Industrial Training Diary Weekly Activity Log
Industrial Training Diary Weekly Activity Log
Name of Company :
Day of the
Date Projects / Activities
Week
Monday 14/02/11 1) First day, I follow Mr.Lau(site supervisor) to
which is at Kim kee Lot 13453. After that Mr. lau told
2) After me look around the site, and familiar with the site,
Mr. Lau teach and explain the procedure and the method
Lau is using the black oil and square shape of wood with
method that cant get from the book that study at college.
4) I aslo help Mr. Lao pat the wood on the ground to tag the
location that will be excavate.
water in the pit that for the footing before cast in the
part of the site. They pump out the water inside the pit by
of 30m3, but in the end there is not enough for the few
havent cast in. In the end I found that this method can
progress smooth.
there, I learn that before lay the dpc, must lay a layer of a
moisture.
the worker can view the position and easy to insert the
drawing on site.
1) Mr.Lau ask me go to site at Jalan Junid , Cempeka to see
bottom.
the requirement.
Signature of Supervisor: