Road Pavements Bituminous Mixes
Road Pavements Bituminous Mixes
May 2005 1
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Contents – continued
May 2005 2
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 3
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
oil, or other non-solvent solutions may be pavement up to the joint, and the
used on the interior of the vehicles, but corresponding area beyond it by hand, the
the amount shall be kept to a minimum joint or joint cavity shall be kept clear of
by brushing. Prior to loading, the body surfacing material.
shall be tipped to its fullest extent with
the tailboard open to ensure drainage of 10 With the exception of sand asphalt carpet,
any excess. The floor of the vehicle shall bituminous materials with a temperature
be free from adherent bituminous greater than 125°C shall not be laid or
materials or other contaminants. deposited on bridge deck waterproofing
systems unless adequate precautions are
Laying taken to avoid heat damage in accordance
with a good industry practice. A
5 On each day, and at each location where maximum temperature of 145°C is
bituminous material is laid, at least 300 permitted for sand asphalt carpet.
tonnes from an approved source shall be
placed before material from another 11 Hand placing of bituminous materials
approved source is used. If the Contractor shall only be permitted in the following
demonstrates that the materials from circumstances:
different approved sources are of
equivalent quality and possess equivalent (i) For laying regulating courses of
laying and compaction characteristics this irregular shape and varying
requirement will be waived. thickness.
(ii) In confined spaces where it is
6 Wherever practicable, bituminous impracticable for a paver to operate.
materials shall be spread, levelled and (iii) For footways.
tamped by an approved self-propelled (iv) At the approaches to expansion
paving machine. As soon as possible after joints at bridges viaducts or other
arrival at site the materials shall be structures.
supplied continuously to the paver and (v) For laying mastic asphalt in
laid without delay. The rate of delivery of accordance with BS 1447.
material to the paver shall be regulated to
enable the paver to operate continuously. 12 Hand-raking of surface course material or
The horizontal alignments, surface levels the addition of such material by hand
and surface regularity of the finished spreading to the paved area, for
surface shall comply with Clause 702. adjustment of level, shall only be
permitted in the following circumstances:
7 The travel rate of the paver, and its
method of operation, shall be adjusted to (i) At the edges of the layers of material
ensure an even and uniform flow of and at gullies and manholes.
bituminous material across the screed, so
that the material is free from dragging, (ii) At the approaches to expansion joints
tearing and segregation. at bridges, viaducts or other
structures.
8 Unless otherwise stated in Appendix 7/1,
or elsewhere in this Specification, 13 Hand laid work shall conform with the
materials shall be laid in accordance with requirements of this Clause except those
the requirements and recommendations relating to pavers.
for laying in BS 4987: Part 2 or BS 594:
Part 2, as appropriate. The minimum Compaction
thickness of material laid in each paver
pass shall be in accordance with BS 4987: 14 Bituminous materials shall be laid and
Part 2 or BS 594: Part 2, as appropriate, compacted in layer thicknesses, which
or the full course thickness, where this is enable surface level and regularity
less than the specified minimum in BS requirements to be met and adequate
4987: Part 2 or BS594: Part 2. compaction to be achieved.
May 2005 4
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
(i) by means of site trials in (ii) The materials, mixing and laying
accordance with BS 598: Part 109; plant proposed for the Works shall
or be used for the trial.
May 2005 5
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 6
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Density testing procedures shall not be 30 Tack coat or bond coat in accordance
situated in wheel track zones. with Clause 920 shall be spraying grade
cationic bitumen emulsion complying
Bituminous Sprays with Table 3 or Table 5 of the ‗Binder
Specification‘ published by the National
25 All bituminous surfaces shall be treated Roads Authority and shall be applied at
with a tack coat prior to overlay. The the uniform rate of spread specified in
application of the bituminous tack coat Appendix 7/4. The cationic bitumen
spray shall be carried out immediately emulsion shall not be permitted to collect
prior to laying the following course or in any hollows and shall be allowed to
surface treatment, which ever is specified break before the next layer is placed.
in the contract. The bituminous tack coat
spray shall comply with Clause 920 of 31 Construction plant and traffic used on
this series. This requirement shall not pavements under construction shall be
apply to bond and tack coats for thin suitable in relation to the material,
surface course systems complying with condition and thickness of the courses it
Clause 942. traverses so that damage is not caused to
the subgrade or the pavement courses
Protection and Rectification of Bituminous already constructed. The wheels or tracks
Layers of plant moving over the various
pavement courses shall be kept free from
26 Bituminous material shall be kept clean deleterious materials.
and uncontaminated. The only traffic
permitted to run on bituminous material 902 Reclaimed Bituminous
to be overlaid shall be that engaged in
laying and compacting the next course or, Materials
where a binder course is to be blinded or
surface dressed, that engaged on such 1 Reclaimed bituminous materials may be
surface treatment. Should any bituminous used in the production of bituminous
material become contaminated the base. The maximum amount of reclaimed
Contractor shall make it good by cleaning bituminous material permitted shall be
it and, if this proves impracticable, by 20% for coated macadam base complying
rectification in compliance with the 700 with BS 4987. The mixed material shall
Series. comply with the requirements of this
Series.
Regulating Course
2 When the amount of reclaimed
27 Regulating course material shall be made bituminous material comprises 10% by
and laid in accordance with the mass or less, compliance with this Clause
requirements of Clause 907. is not required. However, when it exceeds
10% by mass, the Contractor shall carry
Use of Surfaces by Traffic and Construction out trials to the satisfaction of the
Plant Employers Representative to demonstrate
that the mixed materials comply with the
28 Where a bituminous layer other than the requirements of this Clause.
surface course is to be opened to roadway
traffic as a temporary running surface 3 After mixing with recycled materials, the
without speed restriction, it shall be binder recovered from the mixture shall
surface dressed in accordance with have a recovered penetration value not
Clause 919 using chippings of category less than the value specified below. The
PSV60declared, unless otherwise specified binder shall be recovered from the
in Appendix 7/1. mixture in accordance with the
requirements of BS 2000: Part 397 and
29 All temporary running surfaces shall be tested in accordance with IS EN 1426.
thoroughly cleaned and a tack or bond
coat applied immediately prior to laying Specified Grade of Minimum Recovered
the succeeding course. Binder to IS EN 12591 Penetration Value of
(Paving Grade) Binder after Mixing
40/60 30
70/100 50
160/220 120
May 2005 7
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Aggregate Filler
2 The coarse aggregate shall comply with 3 When the coarse aggregate is crushed
Clause 901.3. The fine aggregate may be gravel, 2% by mass of total aggregate of
crushed rock or sand or mixtures thereof Portland cement or hydrated lime shall be
and the quality of the fine aggregate shall added. The percentage of fine aggregate
comply with the requirements of BS shall be reduced accordingly. Cement or
4987. The aggregate shall be in a surface hydrated lime is not required when
dry condition prior to mixing. crushed limestone gravel is used as the
coarse aggregate.
