Computer Application Lab (5019)
Computer Application Lab (5019)
5019-COMPUTER APPLICATION
LAB
SEMESTER - V
LAB MANUAL
LIST OF EXPERIMENT
3 ANALYSIS OF A FRAME
5 DESIGN OF A FRAME
1 INTRODUCTION TO MS PROJECT
1 PROFILE LEVELLING
INTRODUCTION TO MS PROJECT
AIM
To familiarize the basic operations like task and duration in MS Project Professional 2016
SOFTWARE USED
THEORY
1. Material resources
2. Man power resources
Technology deals with material resources whereas management deals with both
material resources as well as man power resources.
Microsoft Project
1. Quick Access Toolbar − A customizable area where you can add the frequently
used commands.
2. Ribbons interface area – where tools are placed in organised groups.
3. Commands − The specific features used to perform actions. Each tab contains
several commands. Pointing at a command, its description is available in a
toolpit.
4. View Label − This appears along the left edge of the active view. Active view
is the one you can see in the main window at a given point in time. Project
includes lots of views like Gantt Chart view, Network Diagram view, Task
Usage view, etc. The View label just tells you about the view you are using
currently. Project can display a single view or multiple views in separate panes.
5. View Shortcuts − This lets you switch between frequently used views in Project.
6. Zoom Slider − Simply zooms the active view in or out.
7. Status bar − Displays details like the scheduling mode of new tasks (manual or
automatic) and details of filter applied to the active view.
MA’DIN POLITECHNIC COLLEGE Page 5
COMPUTER APPLICATION LAB Civil Engineering Department
PROJECT INFORMATION
A dialog box appears. In the start date box, type DD/MM/YY, or click the down arrow
to display the calendar, select any date. Click OK to accept the start date.
Night Shift − Covers 11 PM to 8 AM, night shifts covering all nights from Monday
to Friday, with one hour breaks.
1. Launch MS Project
2. Click File Tab. Under Info Tab go to Project Information. Click arrow near
Project Information to click Advanced Properties. A dialog box opens, you can
type in the changes as required. Click OK and don‟t forget to save by clicking
on Save.
A view is a working place in MS Project where you can enter, edit, display and analyse
information of the project plan.
It shows details about each task that which task is assigned to whom and
working schedule of each resource.
5. Calendar view
Tasks bars appear on the days they are scheduled to start.
6. Network Diagram view
It shows relationship among tasks and also the dependencies
PROJECT PLAN:
A project plan is a model which is constructed based on some of the following aspects
of real project.While starting a new project, Project Manager must have answers to the
following important questions in his/her mind to produce deliverable of the project:
1. Project Planning : Plan is made and strategies are set, taking into
consideration the company‟s policies, procedure and rules.
2. Project Scheduling: Allocation of resources
3. Project Controlling: Reviewing the difference between the schedule and actual
performance once the project has begun.
PLAN
SCHEDULE
TASKS
Defining the right tasks to create the right deliverables (product) is must. Tasks listed
in a project should describe all of the work required to complete the project
successfully.
DURATION
A duration of the task is the estimated amount of time it will take to complete a task.
MILESTONES
A milestone is a check point in your project that must occur but does not take any time.
Because the milestone normally does not include any work, so presented as task with
ZERO duration. They are used as major progress points to manage project success and
stakeholder expectations. They are primarily used for review, inputs and budgets.
In a Task entry table, enter a name for milestone and in the duration field enter
„0‟ day and then press “ENTER”. It creates a milestone.
SUMMARY TASK:
The highest level of a plan‟s outline structure is called the Project Summary Task,
which encompasses the entire project schedule. A bunch of related tasks rolled up
together to organize the plans to phases. There are several number of sub-tasks under
any higher level task. These higher level tasks are called Summary Task. At an even
higher level, they are called Phases.
Summary task is not a separate task entity but a phase of the project with several sub-
tasks in it, the duration of the summary task is from the start of the first sub-task to the
finish of the last sub-task. This will be automatically calculated by MS Project.
