Materials Management Manual - OnGC
Materials Management Manual - OnGC
TEL BHAVAN
DEHRADUN - 248 003
INDEX…………………
Brief Description Para No. Page No.
INTRODUCTION 1-5 1
CHAPTER-1
PURCHASE PROCEDURE
* Dependent Factors 7 3
* Classification of materials 8 3
- Proprietary Materials 8.2(a) 3
- Non-Proprietary Materials 8.2(b) 3
- Stock items 8.2(c) 3
- Non Stock items 8.2(d) 4
- Capital Items 8.2(e) 4
- Stores & Spares 8.2(f) 4
INVITATION OF TENDERS
* Coordination and bulking of Demands for
purpose of inviting tenders 25 41
* Enquiry register 26 41
* Tender Sets to be kept ready and tender 27 41
intimation to be sent to prospective bidders
* Submission of tender for publication in press 28 42
* Time to be allowed to bidders to quote 29-29.3 42
* Validity period 30 42
* Notice inviting Quotations/tenders (NIT) 31 43
* Number of copies of offers to be called 32 44
from bidders
* Variation in quantity after invitation of tender 33 44
* Sale of bidding document to firms with whom 34 45
business has been banned/suspended.
* Tender fee 35 45
* Purchase of bidding documents by Agents 36 46
in India
* Cancellation of tenders-Refund of tender fee 37 46
* Exemption from payment of tender fee 38 46
* Intimation regarding invitation of tender to 39 47
trade Commissions/Consulates/Representatives
of foreign Govts.
* Tender fee 40 48
* Offers without having prescribed bidding 41 49
document of ONGC
* Sale of bidding document 42 49
* Issue of bidding document 43 50
* Issue of bidding document after closing date 44 51
* Receipt of tenders 45 52
* Tender Box 46 52
* Nomination of tender receiving / opening 47 53
officer(s)
* Accounting of tenders 48 53
* Opening of tenders 49 55
* Numbering of Tenders/disclosure of 50-51 55
prices/reading out the rates of tenders
* Opening of tenders in public 52 56
* E-mail/fax/telex/telegraphic offers 53 57
* Cancellation/Re-invitation of tenders 54 57
* Extension of tender opening/closing date 55 58
* Clauses in tenders/ Supply orders 56 59
- Warranty & Guarantee 56.1. 59
- Warranty clause 56.1.2 59
- Penalty/Liquidated Damages/Cancellation 56 .2 59
clause
- Liquidated damage/Failure & Termination 56.3 60
clause
- Procurement of goods 56.3.1 60
- Fall clause 56.4 61
- Inspection and rejection of material by 56.5 63
consignee(s)
- Subletting and Assignment 56.6 63
- Earlier Delivery 56.7 63
- Pilot approval 56.9 64
- Bulk inspection 56.10 65
- E-Mail/Telegraphic/Fax offers 56.11 65
- Arbitration clause 56.12 65
- Submission of tender samples after 56.13 66
opening of tenders
- Scale of Rebate 56.14 66
- Catalogue and manual in case of new buys 56.15 66
- General conditions 56.16 66
* Earnest money and Security Deposit 57 67
- Earnest money/Bid bond/Bid Security 57.1 67
- Security Deposit/Performance Bank 57.2 68
Guarantee/Contract Security
- Security Deposit/Contract Security / 57-3 70
Performance Bond against development
orders/rate contract under import
Substitution programme
- Release of Security Deposit/Performance 57.4 70
Bond/Contract Security
- Release of Earnest Money/Bid Security/ 57.5 70
Bid bond/Security Deposit/Contract
security/PBG
- Invoking of Bank Guarantee 57.6 71
(MM/53/2010 dated 17.05.2010)
* Provisions as per various Govt./Statutory 58 72
guidelines
- Price preference to domestic bidders in ICB 58.2 72
- Supplies of material and equipments 58.2.1 72
- Methodology for calculation of price 58.2.1.3 72
preference
- Granting of price preference 58.2.1.4 72
- Turnkey projects 58.2.2 73
- Oil field services 58.2.3 73
- Price/purchase preference to the products 58.3 73
of Small Scale Sector
- Purchase of ‘Lead Acid Batteries’ with 58.4
provision for ‘buy-back’ of the used batteries
by the supplier.
* Comparative statement 59 74
* Clarification from bidders after tender opening 60 77
- Correspondence with Suppliers 61 77
by indentors
- Technical comments on offers 62 78
- Level for technical comments on offers 62.4 78
* Formation of tender committee and its 63 79
monetary limits
* Single item/group of similar items 64 79
* Convening of tender committee 65 80
* Brief for and level of tender committee 66 80
* Constitution of Tender committee 66.1
* Evaluation of bids by Tender Committee 67 81
and preparation of tender committee proceedings
* Acceptance of Recommendations of T.C. 68 81
* Proposals to Executives Purchase 69 82
Committee (EPC)
* Minutes of discussion of Executive Purchase 70 83
Committee
* Consideration of offers 71 84
* Purchase of Machinery and Equipment 72 84
* Purchase of capital items and spares therefore 73 84
* Late tenders 74 85
* Splitting of tenders/Supply orders 75 86
* Insufficient competition and Reasonability 76 88
of Rates
- Placement of order when one offers 76.2 88
is received
- Certification of urgency 76.3
- Reasonability of rates 76.4
* Negotiation 77 89
* Powers for various activities 78 91
- Competent Authority for approving 78.1 91
various activities
- Open tenders where TC is required 78.3(a) 91
- Limited tender where TC is required 78.3(b) 92
- Single tender on PAC tender 78.3(c) 93
where TC is required
- Single tender on Nomination basis 78.3(c)(i)
where TC is required
- Board Purchase 78.3(c) (ii)
- Acceptance of TC recommendations when 78.3(d) 93
majority views are not acceptable
- Acceptance of offer other than lowest 78.3(f) 93
technically acceptable offer (where TC
not held)
* Powers for placing educational/Development 79 93
order under Import Substitution
* Miscellaneous powers of officers of MM 80 95
- Powers for sanctioning freight by road 80.1
for materials carried
- Powers for sanctioning freight by air 80.2
where air freight is cheaper than freight
by alternative mode of transportation
- Powers for sanctioning handling and 80.3
transportation charges at Railway Station,
Stores Yards and Ware-houses
- Powers for Expenditure sanction 80.4
and purchase of stationery
* Power for purchase of proprietary Articles 81 97
* Powers for purchase by negotiation 82 98
* Signing of supply orders/contracts by 83 98
officers
* Exercising of powers of MM discipline by 84 99
officers designated in Mechanical/Electrical/
Civil etc.
* Observance of laid down procedure 85 100
* Relaxation in conditions of tenders 86 100
- Relaxation in standard terms and 86.3 100
condition of supply order for purchases
form OEM/Manufacturer of proprietary items
* Post contract issues 87 101
* Acceptance of material in deviation to 88 101
specified specifications
* Marginal adjustment in supply orders 89 102
Placing/Termination of supply orders/Contracts 90 102
- Placing of supply orders/Contracts 90.1 102
- Termination of contract/supply order 90.2 107
* Distribution of copies of supply orders 91 107
* Follow up of supply orders 92 108
* Service contracts 93 108
* Extension of delivery / mobilization / 94 109
completion date
* Extension in Delivery period and liquidated 95 110
damages in case of Development orders
* Levy of liquidated damages for delays in supply 96 111
* Review of earlier decision 97 112
* Copies of letter authorizing extension of 98 113
Delivery/Mobilization/Completion date
* Procurement of mud chemicals 99 114
- Schedule for placing indent/supply orders 99.1 114
for mud chemicals and handling thereof
- Classification of chemicals 99.2 114
- Commodity chemicals 99.2(i) 114
- Speciality chemicals 99.2(ii) 114
- Procurement method 99.3 115
- Commodity chemicals 99.3.1 115
- Payment 99.3.5 116
- Speciality chemicals 99.4 117
- Information to be provided by Bidders 99.4.6 117
alongwith their offers
- Sampling, bonding and debonding of 99.6 118
bulk material
- Rejection of Bulk sample 99.7 119
- Debonding and despatch of mud chemicals 99.8 119
- Random Sampling 99.9 120
- Purchase from manufacturers/public 99.10 120
undertakings
- Earnest money/Security Deposit 99.11 120
- Substandard product 99.12 120
- Third party inspection for accepting bulk 99.13 121
supplies of mud chemicals from abroad
- Procurement of Barytes and CMC 99.14 121
* Vendor Rating 100 124
* Securing Adjustment-follow up of claims 101 124
* Amount of compensation 102 124
* Retirement of Documents from bank 103 124
* Kardex showing progress of action on indents 104 124
* Period within which indents to be processed 105 125
* Complaints/Representation Consideration 106 125
CHAPTER-2
* Maintenance of Kardex 107 136
* Maintenance of Buffer Stock 108 137
* Fixation of maximum/minimum limits 109 137
- Indigenous items 109.2 138
- Imported items 109.3 139
* Review of Minimum/Maximum limits 111 140
* Preparation of recoupment requisition 112 140
CHAPTER-3
* Project Stores 113 142
CHAPTER-4
CLEARING AND FORWARDING PROCEDURE
* C&F section Responsibility 114 143
* Transit documents-Receipt of 115 143
* Arrival of materials 116 144
* Damages/discrepancy in Receipt of materials 117 145
* Raising of discrepancy report 118 146
- Discrepancies of trivial value 118.3 147
- Stock Discrepancy 118.4 147
- Stock Verification Discrepancy 118.5 147
* Despatch of materials 119 147
* Despatch convoy note/despatch register 120 148
* Escorting of material 121 149
CHAPTER-5
INSPECTION AND ACCOUNTING OF MATERIAL
* Inspection of material 122 150
* Inspection after expiry of contract delivery period 123 151
- Third party inspection for accepting bulk 123.3 152
supplies of mud chemicals form abroad
* Receipt of Material 124 152
* Packing material-accounting of 125 153
* Preparation of Goods Receipt Voucher(GRV) 126 153
* Binning of materials 127 154
* Stocking of materials 128 155
* Scrutiny of material Requisition/Issue note 129 156
* Material requisition/Issue Voucher-Preparation of 130 157
* Disposal of indent-issue return Voucher 131 158
- Guidelines for stock holder 131.1-131.5 158
* Issue of material-timings 132 159
* Issue of material to out station 133 160
* Items received against adhoc demand(s) 134 160
* Recording of capital/stores and spares items 135 160
- Stores & spares 135.1 160
- Capital items 135.2 161
* Return of material 136 162
* Replenishment of spares 137 163
* Transfer of material-preparation of 138 163
Materials Transfer Note(STR-19)(SA03)(MTN)
* Submission of vouchers 139 164
* Cancelled or missing vouchers 140 165
* Central register of ledger/Stock cards 141 165
and auditable documents
* Kardex cards-index register 142 166
* Kardex cards maintenance of 143 166
* Kardex cards-numbering of 144 166
* Kardex cards-opening of 145 167
* Closing of Kardex cards 146 167
* Kardex cards reconciliation of 147 167
* Kardex cards-posting of/preparation 148 169
of adjustment vouchers
* Duties of numerical ledger poster 149 170
* Filling up of various formats 150 170
for computerised inventory control
* Stock status report 151 170
* Slow/Fast moving items 152 170
CHAPTER-6
* Packing Section 153 172
* Packing of material 154 172
CHAPTER-7
* Control office 155 174
* Drill site material 156 174
* Disposal of unserviceable material 157 174
* Issue hours of material 158 174
* Payments of Bills 159 175
- Foreign Bidders/Indian Bidders 159.1 175
* Railway credit notes 160 177
CHAPTER-8
COMPUTERISED INVENTORY CONTROL
* Annexure of order schedule 161 178
* Instruction for preparing Annexure of 161(i)- 178-244
order schedules 161(iii)(h)
CHAPTER-9
*e-PROCUREMENT 162
*Reverse auction 162.10
- Types of Auction 162.10.4
- Price Preference 162.10.5
- Purchase Preference 162.10.6
- Features of the Online event 162.10.10
- Implementation of e-procurement 162.11
& Reverse Auction
- Bid return procedure 162.12
- Familiarization/training of vendors 162.13
CHAPTER-10
PROCUREMENT OF PREMIUM BITS ON CONSIGNMENT BASIS
FORMATS
STR-1 Goods Receipt Voucher 245
STR-2 Goods Receipt Control Register 246
STR-3 Consignment Inward Register 247
STR-4 Stores Requisition/Issue Note 248
STR-4A Stores Return Note 252
STR-5 Proforma for Maintenance of Records of 253
Capital/Stores & Spares
STR-6 Indent Form for Purchase 254
STR-6A Non-availability Certificate in case 258
of Emergency Purchase
STR-7 Kardex Card 259
STR-8 Gate Pass 262
STR-9 Stock Account Register 263
STR-10 Stock Taking Sheet-Capital Items 264
STR-10A Stock Taking Sheet-Stores & Spares 265
STR-11 Quotation Form 266
STR-12 Convoy Note Register 271
STR-13 Comparative Statement 272
STR-14 Railway Receipt Register 274
STR-15 Discrepancy Report 275
STR-16 Bill/Purchase Register 276
STR-17 Packing List 277
STR-18 Despatch Register 278
STR-19 Material Transfer Note 279
STR-20 Proforma for Explanation of Discrepant Items 280
STR-21 Material Adjustment Voucher/Loss Statement 281
STR-22 Register to watch finalisation of discrepancies 282
STR-23 Provisional Loss Statement 283
STR-24 Final Loss Statement 284
STR-25 Register of Serial Numbers of Stock Sheets 285
STR-26 Register of Losses 286
STR-27 Daily Wagons Register 287
STR-28 Despatch Note 288
STR-29 Convoy Note 289
STR-30 Despatch Convoy Note 290
STR-31 Issue Control Register 291
STR-32 MT Note Register 292
STR-35 Emergency Purchase Inspection Requisition 293
STR-36 Opening Advice 294
STR-37 Closing Advice 295
STR-38 Fortnightly Completion Certificate for months 296
STR-39 Port Arrival and Forwarding Note 297
STR-40 Purchase Order Upto Rs. 1,00,000/- 298
STR-41 Vendor Performance Card 303
_________________
INTRODUCTION
1.1 Work in the Oil & Natural Gas Corporation Ltd. (ONGC) has been
organised on the basis of functional Business Groups with commercial
working relationship among these groups.
a) Exploration
b) Drilling
c) Operations
d) Technical
3.1 Various powers indicated in this manual, as per authorities delegated under
the provisions of BDP, shall stand automatically updated in accordance with the
revisions / amendments carried out to the respective provisions of BDP (from time to
time), unless any other specific instruction is issued subsequently by Chief MM-
Services/PMC with respect to the provisions of such revisions in BDP.
CLASSIFICATION OF STORES
CHAPTER-1
PURCHASE PROCEDURE
6. Aim of the Materials Management Organisation is to procure, preserve
and deliver Materials in proper time to ensure smooth progress of the
project works and administrative machinery.
7. DEPENDANT FACTORS
8. CLASSIFICATION OF MATERIALS
8.1. The purchase can be made with advantage on the results of classification of
material and stock levels. It is, therefore essential that either of these points is
given treatment before passing on to the purchase procedure.
e) Capital Items:
i) All items costing Rs.5, 000/- or more and with a life of more than one
year are categorised as “Capital Items".
ii) Items costing less than Rs.5,000/- which have a life of more than one
year and can be regarded as complete units in themselves (e.g. small
compressors, pumps, electrical motors, welding sets, electrical testing
instruments etc.) are also to be categorised as "Capital Items".
Chief - MM Services will have full powers with the concurrence of Finance to
declare an item costing less than Rs.5,000/- as "capital item".
f) Stores & Spares: All the items, which cost less than Rs.5, 000/- and
have a life of less than one year are to be treated as "Stores &
Spares".
8.3 The Inventories in ONGC have been broadly classified into two separate
groups e.g. "Stores" and "Spares". These two groups have been further sub-
divided into the following classes:-
1 2 3 4 5
STORES
1. Drill Pipes 01 DP
2. Casing Pipes 02 CP
3. Other Pipes and Pipe fittings 03 OP
4. Drill bits 04 DB
5. Other Drilling Stores (all other 06 DS
sub-groups under DT class
excluding those stated above)
6. Electrical material i.e. Electrical 07 EG
fittings, cables, insulating
materials etc. including
Electrical instruments.
7. Building Materials and other 08 BM
Civil Engineering Materials
including Timber
SPARES
9.2 The Purchase Department while making any purchase should see that :
i) All the purchases are made for the properly authorised requisitions
clarifying the purpose for which these are required;
ii) All the materials requisitioned are duly ordered out from the right
source after full enquiries;
iii) The right type and quality of the materials are bought from the cheapest
source;
vi) supplier's bills are paid promptly to maintain good relations with the trade;
(a) Pre-bid conference shall not be held in each and every case.
However, Work Center may hold pre-bid conference in any case based on
the need/justification for the same with the prior approval of concerned L-1
officer for cases where CPA is L-1 or below and of Director concerned for
cases beyond the powers of concerned L-1 officer. Proposal for holding
pre-bid conference should be initiated preferably by the Indentor at the
indenting stage. However, if a need for holding pre-bid conference is felt by
the TC in its meeting held before invitation of the tender, then TC can also
propose for holding of the pre-bid conference.
(c) The issues raised by the prospective bidders during the pre-bid
conference will be examined in detail by the Tender Committee. If due to
the points/doubts raised by the prospective bidders, tender specifications or
any specific term(s), condition(s) which is not a part of “Standard Terms and
Conditions of the Tender” needs to be modified, then the same will be
considered for modification. However, if there are any points/issues, which
have been raised by prospective bidders during the pre-bid conference but
have not been resolved, then a second pre-bid conference will be held
which will be attended by all the Tender Committee Members. In this pre-
bid conference, Tender Committee Members would again try to clarify the
doubts raised by the prospective bidders, with a view to ensure adequate
participation.
ii) Equipment / OEM-wise indents for stores & spares: Indents for
procurement of stores and spares will be raised equipment / OEM-wise.
(v) Specifications :
The indent must specify the time by which the material is required.
In Indent, the definite delivery date and the place at which the
materials are to be delivered or dispatched, will be indicated. The
use of such terms as 'IMMEDIATE', 'AS EARLY AS
POSSIBLE', 'URGENTLY REQUIRED', 'PRIORITY', as substitutes for the
actual delivery dates are to be avoided and the delivery dates always
indicated in red ink in the following manner:-
a) by_________________________________________(date) (meaning
thereby that the whole quantity is required by the date).
The indentor should give the estimated cost item-wise in the indent. If
the cost of the item at the time of placing the contract is more than the
estimated cost, but the price difference is Rs. 100/- or less, no reference will
be made to the indentor. If the price difference is more than Rs. 100/- then
upto 10% of the estimated cost or Rs. 1,000/-, whichever is less, no
reference need to be made to the indentor. In all other cases, a
reference to the indentor will be necessary to confirm that there is budget
provision and that full quantity of materials is still required.
(For Cost estimates, in case of OEM/OES cases, para 76.4.2(a) may be referred)
If the above points are not complied with by the indentor, that indent will not
be treated as a firm indent, till all points are clarified. The date on which all
the points or irregularities in indent are settled that date will be considered
the date of indent. The time of completing of supply will be considered from
that date.
(xiii) Recoupment of Stock Items:
In the case of Stock items, the maximum & minimum and re-order levels
will be fixed scientifically and according to the instructions issued by
Director (Technical) in consultation with Finance keeping in view past
consumption, rates, lead time and safety margins etc. Once these levels
have been fixed, the Materials Management (Stock) can take recoupment
action without any further reference to Finance. However, the Materials
Management (Stock) will request the associated Finance to earmark
funds before entering into any purchase commitment.
(xiv) The Materials Management (Stock) will intimate its requirements to the
purchase section through recoupment demands.
(xv) Wherever maximum/minimum and re-order levels have not been fixed in
the manner stated above, the indenting section will continue to assess its
requirement and to place its indent on the purchase section after obtaining
financial concurrence.
(xvi) The review of levels in respect of Stock Items will be carried out once a
year. However, if circumstances, such as change in the programme of
operation or change in norms, necessitate it, the review will be carried out
earlier.
As far as possible, adhoc purchases will be avoided. Items, for which there
is repeated emergency purchase, will be added to the list of Stock Items,
which would be progressively increased and the list of Non-Stock items
correspondingly reduced.
(xix) When a budget is drawn up on a functional basis and gives the break-up of
the provision of materials, itemwise indent upto Rs.5,000/-within the
budgetary provision, need not be referred to Finance again for concurrence.
However, in the absence of budget on functional basis, prior financial
concurrence will be obtained by the indentor before placing indent on the
purchase section, irrespective of the amount involved. The sanction from
the competent authority will accompany all indents.
In case of new buys and where permanent codes have not been allotted
Regional Corporate Materials and Logistics Organisation (RCMLO) will be
consulted who will act as Coordinating Agency of the Project / Region and
will interact with Inventory Control Cell to get the permanent code. Where the
material code is not communicated by Inventory Control Cell within 7 days
from the date of reference to them, temporary code will be allotted by the
RCMLO. Indent can be raised by the Indentor with such allotted temporary
code with the prior approval of concerned Regional Director. Permanent
code number obtained by RCMLO will thereafter be notified to concerned
Indentor and Purchase Section.