Filler
Binder
3 When the coarse aggregate is crushed
gravel, 2% by mass of total aggregate of 4 The binder shall be petroleum bitumen of
Portland cement or hydrated lime shall be paving grade 70/100 Pen complying with
added. The percentage of fine aggregate IS EN 12591.
shall be reduced accordingly. Cement or
hydrated lime is not required when
crushed limestone gravel is used as the
907 Regulating Course
coarse aggregate.
1 Regulating courses shall be in accordance
with sub-Clauses 2, 3 and 4 of this Clause
Binder
and the requirements of Appendix 7/1.
Bituminous materials for regulating
4 The binder shall be petroleum bitumen of
courses shall meet the requirements for
paving grade 70/100 complying with IS
the appropriate material, as specified in
EN 12591.
BS 594 or BS 4987 as relevant.
May 2005 8
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Binder
May 2005 9
Table 9/1: Composition of Base and Binder Course mixes
Clause 903 906 930 932 933 934
Heavy Duty Dense Macadam Heavy Duty Macadam Dense Macadam
Dense Macadam Dense Macadam Macadam Base with Base with grade Binder Course with Binder Course with
Description
Volume 1
May 2005
Base Binder Course grade 40/60 Pen 40/60 Pen Binder grade 40/60 Pen Binder grade 40/60 Pen
Binder (HDM50) (DBM50) (HDM50) Binder (DBM50)
Nominal Size 0/32 mm 0/20 mm 0/32 mm 0/32 mm 0/20 mm 0/20 mm
Nominal Layer Thickness (mm) 70 – 150 50 – 100 70 – 150 70 – 150 50 – 100 50 – 100
Min. Thickness at any one point (mm) 55 40 55 55 40 40
Aggregate Grading (% by mass passing)
Specification for Road Works
Crushed Rock Aggregate 4.0 % ± 0.6 4.7 % ± 0.6 4.0 % ± 0.6 4.0 % ± 0.6 4.7 % ± 0.6 4.7 % ± 0.6
Crushed Gravel Aggregate 4.5 % ± 0.6 5.0 % ± 0.6 4.5 % ± 0.6 4.5 % ± 0.6 5.0 % ± 0.6 5.0 % ± 0.6
Range of Temperatures
10
Max. Mixing Temperature (oC) 180 185
Series 900
Road Pavements – Bituminous Bound Materials
* When gravel other than limestone gravel is the aggregate, the material passing the 63 m test sieve shall include Portland cement or hydrated lime to the amount of 2 per cent by mass of the
total aggregate.
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 11
Table 9/2: Composition of Surface Course Mixes
Clause 910 911 915 912 909 916
Rolled Asphalt Surface Rolled Asphalt Coated Chippings Close Graded Dense Open Graded
Description Course Surface Course For Rolled Asphalt Macadam Surface Macadam Macadam Surface
(Recipe Mix) (Design Mix) Surface Course Course Surface Course Course
Volume 1
May 2005
Designationa 30% 0/14 35% 0/14 30% 0/14 35% 0/14 14/20 Gc 85/20 0/14 mm 0/10 mm 0/6 mm 0/10 mm
Nominal Layer Thickness (mm) 40 45 or 50 40 45 or 50 N/A 40 – 55 30 – 40 20 – 30 30 – 35
Min. Thickness at any one point (mm) --------- --------- N/A 35 25 15 25
Aggregate Grading (% by mass passing)
40 mm 100
31.5 mm 98 – 100
Specification for Road Works
Crushed Rock Aggregate 7.8 % 0.6 7.4% 0.6 6.5 % Min. 6.4 % Min. 1.5 % 0.3 --------- --------- --------- ---------
Crushed Gravel Aggregate 7.5 % 0.6 7.0% 0.6 6.5 % Min. 6.4 % Min. --------- --------- --------- --------- ---------
Crushed Rock Aggregate (excluding limestone) --------- --------- --------- --------- --------- 5.1% 0.5 5.3% 0.5 6.3 % 0.5 5.3 % 0.5
Crushed Rock Aggregate (limestone) --------- --------- --------- --------- --------- 4.9 % 0.5 5.2 % 0.5 6.0 % 0.5 5.1% 0.5
Binder Grade 40/60 Pen 40/60 Pen 40/60 Pen 70/100 Pen or 160/220 Pen 160/220 Pen
Range of Temperatures
12
Max. Mixing Temperature (oC) 190 170 180 155 145
Min. Rolling Temperature (oC) 105 --------- 85 60 80
Series 900
Road Pavements – Bituminous Bound Materials
a
The mixture designation numbers (e.g. 30% 0/14) refer to the nominal coarse aggregate content of the mixture and nominal size of the coarse aggregate in the mixture respectively.
b
May be increased to 38 in Clause 912 mixes and 60 in Clause 909 mix when sand fine aggregate is used.
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 14
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 15
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
17 For each of the satisfactory trial mixes, at Table 9/4: Site Control Test Requirements
least two circular specimens shall be Frequency
prepared, as described in BS 434: Part 2, Test Batch Continuous
for a wet track abrasion test. The
mixing mixing
approved mix proportions for the main
work shall be selected following Wet Track 4 times Every
laboratory tests using a combination of Abrasion Test (BS daily second run
bitumen emulsion, aggregate blended 434: Part 2)
where necessary with additive and water,
having a wet track abrasion test result of Grading of each Every 20 Every 20
less than 500 g/m2. separate stockpile tonnes tonnes
of sand and
18 When a proposed mix has been approved crusher run fine
variations shall not be made in mixing aggregate
time, mix proportions or in the type, size,
grading or source of any of the Grading of 4 times 4 times
constituents without the agreement of the samples of the daily daily
Employer's Representative who may blended aggregate
require further tests to be made.
Percentage of 4 times 4 times
Site Control Tests bitumen in the daily daily
cured seal
19 The mix proportions shall be controlled
and the mass of all materials incorporated 919 Surface Dressing
shall be checked and recorded at least
four times daily. The quantity of 1 Surface dressing shall be designed and
emulsion used, and the rate of spread of carried out in accordance with the
mixed material, in kilogrammes of recommendations of the Institute of
aggregate per square metre, shall be Asphalt Technology (IAT) – Guidelines
recorded for each load of aggregate and, for Surface Dressing in Ireland, published
if required, for each separate run within a in 2003, and the requirements as stated in
load of aggregate. Appendix 7/3.