RECURRING TASKS
A recurring task is any task that occurs at regular intervals (daily, weekly, monthly, or
yearly) during the course of a project. Examples of such tasks might be weekly visits
to a project site, daily preparation of project status reports, or monthly meetings with
members of the project team.
When you enter tasks initially, Project schedules each task to begin on the project start
date and to run for the task duration. You may, however, want your tasks to occur in a
particular sequence.
1. Predecessor task - A task that must start or finish before another task can start
or finish is called a predecessor task.
2. Successor task - A task that cannot start or finish until another task starts or
finishes is called a successor task.
Task
Meaning Gantt Chart Example
Relationship
The finish date of the Painting is done
Finish-to-
Start(FS) predecessor task determines the after plastering is
start date of successor task. completed.
The start date of the predecessor Slab works of upper
Start-to-
Start(SS) task determines the start date of floors and plastering
successor task. in down floors can
do simultaneously.
The finish date of the Tasks that require
Finish-to-
Finish(FF) predecessor task determines the specific equipment
finish date of the successor task. must end when the
equipment rental
ends.
The start date of the predecessor In water cycle, if
Start-to-
Finish(SF) task determines the finish date of condensation starts,
successor task. evaporation ends.
ORGANIZE TASKS INTO PHASES
RESULT
Familiarized the basic operations like tasks and duration in MS Project 2016.
AIM
To do a simple construction plan and print it using Microsoft Project Professional 2016
SOFTWARE USED
PROCEDURE
1. Open Microsoft Project Project 2016 and save the file (can be saved in
previous formats if required) with a file name.
2. Create a New Project and Save the file using suitable name
3. Set the „Project Information‟ details.
Go to „Project‟ „Project Properties‟ ribbon „Project information‟
● Title of the Project
● Manager of the Project
● Company Information
Set the starting and current date. Choose the type of calendar(Standard).
4. Set working and non-working time
a. The project calendar defines the general working & non-working time for tasks.
Project Properties ribbon Change Working Time
i. Select the base calendar (Normally standard)
ii. In the Name field on Exception tab, enter a descriptive name for
the non- working time, such as Holiday.
iii. In the Start and Finish fields, type or select the start and finish
dates for the non-working time span.
iv. Active “Work Weeks” tab and then click Details button to change the
v. default non-working days and timing. Click OK.
5. Enter the name of tasks
a. Go to the „Task Name‟ column and enter the „Task Name‟.
b. Press „Tab key‟ to change to next cell, add duration of that task.
6. To auto schedule all the cells, click on the cell near to „Indicators‟. Then go ot „Task‟
„Tasks‟ ribbon Select „Auto Schedule‟. Gantt chart colour becomes dark blue.
RESULT
Simple construction plan is done and printed using Microsoft Project Professional 2016
AIM
To assign man and equipment resources to a project; and to estimate the completion
time and cost of a simple construction project using Project 2016.
SOFTWARE USED
RESOURCES:
MS Project works with three types of resources: work, material and cost. Work
Resources are the Individual People can be identified by their Name (like Mr. Ahmad)
or designation (like Manager) and group of people resources can be defined by their
common skills like programmers. People and equipment that do the work of the
project. Optimum Resource Scheduling is the key to successful project management.
RESOURCE TYPES
Resource Example
Work resource as an identified person Aman, Vishnu, John
Work resource as a job function or group Engineer, Coordinator, Typist
Work resource as an equipment Lathe machine, Earth mover
1. lick Task Tab → double-click the required task under Task Name column → Task Information dia
2. Click the box under the Type column and choose the relationship according to
your requirement.
RECURRING TASK
Status meetings, status reports, inspection dates can recur with a particular frequency.
a. Gantt Chart View → Task Tab → Insert → dropdown box for Task →
Recurring Task.
b. Enter Task Name and choose Recurrence pattern.
PROCEDURE
10. Open Microsoft Project 2010 and save the file (can be saved in previous
formats if required) with a file name.