All Indents for procurement of stores and spares will be routed through
RCMLO at Regions / Projects and through CMLO in the Hqrs. who will
scrutinize the same with reference to stock in hand, material in pipe line
and likely consumption schedule. This exercise should not take more than
five days.
CENTRALISATION / DECENTRALISATION
OF PURCHASES
11. CENTRALISED / DE-CENTRALISED PURCHASES
11.1 In Drilling Business Group, purchase functions of the following items would
be handled as under:-
1. Barytes Chennai
2. CMC Dehradun
4. Bits
Indigenous Dehradun
Imported Dehradun
Onland Dehradun
Offshore Mumbai
9. Well Heads
Onland Dehradun
Offshore Mumbai
ii) All such purchase shall be against sanctioned estimates for which
administrative approval and expenditure sanction of Competent Authority exist.
iv) The word "Building materials" includes all type of materials required to carry
out work including all tools, plants implements, etc.
12.1.1 For the purpose of sending enquiries for indigenous purchases against
limited tenders to be invited in the normal limit of the value of limited tender,
registration of firms will be done by Head of Materials Management(TBG) at
Regions / Projects / Hqrs keeping in view the requirement of the work
centre. Firms willing to register at more than one work centre, will require
to get themselves registered with all such work centres. The firm(s) will be
registered for each group of items separately for which they will need to send
separate application alongwith application fee as indicated in para 12.1.3.
The firm(s) will be registered for a period of three years. In Registration
Certificate also it will be made clear that the facility for exemption from
payment of earnest money / furnishing of bid bond will be available in normal
limited tenders only.
iii) 50% of annual turn over of the item(s) / group of item(s) for
which the party requires registration, duly certified by a
Chartered Accountant.
12.1.4 While confirming registration number of the firm, it will clearly be advised
that they should apply for renewal of registration at least 3 months prior to
expiration of the validity of registration. Renewal of registration will be done
on the basis of past satisfactory performance.
12.1.6 In case a firm already registered with a work centre, wants to get itself
registered with other work centre(s) for same item(s) then a fresh
verification of Income Tax Clearance, Sales Tax Registration and annual
turnover will not be necessary and the party will be registered for the
same monetary limit and period upto which its registration with initial work
centre is valid.
12.1.7 Firms registered with DGS&D / NSIC will be treated as registered firms of
ONGC for the item(s) they are registered with DGS&D / NSIC for sending
limited tender enquiries provided a formal request alongwith non-
refundable registration fee of Rs.50.00 for each group of item(s) and proof of
such registration from such firms has been received.
12.1.9 It will be ensured that enquiries are sent to all firms registered for the item(s)
required to be purchased. In case the number of registered firms is large,
enquiries may be sent by rotation to ensure healthy competition and allowing
all firms an opportunity to compete.
12.1.10 Any case for de-registration of firms shall require approval of an officer
at E-7 level (General Manager).
14.1 There are three ways of purchase of materials through the DGS&D:-
i) By placing indent on DGS&D who on his side invites the tenders from
the dealers on his approved list.
ii) Through DGS&D Rate / Running Contract: In this case also the
indents are to be placed on DGS&D who places order on the firms
with whom they have concluded the rate / running contracts, such as
petroleum products.
14.2 Full advantage of the DGS&D Rate / Running Contract should be taken as
far as possible when such contract exists and the delivery period suits our
requirement. No separate tenders need be invited when the delivery period
stipulated in the DGS&D Rate / Running Contracts is acceptable. However,
where the delivery period of any such contract is not suitable, the Purchase
Officer may place a direct supply order on the DGS&D Rate contractors on
DGS&D rates or lower rates and where it is not possible to obtain supply
of an item either by operating on the DGS&D Rate Contract or by placing a
direct supply order on the DGS&D Rate Contract Holders because the
delivery period does not suit our requirement, the Purchase Officer may
resort to the other methods of purchase outlined in para 13 above even
though the items are available against DGS&D Rate/Running Contracts.
14.3 All other items not covered by the Rate / Running Contracts will be
arranged by the Materials Management by inviting tenders.
15. OPEN TENDERS
(MM/33/2008 dated 29.04.2008)
15.1 Except for situations covered under provisions at para 15.3, when the value of
the tender is more than Rs. 25.00 lakhs, open tenders will be invited. Open
tenders will be advertised through the press.
15.3 Invitation of open tenders will not be necessary in the following cases:-
16.1 For purchases of the value of Rs. 25.00 lakhs or less, the tender need not
be advertised through the press.
In accordance with the instructions issued from time to time, all limited tenders
of value above 5.00 lakhs are to be posted on ONGC’s tender website, along
with the pre-qualification criteria which has been used for selecting the
vendors. After framing the pre-qualification criteria, indentor would forward the
name of those vendors to the MM Department who meet the pre-qualification
criteria. Besides issuance of the tender enquiry to vendors who meet the pre-
qualification criteria, MM Department would also publish the tender enquiry on
the website along with the pre-qualification criteria. After publication of the
limited tender enquiry on the web site, tender enquiry can also be issued to
those vendors who request ONGC for issuance of the tender enquiry and who
meet the pre-qualification criteria. Such requests are to be entertained within
10 days of publication of the tender enquiry on the web site. Indenting
Department would have to certify that such vendors meet the pre-qualification
criteria and based on this certification, enquiry would be issued by MM
Department.
The names and addresses of vendors to whom the Limited Tender enquiry
has been issued should also be posted on the website alongwith the PQC.
For limited tenders upto Rs 5 lakhs, the purchase officer may send enquiries
to vendors known to ONGC. The enquiries will also be sent to the registered
vendors as defined in para 12.1 under the heading “Registration of
Vendors." In-charge MM at each work center shall make necessary
arrangements for registration of vendors as per para 12.1, keeping in view of
the requirements of the work center.
16.3 For tenders valuing less than or equal to Rs.5 Lakhs, when the number of
vendors known to / registered with ONGC is less than the required, the
enquiry may be sent to all such vendors after obtaining the approval of an
officer one level higher than the Competent Purchase Authority.
For tenders valuing above Rs.5 Lakhs, if the number of vendors who meet
the PQC are less than the required, approval of an officer one level higher
than the sanctioning authority shall be obtained by the indenting department
and conveyed to MM department alongwith the indent. However, concerned
Director will have full powers to approve such cases, including EPC level
cases.
The dealing officer will float limited tender enquiries [as per specified format of
STR 11], as per para 16.1 & 16.2 above.
After receipt of offers within the closing time and date, the offers shall be
opened by the nominated opening officers from MM and F&A. After opening,
the offers will be handed over to the concerned dealing officer who shall
tabulate the data from the offers in the comparative statement, to be prepared
within one working day. In all cases where technical evaluation is involved,
the duplicate copy of the offers are to be referred within one working day to
the indentor for technical comments. The indentor [not below E-1] shall furnish
the technical comments immediately, which in no case shall exceed two
working days. Subject to provisions of Para 78.3 (f) of this Manual, the
approval of a Purchase Authority [not below E-4(MM)] will be obtained before
placing order (within 7 working days from opening of bids) as per Annexure A
of STR 40, without holding Tender Committee).
17.2.3 . Accordingly, for such purchases of proprietary items from single source,
Indenter shall provide a ‘Proprietary Article Certificate’ (PAC) alongwith indent, as
per following format:
(iii) The In-charges of MM and Finance disciplines of the work centers have
examined and cleared the proposal for purchasing the required item(s) as a
proprietary article.
(Signature)
Name and Designation……………..
Date:
Place:
[Note: The certificate should be signed by the authority competent to approve the
Technical specifications (as per para 78.1-1(i)), in accordance with the value of the
purchase].
17.2.4 Features of the model / version of the products are regularly upgraded by
the manufacturers. Similarly, new products and new technologies are being
introduced very frequently and the market conditions are likely to vary at different
point of time. Therefore, the approval for purchasing an item as proprietary article
(PAC) should be obtained separately on each occasion of its purchase.
17.2.5 The purchase of proprietary articles against the Proprietary Article Certificate
should be made either from Original Equipment Manufacturer or from Authorised
Dealers/Distributors/ Stockists of Original Equipment Manufacturer (and not through
a third party).
17.2.6 It must be ensured that such items purchased against PAC are consumed
within one year from the date of receipt of the material.
17.3 Purchase of stand-by equipment & accessories and spares from OEM:
17.3.1 Stand by equipment and accessories which form part of the main equipment,
and are required for ready replacement and which can not be replaced with other
makes on technical grounds can be purchased from OEM or authorized
Dealers/Distributors/ Stockists of OEM, as proprietary article without PAC provided
Indenter certifies that no other make or model can be used as replacement on
technical ground and competent authority approves the same in consultation with
MM. In such cases, approval of competent authority as per powers delegated under
item No. R1 and MM2 of BDP-2009 shall be obtained.
17.3.2 Spares for vehicles / machineries / tools / equipment, which are manufactured
only by particular firms and for which no substitutes are available are to be treated
as proprietary articles. No PAC would be necessary for procurement of such
items. For carrying out such purchases, approval of competent authority as per
powers delegated under item No. R1 and MM2 of BDP-2009, shall be obtained.
However, before submitting the proposal to competent authority for approval, the
same will be examined by the In-charge of MM discipline of the respective work
center. These items are to be procured from Original Equipment Manufacturers /
Authorised Dealers/Distributors/ Stockists of Original Equipment Manufacturers, as
per procedure laid down in para 17.3.3 below.
The OEM will also be requested to notify to ONGC if any change occurs
in Authorised Dealers/Distributors/ stockists during the period of one
year. Enquiries should be sent to all the Authorised Dealers/Distributors/
stockists so intimated by OEM, including the OEM.
iii) In case OEM does not respond to our request for sending us details of
Authorised Dealers/Distributors/ stockists, enquiry may be sent to OEM
only..
18.1. Purchase upto Rs. 10,000.00 (annual cap as per Item No. RG2 of BDP) at a
time may be made without formal enquiries or without obtaining hand
quotations by User Departments themselves.
18.1.3 No GRV will be raised for petty purchases of consumable items upto Rs.
10,000.00 and such transactions need not be routed through concerned
Materials Management. Also no covering supply order need be issued for
petty purchases of consumable items upto Rs. Rs. 10,000.00.
GRV shall also not be required for purchase of materials for special events like
Seminars, Conferences, training, meetings and sports events provided the items are
to be consumed during the same event and need not to be kept in stock .
The requirement should be applicable only in cases GRVs are created for
value upto Rs. 10,000/-, say for Capital items, for other cases as even GRVs
are not created, the item shall not be inventorised at all and booked directly to
expenditure head.
18.2.1 Purchase above Rs. 10,000 but upto Rs. 50,000.00 (annual cap as per Item
No. RG2 of BDP) may be made either by User Department or by the Purchase
Department by obtaining at least three hand quotations. A list of prominent and
reliable local firms will be maintained by all concerned. Hand quotations will be
collected on rotation basis whenever there is scope for rotation. A certificate will
be given by the Officer making such purchase that hand quotations were obtained
on rotation basis. The names and addresses of the firms from whom quotations
are obtained will be given in the certificate. Where the number of dealers is limited
i.e. less than six, rotation system need not apply.
18.2.2 User departments will not go for direct purchases over Rs. 50,000.00 at a
time barring operational emergencies involving breakdown in operations. In
operational emergencies the User Department may make direct purchases as per
powers delegated in the Book of Delegated Powers.
19.1 For items required continuously throughout the year in large quantities, it may
be advantageous to have a rate contract on lines similar to those of the
DGS&D. These contracts will not be for longer than one year and will be
finalised after inviting open tenders and after negotiations in consultation
with finance.
19.2 Items for which annual rate contract should be concluded will be specified
and this list will be reviewed and additions made every year depending upon
the past consumption or on anticipated consumption. Annual rate contracts
will not be entered into in the case of items for which the market shows
marked downward trend. In order to provide against a fall in the market
price during the currency of the rate contract, the contract should include
the standard Fall Clause as in DGS&D Rate Contracts.
iii) If for any reason it is not possible to constitute a purchase board with
competent officers, the board may be constituted with an officer of the
next below rank. However, the reasons should be recorded in writing
and the proceedings of such a purchase board should be got ratified
by the authority constituting the board.
iv) For carrying out the purchase, the board of officers shall explore the local
markets as first priority, before seeking offers from outside the city/town.
Further, the board of officers shall obtain as many quotations as possible
so as to determine the reasonability of rates. In case the supplier(s) do
not agree to give the hand quotations this fact will be recorded by the
board of officers in their proceedings.
viii) Curtain Cloth: Curtain cloth will be purchased from Millshops / Govt. /
Emporiums on as and when required basis but by clubbing the
requirement. If these are not located nearby, purchase may be made
from authorised stockists / dealers. In exceptional cases, the above can
be relaxed with reasons to be recorded in writing, by the concerned Level-
I executive.
21.3 Reporting of single tender cases on nomination basis would be done to the
concerned Director/EPC/Board, as per prevailing instructions issued from time to
time.
21.5 Concerned Indentor / User department shall ensure sufficient stock of critical
spares and the materials for which repeated emergency purchases have been
made, by following normal methods of purchase through MM department.
TWO BID SYSTEM
22. TWO BID SYSTEM
22.1 Two Bid system will be compulsory for all the tender valuing more than Rs 5
lakhs.
22.2 Under Two Bid System the bidders will be asked to submit 'Technical' and
'Commercial' bids separately in sealed cover duly superscribed and both
the offers placed in one single sealed cover, at a central place. For this
purpose, suitable labels in different covers will be provided with the
bidding documents.
22.3 The technical bids will be opened first and scrutinised by Tender
Committee.
22.6 Price bids, which remain, unopened with ONGC, are to be returned to the
concerned bidders within a period of 5 working days of receipt of Performance
Guarantee Bond (s) from the successful bidder (s). A clause in this regard
should be inserted in the Bidding Documents.
24.1 The tendering process at the Assets / Basins / Institutes / Hqrs should
commence with the availability of budget, followed by detailed indent raised
by the indenting department giving specifications and technical BEC along
with cost estimates and the financial sanctions. The Competent Purchase
Authority will decide the required type of tender to be issued viz (i) Public
tender (open tender) (ii) Limited tender (minimum 5 parties) and (iii) Single
tender (nomination, based on delegated powers in this regard). The
Competent Purchase Authority of the tender (on recommendations of the
Tender Committee) will also approve the technical and commercial terms and
conditions in the following context:
The Competent Purchase Authority will record the reasons for deviating, if
any, from the normal tendering procedure spelt out in paras 15 and 16 of this
MM Manual.
Concerned Director shall have full powers, including for the cases falling
under the powers of EPC.
Such cases falling under the power of EPC will be brought to it for approval
after endorsement of the concerned Director. who will consider the factors
(i), (ii) & (iii) given above, after due examination and recommendation by the
Asset Manager / Basin Manager / Chief of Services / Head of Institutes /
Regions Similarly, if there is no change in the mode of tendering earlier
approved by EPC, such cases may be approved by Director concerned
without referring to EPC again.
When dealing with indents, due attention should be paid to the combination
and bulking of demands which will result in economy in purchase.
Demands for materials received simultaneously from different indentors
should be combined as far as possible while inviting tenders. Due regard
should, however, be paid to delivery instructions given by the indentors.
Demands which cannot be suitably combined with others for this or any other
reasons should be dealt with separately.
26.1 Every individual section dealing with purchases will maintain an enquiry
register. A separate page for each enquiry will be allotted in that register.
26.2 In case of limited enquiries, the name of the firms to whom the enquiries will
be addressed will be entered in that register. This will be signed by the
concerned officer sending the enquiry.
All concerned sections dealing with open tenders before they send tender
invitation to the press for advertisement will ensure that :-
a) the tender forms are complete in all respects and are ready for sale.
About 20 sets are to be kept ready and all are to be serially
numbered.
29.1 Save in special cases which should be seen and approved by concerned
Level-1 executive, the following period will be allowed to bidders for
submitting their bids in Open Tenders:
Note:
29.2 The above period is to be reckoned from the date of publication of NIT in the
news papers.
29.3 Bidding documents should be ready for sale at tender selling centres on the
date NIT appears in news papers.
29.4 Save in special cases which should be seen and approved by concerned
Level-1 executive, the following period will be allowed to bidders for
submitting their bids in Limited Tenders valuing above Rs 5 lakhs:-
Cases valuing Cases valuing above
above Rs. 25 Rs. 25 Lakhs without
Description of Activities Lakhs with PBC and cases valuing
PBC between Rs.5 lakhs and
upto Rs.25 Lakhs
(i) Receiving requests for tender 10 days 10 days
enquiries from vendors whose
name not included in original list
(from the date of publication of
tender enquiry on the web site).
(ii) Verification of such requests by 6 days 6 days
indentor and issue of tender
enquiries to eligible bidders
(including the time required for
receiving the same by the bidder).
(iii) Receipt of queries from bidders for 7 days ….
pre-bid conference
(iv) Scrutinizing the queries and 8 days ….
holding pre bid conference
(v) Approval of Pre-bid minutes and 8 days ….
issue of the same
(vi) Submission of offers and opening 21 days 10 days
of techno-commercial offers(TBO)
Note:
29.5 For limited tenders valuing upto Rs 5 Lakhs, a period of 21 days shall be given
to the bidders for submission of offers, from the date of issue of tender
enquiries.
30.1 The bidders will be asked to keep their offers open as under:
For any particular case, if longer bid validity period is considered necessary,
than the validity period prescribed above, then the longer bid validity period
can also be specified in the tender with the approval of CPA (Director
concerned for EPC level cases), but due justifications for such longer bid
validity required must be given while obtaining the approval. However, after
specifying a reasonable time for bid validity period, the same must be
adhered to.
30.2 It should be specified in all tender notices under Single Bid System that
offers with lesser than the required validity will be straightway ignored.
However, under Two Bid System no offer should be rejected on account
of shorter validity. In Two Bid System, as soon as technical evaluation is
completed, reference should be made to all bidders except those which
are technically rejected, for furnishing validity, as required at that stage.
(i) The Notice Inviting Tenders (NIT) will clearly indicate the place at, date
and time by which tenders will be received and the place, date and the time
at which these will be opened.
(ii) The major qualifying criteria (which are very essential) must be specified
clearly in the NIT so that prospective bidders are aware of this requirement at
the time of buying bidding documents.
(ii) The time and venue of the pre-bid conference (if any envisaged) also must be
clearly specified in the NIT.
(iii) Notice Inviting Tender should include an instruction that bids sent by
post must be sent under registered cover so as to reach the place well
before the closing time and date.
(iv) All bids received by the notified closing date and time whether through the
post or through the tender box, will be registered under the signature of the
Tender Receiving Officer.
(v) Notice Inviting Tenders may be transmitted by fax also, wherever required.
(vi) Notice Inviting Quotations / Tenders will indicate the date and time of the
commencement of the sale of the tender.
(vii) Bidding documents depending upon value notified from time to time, will
be made available for sale on specified date and time at (1)Dehra Dun
(2)Calcutta (3)Mumbai (4) New Delhi (5) Chennai.
33.1 Provisions will be made in all tender conditions for procurement of goods that
ONGC is entitled to increase or decrease the quantities amongst any / all the
items of the tender by not more than 20% (twenty percent). However, in case
of procurement of goods under Two bid system, any variations upto + 20%
of the tendered quantity would be permissible only if it is decided before price
bid opening. No change in quantity would therefore be permissible in the
quantities that are proposed to be purchased after price bids are opened.
33.2 In case there is an increase in the quantity beyond 20%, it would be essential
to invite fresh tenders covering the total revised quantity so as to get the
advantage of bulk discount in prices.
33.4 In case of tenders like those of pipes for offshore where large quantity is
involved, even lower percentage may be specified in the tender with
approval of Regional Director concerned.
35.1 All open tenders will be issued after making necessary entries in the tender
register against payment of prescribed tender fee. The tender fee will be
acceptable in the form of crossed "Payee Account only" Bank Draft /
Cashier's Cheque / Banker’s Cheque drawn by Bank and valid for 180 days
from the date of issue of the same or in the form of Indian Postal Orders
payable to the ONGC.
35.2 Subject to provisions laid down vide para 36, the IPOs / Bank Drafts /
Cashier’s Cheques / Banker’s Cheques will be deposited and accounted
for at the station where they are received and credited in the accounts
there itself. The Purchase Formation concerned from where bidding
documents have been received for sale will, however be furnished with full
details of parties to whom the bidding documents have been sold and the
number of bidding documents not sold, which will be returned.
In the event, a particular tender is cancelled the tender fee will be refunded
to the concerned bidder.
Micro and Small Enterprises (MSEs) registered with District Industry Centers
or Khadi and Village Industries Commission or Khadi and Village Industries
Board or Coir Board or National Small Industries Corporation or Directorate of
Handicrafts and Handloom or any other body specified by Ministry of MSME
will be exempted from payment of tender fee irrespective of the monetary
limit mentioned in their registration certificate provided they furnish evidence
that they are registered for the items they intend to quote against ONGC
tenders. The Govt. Deptts. will also be exempted from the payment of
tender fee.
