion:
This recommendation for the SB I-25 ramp to Thornton Parkway may help with deceleration
although it is not entirely needed, as it is a long ramp that allows for deceleration upon leaving I-
25 and it does not experience backup onto I-25.
Recommendation Discussion:
Similar to PV-9, this recommendation for the SB I-25 ramp to Thornton Parkway may help with
deceleration although it is not entirely needed, as it is a long ramp that allows for deceleration
upon leaving I-25 and it does not experience backup onto I-25.
Recommendation Discussion:
Agree that a striped parallel acceleration lane would allow for a smoother transition and
acceleration lane based on restriping.
Recommendation: Accept.
7
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Recommendation Discussion:
Overall the phase construction will have a comprehensive review looking at opportunities for
reducing number of shifts and avoiding scarring on new pavement. Key to an effective overall
construction phasing plan will be the consideration of how I-25 at 88th Avenue will be lowered,
as this was only noted in the FIR plans as needing additional construction phasing by the Final
Office Review.
Recommendation: Consider.
Recommendation Discussion:
As with TC-1, overall the phase construction will have a comprehensive review looking at
opportunities for efficiencies including reduction of Temporary Type 7 Barriers. As noted in the
Value Engineering analysis this may require extra moves to reset barrier, thus it may mean
performing some slight additional shifts contrary to the efforts of TC-1 which is intended to
reduce traffic shifts.
Recommendation: Consider.
Recommendation Discussion:
The actual number of TCI Days required will ultimately be a function of what the final analysis of
project duration will be. This will of course match up with the required TCI Days quantified.
Recommendation: Consider.
8
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Alt No TC-6 Description: Pay for Mobile Attenuators by Day Recommendation: Accept
Recommendation Discussion:
Agree that the overall costs of the Mobile Attenuators should be paid as “days” and that it is
likely to be a higher cost than what is currently reflected in the estimate. This is also consistent
with remarks received from CDOT EEMA stating that Mobile Attenuators should be paid as
“days”.
Recommendation: Accept.
MISCELLANEOUS (MI)
Alt No MI-1 Description: Optimize Conduit Sizes Recommendation: Consider
Recommendation Discussion:
The lighting plan for the project will be fully designed for the Final Office Review. Until then the
3” conduit will be considered a placeholder for the mainline lighting. We will consider the
possibility of using 2” conduit as the design progresses.
Recommendation: Consider.
Recommendation Discussion:
CDOT Region 6 has added lighting to the entire project limits having determined that it be
consistent with lighting on the southern end of I-25. To be consistent (with T-REX being the
basis of the design) lighting would require using 70’ high light standards.
9
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Recommendation Discussion:
As with MI-2, CDOT’s intent is to illuminate the entire corridor, therefore this alternative is not
considered.
Recommendation Discussion:
As a Design Suggestion this would enhance lighting adjacent to the barriers but is not needed
on the project.
Alt No MI-6 Description: Consider Use of LED Fixtures For Recommendation: Consider
Roadway Lighting
Recommendation Discussion:
With an accelerated schedule to advertise this project there are some challenging issues to be
resolved to be able to accept this recommendation, including coordinating and getting local
agency formal acceptance, and working out installation and maintenance issues. At this point in
the project design will proceed with HPS fixtures as potential discussions continue.
Recommendation: Consider.
Recommendation Discussion:
This alternative has considerably more costs associated with it, and it has been determined that
with the frequency of hits to the 88th Avenue structure implementing the lowering of I-25 at this
site is imperative on this project.
10
CDOT – North I-25 Manage Lanes
Value Engineering Responses
February 13, 2013
Alt No MI-8 & Description: Replace In Lieu of Reset Existing Recommendation: Consider
9 Guardrail
Recommendation Discussion:
There will likely be opportunities where installing new Type 3 guardrail makes sense. A quick
estimate performed on replacing all of the guardrail shows additional cost of $60-$70k. This will
be reviewed at all locations where resetting Type 3 guardrail has been called out.
Recommendation: Consider.
Recommendation Discussion:
Knowledge gained from this project would be helpful to future projects in terms of documenting
lessons learned. Agree that CDOT could capitalize on the knowledge gained. Developing
success measures would be meaningful for those measures that can be defined. Because this
project is unique some actual success measures may reveal themselves and come about
through the process of design through construction, thus documenting the lessons learned
would be invaluable.
Recommendation: Consider.
11