May 2005 16
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
6 The Contractor shall monitor the Surface specified blinding, this shall be done in
Dressing closely for a minimum period of accordance with the requirements as set
2 hours, or as specified in Appendix 7/21, out in Clause 919 in so far as it applies to
after the road is opened to traffic. The the work to be undertaken in accordance
Contractor shall reinstate traffic safety with the under mentioned general
and management procedures or institute requirements and any specified
other remedial action where necessary, requirements as described in Appendix
such as dusting, if there are signs of 7/4.
distress, such as turning of the chippings,
in order to prevent further damage to the 3 The binder shall be spraying grade
Surface Dressing. cationic bitumen emulsion complying
with Table 3 or Table 5 of the 'Binder
7 Further operations to remove Specification' published by the National
subsequently loosened chippings shall be Roads Authority. Where a bond coat
carried out over the next 48 hours. The incorporating a polymer modified
road, and adjacent side roads, footways emulsion is proposed for use it shall have
and paved areas shall be kept prior written approval from the
substantially free of loose chippings for a Employers Representative. The binder
period of 30 days after completion of the shall be sprayed at a rate specified in
work. Appendix 7/4.
texture depth of each 1000 m section of discrepancy between the two methods,
carriageway lane or the complete only results obtained using the volumetric
carriageway lane where this is less than patch technique will be considered for
1000 m, shall be not less than 1.5 mm. compliance purposes.
The average of each set of 10 individual
measurements shall be not less than 1.2 922 Not Used
mm.
May 2005 18
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
shall be used with all binders that require 9 Hand application of the binder, to areas
heating. not accessible to the mechanical sprayer,
will be permitted if the Employer's
5 The vessels containing the components Representative approves the proposed
shall each be provided with an approved methods of batching, mixing and
method of measuring the volume of application of binder to the road surface.
material used. Similarly, in areas not accessible to the
mechanical aggregate spreader, hand
6 The machine shall spray the binder, such application of the aggregate will be
that the amount collected on any permitted.
longitudinal stretch of the surface 50 mm
wide within the width of the spray shall Aftercare
not be less than 90% of the overall
minimum requirement for the surface 10 The material used as masking shall be
being treated (see sub-Clause 8 of this removed together with the binder sprayed
Clause). The mean amount of binder upon it and the remainder of the binder
collected on any four adjacent 50 mm allowed to cure. During the curing period
wide strips shall be not less than 95% of no disturbance or trafficking of the
the overall minimum requirement. Before treated surface will be permitted. Before
work commences, and thereafter at opening to traffic at the end of the curing
intervals not exceeding one month, the period the excess aggregate shall be
Contractor shall provide evidence that the removed by vacuum sweeper or other
sprayer and all metering gauges complies approved means.
with the requirements of the
Specification. If required, the test to 11 The Contractor shall have regard to the
measure the spray pattern shall be made increase in cure time of the resin binder
in the presence of the Employer's with decrease in temperature in order to
Representative. allow sufficient time for the resin binder
to cure between the end of the spray
Preparation operation and the time when the road is to
be opened to traffic. Details of cure time
7 The surface shall be vigorously brushed variation of the resin with respect to
to remove dust, laitance and other loose temperature shall be supplied by the resin
matter. Any oil visible on the surface manufacturer.
shall be removed by washing and
scrubbing with a detergent solution Checking and Testing
followed by flushing with clean water or
by another approved method. The surface 12 A check shall be made by the Contractor
shall be allowed to dry before application at the end of each working shift to
of the binder. Existing road markings, determine the quantities used of each
ironwork and road studs shall be suitably binder component. The check shall be
masked. made by means of dip-sticks or other
approved devices. The measured
Application volumetric quantities of the components
shall be converted to mass units to
8 The binder shall be sprayed on to a dry estimate the average rate of spread of
surface at a rate which will vary binder upon the surface, by dividing the
according to the texture and porosity of total mass of the components by the
the surface. On a smooth close textured measured area of the surface treated. The
surface the amount of binder shall be not net aggregate coverage rate shall also be
less than 1.35 kg/m2 or such rate specified recorded.
by the resin manufacturer; on a more
rugous surface a greater rate of spread 13 The average accuracy of batching shall be
may be required. Heated binders shall be determined from the known used masses
allowed to cool before application of the of the components. The relative
aggregate. A mechanically metered plant proportions of components so determined
shall be used to cover the binder shall fall within the limits specified in
uniformly with an excess of aggregate. sub-Clause 4 of this Clause.
Rolling of the aggregate is not permitted.
14 The Contractor shall provide the
Employer's Representative with samples
of the binder, from the spraybar of the
May 2005 19
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 20
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
proposed for the Works shall be used for The air void contents shall be calculated
the trial. to ± 0.1 per cent as follows:
4 During the laying of the trial area, two Air voids content = (1 – ρ/ρMax) x 100%
samples of loose mixture shall be taken at
three evenly spaced locations along the where:
trial length, in accordance with BS 598: ρ is the bulk density in accordance with
Part 100, six samples in total. The BS 598: Part 104 (Mg/m3); and
maximum density of one sample of ρMax is the maximum density in
mixture from each location shall be accordance with IS EN 12697-5 (Mg/m3).
determined in accordance with IS EN
12697-5. The average value of maximum TABLE 9/5: Tolerances for Aggregate
density ρMax expressed in Mg/m3 shall Grading and Binder Content to be applied to
then be used for subsequent calculation of the Agreed Target Grading and Binder
the air void content of the compacted Content
mixture. The remaining samples shall be Tolerance for aggregate
analysed to determine their composition grading in percent by mass of
in accordance with BS 598: Part 102. Test Sieve
aggregate passing test sieve
(mm)
0/32 mm base 0/20 mm
5 At three locations, four nominal 150 mm course binder course
diameter cores shall be taken using a 63 ±0
suitable coring machine, in accordance 40 ±0
with BS 598: Part 100, twelve cores in 31.5 ±10* ±0
total. Two of the locations shall be from 20 ±12 ±5*
the wheel-track zones of the completed 14 ±12 ±10
traffic lane, the third location shall be 10 — ±10
agreed by the Employers Representative. 6.3 ±8 ±8
For the purposes of this Clause the wheel-
2.0 ±7 ±7
track zone shall be taken to be between
0.25 ±6 ±6
0.5 m and 1.1 m and between 2.55 m and
0.063 ±3.5 ±3.5
3.15 m from the centre of the nearside
0.063
lane markings for each traffic lane. Two ±2 ±2
cores from each location shall be tested (HDM)
using the PRD test procedure in
accordance with sub-Clause 2 of this Binder
±0.6 ±0.6
Clause. Content
Note: Application of the above tolerances to
6 At or adjacent to the location of the cores, the agreed aggregate target grading and binder
the density of the macadam shall be content may result in limits outside those
measured using a nuclear density gauge permitted by the appropriate table in BS 4987.
and the results correlated with the in situ Provided the target grading and target binder
air void contents determined in content of the mixture proposed for use, and
accordance with sub-Clause 7 of this agreed after trials, are within the limits
Clause. contained in BS 4987, then the limits obtained
by applying the above table shall prevail over
7 The air void contents of each core those implied in BS 4987.
subjected to the PRD test procedure shall
be determined, as follows: *The upper limit may be less than +5% (or
+10%), depending on the agreed aggregate
(i) The in situ air void content shall be grading.
calculated using, as the bulk density
ρ, the initial dried bulk density 8 The percentage binder volume Bvol shall
determined in accordance with BS be calculated for each location in
598: Part 104, and expressed in accordance with the following
Mg/m3; expression:
(ii) The refusal air void content shall be Bvol = BMass x (ρ/ρ b)
calculated using, as the bulk density
ρ, the refusal density determined in where: BMass is the target binder
accordance with BS 598: Part 104, content by mass added at the
and expressed in Mg/m3. mixer expressed as a
May 2005 21
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
(iii) Following the determination of (iii) The average air void content at
Stiffness Modulus, one core from refusal density of the core samples
each location shall be tested for subjected to the PRD testing
Deformation Resistance in procedure shall be not less than
accordance with DD 226: 1996, and 1.0%.
the other core shall be tested
similarly except that the DD 226 test (iv) The minimum binder volume at
procedure shall be modified in each location shall be as stated in
accordance with TRL Paper PA Table 9/6.