40.1 The following tender fees will be charged from the bidders for sale of
bidding documents for procurement of items not specific to the requirement of Oil
Industry:-
40.2 In the case of high value tenders where technical drawing / specifications
run into several pages, the cost will be fixed by the Head of Materials
Management concerned keeping in view the expenditure incurred thereon
and the labour involved.
40.3 With a view to eliminate the offers without requisite tender fee, the
bidding documents will be serially machine numbered and proper
account of distribution thereof maintained by the purchase section
concerned. The bidders will be required to return the bidding documents
either in original or photocopy thereof for facilitating linking after tender
opening.
The condition "Offer sent without having the prescribed bidding document of
ONGC and without complying with the terms and conditions of bidding
document for submitting the offer, will be ignored straightway" will be
inserted in all tender notices.
(Signature)
Name of the Issuing Officer
Designation
Address of Issuing Centre
The bidder must submit this forwarding letter alongwith the offer (alongwith
unpriced bid in case of Two Bid System). In case the Bidding Document
has been received free of cost, bidder must also submit the forwarding
letter alongwith the valid registration certificate containing the following:-
43.1 The entries of the issue of bidding documents will be made in the register to
be maintained by section concerned for this purpose. One page should be
attached for each tender advertisement. Following columns should be made
in the register:-
Sl. No. Name of the Postal order/ Value of Date of Date of Signature
firm to whom Bank Draft/ Postal receipt of issue
bidding Banker’s order/Bank application
document cheque/Cashi draft/ for bidding
issued er’s cheque Banker’s document
cheque/Ca
shier’s
cheque
Asstt Asstt. MM
officer
Materials
Managem
ent officer
1. 2. 3. 4. 5. 6. 7. 8.
1. Total No. of
43.2 This register should be presented by the Section concerned at the time of
opening of bid. Both the Officers opening the tenders will sign in column 12
and 13 of the above register against the names of firms whose bids have
been received.
44.1 After the closing date and time is over, no bidding documents will be issued.
However, if there is an unscheduled holiday on the date on which the tender sale is
due to end, then the tender sale date will be extended by one day (i.e. upto the next
working day). Thereafter, tender selling section will prepare a statement in the
prescribed proforma showing the following columns: -
44.2 One copy of the above statement is to be sent to the Accounts Section
alongwith the Postal Orders / Bank Drafts / Banker’s Cheque / Cashier’s
Cheque for encashment.
45.2 The Receipt and Despatch (Central Diary) Section will maintain separate
register for the bids received by them through post office / handed over to
them personally by tenderers due to their voluminous size. Tender samples
which cannot be dropped in Tender Box due to their voluminous size will
also be received by Incharge Diary Section from the bidders. All Tenders
and tender samples received by Diary Section will be recorded in this register.
The Diary Section will put date and time of the receipt on each envelope
of tender / sample and hand over the same on day to day basis to the
Tender Receiving Officer before 14.00 hrs. (1600 hrs in Mumbai Region,
including Uran and Hazira) after obtaining his initials in acknowledgement of
having received the same. In no circumstances the cover of tenders will be
opened or destroyed by Diary Section. All late tenders on receipt will be
handed over to the Section concerned on day to day basis for necessary
action as laid down vide para 73.
46.1 A Tender Box of the following dimension with suitable provision on its top
for dropping tenders in it will be placed in Tender Opening Room / Office
verandah.
i) Length 92 cms.
ii) Height 123 cms.
iii) Width 46 cms.
46.2 The Tender Box will always be kept locked and sealed. Keys of Tender
Box will be under the custody of Tender Receiving Officer.
47.1 An Officer of Materials Management not below E-0 level will be nominated
for receipt of tenders each month. In addition, one officer not below E-0
level each from Materials Management and Finance and Accounts Deptt.
will also be nominated for opening of tenders each month. Arrangements
will also be made for nominating officers not below E-0 level as Leave
Reserve for above purpose.
47.2 The names of the officers selected for a particular month for receipt and
opening of tenders will be communicated to all concerned alongwith tender
opening programme on the first day of the month, if not earlier.
48.1 Each Purchase Centre will have an almirah with 31 pigeon holes. Each
pigeon hole will be for each date. Key of this almirah will be under the
custody of Tender Receiving Officer.
(MM/67/2012 dated 07.06.2012)
48.2 The Tender Receiving Officer will take out at 14.00 hrs. (1600 hrs in
Mumbai Region, including Uran and Hazira) on each working day all tenders /
samples from Tender Box and will put dated initials on each envelope.
Thereafter, the lock of Tender Box will be sealed. All these envelopes as well
as envelopes received from Diary Section containing bidding documents /
samples will be placed by him in their respective date bins of the
Almirah provided for this purpose.
48.3 The Tender Receiving Officer will maintain numerical account of the tenders
/ samples taken from Tender Box as well as of the tenders / samples
received by him from Diary Section on the following format:
48.4 In addition, the Tender Receiving Officer will note down full particulars of
each tender / sample received by him every day in a register to be
maintained for this purpose. In this register, there will be one or more pages
allotted for each tender notice and this will have the undermentioned
columns:-
1 2 3 4 5 6
48.5 The tenders / samples received from different sources on different dates
shall be entered in the above register. On the due date of opening, a line will
be drawn at the end indicating thereby the total number of tenders / samples
received against the tender notice in question. In the cases where no
tender / sample has been received on a particular date, the Tender Receiving
Officer will record the fact of non-receipt of any tender on the due date. The
late tenders / samples received by Tender Receiving Officer from Tender
Box shall also be entered in the above register after the closing entry of
the timely received tenders / samples.
48.6 The Tender Opening Officers will put their signatures with date and time
at the end of last entry of timely received tenders / samples in the Tender
Receipt Register in token of their having taken over the tenders mentioned
therein on the due date of opening. Late tenders / samples will be handed
over by Tender Receiving Officer to the concerned Materials Management
Officer after obtaining acknowledgement.
49.1 The tenders should only be opened on limited days to save time. Every
section, while issuing enquiry, will ensure that only the following dates of
the month are given as Due Dates 3,5,7, 9,11,13,15,17,19, 21,23,25,
27,29 and 31. If any due date happens to be Sunday or Gazetted Holiday
then next due date may be fixed. In case of emergency, if it is not possible
to adhere to these due dates, then other dates may be given but such
cases should be reduced to minimum. The Head of Materials Management
of concerned Business Group may, however, authorise opening of
tenders on all working days, if situation so warrants.
49.2 Tenders are to be opened at 15.00 Hrs. (1700 hrs in Mumbai Region,
including Uran and Hazira) on the day they are due to be opened.
49.3 The Tenders / bids will be opened by a team of two officers as per para 47.
Numbering of Tenders
50.1 The Tender Opening Officers will encircle the rates and terms and conditions
and put their initials. If there is any cutting, overwriting or erasing that will
also be stated and signed by both the officers. Total number of
sheets in the bid will be mentioned on the first sheet of bid and all the sheets
should be initialled by both the officers opening the bid and the bid will be
given Serial number. As for example, if 7 bids have been received against
one particular enquiry, then bids should be numbered as 1/7, 2/7 and so
on. The bids which are received by post after due date should be marked
'Late' tender with No. 8/7 and so on. The samples received along with the
tenders should also be signed by both the officers. If it is not possible to sign
on the samples then those samples should be sealed with the label
mentioning the name of the firm. Name of the firm should invariably be
recorded on the sample, if not given already.
50.2 All envelopes are also to be retained on the record and these are to be
initialled by both the officers authorised to open the tenders.
50.3 The Section concerned whose tender is due on that particular date will be
present at the time of opening of the tender with the tender register. Both
Tender Opening Officers will sign the register against the name of the firms
whose bids have been received. The summary/remark in respect of the offers
received, as para 43.1 above, shall be recorded by the tender opening
officers, immediately following the entries made for the individual offers.
Thereafter, the tender opening officers should make sure that no space/pages
are left blank between the last entry of particular tender (which has been
opening by them) and the starting page of the next tender (appearing in the
register), by crossing out the blank space/pages with the remark “space/page
cancelled” and should also initial on these pages.
In the public opening, only the total prices or group-wise prices, if sought
as per tender should be read out in addition to delivery schedule and major
terms and conditions. Offer should not, repeat not, be circulated amongst the
bidders' representatives.
52.1 Unless good and sufficient reasons exist (which must be recorded on the file)
all bids, including bids for service contracts, estimated to cost Rs.1.00 Lakh
and above, must as a rule be opened in the presence of bidders /
authorized representatives of bidders.
.
52.4 Price bids are to be opened only for the qualified bidders and data are to be
tabulated and signed by the Tender Opening Officers immediately, in
presence of the interested bidders. Respective dealing officers/dealing
assistants shall assist the tender opening officers in tabulating the details in
the matrix. It should be clarified in the Matrix relating to the priced bid opening
that priced data reflected in the matrix will be as quoted by the bidders and
subject to necessary correction based on detailed scrutiny of the priced bids,
evaluation for loading criteria etc. The Comparative Statement vetted by
Finance will be the basis for taking the decision for placement of purchase
order / award of contract.
52.5 The officers opening the tenders should verify that only bidders /
authorised representatives of bidders who have actually submitted the bids
are present. Unauthorised representatives (or representatives of firms who
have not submitted the bid) should not be allowed to be present.
54.2.1 In the event of re-invitation of bids whether on a limited or open tender basis
the Competent Purchase Authority will obtain in advance the decision of
the Purchase Authority one step higher. In respect of proposals falling
under the purview of Executive Purchase Committee, the decision for re-
tendering will be taken by concerned Director in consultation with
Chairman-cum-Managing Director.
54.2.2 Such re-invitation of bids, on a limited basis, will be from all the bidders
who quoted against the original tender.
54.2.4 Reasons for re-invitation of tenders in all such cases will be recorded.
Sale of bid documents should close at least 3-4 weeks before the date of
opening of bids and both the dates should be specified in the NITs / Bid
Documents.
56.1.1 In the case of equipment, the warranty for a period of 18 months from the
date of shipment or 12 months from the date of commissioning of the
equipment, whichever is earlier, will be obtained.
The Bank Guarantee for warranty period in the case of equipment will not
be necessary. The guarantee for warranty in the case of Turnkey Project
contracts will be essential, insisted upon and failure to comply with this will
be a rejection criteria of the BEC.
(b) It may further be noted that clause (a) above provides for recovery of
liquidated damages (and not by way of penalty) on the cost of contract /
supply order price of delayed supplies (whole unit) at the rate of ½ % (half
percent) of the contract / supply order price of whole unit (1% of total value
of particular item in case of casing pipes) per week for such delay or part
thereof upto a ceiling of 5% of contract / supply order price of delayed
supplies (whole unit) (10% of the value of particular item in case of casing
pipes). Liquidated damages for delay in supplies thus accrued will be
recovered by the paying authorities of the purchaser specified in the
supply order, from the bill for payment of the cost of materials
submitted by the contractor / supplier or his foreign principal in accordance
with the terms of supply order / contract or otherwise.
(c) Notwithstanding anything stated in the clause (a) and (b) above, equipment
and materials will be deemed to have been delivered only when all its
components and parts are also delivered. If certain components are not
delivered in time, the equipment and material will be considered as
delayed until such time all the missing parts are also delivered.
LD will be imposed on the total value of the order unless 75% of the value
ordered is supplied within the stipulated delivery period. Where 75% of
the value ordered has been supplied within stipulated delivery period,
LD will be imposed on the order value of delayed supply(ies). However,
where in judgment of ONGC, the supply of partial quantity does not fulfill
the operating need, LD will be imposed on full value of the supply order.
However, in cases involving supply to multiple consignees/port consignees,
Work Centre to frame a suitable clause for levy of L/D on consignee/port
consignee wise basis. The due dates for supply of each item/quantities on
consignee/ port consignee wise should be specified and LD should be levied
for delay in supplies beyond the dates specified for respective items/
quantities on consignee/port wise value.
(e) Liquidated damages will be calculated on the basis of contract/ supply
order price of services/materials excluding duties and taxes, where such
duties/taxes have been shown separately in contract/supply order.
(a) CONTRACTOR shall mobilize and deploy the required manpower and the
complete equipment so as to commence the services at the specified site (s)
within a maximum of ……….days from the date of Fax order / LOA / NOA
(Work center should specify the period depending upon nature of the
services).
(b) If the CONTRACTOR fails to mobilize and deploy the required manpower /
equipment and / or fails to commence the services within the period specified
in sub clause (a) above, ONGC shall have, without prejudice to any other right
or remedy in the law or contract including sub clause (c) below, the right to
terminate the contract.
(c) If the contractor is unable to mobilize / deploy and commence the services
within the period specified in sub clause (a) above, it may request ONGC for
extension of the time with unconditionally agreeing for levy and recovery of
LD. Upon receipt of such a request, ONGC may at its discretion, extend the
period of mobilization and shall recover from the contractor, as an ascertained
and agreed Liquidated Damages, a sum equivalent to 1/2 % of annual
contract value, for each week of delay or part thereof, subject to a maximum
of 10% of the annual contract value.
(d) The parties agree that the sum specified above is not a penalty but a genuine
pre-estimate of the loss/damage which will be suffered by ONGC on account
of delay on the part of the CONTRACTOR and the said amount will be
payable without proof of actual loss or damage caused by such delay.
(e) LD will be calculated on the basis of annual contract value excluding duties and
taxes, where such duties/taxes have been shown separately in the contract.
LIQUIDATED DAMAGES
The Contractor shall deploy the Drilling Unit at the designated first drilling
location nominated by Operator, anywhere in Indian waters to
commence operation within (180 days in case of Indian parties and 120
days in case of foreign parties for Offshore charter hire services from the
date of issue of unconditional firm telex order but in no case the Drilling Unit
shall be deployed under this contract without completion of the well/wells-in-
progress under ONGC's Contract No............ In the event period of
completion of well/wells-in-progress exceeds such 180 days, (in case of Indian
contractors)/ 120 days (in case of foreign contractors), then the Drilling Unit
shall be deployed after completion of well/wells-in-progress within the time
limit to be specified by Operator. ONGC reserves the right to extend the date
of mobilisation until weather is cleared for deployment of unit to new location,
if mobilisation period of 180/120 days as may be applicable falls between
the monsoon period (from 16th May to 15th October – both days inclusive),
without imposition of any liquidated damages. If the Contractor fails to
deploy the Drilling Unit within aforesaid period, the Operator as its sole
remedy can recover from contractor as ascertained and agreed Liquidated
Damages and not by way of penalty a sum equivalent to 1/2 % of annual
contract value (i.e. Effective Day Rate based on which bids were evaluated x
365 days) for each week of delay or part thereof subject to maximum of
10%. Operator shall have at any time but before Commencement Date, the
right to terminate the Contract in the event Contractor fails to deploy the
Drilling Unit at the first drilling location within aforesaid period, without
prejudice to any other clauses including LD Clause. The parties agree that
this is a genuine pre-estimate of the loss/damage which will be suffered on
account of delay/breach on the part of the contractor and the said amount
will be payable on demand, without there being any proof of the actual loss
or damages caused by such delay/breach.
LD will be calculated on the basis of annual contract value (i.e. Effective Day
Rate based on which bids were evaluated x 365 days) excluding duties and
taxes, where such duties/taxes have been shown separately in the contract.
Time is the essence of the contract. If the Contractor fails to complete the
entire work by the scheduled completion date, ONGC may without prejudice to
any other right or remedy available to it as under the Contract or Law:
AND/OR
ii) Terminate the Contract or a portion or part of the Work thereof. ONGC shall
give 14 days notice to the contractor of its intention to terminate the Contract
and shall so terminate the contract unless during the 14 days notice period,
the Contractor initiates remedial action acceptable to ONGC.
The parties agree that the amount of LD provided herein is a genuine pre-
estimate of the loss/damage which will be suffered on account of delay on the
part of the Contractor and the said amount shall be payable on demand
without there being any proof of the actual loss or damage caused by such
delay/breach.
LD will be calculated on the basis of contract price excluding duties and taxes,
where such duties/taxes have been shown separately in the contract.
The amount towards Liquidated Damages shall become leviable from the
original completion date as per contract or from the expiry of the extension, if
any, given by ONGC without levy of LD. Applicable LD as on date shall be
recovered progressively from balance due payment on pro-rata basis.
ONGC may without prejudice to its right to effect recovery by any other
method, deduct the amount of Liquidated Damages from any money
belonging to the Contractor in its hand (which includes ONGC’s right to claim
such amount against Contractor’s Bank Guarantee) or which may become
due to the Contractor. Any such recovery of Liquidated Damages shall not in
any way relieve the Contractor from any of its obligations to complete the
Works or from any other obligation and liabilities under the Contract.
After final settlement of the issue regarding levy of LD as per the provisions of
the contract, the applicable LD shall be remitted by the Contractor to ONGC,
failing which the amount of LD shall be recovered by invoking the Bank
Guarantee.
i. The price charged for the materials supplied under the contract / supply
order by the contractor / supplier shall in no event exceed the lowest
price at which the supplier / contractor or his agent / principal / dealer, as
the case may be, sells the materials or offer to sell materials of identical
description to any persons / organisations including the purchaser or any
Department of the Central Govt. or any Deptt. of a State Govt. or any
Statutory Undertaking of the Central or State Govt., as the case may be,
during the currency of the contract/supply order.
ii. If any time, during the said period the contractor / supplier or his agent /
principal / dealer, as the case may be, reduces the sale price, sells or offers
to sell such materials to any persons / organisations including the
purchaser or any Deptt. of Central Govt. or any Deptt. of a State Govt. or any
Statutory Undertaking of the Central or State Govt. as the case may be, at a
price lower than the price chargeable under the contract / supply order, he
shall forthwith notify such reduction or sale or offer of sale to the Purchase
Authority who has issued this Supply Order and the price payable under the
Supply Order / Contract for the materials supplied after the date of coming
into force of such reduction or sale or offer of sale shall stand
correspondingly reduced. The above stipulation will however not apply to :
"I/We certify that there has been no reduction in sale price of the materials
of description identical to the materials supplied to the ONGC under the
contract / supply order herein and such materials have not been offered /
sold by me / us to any person / organisation including the purchaser or
any Deptt. of Central Govt. or any Deptt. of a State Govt. or any Statutory
undertaking of the Central or State Govt., as the case may be upto the date
of bill / during the currency of the supply order/contract whichever is later, at a
price lower than the price charged to the ONGC under the contract / supply
order except for quantity of materials categories under sub-clauses (a), (b)
(c) of sub para (ii) above details of which are as follows:-
------------------------------------------
------------------------------------------
------------------------------------------.
The contractor shall not save with the previous consent in writing of the
Purchase Authority sublet, transfer or assign the contract or any part
thereof or interest therein or benefit or advantage thereof in any manner
whatsoever provided nevertheless that any such consent shall not relieve
the contractor from any obligation, duty or responsibility under the
contract.
When contracts are placed at higher rates for the sake of earlier delivery,
the clause as given below, enabling the ONGC to realise compensation for
the extra cost due to delay in supply must be included therein:-
56.8 The following clause will invariably be included in all invitation for bids:-
56.9.1 Before commencing bulk supply, you would forward two sets of samples
supported by two sets of your manufacturing drawings for approval of the
Inspecting Officer. Such an approval by Inspecting Officer may need at least
15 days time, which should be catered for by you within the delivery
schedule. Inspecting Officer would return to you one set of the samples and
one set of your manufacturing drawings duly sealed for your guidance in bulk
supply.
56.9.2 You will make available free of charge all testing facilities in your plant to the
Inspecting Officer to enable him to test the sample and carry out
inspection. You will arrange for any test desired by the Inspecting Officer,
at any other test house / laboratory as approved by the Inspecting Officer,
if facilities for such test are not available in your plant. In the latter case, the
test charges would be reimbursed by the purchaser if the samples are
considered acceptable, whereas if the samples are not found acceptable,
the test charges would be borne by you.
56.10.1 The bulk shall be accepted in accordance with the samples approved.
The Inspector shall be given sufficient notice which shall not be less than 21
working days to plan out the bulk inspection. Percentage would be
arranged by you on the same lines as in case of the pilot samples and
the test charges would be dealt with accordingly.
56.10.3 The materials rejected by the Inspection Officer during this inspection will
be replaced by you immediately, latest within two weeks of such rejection.
Any rejection by Inspecting Officer shall be considered final and binding on
you.
56.12.1 For indigenous contracts upto Rs.1.00 crore `Sole Arbitration' clause will be
applicable.
56.12.2 For indigenous contracts exceeding Rs.1.00 crores and for all Foreign
Contracts "Two Arbitrators and One Umpire" clause will be applicable.
56.12.3 For Public Sectors, the arbitration clause as per Govt.'s directives will
apply.
56.16.1 When the materials are dispatched to the consignee, intimation must also
be given to this effect to the purchasing authority and also to the consignee.
Reference to the supply order should invariably be given in all relevant
correspondence.
56.16.2 The Bid is liable to be rejected in case the Bidder does not comply with
the tender stipulations or the goods offered do not conform to the
required specifications indicated therein.
56.16.3 Any other terms and conditions, offered by the firm and not included in
this supply order, are not acceptable to the ONGC.
