0% found this document useful (0 votes)
52 views1 page

Quick Guide For Pressure Vessel Drawing Review

The document provides a checklist for reviewing pressure vessel drawing including checking the nozzle schedule, design data, bill of materials, fabrication details like earthing lugs and lifting lugs, weld details, loading data, nozzle allowable loads, painting requirements, and notes referencing project specifications.

Uploaded by

Idil Fitri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views1 page

Quick Guide For Pressure Vessel Drawing Review

The document provides a checklist for reviewing pressure vessel drawing including checking the nozzle schedule, design data, bill of materials, fabrication details like earthing lugs and lifting lugs, weld details, loading data, nozzle allowable loads, painting requirements, and notes referencing project specifications.

Uploaded by

Idil Fitri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Quick Guide for Pressure Vessel Drawing

Review
Quick Guide for Pressure Vessel Drawing Review.

Pressure vessels are among the key items in a mechanical packaged equipment e.g Instrument air
package, Nitrogen generators. Usually, vessel constructions shall comply with ASME Boiler and
Pressure Vessel Code (BPVC) Section VIII and the project specific requirements, including
welding specification. For vessel general arrangement drawing review, it should be completed
together with datasheet, calculations and welding document. This would facilitate the
consistency check between documents.

Checklist:

a. Nozzle schedule
b. Design data or equipment data table
c. Bill of material
d. Fabrication (welding) details to be shown:

 earthing lugs/ boss


 lifting lug
 access opening
 skirts
 nozzles
 other attachments

e. Weld details for main circumferential and longitudinal weld line


f. Loading data – operating, dry, wind, seismic and transportation
g. Nozzle allowable loads
h. Painting requirements
i. Notes referencing project specifications