3287/97. Within 28 days copies of
the test sheets and results for TABLE 9/6: Aggregate Size and Minimum
stiffness modulus and deformation Binder Volume
resistance measured for each core Mixture Minimum Binder
shall be supplied to the Employers Size/Designation Volume (%) of the Total
Representative. Additionally if the Size (mm) Volume of the Mixture
trial area is on site, the exact 0/32 8
location of the cores, their dried 0/20 9.4
bulk densities, in situ air void
contents, the composition of the (v) The compositional analysis of
mixture determined using the aggregate grading and binder
methods specified in BS 598: Part content carried out in accordance
102 and the percentage binder with BS 598: Part 102 shall
volume determined in accordance demonstrate compliance with the
with sub-Clause 929.7 shall be requirements set out in sub-Clause
reported. No limits are specified for 929.1.
the Stiffness Modulus, except for
materials complying with Clause (vi) The horizontal alignments, surface
902, or for Deformation Resistance. levels and surface regularity of the
finished surface shall comply with
10 The trial area shall be acceptable if the Clause 702.
mixture complies with sub-Clause 11 of
May 2005 22
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Sampling and Testing from the Permanent 16 Samples of uncompacted material shall
Works be taken from the paver augers in
accordance with BS 598: Part 100, Clause
12 The compaction of macadams laid in the 6.3, as near to each location from which
Permanent Works shall be assessed by cores are to be taken as is practicable and:
determination of:
(i) The maximum density of a sample
(i) in situ air void content calculated of the mixture shall be measured in
from in situ density measured using accordance with IS EN 12697-5.
a nuclear density gauge on a running The value of maximum density so
basis; and determined, ρMax expressed in
Mg/m3, shall be used for the
(ii) in-situ and refusal air void contents subsequent calculation of the air
of pairs of cores taken every 500 void contents of the compacted
lane metres and subjected to the mixture at that location.
Percentage Refusal Density (PRD)
test procedure carried out in (ii) The compositional analysis of a
accordance with BS 598: Part 104. sample shall be carried out to
determine the aggregate grading and
13 The compaction of base and binder binder content in accordance with
course macadams shall be continuously BS 598: Part 102.
assessed using the nuclear density gauge
with readings taken at 20m intervals in 17 Each core extracted shall be examined for
alternate wheel-tracks, commencing with evidence of excessive voidage below the
readings at a location from which a pair depth to which the nuclear density gauge
of cores is to be extracted. Additional penetrates. If excessive voidage is
readings shall be taken 300 mm from the observed, further cores should be taken to
edge of the mat adjacent to each core determine its extent.
location. The Contractor shall take
corrective action as is necessary whilst 18 Each layer of macadam shall be sampled
the material is still above the minimum and tested separately. Where separate
rolling temperature specified in BS 4987- coring of each layer would unreasonably
2 if low densities are indicated at the time delay placing a second layer, subject to
of laying. the approval of the Employers
Representative, both layers may be cored
14 Initially the calibrations of the nuclear together and the resulting core split prior
density gauges established in accordance to testing.
with sub-Clause 6 of this Clause shall be
used. When results are available from 19 Cores shall be extracted without the use
loose samples and pairs of cores taken of excessive force. Cores shall not be
every 500 lane metres, each gauge shall taken until the material has cooled to a
be re-calibrated if the density measured temperature of 40°C or less at mid-depth
by that gauge and the density of the cores of the course to be cored. The walls and
show a different bias. Each gauge used base of all holes from which core samples
shall be individually calibrated. have been cut shall be dried and painted
with hot bituminous binder or cold
15 For material from each mixing plant, a applied polymer modified intermediate or
pair of nominal 150 mm diameter cores premium grade bitumen emulsion
shall be taken every 500 lane metres laid, immediately prior to making good. Core
one core from each wheel-track zone of holes shall be backfilled with dense
the completed carriageway as defined in bitumen macadam in accordance with BS
sub-Clause 929.5. Cores shall be 4987-1, or with coldlay 0/20 mm nominal
extracted using a suitable coring machine, size dense bitumen macadam binder
in accordance with BS 598: Part 100. course. Dense bitumen macadam
Each core shall be subjected to the PRD incorporating fluxed binder shall not be
test procedure carried out in accordance used. The backfill material shall be
with BS 598: Part 104, and the air void compacted to refusal with a circular
contents shall be determined in headed vibrating hammer, in layers not
accordance with sub-Clause 929.7 using exceeding 75 mm. Where cores have
the maximum density ρMax expressed in been cut through the surface course, the
Mg/m3 determined in accordance with last layer of backfill material shall
sub-Clause 929.16.
May 2005 23
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
comply with the specification for the shall nominate an alternative target
surface course. aggregate grading and target binder
content and a further Job Mixture
20 Two copies of the final nuclear density Approval trial shall be carried out in
test results obtained and their correlation accordance with this Clause. Laying
with in situ air void contents shall be shall not recommence in the
passed to the Employers Representative Permanent Works until compliance
within 24 hours. has been demonstrated.
May 2005 24
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 25
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 26
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
underlying layer with a polymer modified Table 9/8 Target Aggregate Grading and
bonding coat. permitted tolerances.
Column 1 Column 2 Column 3
Aggregate ISO Sieve Percent Tolerances
(mm) Passing around Target
2 The coarse aggregate shall consist of Grading
crushed rock or crushed gravel complying 20 100 **
with the requirements of Clause 901.3. 14 95 – 100 **
When tested in accordance with the 10 55 – 75 ±10
procedures of IS EN 933-3, IS EN1097-2 6.3 15 – 25 ±4
and IS EN 1097-8, each source of coarse 2 10 - 17 **
aggregate shall additionally have the 0.063 4 – 5.5* **
properties described in Table 9/7 or as Note: *Including 2% hydrated lime by weight of
stated in Appendix 7/1. The fine aggregate total aggregate. **Tolerances as for grading in
shall be crushed rock fines or natural column 2. Application of the above tolerances to the
sands or a mixture thereof. target grading may result in limits outside those
permitted by the appropriate envelope in Column 2
Table 9/7: Coarse Aggregate Properties of the table. This is acceptable.