EARNEST MONEY / SECURITY DEPOSIT
57. EARNEST MONEY (BID BOND / BID SECURITY) AND SECURITY
DEPOSIT (PERFORMANCE BOND / CONTRACT SECURITY)
57.1.1 Against each tender, subject to the proviso as given in para 57.1.2, the
Earnest Money / Bid Bond / Bid Security is to be obtained so that the
Bidder does not withdraw his offer within the validity period thereby
causing inconvenience to the department. It will be made clear in the
Bidding document that earnest money / bid bond / bid security of those
bidders who withdraw their bids during validity of offer, will be forfeited.
57.1.2 Fixed amount of earnest money / bid bond / bid security, will be worked out
on the basis of expenditure sanction for complete tender as well as unit-wise
group-wise expenditure sanction and indicated in Bidding document for
submission by the bidders.
57.1.3 When the Bids are invited on quantity basis like weight in respect of
chemicals, the EMD / Bid Bond / Bid Security will be indicated for 25%,
50%, 75% and 100% quantity.
The amount of EMD / Bid Bond / Bid Security for complete tender and
unit(s)/group of items(s)/quantity will be worked out on following slab basis for
indicating the same in bidding document of the same in bidding document for
obtaining of the same from bidders:
However, the maximum limit of EMD/Bid Bond/Bid Security for a tender shall be US$
0.5 million for foreign bidders and Rs 2 crores for Indian bidders.
(MM/56/2010 dated 11.10.2010)
57.1.5 The bidders should offer full quantities of goods or Services for each of the
tendered item or category or group wherein the item or category or group is to be
evaluated separately.
Bidders can however quote for part quantity , if this condition is incorporated in the
BEC with the approval of CPA.
In case the bidders are allowed to quote for part quantity, the bidders can send EMD/
Bid Security according to the quantity offered (not exceeding the EMD / Bid Bond /
Bid Security specified for entire tender). In such event, the amount of EMD/Bid Bond
for part quantity must be indicated in Bid Evaluation Criteria.
No earnest money / bid bond / bid security in the form of Bank Draft or in lieu thereof
Bid Bond will be necessary for purchases upto Rs. 5.00 lakhs. Earnest money /
bid bond / bid security in the form of Bank Draft or in lieu thereof Bid Bond will also
not be necessary for purchases from Central Govt. Departments and Central Public
Sector Undertakings and for buys of spares or stores / capital items /
equipment of proprietary nature from Original Equipment Manufacturers / Authorised
Dealers/Distributors/ Stockists of Original Equipment Manufacturers. No earnest
money shall also be necessary for purchase / service contracts on nomination basis.
The firms registered with ONGC will also be exempted from payment of earnest
money / bid security or in lieu thereof for furnishing of bid bond for buys against
limited tenders provided normal tendering procedure is adopted. In Registration
Certificate also it will be made clear that the facility for exemption from payment of
earnest money / furnishing of bid bond / bid security will be available in normal
limited tenders only in case purchase is against normal tendering procedure.
MSEs registered with District Industry Centers or Khadi and Village Industries
Commission or Khadi and Village Industries Board or Coir Board or National Small
Industries Corporation or Directorate of Handicrafts and Handloom or any other body
specified by Ministry of MSME will be exempted from furnishing bid bond / bid
security / earnest money against open and limited tenders irrespective of monetary
limit mentioned in their registration certificate provided they submit evidence that
they are registered for the item(s) they intend to quote.
EMD / Bid Security can be obtained from bidders in any one of the following
modes:
(i) Bank Draft in favour of ONGC valid for 180 days from the date of issue
of the same.
(ii) Bank Guarantee from banks acceptable to ONGC, valid for 30 days
beyond the required validity of bid.
(iii)
Irrevocable letter of credit (as per prescribed proforma) valid for 30
days beyond the required validity of bid, duly confirmed by Indian
Nationalised / Scheduled banks will be acceptable only from foreign
bidders.
(iv) Cashier’s / Banker cheques valid for 180 days from the date of issue of
the same will be acceptable form foreign bidders only.
(MM/56/2010 dated 11.10.2010)
57.1.7 Subject to provision in para 57.1.5 above, offers without earnest money /
bid bond / bid security will not be considered and summarily rejected. The
condition of furnishing earnest money / bid bond / bid security will not be
relaxed / waived and it would be preferable to go for a re-tender.
For relaxation of condition relating to Bid Security, prior to invitation of bid, the
cases (where exigencies of work so require) are to be put up to concerned
Level-1 Executive upto his purchase powers. Concerned Director has full
powers in this regard.
(ii) All type of service / Rig 10% of one year's contract value. (for rig
hiring contracts. hiring contracts one year’s contract value
shall be the Effective Day Rate based on
which bids were evaluated x 365 days).
In case of contracts with primary term of
two or three years, the Performance Bank
Guarantee / Contract Security will be
obtained with initial validity for two or
three years as the case may be.
57.2.3 In case the firms give their security deposit / contract security /
Performance Security in the form of Bank Guarantee, it will be ensured that
only Bank Guarantee given by any of the Nationalized Bank or Scheduled
Bank or State Bank of India and its wholly owned subsidiaries are
accepted. In case of import purchase, Bank Guarantee from a Bank
acceptable to ONGC will be required.
57.2.4 For offers with shortfall in EMD/bid bond amount, an opportunity can be given
to the bidder to submit additional bid security/bond or amendment in the bid
bond for meeting the shortfall in the bid security amount. This opportunity can
be given to the bidders with the approval of L1, who will have full powers in
this regard.
57.4.1 All concerned authorities shall ensure that details of all claims which are to
be recovered from the supplier / contractor are promptly intimated to the
respective payment authority, without any loss of time, so that the claim can
be recovered before releasing the pending payment(s).
Details of such claims should also be forwarded to the authority who has
concluded the respective purchase order / contract / rate contract and has
obtained the Contract Security. After completion of the supplies / execution
of the contract, the respective authorities as mentioned below should take
prompt actions in respect of the following:
(i) In case of purchase of goods, for recovery of any claims other than
discrepancies / recoveries indicated in the GRV, the respective
consignee(s) [including port consignee / C&F section etc.] should
forward the details of claims which are to be recovered from the
supplier, to the respective purchase officer, immediately after
completion of supplies against the purchase order, i.e. within 15 days
after receipt of last lot of material. Even if there is no claim against a
particular purchase order, the consignee(s) should forward a ‘No
Demand Certificate’ to the respective purchase officer within the
stipulated time as above.
(iii) In case of centrally finalized rate contracts, for which the Contract
Security is obtained centrally for the entire contract, In- charge MM of
each work center should forward details of Purchase Orders placed
against each of such rate contracts to the authority which has
concluded the rate contract. Further, in respect of each such order
which has been placed against the rate contract, In- charge MM of the
work center shall send the details of outstanding claims (if any) or a ‘No
Demand Certificate’, to the authority who has concluded the rate
contract within 15 days after receipt of the last lot of material.
In all cases, wherever the claims are to be recovered from the Contract
Security, it should be ensured that the claims with complete details are
forwarded to the concerned aurhority(ies) well before the expiry of the validity
of Performance Bond.
Under exceptional circumstances, in case where above details can not be
furnished within the stipulated time, approval of concerned L1 executive
should be obtained by the respective authority(ies) (i.e. Consignee/In-charge
MM / Indentor, as the case may be) giving full reasons necessitating
additional time for furnishing ‘No Demand Certificate’. Such approval should
be forwarded to the concerned purchase officer / contract concluding authority
for obtaining suitable extension for the validity of Performance Bond.
57.4.2 On receipt of intimation regarding claims for recovery (if any) / ‘No Demand
Certificate’, as per para 57.4.1 above, the concerned purchase officer /
contract concluding authority shall verify whether the claims have already
been recovered from the payments. After release of final payments, if any
claims are outstanding for recovery, necessary action should be initiated to
recover the same from the Contract Security.
Thereafter, for the release of Contract Security (after recovering the claims if
any as mentioned above), the approval shall be obtained as per para 57.5
below. Accordingly, necessary advice shall be issued to the concerned
Finance section for releasing the Security Deposit / Performance Bond.
The Competent Purchase Authority (who has approved award of contract) will
have powers to approve release of earnest money / Bid Bond / bid security
/ security deposit / contract security performance bank guarantee.
However, concerned L-1 Executive will have full powers in this regard,
irrespective of the type of tender or value of tender / order / contract, including
for cases falling within the powers of Directors and EPC.
Approval of Level-1 executive will be obtained for invoking / forfeiting the Bid
Security / Contract Security / Bank Guarantee(s) for non-EPC cases. For
EPC level cases, approval of concerned Director shall be obtained.
Provisions at para 58.1, 58.1.1, 58.1.2, 58.1.3, 58.2, 58.2.1, 58.2.1, 58.2.1.2,
58.2.1.3, 58.2.1.4 and 58.2.5 deleted vide MM Manual amendment No.
MM/61/2011 dated 14.06.2011. Remaining paras re-numbered.
Domestic bidders providing oil field services in the global tenders will be
entitled to a price preference of 10% over the lowest acceptable (quoted)
foreign bid.
58.1.2 The above Price Preference would be used for the purpose of evaluation of
bids only and the order on the Indian party will be placed on the basis of
quoted price if the same happens to be upto or lower than the limit of price
preference.
58.2 In the case of purchases / services under World Bank financing, price
preference, as per guidelines issued by the World Bank, will apply.
58.4 Purchase of ‘Lead Acid Batteries’ with provision for ‘buy-back’ of the
used batteries by the supplier.
58.4.1 As per ‘The Batteries (Management and Handling) Rules, 2001’, consumers
of lead acid batteries are required to dispose the used batteries, only through
depositing with the dealer/ manufacturer/ importer/ assembler/ registered
recycler/ re-conditioner of the lead acid batteries or at the designated
collection centres. Likewise, it is obligatory on the part of the manufacturer /
dealer of the lead acid batteries to collect the used batteries from the
consumer.
58.4.2 Accordingly, following procedure shall be adopted while procuring new ‘lead
acid batteries’, for replacing the condemned, used and unserviceable
batteries of similar type and specifications:
(ii) Evaluation of offers for new batteries will be carried out based on “Net cost’
for each battery, arrived at as under:
‘Net cost’ for each battery = (cost of each new battery + all taxes and duties)
– (value offered for each used battery)
(iii) Even for the order placed against DGS&D rate contracts, the concerned
vendor should be insisted to submit his offer for buy-back of used batteries.
(iv) Accordingly, the purchase order for new batteries shall be placed, by
indicating the ‘Net Amount’ payable after deducting the value offered for used
batteries. Further, for the purpose of accounting and discharging Tax
liabilities, a separate ‘Sale Letter’ shall be issued for the used batteries (by the
same authority who issued Purchase Order for new batteries), by keeping
provisions for adjusting the deducted amount against the supplies (of new
batteries) as the value for the used batteries.
(v) On receipt of new batteries and adjustment of value for used batteries (in
the payment), concerned Purchase Officer shall issue a ‘Delivery Order’
(addressed to indentor, with copies endorsed to Vendor and the concerned
sections - viz. Finance, Disposal and Security), so that vendor can collect the
used batteries from the locations.
(vi) Accordingly, indentor shall hand over used batteries to the vendor against
proper receipt and Gate Pass (issued on the authority of the Delivery Order).
(vii) Indentor shall forward copies of receipt obtained from the vendor to
Finance and Disposal section for regularization of the sales proceeds and
also for inclusion in the returns to be filed with Sales Tax authorities.
COMPARATIVE STATEMENT
59. Comparative Statement
59.1 After all the quotations have been opened, these will be handed over to
the section concerned for making comparative statement.
59.3 Every section will ensure that the comparative statement is prepared
within shortest possible time, not exceeding 04 days of the receipt of the
quotations after techno-commercial bid opening and not exceeding 03 days
after price bid opening.
59.4 The local Bids which are received after the due date and hour are not to be
considered. Similarly, all quotations dispatched by the outside Bidders
after the due dates are also not to be considered. These will not be
entered in the comparative Statement.
59.5 The comparative statement will be prepared and signed by the concerned
Store Keeper / Dealing Asstt ./ Dealing Officer.
59.7 The comparative statement will be checked and signed by the officer of
Materials Management as per monetary limits indicated below before the
same is submitted with details / due recommendations to Tender Committee
/ Competent Purchase Authority:
Monetary Value Officers
59.9 All comparative statements for tenders exceeding the value of Rs.50,000/-
will be referred to Finance for scrutiny. The monetary limits of different
levels of Finance and Accounts Officers for checking the comparative
statement will be as under:
59.11 The comparative statement will be checked by the associated Finance. The
comparative statement will invariably be vetted within shortest possible time,
not exceeding 04 days of its receipt in Finance. Each page of the
comparative statement will be initialled by both the Materials Management
Officer and the Finance & Accounts Officer as per above Monetary limits.
59.12 The vetting of the comparative statement by Finance will, however, not
absolve the Department originally preparing the comparative statement
from the responsibility.
59.13 In the cases where Tender Committee is required to be held, a copy of the
Comparative Statement should be made available to the members of the
Tender Committee at least 48 hours before the first meeting of the committee
alongwith a covering docket containing the following information:
60.1.2 At the techno-commercial bid evaluation stage (under two bid system) also,
post tender clarifications should be avoided, as far as possible. In case
implied clarifications / confirmations exist in the bid on the issues involved,
work center may consider processing of the bid further on the basis of such
implied confirmations.
60.1.2.1 In OEM/OEC cases, bidder can be asked to withdraw the exceptions and
deviations taken by them to ONGC’s standard terms and conditions by the
dealing officer in MM after obtaining the approval of I/c MM directly without
holding TC.
60.1.3 With a view to widen competition in the tender, decision would need to be
taken on case to case basis as to whether one more round of clarifications
need to be sought from the bidders. In that case, TC will deliberate specifically
on the issues requiring second round of clarifications/ confirmations/ deficient
documents and submit their recommendations to CPA for approval for asking
the bidders to submit clarifications/ confirmations/deficient documents after
recording proper justification for the same. However, concerned Key
Executive (Level I-A/B/C/D/E/F) shall have full powers to approve seeking of
upto two rounds of clarifications / confirmations / deficient documents,
including in cases falling within the powers of Directors and EPC.
61.1 Before finalisation of the tender, all correspondence with the bidders must be
done by concerned Materials Management. However, after placing supply
order / contract, if considered necessary, the indentor(s) may interact with
supplier(s) / contractor(s) for any clarification provided the same does not
result into modification of any condition of supply order / contract and does
not involve financial implications. However, copy of such correspondence
must be marked to MM Department for record.
61.2 It must be ensured that clarifications asked for by the Indentor(s) did not
have any bearing on the price aspect.
62.1 In all cases where technical evaluation is involved, the offers shall be
referred to the indentor and its comments put up to tender committee.
62.2 7 (Seven) days time will be allowed to Indentor / User to furnish the Technical
Comments. It will be ensured by the User Deptt. that comments are invariably
furnished within specified time. Indentor / User will be fully responsible for the
acceptability of the materials recommended for purchase. If their
recommendations are at variance with the specifications laid down in the
bidding document, they will clearly specify and indicate the difference and
acceptability.
62.4.1 In case of purchase of general nature of items such as bulbs, tubes and
stationery, technical comments will not be necessary. In other cases,
technical scrutiny and evaluation of offers will be done and comments
thereon made at the level at which the tender committee in the case is to
be held.
TENDER COMMITTEE
(MM/56/2010 dated 11.10.2010)
63.1 No Tender Committee will be held for cases valuing upto Rs 5.00 Lakhs. All
procurement cases (including finalization of Rate Contracts), valuing above Rs.
5.00 Lakhs, will be referred to Tender Committee. However, TC is not required
for placement of individual orders against DGS&D and ONGC rate contracts.
TC is also required to be held for carrying out price negotiations with bidders in
all cases, irrespective of the value of the case.
a) Single item
One capital item (other than furniture) and or its assemblies and
components or stores like barytes, bentonite, cutch, CMC, Mica etc.
are single items, although they form a group of stores e.g. mud
chemicals. Similarly, shoes and chappals are two single items.
Furniture, spares for one type of vehicle etc. e.g. jeep spares and
TMB spares are two group of items.
The following levels of MM & Finance officers and indenting Deptt. shall form part
of the Tender Committees:
Note:
(i) # Second level officer in MM and Finance as designated at the work center
(ii) The level of TC and CPA will be with reference to sanction value or tender value
whichever is higher. However, after opening the price bids, if the evaluated price
of lowest bid / bids is higher than the tender value and the tender accepting
power is not within the power of original CPA, then the CPA and TC level will be
raised to appropriate higher level.
(iii) If the required level of TC member is not posted/ not in station (on leave/tour) at
a work centre then the TC member will be of the next lower level available and
/or as nominated by the Tender accepting authority. Level–I shall have full
powers in such cases.
(iv) In case of turnkey projects wherever indentor is not end user and requirement is
for use within the work centre then end user will also be a member of tender
committee.
(vi) For all other items/services also, TC will continue to have only three members.
Wherever Indenting department and User department(s) are different,
depending on technical complexity of the item/service being procured, Indenting
Department can co-opt for having a representative from User department also in
the TC.
(vii) For OEM/OES/PAC/ cases where tender value is upto 5% / 1% of the open
tender acceptance powers of Level-1 executive as per BDP item MP4 (a), TC
shall be held at the level of 2nd level MM Officer / MM Officer E-4 level
respectively as stated at Sl. No. 2/ Sl. No. 3 above. In such cases, TC
recommendations shall be put upto CPA (Level-1 executive) for approval
through I/c MM.
66.2 Tender Committees should invariably be held when the same is scheduled. In
case any of the TC members proceeds on leave / tour, he may authorize in writing
the next subordinate senior most officer available in station to attend the TC
meetings during his absence and to sign the TC proceedings.
66.3 The concerned dealing officer will prepare brief for perusal of all members of
Tender Committee wherein complete details of case will be brought out.
Such a brief, duly signed, will be given to members of Tender Committee
well in advance of the meeting. This will, however, in no way, dilute the
responsibilities of the tender committee.
67.1 Tender Committee will examine the bids to prepare its recommendations for
submission to the authority competent to accept the tender. Where a higher
bid is recommended, under exceptional circumstances adequate reasons in
support of recommendation will be recorded.
67.2 It will be ensured by all TC members that Tender Committee proceedings are
signed immediately on completion of the meeting, not exceeding 3 days from
the date of the meeting.
(ii) In EPC level cases, approval of EPC will be required on the BEC to be
followed for tender except in cases wherein earlier EPC approved BEC is
proposed to be adopted for which purpose the approval of concerned Director
will be obtained. (Provisions of para 24 of this Manual refers in this regard]
(iii) In all cases exceeding powers of Director, after price evaluation of short-listed
bidders, purchase approval of Executive Procurement Committee (EPC) will
be obtained, after endorsement by Director – in charge.
69.2 It will be ensured by concerned work centre that all procedural aspects have
been taken care of before submitting cases to Executive Procurement
Committee.
(MM/8/2003 dated 02.04.03)
70.1 The Executive Procurement Committee Cell will circulate amongst EPC
members a copy of agenda brief and after discussions of the case in the
meeting, will prepare draft record note of the Executive Procurement
Committee meeting (within 3 working days if summary is not to be prepared
and 5 working days if summary is to be prepared) and circulate the same
through Chief-CP to all the EPC members for their comments. Comments if
any, are to be given by EPC Members on the draft Record Note to the EPC
Cell within two working days. The draft Record Note will be modified by EPC
cell based on the comments received from EPC members and thereafter, the
final draft will be submitted to C&MD for approval through the concerned
Director. Upon approval of the Record Note by C&MD, EPC cell will forward
the approved Record Note to all the EPC members and also to the concerned
work centre for taking further action. However, the present practice of issue
of the summary of EPC decision with the approval of concerned Director, will
remain unaltered, but summary would be issued in respect of urgent cases
only based on the discussions in EPC meeting.
In case of urgency, EPC meeting can be held in the absence of C&MD who
would authorize the senior most Director (other than the Director concerned
whose proposal is under consideration) to Chair the meeting in his absence.
The Draft Record notes will be put up to the Director who chaired the EPC
meeting for his consideration and approval. However, the Record Note of
discussion of such EPC meeting(s) will be put up to C&MD for information.
Similarly, in case Director concerned is unable to attend the EPC meeting, he
may request another functional Director to represent him in the EPC meeting
for the case.
71.1 The following points should be taken into consideration for placement of
an order:-
ii. If the lowest Bidder does not comply with the tender stipulation, his
bids should be rejected.
73.2 However, for regularly procured equipment where requirement of fast moving
/ critical spares is considered necessary for one or two years operation of the
plant and equipment and the same can be estimated based on the past
experience, the list of such critical spares with quantity should be included in
the tenders and the cost of only those spares should be considered for
evaluation purpose alongwith the main plant and equipment. In such cases it
should be made clear to the bidders that they should quote the prices for
each item of the spares separately.
LATE TENDERS
74. LATE TENDERS
74.1 All bids received after the notified time and date of closing of tenders will
be treated as late tenders.
