Questions - Task 2
Questions - Task 2
1. What are at least six (6) major resources required for tasks identified in a
work breakdown structure?
The main features required for the identified tasks of a work breakdown
structure are as follows:
Human Resources
Equipments
Materials
services
Costs
Fees and charges
installations
2. What are the main steps in the budgeting process for a project?
Cost estimation;
Budget determination;
Control and monitoring of expenses.
3. List at least (3) three environmental enterprise factors that can influence
a cost management process.
Resource availability.
Geographic distribution of facilities and resources.
The infrastructure.
Employee capability.
4. List (4) four organisational process assets that can influence the cost
management plan of a project.
The four organizational process assets that can influence a project's cost
management plan are as follows:
There are several tools and techniques to estimate costs, among which
we can highlight the following:
Analogous Estimate
Bottom-up estimates
Computerized tools.
Stadium Estimate
6. Describe the ‘Estimated Costs’ process and the key benefit of the
process.
The “estimated costs” process initially takes into account a list of project
costs. Cost estimates detail each component of the work required to
bring the project to life, describing the assumptions underlying each cost,
inclusions and exclusions, and associated risks. Then, an estimation
technique and/or tool is applied depending on the complexity of the
project.
The main benefit of the process is to ensure that no stage of the project
is forgotten and to provide a budget that is closer to reality.
7. Describe the ‘Determine Budget’ process and the key benefit of the
process.
The main benefit of this process is the determination of baseline costs for
monitoring and controlling project performance. This process is carried
out once or at predefined points in the project.
direct costs
Indirect costs
human resources cost
project costs
Risk assessment
The Cost Management Plan describes how project costs will be planned,
structured and controlled by providing details of the processes and tools
used, and is intended to guide the team throughout the project to cost-
related issues to ensure that the project be delivered within the approved
budget.
11. What is Cost Performance Index (CPI) and the formula used to calculate
it?
The Cost Performance Index (CPI) is a method for calculating the cost
efficiency and financial effectiveness of a specific project through the
following formula:
12. What is Schedule Performance Index (SPI) and the formula used to
calculate it?
Formula: SPI=EV/PV
13. If a cost estimate is $50 000 +/- 20%, what is the range?
14. A project has an Earned Value (EV) of $10 000, Actual Cost (AC) of
$8000 and Planned Value (PV) of $8000. Using the correct formula, what
is the Schedule Variance (SV)?
SV=EV-PV
SV=10,000 - 8,000
SV=2,000
16. You discover you cannot meet your current project cost baseline due to
fluctuating international exchange rates. You calculate a bottom-up
estimate of remaining work at $2.5 million. The project’s current actual
cost (AC) is $3.5 million. Using the correct forecasting formula, calculate
the project estimate at completion. (You must show formula and
breakdown).
17. Imagine you need to make changes to existing time frames in order for
project tasks to be completed by a specific time and to maintain financial
objectives. Describe how you would implement an agreed action and
provide timely financial reporting.
18. Outline the procedures of a cost change process for a project.
19. In the role of project manager, what six (6) activities would you conduct
on financial completion of a project?
20. When completing cost management processes, what four (4) records
could you review to determine the outcomes reached?
21. Briefly explain the process of reviewing cost management issues and
documenting improvements.