11. Fill the project information – File Project Information Advanced properties
12. Go to View menu Resource views Resource sheet
a. In the Resource Name field, enter the resource‟s name
b. In the Type field, select the type (Work/Material/cost).
c. In the Max. Units field, type or click the maximum capacity of this
resource to accomplish any work in terms of %.
d. Enter any other useful information related to your project
e. Repeat these steps for each resources.
13. Once the task and resource list are complete, resources need to be assigned to
tasks in order to work on them.
a. Click View Tab → Gantt Chart View → Resource Name column.
b. Click the box below the Resource Name column for the task you
need the resource to be assigned.
c. From the dropdown, choose the resource or material names.
14. After assigning resources to tasks you can view the cost, duration and work
required for the plan to complete.
a. To see the plan‟s start and finish dates, see the „Timeline‟
b. To see the plan‟s cost, Click View tab → Data group → Tables → Cost.
15. To get the total cost of project, Format menu → Show/Hide → „Project Summary Task‟.
RESULT
Rs. 59.690/-
AIM
SOFTWARE USED
CRITICAL PATH
The critical path is the longest sequence of activities in a project plan which must be
completed on time for the project to complete on due date.
An activity on the critical path cannot be started until its predecessor activity is
complete; if it is delayed for a day, the entire project will be delayed for a day unless
the activity following the delayed activity is completed a day earlier.
If any of the activities on the critical path change, the end date of the project will be affected.
The word “critical” does not mean that the tasks are complex or important or need
to be closely monitored, but the focus is on terms schedule that will affect the
project finish date.
If you want to shorten the duration of a project, you should first start with
activities/tasks on the critical path.
Critical path is the longest path through a network of activities, which in-turn, determines the
shortest time possible to complete all tasks in the network (i.e. the shortest time to complete
the project).
There are three possible paths in the network, with one being the
longest: A → B → C → F = 1 + 2 + 1 + 1 = 5 days
SLACK OR FLOAT
Slack or Float are key to understanding Critical path. There are two types of
Float –
a. Free Float − It is the amount of time a task can be delayed without delaying another task.
b. Total Float − It is the amount of time a task can be delayed without delaying the
completion of the project.
Estimated finish date and time details can be noted from the timeline.
DEFINITIONS
Early Start – The earliest time that an activity can start according to the logical constraints.
Early Finish – The earliest time that an activity can finish according to logical constraints.
Late Start – The latest time that an activity can start according to logical
constraints and without affecting the overall project duration.
Float – The time by which an activity may be delayed without affecting the overall
project duration.
Late Finish – The latest time that an activity can finish according to logical
constraints and without affecting the overall project duration.
PROCEDURE
1. Open Microsoft Project 2010 and save the project file (.mpp)
2. Set the currency units and default settings
File Options Display Currency
3. Fill the project information
File Project Information Advanced properties
1. Title
2. Manager
3. Company Name, etc
4. Set the start and finish dates
a. Set the calendar
5. Set working and non-working time
a. Specify holidays
b. Specify working hours
6. Enter tasks and sub tasks in the „Task Name‟ column with suitable indentation.
a. Auto schedule the tasks.
b. Link the adjacent tasks.
c. Add predecessor details.
i. Add lag or lead details
d. Enter duration for
each tasks.
7. Add man and material resources to resource sheet.
a. Add Resource name
b. Type
c. Standard rates
d. Over time rates
e. Fixed cost, etc
8. Display the critical path of the project
a. Format menu → Bar Styles Group → Check the Critical Tasks box ON.
9. Display and print the Gantt chart view and Network diagram for the entire
project with its resource sheet in an A3 Sheet.
RESULT
Estimated completion time for the project is found from timeline as 2018 Mar
18. The critical path is found and is indicated in the report.
AIM
To familiarize the user interface and analyse a simple beam using STAAD.Pro
SOFTWARE USED
STAAD.Pro
THEORY
STRUCTURE
When a body is subjected to a system of loads and deformation takes place and the
resistance is set up against the deformation, then the body is known as structure. The
structure are means of transferring forces and moments.