74.3 Late tenders, as defined in para 74.1 above, shall not be considered. Such late
tenders, after recording with the concerned Materials Management officer, will
be returned un-opened to the concerned bidder(s) within a period of seven days
from the due date of opening of tenders.
75.1 While tenders are generally considered on an itemwise basis and the
practice is to split these items where necessary and award the contract to the
lowest acceptable bidder on an itemised basis, it is not necessary to split up
where the monetary gain in splitting the of contract is less than Rs.150/-.
The Materials Management Officer acting within his power, will have the
authority to award contract on an overall basis for all items or by grouping
items, provided that the total price paid as a result of doing so does not
exceed by more than Rs.150/- the total price that would have been paid had
the contract been awarded on an itemised basis.
75.2 Items in a tender may be split up in more than one order depending on the
merit of each case. In case of operational needs, tender for part of items
may be finalised with the approval of Competent Purchase Authority for
complete tender. For finalisation of tender for the remaining items, the case
will be submitted to the Competent Purchase Authority for complete tender
reflecting therein the facts that tender for part items in this case has already
been finalised.
76.1 In Limited Tenders which are not published on website (i.e. LTs upto Rs. 5
lakhs), minimum three techno-commercially acceptable quotations must be
available before the tender is finalized. However, if less than three quotations
are received in a case of such limited tender, then the case should be put up to
the authority one level higher than the CPA for further decision.
If after inviting open / limited tenders (including the tenders mentioned in para
76.1 above), only one quotation is received against the tender, the order
should be placed on the bidder provided the rates are considered reasonable or if the
requirement is urgent.
76.4.1 Tender Committee shall be required to establish and certify the reasonability
of rates of L-1 bidder received in a tender. Rate reasonability can be
established in comparison to cost estimates and / or last purchase rate (if
available) and / or price trends prevailing in the market (if the same can be
determined depending on either the type of items being purchased or if there is
any published documents / data reflecting the price trends or if there is
relationship between raw material being used in manufacture of items like steel
is used for manufacture of tubular goods). (When purchase does not fall under
purview of tender committee, dealing officer of MM in consultation with
Indentor and Finance shall ascertain the rate reasonability and put up the
proposals for approval of CPA). Accordingly, the case shall be processed for
finalisation, if the rates of L-1 bidder are considered to be reasonable on the
basis of above analysis. Wherever the rates of L-I bidder are substantially high
as compared to cost estimates / or LPR or not in line with the price trend
prevailing in the market, a decision shall be taken as to whether price
negotiation need to be conducted.
76.4.2(a) In OEM/OES cases, budgetary offers need not be considered as basis for
working out cost estimates. Instead, Last Purchase Rate (LPR) of the same
item or similar item with suitable escalation, to take care of increase in cost
from the date of last purchase, may be considered as basis for working out
reasonable cost estimates. Option of taking budgetary quote from the original
equipment manufacturer/supplier may be resorted to only in situations where
LPR is not available and no other reasonable basis is available for working out
cost estimate.
76.4.3 For price negotiations procedure specified vide para 77 will be adhered to.
NEGOTIATIONS
77. NEGOTIATIONS
77.1 There should not be any Price negotiations. Negotiations, if at all, shall be an
exception as provided herein below and shall be held with L-1 bidder only.
77.3 Negotiations should not be misused as a tool for bargaining with L-1 with
dubious intentions or lead to delays in decision-making. Convincing reasons must be
recorded by the Tender Committee recommending negotiations. Competent
Purchase Authority should exercise due diligence while accepting a tender or
ordering negotiations or calling for a re-tender and the time taken for according
requisite approvals for the entire process of negotiation and award of order should
not exceed 30 days from the date of submission of recommendations. In cases
where the proposal is to be approved at EPC level, a maximum of additional 15 days
shall be allowed. In no case should the overall timeframe exceed the validity period
of the tender and it should be ensured that tenders are invariably finalised within
their validity period.
77.5 Where it is required to have more than one source of supply (due to critical or
vital nature of the item), it is mandatory to pre-disclose the ratio of splitting the supply
(in accordance with prevailing instructions, so as to award maximum quantity to the
L-1 bidder) in the Bid Evaluation Criteria, after due deliberation in Tender Committee.
This must be followed scrupulously.
77.6 After due processing, if it is discovered that the quantity to be ordered is far
more than what L-1 alone is capable of supplying (in tenders where bidders are
allowed to quote part quantities) and there was no prior decision to split the
quantities, then the quantity being finally ordered should be distributed among the
other bidders in a manner that is fair, transparent and equitable as given below:
(i) If the requirement of tender quantity cannot be met by L-1 bidder, negotiations
will be carried out with the approval of Competent Purchase Authority (CPA). To
expedite the process of negotiations, all other acceptable bidders will be advised to
submit their confirmations in sealed envelopes, to match their rates with those of
evaluated L-1 bidder.
(ii) Sealed covers will be opened in the order of ranking originally established and
in the presence of bidders’ representatives who choose to be present. Bidders who
match their prices with the L-1 bidder would be considered for award on basis of
their original ranking and to the extent of quantity / number offered by them.
Opening of sealed cover will be stopped when the total quantity requirement is met.
77.8 If L-1 bidder backs out, there should be re-tendering in a transparent and fair
manner. The Competent Purchase Authority may in such a situation call for Limited
or Short Notice tender, if so justified in the interest of work, on the basis of
examination and recommendation by Tender Committee.
77.9 For the cases valuing upto Rs 5 lacs also, convening of tender committee is
necessary for recommending and conducting negotiations. The Tender Committee
in such cases shall consist of one officer each from MM, Finance and Indentor at one
level below Competent Purchase Authority. The recommendations of said Tender
Committee shall require the approval of Competent Purchase Authority.
(ii) Pre-Qualification Criteria (PQC) for Level-II- For tenders valuing between
Limited Tender and the list of bidders Rs. 5 lakhs to Rs. 25 lakhs.
who meet the PQC.
Level-I – For tenders valuing
between Rs. 25 lakhs to their
purchase powers under MP-4(b).
Note: Any proposed provisions, which are in conflict with the existing policy/
procedure/ PMC instructions, will require approval of EPC..
78.2 The Head of Materials Management of concerned Business Group and the
other Materials Management Officers are classified as Indenting Officers
for the recoupment of stock items provided the minima, re-order and maxima
limits have been fixed by duly constituted board.
(MM/56/2010 dated 11.10.2010)
Accept a tender for the procurement of goods (single item or a group of items as
defined in para 64 of MM Manual) / Services / turnkey projects contracts and offer is
technically and commercially accepted:
78.3 (f) Acceptance of offer other than lowest technically acceptable offer
(where Tender Committee is not held)
For tenders of value of less than Rs. 5 lakhs purchase shall be finalised with
concurrence of Finance if the lowest technically acceptable offer is not
operated. (MM/8/2003 dated 02.04.03)
(i)Ocean, River, Railway, Road and Air (where Air is cheaper or more suitable than
alternative modes)
Note: Above powers ((i) & (ii) above) appearing under RL2 of BDP-2009 (powers for
Logistics) can be exercised by MM section also.
Level-III (not below E-5) Upto Rs. 5,000 for each case
Notes:
1. Above powers appearing under RL5 of BDP-2009 (powers for Logistics) can be
exercised by MM section also.
Signing and placement of supply order for stores, spares and capital items and for
signing contracts.
Note:
85.1 The purchase powers are exercisable only if the purchase is effected
subject to the observance of normal procedure for open / limited tenders.
No tender need be invited when purchase is made against a Rate
Contract of DGS&D.
85.2 If in any case it is considered desirable to invite tenders from a few selected
firms, the prescribed procedure will be followed.
86.1 All contracts should normally be entered into on the standard form
prescribed for making purchases for the ONGC except where existing
clauses are to be modified or special clauses added for compliance by the
suppliers.
89.1 Marginal adjustment upto 5% of the quantity indented may be made by the
Materials Management officer without reference to indentor or finance, to fit
the supply order within the pack units offered by trade provided the
increase in cost is not more than Rs. 1000/=.
89.2 Where no adjustments are to be permitted, the indentor will clearly indicate
that only indented quantity and nothing more or less is to be purchased.
90.1.1 After the decision has been taken to place order / contract on a particular
firm, necessary LOA/NOA will be placed on the firm immediately. In EPC
level cases, LOA/NOA is to be issued on the same day or latest by the next
day of receipt of decisions of EPC meeting.
90.1.2 For purchases upto Rs. 5.00 lakh in each case, the purchase order will be
placed on STR-40. No covering supply order need be issued for petty
purchases of consumable items upto Rs 10,000/-.
90.1.3 For purchases exceeding Rs.5.00 lakh the following information / clauses
must invariably be incorporated in the supply order:-
ii) Consignee
v) Despatch instructions
vi) Packing
a) By the
b) During the year.
xvi) Terms and conditions of the supply order (to be enclosed separately
as annexure to the order).
Sl. ONGC Description of makers Unit of Ordered Ordered Value Delivery date
No Material items with full Pt. No./ measure quantity rate
Code specifications Drg. Ref. s CIF/FOB
No. FOR etc.
1. 2. 3. 4. 5. 6. 7. 8. 9.
In figures_____________________________
In words _____________________________
SIGNATURE _____________________
Name ____________________
Designation _____________________
1. 2. 3. 4. 5 6. 7. 8. 9. 10.
Code for CL EM
computer
purpose only
for Example 40 20 20 - 10 10 - - 50
Signature ________________
Name ________________
Designation _______________
Vendor Extra Code Charges Amount Covering Code for L.C. Code for
Code No. details against indent condition 252 supply
No. each extra Nos. (251) col.77 order
charges condition
code 252 Col.
78
............. .................... .................. ................. .................
...................... .................
............. .................... .................. ................. .................
...................... .................
.. .... .... .... ....
.... ..
Expected Currency Exchange Advance Section Order
date of (254) Rate (254) (254) No. (254)
payment
(252)
(Col.49to50) (Col.51to58) (Col.59to70) (Col.71to80)
Amount Date
1. Payment ____________ ____________
Signature____________
Name ______________
Designation__________
90.1.4 It should be ensured that all items of supply orders bear a continuous
numerical Sl.No. and in no case alpha numeric numbers as 1(a)/(b) are
used. In case of annexures to supply orders also continuous Sl.Nos.
should be maintained and fresh Sl.Nos. for each annexure should not be
used.
Competent Purchase Authority for cases upto their purchase powers and
CMD for Executive Procurement Committee cases will have full powers to
cancel the contract / supply order in the event(s) indicated in sub-paras (i) to
(iv) below. Provisions of paras 56.2 and 88 on Liquidated Damages / Failure
and Termination and acceptance of materials in deviation to specified
specifications respectively will be kept in view while exercising powers in
respect of sub-paras (i) and (ii) below:-
ii. Laid down specifications are not adhered to or when the performance
of the contract is un-satisfactory.
iv. Insolvency.
ii. Consignee
x. EDP Section
After the supply order is issued, the Purchase Authority concerned will follow
up the order so that supply is received in time.
Except the following type of services / works, all the services or works
contracts such as charter hiring of vessels, Helicopters, Heli Rigs, Seismic
/ Geophysical Survey, etc will be handled through Materials Management:
(i) Catering, house keeping and other general services for value upto Rs.10
Lakh in each case,
(ii) Empanelment of hotels
(iii) Empanelment of hospitals / Doctors.
(iv) Land acquisition.
(v) Empanelment of advocates.
(vi) Hiring of goods and passenger transport upto Rs.10 Lakh in each case.
(vii) Contract services including AMCs, Grass Cutting etc., upto Rs.10 Lakh in
each case.
(viii) Works as defined in works manual below Rs. 100 Lakh.
(ix) Electrical works pertaining to building construction and all civil works
irrespective of value.
(x) Repairs / AMC from OEM / OES up to Rs. 10 Lakh in each case.
(xi) Any specialized job like consultancy, appointment of auditors, certification
agencies, etc up to Rs 25 Lakh in each case.
94.1 While granting extension in delivery date in terms of para 94.3, the
following points should be taken into consideration:
ii. If the contract has been entered into at higher prices because of the
assurance of earlier delivery, but the supplier has failed to deliver the
goods within the agreed schedule, in such cases the amount paid by
way of such price preference should be recovered from the supplier.
iv. All extensions are to be granted subject to the right of ONGC to claim a
reduction in prices on account of reduction in statutory duties/taxes etc.
which may take place during the extended period of delivery.
However, increase in prices during extended delivery period on
account of increase in statutory duties/taxes etc. admissible under
change in law clause shall be granted, only if extension is due to delay
on the part of ONGC.
v. Provision deleted.
94.2 When it is decided to extend the delivery period subject to the recovery of
liquidated damages for delay in supplies, contractor must be warned in
writing. Merely stating that extension is granted without prejudice to the rights
of purchaser under the terms and conditions of contract, is not enough.
(i) In cases where the delivery/work is not likely to be completed within the
contracted schedule and cancellation/termination of contract is not contemplated,
the time of delivery/completion should be suitably extended as per instructions given
hereunder, before the expiry date of mobilization/delivery/completion, in order that
the contract shall continue to be in force and the contractor remains liable to
execute the contract.
(ii) Any extension due to entire delay being solely on account of contractor /
supplier will be decided by CPA, on recommendation by the indentor and MM. This
extension will be with levy of LD as per the terms of contract, provided the indentor
confirms continued existence of the requirement. No tender committee is required in
this case. No financial concurrence is required. Normally, such extension will be
communicated to the contractor in the format given at Annexure-A-1. For cases
falling under the powers of EPC such extension can be granted with the approval of
concerned Director.
(iii) Any extension, where delay either in part or full may be on account of ONGC,
will be granted by the Competent Purchase Authority, on recommendation by the
Indentor and MM, with ONGC reserving right to levy LD, provided the indentor
confirms continued existence of the requirement. No tender committee is required
for such decision. No financial concurrence is required. Normally, such extension
will be communicated to the contractor in the format given at Annexure-A-2. For
cases falling under the powers of EPC, such extension can be granted with prior
approval of concerned Director.
The amount of LD shall be withheld on the proportionate basis, by finance, from the
bills of supplier/contractor, while releasing payments.
94.4.1 In LSTK projects where delay is solely attributable to ONGC, the reasons for
delay should be jointly recorded in writing by the designated Project Coordinator
from ONGC and authorized representative of Contractor. Under such circumstances,
Competent Purchase Authority (CPA) may grant extension of completion period to
the extent of such delay is attributable to ONGC, without imposing liquidated
damages. In cases where EPC is CPA, Director concerned may approve such
proposal.
95.1 The Competent Purchase Authority will have powers to grant extension in
delivery period upto one year of the expiry of initial delivery period.
95.2 Depending upon merits of the case, any extension in delivery period beyond
one year of the expiry of initial delivery period will be granted with approval of
Competent Purchase Authority not below the concerned Director.
iii. Time lost due to delay on the part of ONGC will be taken into consideration
and stipulated delivery period extended correspondingly.
L.D. will be imposed on the total value of the order unless 75% of the
value ordered is supplied within the stipulated delivery period. Where
75% of the value ordered has been supplied within stipulated delivery
period, LD will be imposed on the cost of contract price of delayed supplies.
However, where, in the judgement of ONGC, the supply of partial quantity
does not fulfill the operating need, LD will be imposed on full value of the
supply order.
In case where company (ONGC) takes over certain facilities for the
envisaged objectives, which can be commissioned and can function
independently irrespective of the availability of balance work of the project,
ONGC may issue part completion certificate by taking over such facilities
without imposing LD. Where such facilities can not be commissioned and
can not function independently, LD in that event will be levied on full value
of the project.
99.1 Schedule for placing indent / purchase orders for chemicals and
handling thereo.
99.1.1 User/Indentor shall forward the indent alongwith expenditure sanction and
PR for purchase of chemicals to the Materials Management Deptt. by 30th
June for the requirements of the subsequent year. Indents should be
accompanied with the Corporate specifications of chemical(s) including
packing and marking details which have been duly approved by Director(E)
and issued by Chief/Head Labs. In the case of low quantity and low value
chemicals, proprietary chemicals and new chemicals for which Corporate
specifications have not been formulated, the User/Indentor at the concerned
work centre (Asset/Basin/Plant/Institute/ Services) can formulate the
specifications including the modalities of testing and also the packing and
marking details in consultation with Regional/Plant Lab and get the same
approved by the concerned Level-I executive of the work centre
(Asset/Basin/Plant /Institute/ Services) before forwarding it to Material
Management Deptt. alongwith the indent for taking procurement action.
99.1.2 The requirement of the chemicals will be worked out by the User/Indentor at
the concerned work centre in accordance with approved plan and
procurement will be done by the concerned Materials Management Dept.
99.1.3MM Deptt. shall process the tenders expeditiously and ensure that the orders
are placed well in time to ensure timely availability of chemicals. MM Deptt.
shall also regularly follow-up with the supplier for timely supplies. However, for
delayed supplies, Liquidated Damages clause shall be enforced as per the
purchase order conditions.
This group will consist of chemicals which are used in various other industries
besides oil exploration and exploitation.
These chemicals are mainly developed and manufactured in bulk for oil
exploration purposes and are used mainly by the oil industry.
99.3. Procurement method
i. Industrial license of SSI certificate indicating annual capacity for the item
quoted.
iii. A laboratory Test Report of latest production batch of the item quoted,
not older than one year from the date of tender opening, from the
laboratories as indicated in para 99.3.1
iv. Certificate from the manufacturer (even if the item is being purchased
through the authorised dealer) that the material being offered / supplied is
of the same standard and quality as the one for which the laboratory
certificate has been attached.
vii. Earnest Money / Bid Bond / Bid Security as per instructions contained
in para 57.
99.3.4 No sample, whatsoever, will be asked alongwith the offers. Order on the
technically acceptable and commercially lowest offer will be placed.
99.3.5 Payment
99.4.1 Speciality chemicals are further classified into two categories imported and
indigenous.
99.4.2 For these chemicals an identical approach will be made as in the case of
commodity chemicals for inviting tenders and documentation.
99.4.3 Speciality chemicals are basically sold under trade names. Therefore, for the
induction of competitors for better competition and greater flexibility a list of
suppliers whose performance has been found satisfactory during the past will
be drawn.
99.4.5 No sample will be called alongwith offers from the Bidders whose
performance has been found satisfactory during past and from the Bidders
whose samples have been approved by any laboratory as indicated in para
99.4.4. Offers from suppliers not falling under the above criteria will not be
considered.
i. Laboratory Test Certificate not older than one year from the date of
tender opening from any of the specified laboratories.
99.5 For imports of chemicals of order value exceeding Rs.1.00 crore, inspection,
testing and bonding before dispatch will be done by a Chemist of ONGC at
supplier's end ; the chemist will be accountable for proper quality check as
well as bonding. . For despatch of material by the supplier in the presence
of team of officers deputed abroad for inspection, testing and bonding, each
case will be decided on merit after taking into consideration the position
of availability of ships etc. Suitable provisions will be made in supply order
reserving ONGC's right to ask the supplier to despatch material in the
presence of the Chemist deputed abroad for inspection, testing and bonding.
Supplies valuing upto Rs.1.00 crore will be tested and inspected on
receipt before taking the material on charge. This process will not take a period
of more than 30 days. No Chemist for sampling and bonding in these cases
will be detailed. However, the supplier will be asked to give a certificate to
the effect that the product in question has been tested by the ONGC approved
laboratory. Each packing will bear mark of the manufacturer as well as
name of the Chemical, Lot No. / Batch No., Date of manufacture and
supply order number.
99.6.1 Before despatch of material, sampling / bonding of each lot of the product
including Barytes, CMC, PPD and OWC etc. will be done at firm's premises
by a Chemist; the chemist will be accountable for proper quality check as well
as bonding. The Chemist will ensure that supply of chemicals is in
manufacturer's original packing as specified in the supply order. Each bag /
drum of the product should bear mark of the manufacturer, name of the
chemical, Lot No, Batch No., date of manufacture and Supply order No.
Testing of the samples will be carried out in the ONGC laboratories / ONGC
approved laboratories as per para 99.3 / 99.4. The Barytes sampling and
bonding will be of 500 MT lot at a time.
99.6.2 Total four bulk samples will be drawn during sampling / bonding. The bulk
samples taken at supplier's premises will have the seal of both, the party and
ONGC.
99.6.3 Two samples will be sent to lab. for test, one sample will be given to supplier
and the fourth one is to be retained with Chemistry Deptt. Chemistry Deptt.
Shall forward the sample directly to the lab. and only send the intimation to
the Purchase Deptt. regarding forwarding of samples to the lab. for testing.
In all cases where sample has passed the test and there is no dispute, the
sample will be destroyed after one month from the date of receipt of
corresponding bulk consignment at the Project. In case of any dispute, these
samples shall be retained till resolution of said dispute. Destruction / non-
destruction of such samples shall not override the supplier’s obligations under
warranty / shelf life or any other supply order conditions.
In the event of bulk sample getting rejected, the supplier will be asked to
reprocess it and offer again. However if the product fails even second time,
the supplier will have the option to get it tested on payment basis in his
presence from the same laboratory where it was tested earlier on following
conditions:-
a) ONGC will refund the testing fee if the earlier results or found faulty.
b) The supplier on his part will be debarred from participating in ONGC tenders
for a period of one year if earlier results are confirmed.