Property Category
Binder
Polished Stone Value
PSV 60declared
(PSV) 5 The binder shall be preblended polymer
Resistance to modified bitumen and shall comply with
Fragmentation (Los LA25 the selected requirements of IS EN 14023
Angeles Test) as detailed in Table 9/9. During storage
Aggregate Abrasion the binder shall be agitated/circulated in
AAV10 an agreed manner to ensure the
Value (AAV)
homogeneity of the binder. When tested
Flakiness Index (10 – in accordance with Clause 941, 'Modified
FI15
14mm fraction) Binder Storage Stability Test' preblended
Flakiness Index (6.3 – modified binders shall meet the original
FI20
10mm fraction) specification for softening point and
penetration for that binder after the four
3 When sampled and tested in accordance day storage period. The supplier shall
with IS EN 12697-27, IS EN 12697-28 ensure the preblended modified binder is
and BS 598 part 102, the target aggregate manufactured to the same specification as
Grading shall fall within the envelope that for the sample submitted for the
formed by the limits given in column 2 of 'Binder Drainage Test', Clause 939.
Table 9/8. The agreed grading for the
mixture shall be obtained by applying the Binder Content
tolerances given in column 3 to the target
aggregate grading. The grading curve of 6 The target binder content (polymer
the aggregates shall be broadly parallel to modified bitumen) shall be established
the limits of the envelope and shall not from binder drainage tests as described in
vary from the low limit on one size of Clause 939. In addition, at the target
sieve to the high limit on the adjacent binder content the porous asphalt mixture
sieve or vice-versa. shall comply with the requirements of the
Cantabro Wear Test as specified in sub-
Filler Clause 938.17, with the Water Sensitivity
Test as specified in sub-Clause 938.16
4 At least 2.0 percent by mass of the total and with the Relative Hydraulic
aggregate shall be hydrated lime filler. Conductivity requirements as specified in
The minimum calcium and magnesium Clause 938.15. The tolerance for the
hydroxide content of the hydrated lime binder content to be used in the works
shall be 90%. shall not exceed ±0.3% of the target
value. Notwithstanding the above
requirements the found binder content on
analysis shall not be less than 5% of the
total mixture.
May 2005 27
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 28
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
of 10m ±0.5m situated at the site office, edge. Where an impermeable surface is to
or by portable anemometer erected at a be laid downstream of the porous asphalt,
height of 2m ±0.1m situated in close the lane ends of the porous asphalt shall
proximity to the laying works. The be staggered across the carriageway in the
anemometer shall be fitted with a digital direction of the drainage path in order to
accumulative device. prevent excess rainwater from welling up
over the transverse joint. Porous asphalt
Compacting shall be designed to finish on a level
grade or on an up-grade and shall not
13 Porous asphalt shall be compacted using finish/commence at a junction.
at least two 6-8 tonne, non-vibrating, steel
wheel tandem drum rollers for each Relative Hydraulic Conductivity
paving machine. If a vibratory type roller
is used it shall be operated in the non- 15 After the porous asphalt has cooled to
vibrating mode. To avoid pick-up, the ambient temperature, and before
rollers drum surfaces shall be initially trafficking, the relative hydraulic
clean and completely wetted prior to and conductivity of the material shall be
during rolling. Rubber tyred rollers and 3- measured, in accordance with the
wheeled rollers shall not be used. Rolling procedures specified at Clause 940. The
shall commence at the highest mat average value, from any 5 consecutive
temperature consistent with no shoving determinations at 20m spacings in the
and shall be substantially completed near-side wheel track of each lane of a
within the temperature range given in carriageway, shall be not less than 0.12s-1
Table 9/10. The first roller pass shall be and no single value shall be less than
on the low edge of the mat, followed by 0.08s-1.
the high edge. Rolling of the rest of the
mat shall then proceed from low to high Water Sensitivity
side and shall continue until all roller
marks have been removed. 16 The water sensitivity shall be determined
in accordance with IS EN 12697 Parts 12
Longitudinal and Transverse Joints & 23. The ratio of wet to dry strength
shall not be less than 0.75. The specimen
14 Wherever possible pavers shall be used in compacting procedure shall be such as to
echelon, as described in sub-Clause 12 of provide the air voids content expected in
this Clause, to eliminate longitudinal the field, i.e. in the range 20-28 percent
joints. Where exposed longitudinal joints without causing significant crushing of
are unavoidable they may be cold butted, the large aggregate particles as observed
provided that the edge of the porous from analysis of the specimens and
asphalt layer laid previously has not been measurement of any reduction in size. A
damaged and is clean. Where damage to reduction such that the grading no longer
edges has occurred they shall be trimmed lies within the grading envelope shall not
by power saw with appropriate measures be acceptable.
including suction extraction, to prevent
clogging of the pores with detritus. Abrasion (Cantabro Wear Test)
Longitudinal joints shall be placed
adjacent to pavement lane markings or 17 When tested in accordance with the
outside wheel track zones and shall be procedure described in NRA report RC
formed by butting-up to the adjacent 369 the wear of the mixture shall not
porous asphalt to form a tight joint. exceed 25 percent at 18°C or 20 percent
Transverse joints shall be formed against at 25°C.
a 200 mm wide and 45 mm thick hard
timber stop-end nailed to the road surface (i) The Cantabro test shall be carried
in advance of the paving operation. The out on mixture specimens
cutting of edges shall be avoided but unconditioned by any simulated
where transverse edge cutting is essential, aging procedures or by soaking in
only sawing with appropriate measures, water and,
including suction extraction shall be (ii) The specimen compaction shall
permitted. Nothing shall be done, nor any achieve maximum air voids up to 28
articles positioned, such as to impede the per cent without causing significant
run-off water freely entering the drainage crushing of the coarse aggregate as
channel or filter drain provided to remove defined in sub-Clause 16 of this
the water from the pavement surface Clause.
May 2005 29
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
1 This test determines the target binder (viii)Metal boxes, approximately 150 mm
content for porous asphalt, which is the by 150 mm by 150 mm, eleven in
highest binder content at which excessive number.
binder drainage will not occur during
manufacture, transportation and laying. (ix) Aluminium foil, of thickness 0.015
± 0.005 mm.
Summary of method
Materials
2 The quantity of binder lost through
drainage, after a specified time at the 4 Sufficient aggregates and binder to
maximum mixing temperature, shall be manufacture at least 20 kg of porous
measured in duplicate for mixes with the asphalt are required. The aggregates shall
same aggregate contents but with be dried and graded in the fractions
different binder contents. The target appropriate to the specified grading.
binder content shall be defined as the
value 0.3 per cent less than that at which Procedure
0.3 per cent binder drainage occurs, see
also sub-Clause 9 below. 5 The procedure shall be as follows:
(ii) Oven, with fan-assisted air (ii) Weigh eleven batches of 1.1 kg of
circulation, fitted with thermostatic combined aggregate, in the
control to maintain the temperature proportions for each fraction, to the
to ±3°C in the range of 80°C to nearest 1g to give a grading
200°C and having sufficient internal complying with the mid-point of the
volume to accommodate 10 specified grading limits in Table
drainage baskets and trays. 9/8, Clause 938. Place each batch in
a separate tin.
