Project Description For Scoping
Project Description For Scoping
There is obviously a need for this type of project since LPG is now becoming the preferred
fuel in the country for economic reasons and convenience to customers.
project was found acceptable to the barangay residents and officials due to its beneficial
social and economic benefits to the community.
The station will be provided with a centralized wastewater treatment plant for the various
refilling effluents. All domestic wastewaters discharged from the various refilling activities
will be treated in three (3) chamber septic tanks.
Project Size
Total Project Area
The proposed project shall cover a land area of FIVE THOUSAND SIXTEEN (5,016)
SQUARE METERS (0.5 hectare) which i
is attached as
Liquefied Petroleum Gas (LPG) is available locally as a combination of liquid propane and
butane gases which is produced by the local or foreign oil refineries. LPG in bulk is
delivered by tank trailers and pumped to the horizontal, bullet-shaped storage tanks. LPG
is kept under pressure by means of compressors with propane having a compression rate
of 94 MJ/cu. m. and butane at 121 MJ/cu. m.
By means of a Corker pump which is equipped with multi-pass differential valve, LPG is
filled into cylinders at the filling rows. The LPG cylinders will come in three (3) standard
sizes, 11.0, 22.0 and 50 kilograms. After the desired weight is attained, the fillers are
uncoupled and the filled cylinders are stored ready for delivery.
Power Generation & Water Supply System
The project proponent shall obtain its power requirements from the local electric
cooperative. The LPG refilling station project will also be provided with a standby diesel-
engine generator set to supply any electrical requirements in case of power failure. The
water requirement needs for the LPG refilling station project will be provided with a deep-
well and water storage tank.
waste treaters.
Pre-Construction Phase
The pre-construction activities which consist essentially of the planning aspects of the
project have been virtually completed. These include the preparation of the financial
feasibility studies, master development plans, detailed engineering specifications, budget
estimates, project timetable, etc.
This period also includes the obtainment of the various clearances/ permits from the
DENR, HLURB, LGUs and other government agencies. These are presently in progress.
Construction Phase
The site development and construction phase shall start the physical implementation of
the project. The major activities to be undertaken during this period are the following:
The various construction activities shall be implemented using the following
guidelines/specifications:
Construction Materials
The construction materials to be used in the project shall be strictly in accordance with the
codes, standards and specifications acceptable in the Philippines such as those set by the
American Institute on Steel Construction (AISC), American Concrete Institute (ACI),
American Welding Society (AWS) and the American Society for Testing and Materials
(ASTM). Some of the materials to be utilized are cement, sand and gravel, aggregates,
steel bars, lumber, welding rods, etc. These are all available locally and shall be
purchased from the most convenient sources.
Construction Equipment
At one stage or another of the construction activities, the project proponent or its
contractors may utilize the following commonly used construction equipment:
Compactor
Concrete Mixer
Concrete Pump
Crane
Front Loader
Generator
Grader
Jackhammer
Paver
Pile Driver
Pump
Tractor
Bulldozer
Truck
Vibrator
Construction Facilities
The proposed site will be provided with temporary structures which will be needed during
the construction period. These include the following:
The contractors shall likewise be required to enforce all safety measures to prevent /
minimize accidents and injuries to the construction workers. These include the compulsory
wearing of hard hats, goggles, gloves and the general observance of safe construction
practices.
The waste generated during construction is provided with the portalet and will be treated
by the DENR accredited treater.