ANALYSIS
1. Stress distribution
2. Displacement
3. Critical buckling loads
METHODS OF ANALYSIS
TYPES OF STRUCTURES
Type of
Details
Structure
Space 3D framed structure with loads applied in any plane (The most general).
Plane 2D structure framed in the X-Y plane with loads in the same plane
2D or 3D structure having no horizontal (global X or Z) movement of the
Floor
structure (FX, FZ & MY, are restrained at every joint)
Any structure consists of truss members only, which can have only axial
member forces and no bending in the members Columns can also be modelled
Truss with the floor in a FLOOR structure as long as the structure has no horizontal
loading. If there is any horizontal load, it must be analysed as a SPACE
structure.
Stiffed joint with 6 reactions. It is located at each end of Beam, and each corner
of Plate. Nodes considered the essence of the Geometry of any structure in
Node STAAD.Pro. Each Node will hold the following information:
Node Number.
Node Coordinate in XYZ space
Any member in the structure. It can be beam, column, bracing member, or truss
member. Each Beam will hold the following information:
Beam
• Beam Number.
The Node numbers at its ends.
a thin shell with multi-nodded shape
Starting from 3 nodes, and more. It can be anything of slab, wall, or raft
Plate foundation. Each Plate will hold the following information:
• Plate Number.
• Node Numbers at each corner of it.
PROCEDURE:
2. Click New Project Tick “ Space” Add „File Name‟ and choose location
Change Length Units to “Meter” and Force units “Kilo Newton” Click
„Next‟.
Select geometry from menu bar and click on „Nodes‟ or we can add Nodes
directly in the Grid that appears in the main window.
them too.)
Select the added load from the „Load and Definition‟ window in the data area.
11. Add Load values : Scale Labels Load values Apply OK.
6) ANALYSIS
14. Analysis:
16. Results:
Mode Post processing Result view options Apply
OK. Click „View Output file‟ Done.
7) STRUCTURE DIAGRAMS
This may not visible like this. This is incorporated in toolbar as below.
Click on required icons to get various result diagrams.
automatically)
Click OK Close.
RESULT
Analysed a simple beam and plotted various structural diagrams using STAAD.Pro
AIM
To analyse a cantilever beam and to plot various structural diagrams using STAAD.Pro
SOFTWARE USED
STAAD.Pro
PROCEDURE
RESULT
Analysed a cantilever beam and to plotted various structural diagrams using STAAD.Pro
AIM
To analyse a continuous beam and to plot various structural diagrams using STAAD.Pro
SOFTWARE USED
STAAD.Pro
PROCEDURE
RESULT
Analysed a continuous beam and plotted various structural diagrams using STAAD.Pro
AIM
SOFTWARE USED
STAAD.Pro
PROCEDURE
RESULT
AIM
To analyse a frame with sway and to plot various structural diagrams using STAAD.Pro
SOFTWARE USED
STAAD.Pro
PROCEDURE
RESULT
Analysed a frame with sway and plotted various structural diagrams using STAAD.Pro
AIM
SOFTWARE USED
STAAD.Pro
PROCEDURE:
23. Click on to View from +Z. [Can consider it as the Front view]
24. Draw the beam length using Snap Node.
29. Add Load values : Scale Labels Load values Apply OK.
6) ANALYSIS
32. Analysis:
Commands Analysis Perform Analysis
All or No Print OK.
33. Result Analysis:
Commands Post Analysis Analysis Results Yes
OK Commands Analyze Run Analysis
34. Results:
Mode Post processing Result view options Apply
OK. Click „Go to post processing mode‟ Done.
7) STRUCTURE DIAGRAMS
8) DESIGN
456‟
Click on symbol „<<‟ Add necessary parameters like clear, Fc, Fymain, etc.
Copy and paste to MS Word and print required details from it.
RESULT
Analysis and design of a simple beam is done and the required structural
drawings were obtained using STAAD.Pro.