(iii) Mechanical mixing unit of more
than 8 litres capacity, capable of (iii) Pre-heat the oven to the maximum
combining 1500g of aggregate, filler mixing temperature and place the
and binder speedily and thoroughly, tins with aggregates in the oven for
without loss, as described in BS at least 3 ± 1 hours prior to use.
598: Part 107.
(iv) Pre-heat, stir and sub-divide the
(iv) Whisk, as described in BS 598: Part binder by the method stated in BS
107. 598: Part 107.
(v) Drainage baskets, ten in number, (v) Wrap each tray with aluminium foil.
constructed from perforated metal Weigh each tray with foil to the
with 3.1 ± 0.1mm diameter holes nearest 0.1g (W1).
and with 38 ± 3 per cent open area,
on sides and base to form 100 ± 2 (vi) Pre-heat the mixing unit to the
mm cubes, with feet, at each corner maximum mixing temperature for at
of the base, of 3 ± 0.5 mm diameter least 1.5 ± 0.5 hours prior to use.
and 5 ± 1 mm height.
(vii) Transfer a 1.1kg batch of aggregate
(vi) Spatula, with a blade approximately to the mixing bowl.
150 mm long by 25 mm wide.
May 2005 31
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
(viii) When natural rubber powder is to the binder content in step (ix) to 5.0,
be used, add the required quantity to 5.5 and 6.0 per cent by mass,
the mixing bowl. Fit the mixing respectively.
bowl to the mixer and fit the whisk.
Dry mix for 30 ± 3 s before adding (xix) When a modifier other than natural
the bitumen. rubber is used, the procedure for
incorporating the modifier shall be
(ix) Stir the heated binder in its according to the manufacturers'
container and weigh by difference instructions.
the required amount of binder to the
nearest 0.5g, into the mixing bowl to Calculations
give 4.5 per cent by mass in the unit.
6 For each mix, the retained binder (per
(x) When natural rubber latex is to be cent), R, shall be calculated from R% =
used; after adding the bitumen fit 100 x B [1-D/(B+F)]/(1100+B) Where:
the mixing bowl to the mixer and fit
the whisk. Mix the aggregates and D is the mass of binder and filler drained
bitumen for 60 ± 6s. Stir the latex [W2 - W1] (g)
well and add the required quantity
evenly over the mix. B is the initial mass of binder in the mix
(g)
(xi) Fit the mixing bowl to the mixer; fit
the whisk and mix for another 60 ± F is the initial mass of filler in the mix (g)
6s. Using the spatula, scrape around
the top of the bowl and whisk and 7 If, for any pair of mixes at the same
transfer the scraped material into the binder content, the difference in retained
mix. Continue mixing for a further binder per cent exceeds 0.5 per cent of
60 ± 6s. binder, the procedure in sub-Clause 5 and
calculation in sub-Clause 6 of this Clause,
(xii) Discard the first mix. for the pair of mixes at the same binder
content, shall be repeated.
(xiii) Repeat steps (vii) to (xi)
8 The mean retained binder shall be
(xiv) Transfer the material to a basket, calculated for each binder content. The
ensuring that the mixer bowl and retained binder shall be plotted against
whisk are scraped thoroughly using the initial mixed binder content, together
the spatula. Carry out this operation with the line of equality where the
as rapidly as possible to minimize retained binder equals the mixed binder
heat losses. content. A smooth curve shall be drawn
through the plotted values and
(xv) Place the basket with the mix on a extrapolated to intercept the line of
pre-wrapped tray in the oven at the equality in Figure 9/2. The critical binder
maximum mixing temperature for content, the maximum mixed binder
between 3 hours and 3.25 hours. content, and the maximum retained
binder content shall be recorded.
(xvi) Remove the basket and tray from
the oven. Remove the basket from Determination of Target Binder Content
the drainage tray. When the tray has
cooled sufficiently, weigh the tray 9 From Figure 9/2, the mixed binder
and aluminium foil to the nearest content (M) shall be determined where
0.1g (W2). the binder drainage is 0.3 per cent (yz).
The target binder content shall be (M-0.3)
(xvii) After placing the first mix in the per cent. As a check, the abscissa, (xy),
oven, repeat the procedure in steps should also equal 0.3 per cent between
(xiii) to (xvi) for a duplicate sample the line of equality and the point on the
at the same binder content. drainage curve where the binder drainage
is 0.3 per cent (yz).
(xviii) Repeat the procedure in steps (xiii)
to (xvii) four times, but increasing
May 2005 32
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
1 This test determines the in situ relative (ii) Stopwatch, accurate to 0.1s.
hydraulic conductivity, at specific
locations, of a permeable road surfacing. (iii) Thermometer, with an accuracy of
An estimate of the average value for the at least ± 1°C in the range 0 to 25
surfacing is obtained from the mean value °C.
of a number of determinations on each
section of road. (iv) Clean water, in the range 0 to 25 °C.
2 A radial-flow, falling-head, permeameter 4 The outflow time shall be the time that
shall be used to determine the time taken elapses for an outflow of 2.0 litres
for a specified amount of water, under through the permeameter, between the
known head conditions, to dissipate meniscus at the 2.5 litre mark and when it
through an annular area of the surfacing. falls to the 0.5 litre mark. The series
The reciprocal of the corrected outflow resistance time, r, shall be the outflow
time shall be used to calculate the relative time(s), corrected to 20°C, when the
hydraulic conductivity of the surfacing. outlet is not restricted by a surfacing. It
shall be subtracted from measurements of
Apparatus outflow time when the permeameter is
used on a surfacing. The parallel leakage
3 The apparatus shall consist of: time shall be the outflow time when the
outlet is restricted by an impermeable
(i) Radial-flow falling head surface. The relative hydraulic
permeameter and standing board, conductivity (HC) is the reciprocal of the
constructed to the requirements and outflow time, after correction to 20°C,
less the series resistance time.
May 2005 33
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 34
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
(v) Repeat step (iv) to obtain t2. (viii)Report the relative hydraulic
conductivity, corrected to 20°C, to
(vi) Calculate the average outflow time the nearest 0.01s-1.
and the range, both to the nearest
0.1s. If the range exceeds 5 per cent Measurement of the Average Relative
of the average outflow time, repeat Hydraulic Conductivity of a Section.
step (iv) until the range criterion is
met by two successive outflow 7 The procedure shall be as follows:
times and discard other readings.