99.8.1 Barytes mines are mainly located in well defined area of Andhra Pradesh.
As a result, pulverising units of the suppliers are located in this area. To avoid
problems due to non-availability of wagons, it is desirable that a
warehousing capacity of around 10,000 tonnes is created by ONGC at a
logistically optimal point in between Kadappa / Kudur where loading
facilities are available and in due course a Railway spur is developed next
to the sheds for direct loading.
99.9.2 It will be a condition of the contract that supplies not found as per
requirement at destination will be replaced free of cost by the supplier.
99.10.1 As far as possible purchase of barytes etc. should be made directly from the
mine-owners / Pulverisers / Manufacturers or through their authorised
dealers only and a stipulation to this effect should be made in the NIT.
99.12.1 Information should be exchanged with all Purchase Centres within ONGC
about the instances immediately where supplies of sub-standard product /
defective material have been noticed so that further dealings with such firms
are discontinued.
99.12.2 Dealing with such suppliers whose products have been found sub-
standard should be banned after following existing procedure for banning
business dealings with the firms.
99.12.3 The Projects should maintain sufficient stocks of mud chemicals to meet
any emergency arising out of supply of sub-standard material. Sufficient
stocks should be maintained to last till such time fresh supplies are
received which should be specified by User Deptt.
99.13 Third party inspection for accepting bulk supplies of mud chemicals
from abroad.
99.14.1 In respect of items like CMC and barytes where ONGC / OIL are the only
or major consumers, in order to keep up the competition and also to ensure
availability of the vital materials at the Projects, it is essential that orders
should be placed on more than one bidder. While taking a decision to
award contract, following factors should be essentially kept in view:-
A) CMC
If there are less than three acceptable bidders, then 75% should be ordered
on lowest bidder and 25% on the second lowest provided he matches the
rates with the lowest. If there are three or more acceptable bidders then
distribution should be 60% on the 1st lowest, 20% on 2nd lowest and 20%
on the 3rd lowest provided 2nd and 3rd lowest bidders match the rates of the
lowest bidder.
B) Barytes
The order should be given to the 1st lowest bidder subject to his capacity
and suitability.
The order should be given to the minimum of five bidders. The 1st
lowest bidder should get 30000 tonnes(60% of 50,000 tonnes) subject to
his capacity and suitability. For tendered quantity exceeding 50000 MT
the 1st lowest bidder should get 50% quantity subject to his capacity and
suitability. The remaining quantity should be equally divided amongst the
remaining four bidders or more if some more acceptable bids exist,
subject to their matching the price with the 1st lowest bidder and
subject to their capacity.
The order should be given for 50% quantity to the 1st lowest bidder
subject to his capacity and suitability. The remaining quantity should
be equally divided amongst the remaining six bidders, subject to their
matching the price with the 1st lowest bidder and subject to their
capacity and suitability.
100.1 Once the orders are placed and executed, vender rating should be carried
out by concerned Material Management. For rating the vendors the factors like
past performance, capacity and capability should be taken into consideration.
A Format for vendor rating at STR-41 refers.
100.2 The lists of vendors so rated should be circulated to all purchase centres
within ONGC and up-to-date records maintained by all concerned.
Purchase Section will secure adjustment in all claims preferred with Insurance
and with firms for short / damaged supply of material received against the
supply order.
The bank documents will be retired by the Accounts Section of the Project /
Office concerned.
104.2 The Kardex Sheets must be kept duly filled in and up-to-date so that the
position of any case may be known at a glance.
(MM/42/2009 dated 08.07.2009)
The maximum time limits for various activities under different categories of
tenders are prescribed in the schedules, as per details below:
In all cases valuing above Rs 5 lakhs, the concerned dealing officer will
indicate in the inner side of file cover the time norm prescribed for each
activity, the scheduled date of completion of the activity and actual date of
completion. In case of concurrent activities, the date of completion of last
activity (among the concurrent activities) should be indicated. In case of delays
in completion of any activity, the number of days of delay should be separately
indicated alongwith the reasons for delay, if any. The formats for this purpose
are appended as Annexure-C-I and C-II. All agendas submitted for approval of
EPC and proposals for approval of Directors must also contain such
information, tabulated in the prescribed format.
In high value cases and in those cases where a large number of bidders are
expected to participate, if the actual time required for any particular activity is
expected to be more than the time norms specified for the same, extra time
can be given for that activity (where it is felt necessary) with the approval of
CPA not below L-I (concerned Director in EPC level cases) specifically
indicating the reasons for the same. Further, such approval should be
obtained prior to initiating the processing of the tender. Accordingly, the
‘Format for reporting tender processing time’ should also be modified suitably.
(Form for extension of delivery date, required due to entire delay being solely on
account of contractor/supplier)
No.____________ Date___________
Dear Sirs,
You failed to deliver the entire quantity of materials within the contract delivery period.
In your letter under reference, you have asked for extension of time for delivery. In view of
the circumstances stated in your above referred letter, the time for delivery is extended from
_________to _________. Please note that an amount equal to the liquidated damages for
delay in the supply of the materials after the expiry of the contract delivery period shall be
recovered from you as mentioned in clause ________ for the extended period,
notwithstanding the grant of this extension.
2. The above extension of delivery date shall also be subject to the following further
conditions:
b) that notwithstanding any stipulation in the contract for increase in price on any
other ground, no such increase which takes place after _________ shall be
admissible on such materials as are delivered after the said date;
c) but, nevertheless, the purchaser shall be entitled to the benefit of any decrease
in price on account of reduction in or remission of Customs Duty, Excise
Duty, Sales Tax or on account of any other tax or duty, which takes place after the
expiry of the above mentioned date namely __________.
3. You may now tender the materials for inspection in terms of this letter. Materials,
if any, already tendered by you for inspection but not inspected, will now be inspected
accordingly.
Yours sincerely,
(MM/25/2006 dated 15.09.2006) ANNEXURE `A-2'
(Form for extension of delivery date, where delay, in part or full, is on account of
ONGC)
No.____________ Date___________
Dear Sirs,
You failed to deliver the entire quantity of materials within the contract delivery period.
In your letter under reference, you have asked for extension of time for delivery. In view of
the circumstances stated in your above referred letter, the time for delivery is extended from
_________to _________, reserving our right to levy liquidated damages from you for delay
in the supply of the materials after the expiry of the contract delivery period as mentioned
in clause ________ for the extended period, notwithstanding the grant of this extension.
2. The above extension of delivery date shall also be subject to the right of ONGC to
claim a reduction in prices on account of reduction in statutory duties / taxes etc. which
may take place during the extended period of delivery. However, increase in prices during
extended delivery period on account of increase in statutory duties/taxes etc. admissible
under Change in Law clause of this supply order/contract shall be granted, only if extension
is due to delay on the part of ONGC.
3. You may now tender the materials for inspection in terms of this letter. Materials, if
any, already tendered by you for inspection but not inspected, will now be inspected
accordingly.
Yours sincerely,
(MM/42/2009 dated 08.07.2009)
Annexure-B-I (of Chapter -1)
5 Submission of offers
21 21
(i.e. Opening of Techno-commercial bid)
(Total days for phase-B) (65) (65)
6 Submission of offers
(i.e. Opening of Techno-commercial
21 21 10
bid in two bid system / bid opening in
single bid system)
(Total days for phase-B) (60) (60) (26)
Sl. Activity Time schedule in number of days
No. Non EPC Cases
EPC Cases Above Rs 25 Rs 5 lakhs upto
lakhs Rs 25 lakhs
C Techno-commercial bid opening (TBO) to LOA/NOA
1 (a) Preparation of techno- 4 8 4 4 8
commercial CS 8
(1 & 2 to be (1 & 2 to be
(b) Vetting of CS. carried out (1 & 2 to be carried out
4 4 4
concurrently carried out concurrently
2 (a) Forwarding the offers for 1 ) 1 concurrentl 1 )
technical comments y)
(b) Technical Comments
7 7 7
3 TC for evaluation
8 8 8
(Holding TC and signing minutes)
4 Approval of TC minutes
3 3 2
Notes:
(i) In case any activity is completed before specified time, next activity should be
commenced immediately.
(ii) Wherever pre-bid conference is not held / required, allotted time for the
activities related to pre-bid conference (i.e. B3, B4 and B5) shall be excluded
and the time for submission of offers (i.e. B6) shall be reduced to 10 days.
(iii) Only in LSTK contracts, an additional time of 30 days for “Process Platforms”
and 15 days for all other LSTK projects including “Well Platforms” and “Pipe
Lines” shall be applicable for the activities between pre-bid conference to
TBO.
(iv) If seeking clarifications becomes necessary (applicable for all types of
tenders), an additional time of 20 days shall be allocated for each round of
clarifications (to cover the time required for obtaining clarifications, scrutiny of
clarifications, holding TC and approval thereof etc.). However, the time for
scrutiny, holding TC, approval etc. should be curtailed to the barest minimum
possible.
(i)(v) Wherever approval of Director is required an additional time of 5 days would
be applicable. Wherever approval of EPC (other than for activity indicated at
C.9 above) is required, an additional time of 15 days would be applicable.
Annexure-C-I (of Chapter -1)
3 TC for evaluation 8
(Holding TC and signing minutes)
4 Approval of TC minutes 3
Total Phase C
Total Tender processing time (A+B+C)
Annexure-C-II (of Chapter -l)
To,
3. The Bank also agree that Company at its option shall be entitled to enforce
this Guarantee against the Bank as a principal debtor, in the first instance,
without proceeding against the Contractor and notwithstanding any security or
other guarantee that Company may have in relation to the Contractor's
liabilities.
4. The Bank further agree that Company shall have the fullest liberty without our
consent and without affecting in any manner our obligations hereunder to vary
any of the terms and conditions of the said Contract or to extend time of
performance by the said Contractor(s) from time to time or to postpone for any
time or from time to time exercise of any of the powers vested in Company
against the said Contractor(s) and to forebear or enforce any of the terms and
conditions relating to the said agreement and we shall not be relieved from our
liability by reason of any such variation, or extension being granted to the said
Contractor(s) or for any forbearance, act or omission on the part of Company
or any indulgence by Company to the said Contractor(s) or any such matter or
thing whatsoever which under the law relating to sureties would, but for this
provision, have effect of so relieving us.
5. The Bank further agree that the Guarantee herein contained shall remain in
full force during the period that is taken for the performance of the Contract
and all dues of Company under or by virtue of this Contract have been fully
paid and its claim satisfied or discharged or till Company discharges this
guarantee in writing, whichever is earlier or until the date of expiry of the claim
period specified in para 9 of this Bank Guarantee, whichever shall first occur.
7. The Bank confirms that this guarantee has been issued with observance of
appropriate laws of the country of issue.
8. The Bank also agree that this guarantee shall be governed and construed in
accordance with Indian Laws and subject to the exclusive jurisdiction of Indian
Courts in Mumbai.
Any claim under this Guarantee must be received by us before the expiry of
this Bank Guarantee. If no such claim has been received by us by the said
date, the rights of Company under this Guarantee will cease. However, if such
a claim has been received by us within the said date, all the rights of Company
under this Guarantee shall be valid and shall not cease until we have satisfied
that claim.
In witness whereon, the Bank through its authorised officer has set its hand
and stamp on this......... day of....... at.........
.........................
(SIGNATURE)
WITNESS NO.2
..........................
(SIGNATURE)
Full name and official address (in legible letters)
INSTRUCTIONS FOR FURNISHING BANK GUARANTEE FOR LIQUIDATED
DAMAGES
1. The Bank Guarantee by Indian Bidders will be given on non-judicial stamp paper
/franking receipt as per stamp duty applicable at the place from where the NOA has
been issued. The non-judicial stamp paper /franking receipt should be either in
name of the issuing bank or the contractor.
2. Foreign parties are requested to execute bank guarantee as par law in their
country.
3. Foreign bidders will give guarantee either in the currency of the offer or US $
(US Dollar)i.e. Indian Rs/US $ have been mentioned only for illustration. Therefore,
in case where bank guarantee is being given in currency other than 'Rupees' or
U.S.$, indicate the relevant currency of the offer.
4.(a) The Bank Guarantee by Indian contractor can be given from Nationalized/
Scheduled Banks only. The Foreign contractor can give the Bank Guarantee either
from Nationalized/ Scheduled Bank situated in India or from an Indian Scheduled
Bank situated in their country.
(b) In case the Bank Guarantee is being issued by a foreign bank (the same should
be issued from any of the banks indicated at Appendix-____ of Annexure-___ of this
bid document), then such Bank Guarantee shall be accepted only with collateral
security/ guarantee/ confirmation from any Indian Scheduled Bank.
CHAPTER - 2
RECOUPMENT OF DEMANDS
CHAPTER - 2
107. MAINTENANCE OF KARDEX
107.2 One copy of all receipt and issue vouchers will be forwarded to the Kardex
Section for keeping the postings up-to-date. One copy each of the supply
orders from purchase sections will also be sent to the Kardex Section.
107.3 It is necessary that review of each card is conducted at the following stages to
account for any fluctuation in consumption and to revise the limits where
necessary and thus take timely steps for either reducing the outstanding
dues or estimate any additional requirements:-
i. When the stocks and dues on order of each item reach the minimum
level. This is a must.
ii. At the time when the physical stocks reach the safety stock level
iii. Irrespective of the review at the above two stages, each card should be
reviewed annually.
iv. In addition to the above, Ledgers Posters (Stock Holders), while posting
transactions should normally take note of any abnormal issues viz.
variation of over 20% consumption over a six months period.
107.4 The dues on order against imported material should be promptly recorded by
the Project / Regional Stores in the Top Cards the allocation made for the
Project / Region against the contracts should be reflected and the cards
kept up-to-date by posting receipts and the balance due etc.
107.5 Each numerical ledger card should be embossed with rubber stamps
"Indigenous" or "Imported", as the case may be, to differentiate between
imported and indigenous items.
108.1 The Purchase Department takes purchase action on receipt of indents from
the user / provisioning sections together with financial sanction. For the
purpose of maintaining buffer stocks, Regional Stores functions to meet
demands of the materials of recurring nature required by the Projects.
Assessment of buffer stocks in normal Departments is not a difficult affair but
in an organisation like the ONGC, it is rather difficult. Hence these buffer
stocks can only be maintained if the work centres plan atleast two years
ahead and advise their requirements to the Headquarters / Regional Stores.
109.2.1 In the case of the indigenous items the requirements are worked out by
the MM Deptt. (Stock) at the Projects / Regions either by automatic
replenishment on Min. / Max. basis or on receipt of requirements from the
indentors. The orders are placed by them to the extent of their powers
except for items where purchases have been centralised.
“Min.” Represents the R.O.L. i.e. safety stock and lead time
requirement.
110. *The senior most Materials Management Officer not below E-1(MM) will
have full powers to fix maximum-minimum limits for stock items in
consultation with the concerned indentor and with concurrence of Finance.
1 2 3 4 5 6 7 8 9
PROJECT STORES
CHAPTER-3
113.1 PROJECT STORES
113.1 Regional MM Deptt. maintains buffer stocks to meet the requirement of the
Projects from time to time. Minimum / Maximum limits of the stock holdings in
Projects will also be fixed.
113.2 The procurement section will obtain report of stock holdings from various
stock holders and place timely demands on the Regional MM Deptt. to
recoup the stock.
113.3 If any materials are not available in the Regional MM (Stock) and the same
fall within the financial powers of the Project Head, procurement of such
items can be undertaken direct to meet the requirement after obtaining
necessary financial sanction. In case it does not fall within the financial
powers of the Project Head, he will be requested to arrange financial sanction
through the concerned Region.
113.4 When the purchase power does not fall within the competency of the
Project Head, indent alongwith the financial sanction will be sent to the
Regional MM Deptt. for taking procurement action.
113.6 The Project Head will be the 'Direct Demanding Officer' to place indent on
Regional MM (Stock).
CHAPTER – 4
115.1 Transit documents such as Railway Receipts (RR), Parcel Way Bills
(PWB), Goods Transport Receipt(GTR) and Convoy Notes in respect of
materials dispatched by the consignor will be received from the Central Diary
Section.
115.3 Railway Receipts / Parcel Way Bills (PWB) / GTRs held with the Clearing &
Forwarding Section will be regularly examined by them and necessary
hastening action taken with carriers to expedite delivery of materials which
have not been received within the normal time allowed for transit.
115.5 If, however, the materials are not received within the reasonable period and
RRs / PWBs remain outstanding, a formal claim on the Railway / Carriers
will be lodged by the Clearing & Forwarding Section and intimated to the
Officer-in-Charge, Stores. This submission of the claim will not be delayed
beyond three months from the date of despatch of materials by the
consignor.
115.6 If the materials arrive at the Railway Station prior to receipt of RRs / PWBs,
delivery of the same should be taken against the Indemnity Bonds.
Necessary record is, however, to be maintained on RR register. RR / PWB
will be tendered to the Railway as soon as they are received from the
consignor and the Indemnity Bond cleared.
115.7 Postal Despatch Advice Notes are also to be entered in the RR register. All
instances of non-receipt of post parcels within one month from the date of
the despatch will be reported to the consignor for taking up the matter with
postal authorities. In case where the materials have been received prior to
the receipt of postal despatch advice from the consignor, proper linking will
be maintained in the register.
116. ARRIVAL OF MATERIALS.
116.1 The materials may arrive in Clearing & Forwarding Section as follows :-
iv. By Post.
v. By Air.
116.2 When full wagon(s) is / are received at the Railway Station or at the
Railway siding inside the Stores yard, immediate steps will be taken to
unload the wagon(s) to avoid any demurrage. If due to any unavoidable
circumstances the wagons cannot be unloaded within the period authorised
by the Railways, necessary reasons therefore will be recorded in the
Remarks column of RR Register.
116.5 In case of stores received after transhipment, the original wagon No. will be
entered in the Remark column of Daily Wagon Register (STR-27).
116.7 The Clearing and Forwarding Section's representative is to visit the Railway
Station daily and collect all the materials received at the station. He will take
with him the RR / PWB and while taking delivery of materials, will sign the
Railway Delivery Book on behalf of the Corporation. The RR / PWB in
respect of the consignments which are being taken over from the Railways
will be handed over to the Railways authorities.
116.8 The Section Incharge will ensure that all RR / PWB are properly recorded in
the RR Register and while handing over to his representative for station
duty, his signatures are obtained for record.
116.9 The Clearing and Forwarding Section is to hand over all consignments to
the concerned stock holder alongwith the original copy of Receipt Convoy
Note as per form STR No. 29 after obtaining signature from the stock holder
on his office copy.
117.1 Before collecting the material the representative of the Clearing and
Forwarding Section will ensure that the packages are in good condition and
show no signs of any loss or any damages to the materials enroute and the
weight of the packages / consignments agree with the weight shown on the
RR / PWB. In case of sealed packages, all the seals will be checked to
ensure that these are intact.
118.2 Discrepancy reports should be raised within 7 days of the inspection. It must
be ensured that the discrepancy reports reach the consignor within the period
of insurance so that claims do not become time barred. The inspecting
authorities must complete the inspection expeditiously so that the claims
can be preferred on the insurance companies within the validity period.
The MM officer(s) not below E-1 level will have full powers to approve and
countersign a Stock Discrepancy Report and direct follow up action.
Officer(s) of E-0 level shall exercise these power upto Rs 10,000.00.
However, Where materials management officer of E.1 level is not posted,
E.0(MM) may exercise full powers.
The Assistant MM Officer(s) of E-0 level will have full powers to approve
accounting of Stock Verification Discrepancies.
119.1 When any materials are required to be despatched from the MM (Stock), the
stock holder will intimate the Clearing and Forwarding section on 'Despatch
Note' (form No. STR 28).
119.2 The Clearing and Forwarding section will take immediate steps to arrange
the despatch of the materials as required i.e. by Rail/Road/Post.
119.3 Before taking over the packages for despatch, the Clearing and Forwarding
Section will endorse a certificate on the office copy of the 'Despatch
Note' of the Stock-holding section indicating thereon the time and date
when the packages were taken over by them.
119.4 As soon as the materials are dispatched / delivered, the RR etc. is to be
immediately handed over to the concerned stock-holder for further disposal.
119.5 In case of full wagon loading, the existing regulations covering the demand of
wagons will be observed.
119.6 Wagons will be loaded to the full capacity considering the type and weight of
the items being loaded. If the materials are to be despatched needing a
number of wagons, urgently required materials are to be loaded and
dispatched first.
120.1 In case of full wagon loads, Despatch Convoy Note is to be prepared as per
form STR-30. Original copy of the Dispatched Convoy Note is to be retained
by the section, 2nd copy to be sent to the consignee, 3rd copy is to be
handed over to the consignor (stock holding section) and 4th & 5th copy will
be placed in the wagon.
120.2 Each copy of the Despatch Convoy Note, placed in the wagon, is to be kept
inside the wagon near the door so that when the door is opened, one copy
of the Convoy Note is readily available and can be taken out at once. Care
will be taken to ensure that the Convoy Notes are well placed and are
secured from slipping down amongst the packages.