LOADING DIAGRAM
DEFLECTION PATTERN
INPUT FILE
MA’DIN POLITECHNIC COLLEGE Page 56
COMPUTER APPLICATION LAB Civil Engineering Department
STAAD SPACE
START JOB
INFORMATION
INFORMATION INPUT
WIDTH 79
UNIT METER KN
JOINT
COORDINATES 1
1 5 0; 2 9 5 0;
MEMBER
INCIDENCES 1 1
2;
DEFINE MATERIAL
START ISOTROPIC
CONCRETE
2.17185e+0
MA’DIN POLITECHNIC COLLEGE Page 57
COMPUTER APPLICATION LAB Civil Engineering Department
07 POISSON
0.17
DENSITY
23.5616
ALPHA 1e-
005 DAMP
0.05
TYPE CONCRETE
STRENGTH FCU
27579
END DEFINE
MATERIAL
MEMBER
PROPERTY
1 PRIS YD 0.45 ZD
0.23 CONSTANTS
MATERIAL CONCRETE
ALL SUPPORTS
1 2 FIXED
MEMBER
LOAD 1 UNI
GY -20 0 3
1 CON GY -50 6 0
ANALYSIS RESULTS
START CONCRETE
FC 25000 ALL
DESIGN
BEAM 1
CONCRETE
TAKE
RESULTS FINISH
SUPPORT REACTIONS
DESIGN RESULTS
AIM
SOFTWARE USED
STAAD.Pro
PROCEDURE:
RESULT
AIM
SOFTWARE USED
MS Excel
THEORY
Microsoft Excel is a spreadsheet application that is used for basic data organization,
statistical analysis, graphing data as well as many other uses. For mix design calculation
works, MS Excel can do a lot.
1) Start MS Excel and Set the page layout. Go to „Page Layout‟ ribbon
2) Check the data structure in IS 10262-2009 and Merge rows and columns as
required. It is done from complicated things to simpler. This is mind blowing task.
3) Center, right or left align the „Texts‟ using Alignment ribbon tools. Indentation
(increase or decrease of space between the left and right margin) can also done if
needed.
6) Add formula to cells : press „=‟ sign in a cell to start a formula definition.
RESULT
Concrete Mix Design is done for M40 and the mix ratio is obtained as 1:3:3.26 with
water cement ratio 0.40.
AIM
0.pdf )
SOFTWARE USED
MS Excel
PROCEDURE:
6. Using alignment tools like „merge and center‟, Left, indentation, etc, align
the data suitably so that easy understanding is obtained.
RESULT
Estimated the given masonry platform and prepared abstract of cost in MS Excel.
Grand total is obtained as Rs. 1,32,420/-.
AIM
SOFTWARE USED
MS Excel
PROCEDURE
PROFILE LEVELLING
102.500
101.820
102.000
101.500
101.000
Reduced Level (in m)
100.305
100.500
100.000
100.000 99.680 99.640
99.505
99.500
99.000
99.000
98.500
98.000 97.650
97.500
97.000
0 5 10 15 20 25 30 35 40
Chainage length (in m)
f. Add required chart elements like Data labels (To get value on each
points), Trendline (to get optimum formation level), etc.
7. The required profile is plotted.
RESULT
AIM
To plot the profile of plot and to estimate the cut and fill volumes for the given
earthwork project using AutoCAD
Size of a grid : 5 m x 5 m
SOFTWARE USED
1. AutoCAD 2016
2. MS Excel
THEORY:
CROSS-SECTION METHOD
The cross section method involves plotting cross sections of the existing and proposed
levels at regular intervals across the project site. For each of the cross sections, the cut
area and the fill area is determined. The volume between each pair of sections is
estimated by multiplying the average cut or fill area of the two sections by the distance
between them. Once these volumes have been calculated for each pair of sections the
total cut and fill volumes are obtained by adding them all together.
PROCEDURE:
RESULT:
Plotted the 3D profile of given plot and estimated the cut and fill volumes for
the given earthwork project using AutoCAD