Correct the average outflow time to (i) Measure the relative hydraulic
20°C by dividing by the appropriate conductivity as soon as possible
temperature correction factor from after the surfacing has been laid and
Table 9/12 and record the corrected cooled to ambient temperature, but
average outflow time, t, to the before the surfacing has been
nearest 0.1s. opened to traffic. The road shall be
clean and free from loose material.
Table 9/12: Temperature Correction Measurements can be made when
Factors the road is wet, but not if in a frozen
Temperature of Temperature state.
water (°C) Correction factor
0 1.79 (ii) Make individual determinations of
1 1.73 the relative hydraulic conductivity
2 1.67 in the nearside wheel path at 20m
3 1.62 intervals along each carriageway
4 1.57 lane.
5 1.52
6 1.47 (iii) Calculate the running mean of each
7 1.43 5 consecutive measurements along
each carriageway lane.
8 1.39
9 1.34
(iv) Report the average relative
10 1.31
hydraulic conductivity and the
11 1.27 individual results, all corrected to
12 1.24 20°C, of each running mean of 5
13 1.20 individual determinations along
14 1.17 each carriageway lane to the nearest
15 1.14 0.01s-1.
16 1.11
17 1.08 (v) When an individual determination
18 1.06 does not comply with the specified
19 1.03 minimum requirement for relative
20 1.00 hydraulic conductivity, further
21 .98 determinations shall be carried out
22 .96 at 5 m intervals in the wheel-path on
23 .94 either side of the noncomplying
24 .91 location to determine the extent of
25 .89 the non-complying length. If the
non-complying length exceeds 20
(vii) The relative hydraulic conductivity m, rectification shall be carried out
(HC), corrected to 20°C is by removing the full depth of the
calculated from: course and replacing it with fresh
material laid and compacted in
HC = 1/(t-r) s-1 accordance with the Specification.
The area rectified shall be the full
Where t is the average outflow width of the paving laid in one
time(s) corrected to 20°C; operation, and at least 30 m long.
May 2005 35
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
2 A sample of modified binder shall be (i) The bulk sample of modified binder
contained in a closed vessel of specific shall be obtained by sampling in
dimensions and shall be maintained at accordance with BS 3195-3 and IS
160 ± 2°C for 4 days ± 2 hours. A binder EN 58.
sample shall then be taken from the top
and bottom thirds of the vessel and both (ii) Place the bulk sample of modified
samples shall be tested for compliance binder and the glass cylinder (or
with the binder specification. metal tube or equivalent vessel) in
the preheated oven at 160 ± 2°C for
Apparatus a period not exceeding 3.75 ± 0.25
hours.
3 The apparatus shall consist of:
(iii) Remove the bulk sample from the
(i) Cylinder, made of heat resistant oven and thoroughly mix by stirring
glass, 190 ± 30 mm long and 65 ± 5 to ensure obtaining a representative
mm internal diameter having a test sample.
removable lid, flush fitting to
exclude air when the cylinder is (iv) Remove the glass cylinder (or metal
filled with binder, and provided with tube or equivalent vessel) from the
three drain-valves, one at the base, oven and completely fill with the
the other two spaced equally down modified binder test sample to allow
the side of the cylinder, to allow the no air space when the lid is fitted.
sample to be divided into three
equal portions as in sub-Clause 4 (v) Support the filled cylinder in a
(vii) of the procedure. Alternatively, vertical position in the holder and
a thin-wall sheet metal tube or transfer to the oven which shall be
similar vessel such as a 500 ml controlled at a temperature of 160 ±
beverage can, of similar dimensions 2°C and allow to stand undisturbed
to the glass cylinder, and having a for a period of 168 ± 2 hours.
similarly removable lid, fitted either
with or without drain- valves. (vi) If a vessel having drain-valves has
been used for the test proceed using
(ii) Oven, electrically heated, fan Method A below, otherwise proceed
assisted, and capable of maintaining using Method B.
a temperature of 160 ± 2°C, having
interior dimensions not less than (vii) Method A
330 mm from the top of the heating
element to the top of the chamber (a) Remove the glass cylinder (or
and not less than 305 mm in width alternative approved vessel)
and depth. from the oven, keeping the
cylinder vertical.
(iii) Tube holder, made of metal, that
will hold either the glass cylinder or (b) Open the upper-most drain-
sheet metal can, in a vertical valve and run off the top third
position, such that the base of the portion of the test sample into a
cylinder or can is not in direct transfer dish for testing.
contact with the oven floor.
May 2005 36
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 37
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
(iv) materials are traceable to test (iv) the control of equipment and
certification proving their machines required to
conformance to specification, manufacture the thin surfacing,
which shall be held on file for all including the necessary
thin surfacings; verification equipment (e.g.
gauges);
(v) personnel are trained and
qualified to operate the relevant (vi) assessment of the personnel
manufacturing processes qualified to carry out the relevant
including ongoing testing as manufacturing processes.
appropriate;
Continuous Surveillance
(vi) quality control measures are
operated and records kept of all 6 The Contractor shall ensure the
measurements on materials etc; manufacturer provides evidence that they
exercise continuous surveillance of their
(vii) continuous surveillance of the Quality Control system. This shall take the
processes and procedures are form of inspection reports highlighting the
undertaken and reports produced areas and procedures inspected and the
to identify non-compliance with outcome of these inspections.
the Quality Manual.
Aggregate
Factory Production Control
7 The coarse aggregate shall comply with
5 The Contractor shall ensure that the the requirements of Clause 901.3. When
manufacturer exercises continuous internal tested in accordance with the procedures
control of production. All elements, of IS EN 933-3, IS EN 1097-2 and IS EN
requirements and provisions adopted by 1097-8, each source of coarse aggregate
the manufacturer shall be documented in a shall additionally have the properties
systematic manner in the form of written described in Table 9/13 or as stated in
policies and procedures. This Production Appendix 7/1. The fine aggregate may be
Control System documentation shall crushed rock or sand or a mixture thereof
ensure a common understanding of but shall be subject to the approval of the
Factory Production Control and enable the Employers Representative.
achievement of the required product
characteristics and the effective operation Tabe9/13: Coarse Aggregate Properties
of the Production Control System to be Property Category
inspected. Factory Production Control
Polished Stone Value (PSV) *PSV 60declared
shall be a documented procedure in the
Quality Manual. Resistance to Fragmentation
LA25
(Los Angeles Test)
The manufacturer's documentation shall Aggregate Abrasion Value
be appropriate to the technical description AAV10
(AAV)
of the products and processes.
Flakiness Index FI15
Production control operations shall * Unless otherwise stated in Table 3.1 of HD36
comprise at least the following: (NRA DMRB 7.5.1).
May 2005 38
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
8 The maximum nominal aggregate sizes in range of binder contents shall be 5.0 to 6.5
the mixture shall be 0/14mm or 0/10mm. percent.