120.4 When any parcels is despatched by the Post, necessary records will also
be maintained in the Despatch Register and postal receipt handed over
to the Stock-holder for record. Necessary receipt of such postal Receipt is
to be taken by the Clearing and Forwarding Section from the stock holder.
121.1 When any materials are sent in open wagon, suitable escort is to be
arranged to accompany the wagons, to avoid pilferage enroute.
121.2 During the transit by Rail, delay may take place. The movement of the
wagons may, therefore, be expedited at the station where the materials are
likely to be transhipped from Broad Gauge to Meter Gauge and vice versa
or at the station where the change of Railways takes place such as from
Northern Railways to Western Railways and the like.
CHAPTER - 5
122.1 All materials will be accepted after inspection, except for the petty
purchases upto Rs.10,000.00 as per para 18.1.3 and 18.1.4.
122.2 (A) The Quality Assurance Department shall be responsible for carrying out
quality control / inspection of all items / equipment against supply orders
placed by MM Deptt., except the following :-
(a) All chemicals including mud chemicals, oil well cement, paints and gases.
(b) P.O.L.
(c) Building materials including cement and timber.
(d) Seismic explosives and detonators.
(e) Cleaning agents, hand gloves, cotton waste.
(f) Printed stationery.
(g) Wooden planks and coal.
122.2 (B) The above items at Sl. No. (a) to (g) except (d), shall be inspected by
concerned Indentor. Item at Sl. No. (d) shall be inspected by an official of
Indenting department, who is authorized / licensed to handle explosives, by
visually checking the items w.r.t verification of quantity (nos.), weight, visual
defects, batch nos. etc., and also subject to obtaining an undertaking from
supplier to the effect that in case the field performance of such visually
inspected items is not satisfactory, the same shall be replaced by the
manufacturer at his cost.
122.3 Quality Assurance Department shall not be responsible for inspection against
supply orders valuing less than Rs. 10,000/- .
122.4 All steps must be taken to commence inspection within 3 days after the
receipt of the intimation from the Materials Section for items to be inspected
locally and within 7 days if the materials to be inspected are located out of
station. Reasons for delay in the inspection beyond this period should
invariably be reported to the Head of concerned Materials Management,
Head of Quality Assurance Department and Project Head. Inspection report
(or, Intimation in respect of rejection of material) should be sent to supplier by
the inspecting authority within 4 days after completion of inspection / receipt
of relevant test reports (if any), under intimation to concerned sections
(including purchaser, Indentor, consignee and payment authority).
122.5 In the case of imported stores and spares manufactured abroad by reputed
manufacturers and accompanied by the manufacturer's warranty, stores may
be accepted after random sampling / visual inspection.
122.6 In case where cost of inspection is not commensurate with the value of the
stores concerned, inspection may be carried out at destination. At the time
of placing the supply order a suitable clause should be inserted to
provide for the return of sub-standard materials at the expense of the
supplier or acceptance of on an agreed reduced cost.
122.7 It is not advisable that the inspection should be carried out by the purchase
section or the stock holder. All technical equipment and mud chemicals
requiring expert check will be put up to the representative of the Indentor/
Department of Quality Assurance, wherever necessary and possible.
122.8 All the cases / packages are to be opened in the presence of Inspecting
Officer. (SP/3/99 dated 24.05.99)
123.1 Normally, no materials should be inspected and accepted after the expiry of
the contract delivery period and, therefore, the Inspecting Officer should
endorse the following clause on the Inspection Note:-
"The fact that the have been inspected after the delivery period and
accepted, will not bind the purchaser, unless at his discretion he agrees
to accept delivery thereof. The materials are being passed without prejudice
to the right of the purchaser under the terms of the contract".
123.2 In case of part delivery offered by the firms for inspection after the expiry of
the contract delivery period, the following clause should be inserted on the
Inspection Note by the Inspection authorities:-
"The materials detailed below have been tendered by you after the expiry of
the delivery date provided in the contract and have been inspected as a
special case; this does not bind the purchaser unless, at his discretion he
agrees to accept delivery thereof; nor does it prejudice the right of the
Purchasing Officer to claim liquidated damages from you for the late
delivery or to cancel the contract on the expiry of the delivery date, under
the terms of the contract".
123.3 Third party inspection for accepting bulk supplies of mud chemicals
from abroad.
124.1 Function of the Receipt, Stock and Issue Section will be to receive the
material from the Clearing & Forwarding Section, check the same with the
Convoy Note / Supply Order; stock the same and issue them, whenever
required.
124.2 As soon as the material is received from the Clearing & Forwarding Section,
the same will be linked up with the supply orders without tampering the
packing cases. The Inspecting officer appointed by the Officer-in-Charge,
Stores, will then be intimated for inspection. (SP/3/99 dated 24.05.99 )
124.3 As soon as any material is received by the Clearing & Forwarding Section,
packages in original condition are to be handed over to the Receipt Section
which will endorse a certificate, in token of having received the packages
on the Receipt convoy Note/RR Register which will be sent to them by
Clearing Section.
124.4 Copies of all supply orders placed by the Procurement Section are to be
sent to the Receipt Section. The Receipt Section will maintain record of the
supply orders item-wise.
124.5 The material is to be checked with the supply order / Convoy Note both
quantitatively and qualitatively. After the completion of inspection,
necessary Receipt Voucher will be prepared.
124.6 Materials Management Officer not below E-I level is authorised to approve
and countersign a Goods Receipt Voucher. Where Materials
Management Officer of E-I level is not posted, MM Officer of E-0 level
may exercise full powers.
126.1 There shall be only one form of GRV for both Imported and Indigenous
materials.
126.2 Separate GRVs will be prepared for Stores, Spares and Capital items to
facilitate correct booking in priced stores ledgers in Accounts Section.
Separate series of GRVs will be used for each category. The GRVs will
be prepared in 7 copies on STR-1 and are to be distributed as under :-
______________________________________________________________
Sl. No. : Department (in order of flow of copies) : Colour
of copies : 1 2 3 :
for one set: :
Note : Where the number of Indentor is more than one then all Indentors
will be informed of the receipt of material.
126.3 One continuous series for GRVs will be maintained by each project. Original
copy of the GRV will be sent to Stores Ledger Section / EDP and duplicate
copy sent to Accounts for payment purposes. On original copy of GRV
would be embossed "for EDP purposes" and on duplicate copy "For payment
purposes". The GRV will be sent to Accounts branch duly completed in all
respects by 11.00 AM on the following day. Third copy is meant for Internal
Audit and is to be sent to them.
126.4 As soon as the Goods Receipt Voucher is prepared, entries are to be made
in the Stock Cards / Kardex Cards and stores binned properly.
126.5 No GRV will be raised for petty purchases of consumable items upto Rs.
10,000/-.
127. BINNING OF MATERIALS
127.1 To identify the materials from the respective suppliers, before binning the
materials, one representative sample from the consignment will be attached
with the identification card, which will indicate :-
127.3 To ensure that there is no wrong binning, fresh consignment to be binned will
be compared with the consignment already lying in the Bin before binning.
If the consignment does not tally, a recheck should be undertaken and
correct Bin No. re-allocated. In case of error in inspection / acceptance,
attention of the Inspection Officer will be drawn.
127.4 As far as possible new receipts will be so arranged in the Bins that these are
last to be selected for issue so that proper turnover of the stock is
maintained.
127.5 Prior to binning action, the quantities already held in Bins will be checked and
determined whether sufficient room exists in the Bins to accommodate the
total quantities received. If there is insufficient place in the Bin to
accommodate the whole of the new receipt in the Bins, a new location,
preferably in the vicinity of old location, will be created and new location will
also be entered in the Stock Card and Receipt Voucher. Ledger Section will
also be apprised accordingly to reconcile its records.
ii. All Racks / Bins will be given location Nos. The same are to be recorded
on the Stock Cards / Kardex Cards.
iv. While stocking materials, the heavier items will be kept at lower rungs of
the racks and lighter on higher ones.
v. Fast moving items should be stored at easily accessible place and to the
nearest point of issue.
vi. Stocking of the items should be so arranged that the principle of 'First
Come' 'First Out' (FIFO) can be easily followed.
129.1 Materials will be issued only on receipt of indents on proper form STR
No.4 from authorised indenting officer(s).
129.2 The Regional / Project / Business Group Head will intimate the name(s) of
officer(s) to the MM who will be authorised to indent stores. Instructions
issued by Director (Tech.) for declaring authorised indentor(s) will be
followed strictly.
129.3 The indenting officer will be informed regarding the division of Stock-Holding
sections in the Materials Management to enable them to place their
indents on the concerned section.
129.5 The Stock Holding Section, before issue of materials, will check the
indent with regard to the following points:-
a) Whether all the items in the indent are for one section? If some of the
items are not kept in the Stock Holding section, the Stock Holder will note
a remark against the items in the indent and draw attention of the
indentor. The indenting officer will then place the indent for those items
on concerned section.
d) Whether the indentor has indicated exact location of the consignee and
full postal address where the materials are required to be dispatched to
the outstation(s)?
130.1 The authorised indentor shall prepare six copies in STR-4 of Materials
Requisition / Issue Voucher and hand over five copies to the Stock Holder
either directly or through his representative. The distribution of copies of
Materials Requisition / Issue Voucher shall be as under :-
______________________________________________________________
Sl. No. : Department (in order of flow of copies) : Colour
of copies : 1 2 3 :
for one set: :
--------------------------------------------------------------------------------------------- -----------
1st MM EDP - White
(Issue)
130.2 Separate vouchers shall be prepared for stores, spares and Capital item
on stock. Separate series will be allotted to the vouchers.
130.3 Materials Management Officer not below E-I level is authorised to approve
and countersign an Issue Voucher. Where Materials Management Officer
of E-I level is not posted, MM Officer of E-0 level may exercise full
powers.
i. issue the goods and post quantity issued, unit balance in the stock
card on the previous day and identification No. on all the copies of the
stores indent;
ii. take the signature of the person receiving the goods on the material
indent;
iii. initial the indent and hand over the indentor's copy to the indentor or his
representative;
iv. make the requisite entries in the Stock Card and extend a new quantity
balance;
v. three copies of all the Indent – Issue – Return voucher shall be sent to
Acctts. Section by MM Stores Department so as to reach that section by
11.00 AM on the following day; and
131.2 While light goods shall be immediately issued to the person bringing the
indent, the heavy goods shall be sent to the indentor through MM Deptt.
labour and MM Deptt. truck. The Incharge of Stock Section shall co-
ordinate the requirements of MM labour and trucks for different Stock
Holders. When the material is to be delivered by the MM truck(s), the
Driver shall take indentor's and Accounts copy of the Materials Indent with
him and bring back the Accounts copy to the Stock Holder with signature of
the indentor in token of receipt of materials.
131.3 For security purposes, the indentor's copy with details of issue shall be
shown to the Watchman at the gate, who shall sign or stamp it in token
of having checked the goods.
131.4 The Internal Audit Section will use Accounts Section copy for audit
purposes.
131.5 The recoupment of Stores and Spares will be done as per existing
instructions.
As far as possible, the Stock Holder shall effect issues and record entries
on stock cards simultaneously. However, with a view of allowing him a little
margin to complete the left over jobs, the goods shall be issued from 8.00
AM to 12.00 noon and from 1.00 PM to 4.00 PM and one hour being allowed
for lunch break and one hour between 4 p.m. to 5 p.m. being allowed for left
jobs. The timings may be specified as per working hours of the Project /
Office accordingly.
133.1 When the materials are required to be dispatched to out station, these are to
be properly checked and packed in the presence of two responsible
officials, one from Stock Holding Section and the other from Clearing &
Forwarding Section.
133.2 For each packing case, independent packing list is to be prepared in triplicate
on form STR-17. One copy will be kept in the case; second will be sent to the
consignee alongwith the Issue Voucher and Railway receipt and the 3rd
copy to be retained by the Stock Holder.
Items of stores and spares which have been purchased on the basis of
adhoc demand(s) from the indentor(s) should not continue to lie in the
stores house(s) for indefinite period. It is necessary that such items
immediately on receipt should be taken over by the indentor(s).The
advice about their receipt(s) in the stores house(s) should be promptly
furnished to the indentor(s). A monthly statement of such items received
and not collected by the indentor(s) should be prepared by the MM Officer
and submitted to the Project / Regional Head for co-ordinating further action.
The items of Stores and Spares, when issued to the users by the MM Deptt.,
will be finally charged off from the Stores and Accounts Book. The User
Department will, however, maintain in STRs the inventories of such stores &
spares items in their possession which may be fit for repeated use over a
long period of time and will be responsible for their safe custody and
accounting until they are written off due to normal wear & tear or any
circumstances like loan to other departments or projects, loss etc. These
records will be subjected to check by Stock Verification Teams to ensure that
these are always complete and up-to-date.
135.2.1 All Capital items on receipt will be posted by the MM Deptt., in the numerical
Kardex Cards which are maintained by them category-wise separately for
serviceable items, repairable items and unserviceable items.
134.2.3 The Capital items once issued against demand(s) of authorised indentor(s)
will be finally struck off from the numerical Kardex Card(s) and further
responsibility for their accounting / distribution / safe custody etc. will lie with
Accounts Deptt. and Indentor / User Deptt., as the case may be, until the item
is returned to MM Deptt. Details of capital items with indentors will be
maintained in STR - 5.
135.2.4 The Deptt. / Office of users will obtain half yearly confirmation from the
actual users regarding physical existence of the item(s).
135.2.5 The Stock Verification Team will verify the stock of capital items held by
MM Deptt.on the basis of Kardex Cards maintained by them and items held
by user agencies will be verified against the record maintained by them and
the total items from Block Registers maintained by the Accounts
Department perpetually.
135.2.6 The balance held in Kardex Card of the MM Deptt. plus balance in user's
record must invariably tally at all times with the balance in Block Register of
the Accounts Formation. The discrepancy found during Stock Verification of
the stocks of MM Deptt. and stocks with users after comparing the same
with the balance of Block Registers will be reconciled by physical checking
of the respective items of MM Deptt. as well as user's stock, wherever
discrepancy has been actually revealed.
136.1 Whenever any materials are found surplus to the indentor's requirements,
these should be returned on Materials Return Note (STR 4-A) to the MM
Deptt. (Stock) from where these were originally drawn, by the Indentor. Six
copies of the Materials Return Note will be prepared for distribution as under
:-
2nd “ -- -- Blue
3rd “ Accounts -- Pink
Note: The above distribution e.g. receiving copy, EDP copy, Accounts
copy, Cost Centre copy and Security Gate copy will be printed in
bold letters on each in red ink.
136.2 The Stock Holder will take the material on charge on the Materials Return
Note itself. The authorised officer will assign the balance life of the returned
material. The person returning the material and the officer authorising the
return must invariably countersign.
136.3 Reference to Issue Voucher under which the material was issued shall
invariably be given on Materials Return Note.
All spares for machinery and automobiles etc. are to be issued against
the production of wornout and unserviceable parts. Therefore, while
requisitioning the replenishment of such spares, the used spares should
invariably be returned.
(Provisions laid down vide para 129.5(e) also refer).
138.1 The Material Transfer Note (STR-19) (SA03) will be prepared for all transfer
of goods from one Project / Unit to another. Separate class-wise MTNs shall
be prepared for transfer of stores, spares and capital items in stock. The
MTN will not require raising of Goods Receipt Voucher and instead the
material received against MTN shall be taken on charge on the MTN itself.
The MTN shall be prepared in 7 copies and distributed as under :-
138.2 Materials Management Officer not below E-I level is authorised to approve
and countersign s Material Transfr Note. Where Materials Management
Officer of E-I level is not posted, MM Officer of E-0 level may exercise
full powers.
139.1 The vouchers should be made over by the MM section to the Stores
Accounts (PSL) office daily. The vouchers of a date say 1st of month
should be completely delivered to the Stores Accounts office without fail,
wherever no holiday intervenes, on the morning of 3rd within 2 hrs of the
opening of the office. The vouchers would be accompanied by a
Forwarding Memo on the following form :-
Class _________________________________________________________
______________________________________________________________
R.O. VOUCHER NO. DATE R.O. VOUCHER NO. DATE
NO. NO.
______________________________________________________________
139.2 Where the MM (Stock) section and the Stores Accounts (PSL) office are not
in the same station, the time allotted may be modified to suit the local
condition taking care to see that there is no avoidable delay in the regular
submission of the vouchers to the Accounts office.
If any voucher is missing, a search should be made for the same and if it
cannot be obtained at once a note should be kept in a register and the
matter pursued until settled satisfactorily. In case of cancelled vouchers, it
should not be destroyed but after necessary endorsement with the remark
"Cancelled" on the foils and against entry of the forwarding memo, Vouchers
should be sent to the Priced Stores Ledger Section where these should be
separated from the rest and filed separately class by class. In checking the
vouchers with forwarding memo, the arrangements of vouchers from the
MM section should not be disturbed even if this involves inconvenience.
-------------------------------------------------------------------------------------------------------
Material Makers Brief Unit of
Code Part No. Description measure
-------------------------------------------------------------------------------------------------------
143.1 Kardex Cards will be maintained by MM Deptt. For each item two cards
are provided, one at the top and the other at the bottom. The top card gives
information regarding equipment, supply position against purchase order and
monthly consumption of an item while in the bottom card receipt and issue
vouchers are to be posted.
143.2 Separate sets of cards should be maintained under each class of material.
144.1 The EDP section will ensure that an Index Register is provided to all the
Stock Holding units in the Corporation with the computer. The Stock Holders
will ensure that all additions in the Stock Cards are entered in the computer
printed index register. On 1st April of every year, new Index Register will
be prepared with the help of the computer. A record of Kardex Cards added
and removed will also be maintained alongwith the Index Register in the
following form :-
-------------------------------------------------------------------------------------------------------
Page : Material : Added : Removed :
: Code : : :
-------------------------------------------------------------------------------------------------------
144.2 All the cards should have stamp of the project concerned and signed by
MM Officer / Asstt. MM Officer.
145.1 No cards will be opened for the first time for an item without the Stores
Accounts and the EDP cells being advised to enable them to open a
corresponding priced card in the PSL being maintained on the computer. Not
more than one card may be maintained for one item at a time unless there
is a difference in quality such as new, second hand etc. or it is found
necessary by raising of different rates of credit to maintain separate records
of stock.
146.1 All Kardex Cards with 'nil' balance i.e. on which no transactions have taken
place during the past three years and if the same have been added and
Stock Verification carried out resulting in 'nil' balance during the last 3
years, will be removed from the cabinets and placed in a separate pad
kept according to the different groups / classification of stores.
146.2 In case the material is again received against the same code for which the
Kardex Card was removed on the above basis, a fresh card is required to
be opened and intimation sent to the Accounts Ledger section and EDP.
When the Numerical Ledger Section of the MM Deptt. proposes to close a
card manuscript closing advice be prepared on STR-37.
147.1 Particular care should be taken to see that all completed cards are carefully
stored chronologically in the order of Class and Code Nos. and are easily
available for immediate reference, suitable Binders or Cabinet being used
for this purpose. If office of the Accounts Officer is not situated in the same
station, the completed cards should be sent to that office for reconciliation
with the priced ledgers before being placed in the Binders or Cabinet for
the completed sheets cases. The Materials Management officer will be
responsible to see that proper arrangements are made for the safe despatch
of the cards. Suitable Binders or Cabinets may be kept apart for the
purpose in which the cards duly arranged by Classes and Code Nos.
should be placed alongwith a manuscript list of such cards, which should
show :-
i. Class
147.2 The Binder or Cabinet should be locked or sealed before being sent to the
Stores Accounts Officer. A spare copy of the list should be kept as office
copy and another should be sent to the Stores Account Officer which should
be returned by him duly signed in acknowledgement of the cards. When the
numerical ledger cards are received back after reconciliation, these should
be checked with office copy of the list.
147.3 In order to ensure that all vouchers of a particular month are completely
received by the Accounts and EDP sections to enable processing of the
transactions being done there, it is necessary to have a watch on the flow of
vouchers through a system of completion certificate. The fortnightly
completion certificates should be prepared in 4 copies on STR-38 and
distributed as under :-
c) Fourth copy to the EDP cell who will watch for the flow of vouchers from
the Accounts.
147.4 While reconciling numerical ledger cards with the priced ledger and noting
the physical balance of Stock Verification it should be seen by Accounts
Section and Stock Verifier that the cards bear the initials of the
Supervisor / Incharge of the Numerical Ledger Section.
There should be no entry in the card ordinarily without a voucher for the
transaction. The cards should be posted with great care, neatness being a
very great factor, no overwriting should be allowed and in no
circumstances should any entry of transaction be scored out. If by
mischance any entry of transaction which would have been correctly made
in another card but has been written in a particular card, the error should be
corrected by back entry giving reference to the ledger card. Also an
Adjustment Voucher in form STR-21 (SA-05) be prepared. All such
corrections should be made under initial of clerk / Incharge of Numerical
Ledger Section. All Receipts, Issues and other Vouchers should be posted
chronologically according to their date and document No. Issue and
Receipt against Material Transfer Note (STR-19) (SA-03) under which
material is transferred from one project to another should be posted in
green ink so that these transactions are not included in monthly
consumption. All receipts should be posted first and then issues. The order
of posting for various Vouchers should be as under :-
He should post receipt and issue vouchers within 24 hours of the date to
which they relate, unless any holiday happens to intervene. He should
also keep "Recoupment Cards" (top cards), of the items in his charge,
duly posted. He is responsible for timely placing of recoupment requisition in
connection with the items in his charge.
150. FILLING UP OF VARIOUS FORMATS FOR COMPUTERISED INVENTORY
CONTROL.
151.2 The lists of non-moving items / slow moving items should also be given to
Regions on yearly basis.
151.3 The lists of non-moving / surplus items should be scrutinised and efforts
made to utilise alternative available as far as possible.
152.1 In case of items for which Max. / Min. limits have been fixed, if Stock
Holder finds that a particular item is moving slow and its limits have been
fixed on the higher side, he will bring it to the notice of Head of the Stock
Section who, in consultation with the concerned User department, will
arrange to review the Max./ Min. limits so fixed. Similar action will be taken
for items which are moving very fast and for which limits have been fixed on
the lower side.
152.2 In-charge Warehouse, not below E-I (MM) level, will have full powers to
declare as item of Stores and Spares as ‘Slow-moving’ or ‘Non-moving’.
These powers will be exercised in consultation with the Indentor and
Finance.
PACKING OF MATERIALS
153. PACKING SECTION
154.2 In packing bay sufficient stock of packing materials such as straw, wood,
cotton waste, paper, water proof paper, cartons etc. will always be
maintained.
154.3 The packer should pay particular attention while packing the items of
fragile nature. The material should be so packed that the material in the
packages, while in transit, do not move or rattle.
154.4 Suitable packing boxes, crates and cartons will be used according to the
nature and quantity of the materials to be packed.
154.5 One copy of the packing slip showing the contents of the particular box
should be put inside the box.
154.6 The box is to be sealed after packing. Name of the consignee, name of the
consignor, Station of Destination, Net weight / Gross weight and nature of
materials specially when it contains items of fragile nature, will be written on
the packages before despatch.
154.7 When packages are despatched by Rail, the same must be consigned to the
Railway Station nearest to the consignee and under no circumstances, the
postal address will be indicated on the packages.
154.8 When the packages are despatched by post, full postal address of the
consignee is to be written on the parcel.
154.9 Stock Holder will check all packages for standard of work and correct
markings.
154.10 The packages will then be handed over to the Clearing and Forwarding
Section for onward despatch.
154.11 The Clearing and Forwarding Section will also check the address and the
markings on the packages.
CHAPTER – 7
GENERAL
CHAPTER 7
155. CONTROL OFFICE
The Officer-in-Charge, MM (Stock) will see that the rules and regulations
issued from time to time on Materials Management by the Corporation
are followed by all the Sections under him to maintain proper control.
All incoming and out-going dak should be routed through Central Diary
Section of his office.
156.1 The Drill Site materials will stock materials for day to day requirement or for
weekly needs of the project works. They are not supposed to stock materials
for a long duration except mud chemicals. They will send their indent to the
Materials Management from time to time to meet their needs. This indent is
to be signed by the officer authorised for signing the indent.
156.2 All the materials consumed at the Drill Sites will be linked up with the Daily
Log Sheets maintained for the operations.
156.3 The Drill Site materials will remain under the direct control of the Officer
Incharge of the Operations at the site and he will be responsible for proper
consumption of material issued to the Drill Site.
159.1 The Corporation's standard policy for making payment for supplies is as
under:-
FOREIGN BIDDERS
(ii) Wherever a Letter of Credit is required, it would be opened through the State
Bank of India ..................., India.
(iii) Payment of F.O.B. / C&F / CIF value, as the case may be, will be made
against negotiable copy of Bill of Lading and other specified documents as
per supply order through irrevocable Letter of Credit to be opened in favour
of the supplier.
(iv) All Foreign Bank charges towards advising negotiations / cable charges and
confirmation of Letter of Credit charges will be borne by the supplier. All
Indian Bank charges will, however, be borne by the ONGC.
(v) Where the supplies are proposed to be made in stages beyond three
months, the bidders should quote staggered delivery schedule giving
item-wise details / amount. The establishment of Letter of Credit in such
cases will be restricted to the period-wise deliveries so offered quarter-wise.
INDIAN BIDDERS
(b) The goods are insured by supplier for losses, damages, breakages and
shortages during transit at their cost and insurance cover in the name of
ONGC sent alongwith documents ; and
159.2 For part supplies i.e. less than instalments stipulated in the supply order,
payment cannot be made. In other cases the payments for part supplies can
be made depending upon the merits of the case and the nature of supplies in
question provided at least 20% of the supplies have been completed.
159.3 However, the Head of Materials Management, in consultation with senior
most Finance Officer in position, may also authorise 100% advance
payment as under:-
159.3.2 Through issue of A/Cs Payee Cheque / Bank Draft in favour of the
manufacturer alongwith Supply Order for the purchase of proprietary
articles like Ambassador Cars where acceptance of order / registering of
requirement is subject to 100% advance payment alongwith the order. In
such cases inspection of material will be carried out and guarantee of the
performance of equipment invariably obtained from the manufacturer
before despatch of the material by them.
159.3.4 Through issue of A/Cs Payee Cheque / Bank Draft in favour of the
suppliers against their Sale Order and / or proforma Invoice in cases where
delivery of the stores is to be obtained on satisfactory inspection and
payment.
159.3.6 The Regional Director(s) will have full powers to decide each case on
merit for advance payments subject to the condition that any deviation from
the provision in paras 158.2.1 to 158.2.5 above shall be reported to
Director (Finance).
159.3.7 In all other cases it must be ensured that payment is made within 30
days from the date of receipt of material at destination if found in
satisfactory condition after inspection.
MM Officer of E-0 level, or above, will have full powers to sign Railway
Credit Notes. The executive deputed for sampling / bonding/de-bonding
chemicals are also empowered to sign Railway Credit Notes. The powers are
subject to the condition that in case of demurrage / wharfage etc. the case
shall be processed concurrently for regularisation under orders of
Competent Authority.
(c) The third pre-requisite is the account head to which the cost is
debitable for budget control purpose. If the Supply Order is totally
for Capital item, "Capital" is to be indicated and if it is for totally stores
and spares "Stores & Spares" would be indicated. If the order is for
capital equipment with operational spares indicated "Capital with
Spares" would be given.
Fortnight for this purpose would be 1st to 15th and 16th to end of the
month. The Supply Order lots for a fortnight will be forwarded to EDP
Section within 5 days of end of fort-night alongwith number and ending
control number of Supply Order.
(h) The order rate column can be further expanded to indicate the rate
basis for contractual purposes e.g. CIF / FAS / FOB / FOR station of
despatch etc.
(k) Various other instructions to the suppliers e.g., packing & forwarding
charges, Insurance charges or other conditions may be shown after
typing out all items on order. The total value of order may also be
exhibited, if so desired.
(ii) Besides the schedule of items ordered, the distribution statement of quantities
ordered consignee-wise should also be shown. This also forms part of the
contract to enable the supplier to despatch the materials to the different
consignees. The code for computer processing has to be shown for the
Port- consignees as well as the Ultimate consignees as per details indicated
hereunder. In case of entire order being consigned to only one consignee,
the consignee's particulars may be shown in the body of the contract order
in detail and the consignee codes may be indicated in the Annexure to supply
order.
(iii) Besides this, each order sent to EDP Cell will have following information for
EDP purpose:-
To be filled as under:
For Ex Factory - 1
for FOR Station of despatch - 2
for FOR Receiving Station - 3
for F.A.S. - 4
for C.I.F. - 5
for C.F. - 6
for F.O.B. - 7
for any other supply - 8
condition not listed above
f) Currency
g) Rate of Exchange
h) CONSIGNEE CODE
i) Argentina O
ii) Australia A
iii) Austria T
iv) Belgium B
v) Canada C
vi) Dubai Z
vii) England E
viii) France F
ix) Finland L
x) Denmark M
xi) Germany G
xii) Hungry H
xiii) Hong Kong Q
xiv) Italy I
xv) Japan J
xvi) Netherland N
xvii) Poland P
xviii) Rumania R
xix) Singapore S
xx) Switzerland W
xxi) Thailand D
xxii) USA K
xxiii) USSR U
xxiv) Czechoslovakia Y
xxv) Spain V
xxvi) Other X
CODES FOR SOURCES OF SUPPLY
i) DGS&D 3
ii) ONGC Rate
Contract 5
iii) Registered
Suppliers
with ONGC 0,1 & 2 (First two fields of
vendors code being PC,
next four places will be
operated starting from
0001 to 2999 continuously)
iv) Non-Registered
suppliers 8&9 (Same as per (iii) above
code '8001' to '9999' to
be operated after PC).
APPENDEX A – 2
1. Number/Pieces/Tins/Barrels/Cans NO
2. Meters MR
3. Metric Tonne MT
4. Kilo Gramme KG
5. Pairs PR
6. Litres LT
7. Set ST
8. Kit KT
9. Roll/Reel RL
10. Gramme GM
11. Milli Litre ML
12. Pounds(Weight) LB
13. Packets PK
14. Square Feet SF
15. Cubic Meter CM
16. Square Meter SM
17. Gross GR
18. Dozen DZ
19. Phail PH
20. Cubic Feet CF
21. Yards YD
22. Feet FT
23. Chain Links LK
24. Short Ton TN
ANNEXURE – B
Group EF EF
Drilling D-I DA DA
D-II DB DB
D-III DC DC
D-IV DD DD
D-V DE DE
D-VI DF -
D-VII DG -
Operation Op-I - PA
Op-II - PB
Op-III - PC
Technical Tec.I - TA
Tec.II - TB
Tec.III - TC
The alphabets E,D,P,T,G and I denote codes for Exploration, Drilling Operation
and Technical Business Groups and General and Import Substitution Purchase
Sections respectively. These alphabets have further been suffixed with alphabets
`A' onwards depending upon the number of existing Purchase Sections. Alphabets
further to above may be suffixed with the codes of Business Group/purchase
sections in case new Purchase Sections are opened.
ANNEXURE – C
NB: Alpa codes are to be used only for clearing and forwarding
purposes by the Port Office.
LIST OF PROJECT CODES
NORTHERN JUMMU - DU - - XU -
REGION JAWALAMUKHI - DU - - - -
WESTERN ANKLESHWAR EA DA
REGION
BARODA EB DB
CAMBAY EC DC
AHMEDABAD ED DD
JODHPUR EG DG
MEHSANA EE DE
CENTRAL - -
WORKSHOP
C&M DIVISION - -
HAZIRA - -
IRS - -
AHMEDABAD
DELHI DELHI - -
CENTRAL WEST EW -
REGION BENGALTRIPU
RA
GANDAK EN - -
CALCUTTA - - -
OFFSHORE
T&S OFFICE - - -
CALCUTTA
GEOSCIENCE - - -
CALCUTTA
SOUTHERN MADRAS - DM PM
REGION OFFSHRE
GEOSCIENCE - - -
MADRAS
CAUVERY - DV -
K.G. PROJECT EK DK PK
EY DY FY
MUMBAI BOP
PORT OFFICE - - -
MUMBAI
ANNEXURE - D
-------------------------------------------------------------------------------------------------
Sl.No. Foreign Currency Symbol
------------------------------------------------------------------------------------------------
1. Argentina Peso AP
2. Australian Dollars AD
3. Austrian Schillings AS
4. Belgium France BF
5. Canadian Dollars CD
6. Czeck Kroners CK
7. Dutch Gliders DG
8. Danish Kroners DK
9. Dubai Dollars DD
10. Deutshe Marks(W.German) DM
11. East Germany Marks EM
12. Espana Dollar VD
13. French France FF
14. Finland Markka FM
15. Hong Kong Dollars HD
16. Hungary Forint HF
17. Indian Rupees RS
18. Italian Liras IL
19. Japanese Yen JY
20. Malaysian Dollars MD
21. Norweign Kroners NK
22. Pound Sterling PS
23. Poland Zloty PZ
24. Russian Roubles RR
25. Rumanian LEU RL
26. Singapore Dollars SD
27. Swiss Francs SF
28. Swedish Kroners SK
29. Thailand Baht TB
30. U.S.Dollars UD
31. Norweian Korea NK
CHAPTER – 9
e-PROCUREMENT
CHAPTER – 9
e-PROCUREMENT
162 E-Procurement:
162.1 The Purchase Requisitions (Indent) for SRM (E-Procurement Module) tenders
will flow automatically from SAP-R/3 system. The process for approval of
BECs, Evaluation matrix etc. will take place as per existing process. After due
approval, all related documents will be up-loaded in the system by the dealing
officer. Thereafter the dealing officer will prepare the bid-invitation and upload
the same after affixing digital signature as per the IT Act, 2000.
162.2 The NIT in respect of all tenders of value more than Rs 5 lakhs shall be
published on the ONGC tender website (www.ongctenders.net). The tender
website shall have a link to SRM server. Prospective bidders who intend to
participate in the Open Tenders can logon to SRM server with Guest user ID
and view the documents and may request for access through the portal by
providing basic information about them. Thereafter, user ID and password will
be issued to them. The vendors will also be given necessary help for
understanding the system.
162.3 For e-procurement tenders, the tender fee shall be specified in Indian Rupees
amount as specified at para 40 of MM Manual, corresponding to the value of
the tender.
The tender fee shall be collected through online payment gateway only, in
case of e-procurement tenders. The prospective bidders can create their bid
online only after payment of tender fee. Indian Agents can not purchase
tender documents on behalf of their foreign principals, in case of e-
procurement tenders. The payment of tender fee through electronic payment
gateway can be made using Credit Cards or Bank Transfers. Foreign bidders
are also allowed to purchase tender document by making e-payment using
Credit Cards issued either in India or outside India.
162.3.1 MSEs registered with District Industry Centers or Khadi and Village
Industries Commission or Khadi and Village Industries Board or Coir Board or
National Small Industries Corporation or Directorate of Handicrafts and
Handloom or any other body specified by Ministry of MSME who intend to
claim exemption from payment of tender fee, must furnish the evidence that
they are registered for the items they intend to quote. Such documentary
evidence should be submitted to ONGC at least 7 days in advance of date of
closing of sale of bid documents. The Govt. Deptts. will also be exempted
from the payment of tender fee.
162.4 In the NIT published on the website, the name, designation and e-mail
address of the designated Administrator who is to be contacted by bidders, as
nominated by concerned In-Charge (MM) for the particular tender, should be
indicated.
162.5 As all tender conditions including the standard booklet conditions will be made
available on the e-procurement portal which can be accessed by the vendors,
hence it will not be necessary for the bidders to separately purchase the
standard booklets (as is the case in respect of other tenders i.e. against a fee
of US$ 10.00 from foreign bidders and Rs. 500.00 from Indian bidders).
162.6 It shall be insisted that all bidders participating in e-tenders should submit bids
only in e-form. Compliance/confirmation for pre-qualification criteria and
technical / commercial BEC should be insisted in e-form only. Only Bid Bond,
Power of attorney of signatory or any specific third party document insisted in
Originals as per tender condition alone shall be accepted in physical form. For
submitting the bids, the vendors will also require digital signature. The system
shall assist in evaluation of bids by providing price comparisons and other
relevant reports. All such reports, TC recommendations and approvals which
will be outside system, will be subsequently uploaded in the system by the
dealing officer.
162.7 After finalization of tender, the supply orders will be issued through SAP – R3
system.
162.8 The activity wise responsibilities in the e-procurement system are defined as
at Annexure-A.
162.9 Other provisions of MM Manual and Instructions issued from time to time,
shall be followed by all concerned, as in case of non e-procurement tenders.
162.12.1 The duly completed bid with no system error message can be ‘submitted’
in SRM any time before the submission deadline is reached. The bidder
shall also be permitted to make changes in his bid and re-submit the same
in SRM till the submission dead line. The final submitted version of bid only
shall be considered by ONGC.
162.13.1 With the assistance of ICE team, training for vendors shall be facilitated
to meet:
162.14 The due date and time for price bid opening should be intimated well in
advance to the bidders, through the System.
Annexure-A
(MM/60/2011 dated
03.06.2011)
36 Opening of price bid of short E In SRM, the price bids are opened
listed vendors on given date as per SRM procedure by dealing
and time. officer after the pre-fixed opening
time and short listed bidders are
entitled to participate in the
automatic opening of price bid and
the prices quoted by different
bidders are read out to all.
(MM/55/2010 dated
05.07.2010)
163.2 Estimated annual off-take shall need to be indicated in the NIT and tender
document so as to enable the bidders to get an idea of the volume of
expected business at the time of bidding. Estimated initial order quantity,
separately for PEL/ML areas and non-PEL/ML areas, shall also be
indicated in the tender documents.
163.3 It shall be made clear in the tender documents that there shall be no
minimum guaranteed off-take by ONGC. Payment shall be released by
ONGC only for the actual quantity consumed or retained beyond 9 months
by ONGC as per contract provisions.
163.4 Evaluation of offers will be based on the “Criteria for Ranking of Bidders”
and “Details and Documents to be submitted for evaluation of Bits”, as per
Annexures to this Chapter (i.e.‘Annexure-A-1’ and ‘Annexure-A-2’
respectively).
163.5 Two Bids System shall be followed in the Price Bid and bidder shall submit
the price list of the offered products. The price list shall cover the sizes
required by ONGC for TCR & PDC bits under their product range. Bidder
shall submit separate sealed price covers for each size of Bits, say 17 ½”,
12 ¼”, 8 ½” & 6”. For any other sizes Annexure A-1 & A-2 will be framed
by Bit Committee [as constituted by Director (T&FS)] on requirement
basis.
163.6 Bidders shall be technically ranked as per the net marks scored against
the evaluation criteria placed at Annexure-A-1. Bidder(s) scoring highest
net marks will be ranked as TR-1, the next highest as ranked as TR-2 and
so on.
163.7 Contract is to be awarded to the top ranked bidder as per procedure given
below:
(a) In case only one bidder is ranked as TR-1, the price bid of such
bidder shall only be opened.
(b) In case of tie in bidders ranked as TR-1, price bid of bidder ranked
as TR-1, with highest marks in ‘B’ in respect of ‘bit specific information’
as per the evaluation criteria specified at Annexure-A-1, shall only be
opened.
163.8 For assessing the reasonability of prices, bidders may be asked to submit
documents establishing the prices at which the bidder has supplied same
or similar type of bit to other Oil / Gas company in last 2 years. In case
the quoted prices are found to be on higher side in comparison to the
supply prices of bidders as above or the LPR of same Bit, negotiations
may be carried out by tender committee with the approval of Competent
Authority, as per the prevalent MM guidelines.
163.9 As only one bid i.e. ranked # 1 shall be considered for award of contract,
the Competent Purchase Authority shall be determined as per the powers
applicable in case of Single Tender, i.e. as per clause MP4 (d) of BDP.
163.10 Supplier shall mobilize the initial quantity within 35 days of placement of
S.O. Subsequent call-out orders shall be placed by the authorized
representative of ONGC, as and when required. Such call out quantity has
to be delivered within 15 days of issue of call-out order.
163.11 Required quantities of each type of bit shall be drawn from the stock
maintained by supplier.
163.12 The inspection of bits shall be carried out by ONGC representative after
receipt of bits in India.
163.13 Selection of suitable TCR/PDC bit of any size from the available lot of bits
will be made by ONGC.
163.14 Payment:
(e) Quantity for which payment shall be made to the supplier should
not exceed the ordered quantity.
163.15 Provision shall also be kept for outright purchase of suitable left over bits
at the end of contract period, at the sole option of ONGC. Quantity of bits
retained at the end of contract period shall not exceed the initially ordered
quantity against the contract.
163.16 Contract duration shall be 3 years from the date of notification of Award of
Rate Contract, without any provision for price escalation and also without
any provision of extension of the contracts.
163.17 Other provisions of MM Manual and Instructions issued from time to time
shall be followed by all concerned, as in case of other tenders.
Annexure – A- 1
Criteria for Ranking of Bidders
A. General Information:
Sl. Parameters Allocation of Marks Weightage Marks
No. Factor
1 Experience of Bit Highest among the 100 0.05
Manufacturer bidders
(Minimum Required Others Percentage to
experience – Five the highest
Years)
2. Sales volume of Highest among the 100 0.05
Bits for the last bidders
three years Others Percentage to
the highest
3. Expenditure on Highest among the 100 0.10
R&D for the last bidders
three years Others Percentage to
the highest
Total (A) (For 1 to 3 0.20
above)
Bits used in No. of bits used for Deep Drilling Last three years
deep drilling Depth 2000M – 3999M Bit record for
Depth 4000M – 4999M 2000M and
Depth above 5000M above depth
Multinational No. of Premium bits supplied to Purchase
clients following companies during last reference, annual
three years: reports or any
Shell, Cheveron, BP, Agip, other authentic
Totalfina, Statoil, Petrobras, documents.
Unocol, Exxcon Mobil, Kerr Mcgee
Supplies in No. of bits supplied to Indian Purchase
India Companies during last three years reference
for offshore
No. of bits supplied to Indian Purchase
Companies during last three years reference
for onshore
Performance of Best five bit performances in last Bit Records
bits three years in depth range of
2000M-3999M
4000M-4999M Bit Records
Above 5000M Bit Records