The requirements for the grading shall be
expressed in terms of the target grading, Bond Coat
which shall be within the maximum and
minimum values stated in table 9/16 for 11 On all occasions that hot applied thin
the percentage passing the following surfacings are used the substrate should be
sieves: sprayed with a polymer modified bitumen
1.4D; emulsion (PMBE). The rate of application
D; of the bonding coat shall be such as to
Up to two optional sieves ensure that the residual bitumen coverage,
between D and 2mm; after curing, is between 0.4kg/m2 and
2mm; 0.7kg/m2. The bond coat and thin
One optional fine sieve between surfacing shall be applied either by a
2mm and 0.063mm; and paving machine fitted with spray bar i.e.
0.063mm; integrated paver or alternatively the bond
coat can be applied separately provided
The notation ― D ‖ refers to the nominal that after a reasonable time period (10 to
size sieve e.g. in a thin surfacing material 20 minutes) it is resistant to ―pick up‖ on
0/14mm the ― D ‖ refers to sieve size the wheels of rubber tyred vehicles and the
14mm. The target proportions passing the footwear of operatives. In this case it shall
various test sieves, expressed as percent provide a strong bond between the
by mass of total aggregate shall be substrate and the hot-mixed thin surfacing
provided by the contractor at least eight when the latter is applied by a
weeks before paving is to commence. conventional paving machine. Fine
aggregate dust shall never be used to
The ranges between maximum and prevent ―pick up‖ as this will inhibit
minimum values, for the grading bonding between substrate and the thin
envelopes, shall be selected as a single surfacing.
value within the given limits (both
included) from Table 9/17. At the target Additives
composition the mixture shall conform to
the specified requirements. 12 Inorganic or organic fibres may be used to
assist in preventing binder drainage from
This specification has adopted the changes the aggregate. The nature and properties of
in grading designation that have occurred all additives e.g. cellulose, mineral or
as a result of the adoption of IS EN glass fibre etc. shall be declared. Fibres
13043:2002 – Aggregates for bituminous shall be added automatically into the
mixtures and surface treatments for roads, mixer to ensure that a homogeneous
airfields and other trafficked areas. dispersion of the fibres is achieved.
May 2005 39
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
target composition shall meet the wheel certificate showing that all weighing
tracking requirements of Table 9/18 and devices have been calibrated in
shall have a Water Sensitivity value of accordance with the quality plan and
greater than 75 percent. The method of audited to ISO 9001, within six months
laboratory compaction is by the Gyratory prior to the contract.
compaction method in accordance with IS
EN 12697-31. Laying
The water sensitivity is a measure of 16 Thin surface course materials shall not be
retained stiffness and is expressed as the laid during rain or when standing water is
indirect tensile strength ratio (ITSR). The present. It shall be laid within the limits of
ITSR is calculated as the ratio of the air temperature and wind speed stated in
indirect tensile strength of wet (water Figure 9/3. The range of delivery and
conditioned) specimens to that of dry rolling temperatures shall be as stated in
specimens, expressed in percent. This test Table 9/15. Prior to laying operations the
should be carried out in accordance with Contractor shall carry out any necessary
IS EN 12697-12 and at a test temperature remedial repairs. The type and extent of
of 25°C. such repairs shall be agreed with the
Employers Representative. Where
Trials necessary, existing surfaces shall be
regulated, in accordance with the
14 At least two months before surfacing is to requirements of Clause 907, in advance of
commence the Contractor shall submit to laying surfacing material to this clause.
the Employers Representative full details
of the constituent materials of the mixture, Performance requirements
all test results and the mixing and laying
proposals including mix temperatures both 17 The Contractor shall guarantee the
at production and delivery to site. At least performance, surfacing materials and
one month prior to the laying of thin workmanship for a period of three years
surfacing in the permanent works the from the date of opening the surfacing to
Contractor shall lay a trial length of at traffic or as otherwise specified in
least 100m adjacent to the site using the Appendix 7/1. In the event of failure of
materials, mix composition, method of the surface to meet the performance
mixing, method of laying including bond specification for the guarantee period, the
coating and layer thickness to be used in Contractor shall replace the material in
the main contract. For the trial to be accordance with this specification. The
acceptable it shall, without remedial requirements for Skid Resistance and
works, comply with the full requirements Texture Depth – initial and after three
of this specification. Alternatively, with years in service shall be as stated in Table
the agreement of the Employers 9/19 and Table 9/20.
Representative, the trial may form part of
the permanent works if the material Skid resistance shall be measured using
installed complies with all the the SCRIM machine. This testing shall be
requirements of this specification. If the carried out at a test speed of 50Km/h.
trial does not conform to all the
requirements of this specification, the The texture depth of the surfacing after
Contractor shall remove all non-compliant compaction and before opening to traffic
material from the permanent works and shall be measured by the volumetric patch
lay further trial lengths until full technique described in IS EN 13036-1 and
compliance with this specification is shall conform to the requirements of Table
achieved. 9/20. The initial measurements should be
made over 50 metre lengths, regularly
Mixing spaced along the section, and covering not
less than one third of the area of surfacing.
15 The materials including any added filler On each 50 metre lane length, 10
shall be accurately weighed into a individual measurements shall be made at
mechanical mixer of approved type and 5 metre intervals, along a diagonal line
thoroughly mixed in such a manner that all across the carriageway lane width, but not
particles are completely coated. The within 300mm of the carriageway edge.
Contractor shall supply a service
May 2005 40
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Figure 9/3: Limiting weather conditions for laying Thin Surfacing Materials.
May 2005 41
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Table 9/16: Overall Grading Limits of Target Composition and Composition tolerances
Nominal Size 0/10 Grading** 0/14 Grading**
Tolerances Tolerances
Nominal
+/- for +/- for
Layer 20-30mm 20-40mm
0/10mm 0/14mm
Thickness
ISO Sieve
10A* 10B* 10C* 14
(mm)
20 100
14 100 100 100 90-100 -8/+5
12.5
10 90-100 90-100 90-100 -8/+5 35-50 7
8
6.3
4
2 15-25 25-35 25-35 6 15-30 6
1
0.063 4-6 7-9 10-12 2 6-12 2
Note: * Hot laid thin bituminous surfacings shall be designated by their nominal size i.e. the upper
sieve size of the aggregate in the mixture, in mm and where relevant, by an indication of the type, A, B
or C.
** Application of the above tolerances may result in limits outside those permitted by the appropriate
envelope. This is acceptable.
May 2005 42
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
Table 9/17: Ranges between maximum and minimum values for the selected grading envelope
Ranges. Percent by mass
Sieve
Smallest range Widest range
First optional sieve between nominal 10 25
sieve and 2mm
Second optional sieve between 10 25
nominal sieve and 2mm
2mm 5 15
Rut rate
Road category Rut depth (mm)
(mm/hr)
Very heavily stressed sites requiring high
60°C 5.0 7.0
rut resistance
Moderately stressed sites requiring high rut
45°C 2.0 4.0
resistance
May 2005 43
Volume 1 Series 900
Specification for Road Works Road Pavements – Bituminous Bound Materials
May 2005 44