Gantt Excel
Gantt Excel
1) Unified Platform: Needless to say, that in a Project there are multiple teams that work
together on different aspects of the project. Keeping track of how the work is
progressing with different teams may become difficult. This is where Gantt charts have
the biggest advantage. Gantt Charts represent all the various aspects of the project on a
single unified document like the progress, timelines, names of individuals, and others.
This makes it extremely easy for the project owners or managers to keep abreast of all
that is happening as work progresses.
4) Resource Management: A major reason why there could be a sudden drop in resource
output is overburden. Gantt Charts helps Project managers to align resources and
delegate tasks in a more effective manner. It gives a systematic picture of where the
resources are being utilized associated with the corresponding timelines allowing
completion of projects within the allotted budget and time.
5) Track Progress of the Project: Effective measurement of the progress of the Project is
required not just for reporting to the Project owner and to the various teams involved
but also to understand if the project is running on track and whether it will be
completed on time. Progress Gantt Charts helps to understand to what degree the
various tasks have been completed. It gives a visual representation of how the work has
progressed and is very easy to interpret.
5. Celebrate milestones:
Take steps to ensure that team’s morale is high throughout the project. It can be stressful
to balance the execution in the midst of some unavoidable circumstances that delay the
project. Therefore creating milestones (mini goals) and celebrating these milestones can
motivate the team to stay on track and to work towards accomplishing the project.
Definition:
Project Management is defined as “a temporary endeavor undertaken to create a unique
product, service or result with a defined beginning and end in time, defined scope and
define resources”.
Project Management Life Cycle
Initiating Phase:
Also known as ‘conception’ phase, here the team identifies the goal to be achieved and
gathers the resources required to get started.
Planning Phase:
Here the team meticulously devises schedule of tasks, allocates tasks and resources
required to accomplish the project goals. Project timeline is created with milestones set so
that the project’s progress can be monitored. It is during this phase and here after that it is
most essential to use a Gantt Chart.
Gantt Excel allows you to visually represent the progress of your project by providing a
comprehensible snapshot of your project’s status.
In the Gantt chart, you begin by creating a timeline for the project, setting milestones
(smaller achievements leading to achieving the bigger goal), you define dependencies if any
(activities that need to be undertaken before or after a certain task), thus giving you and
your team the minimum total time required to complete the project (also called Critical Path
Model).
Gantt chart also allows you to allocate tasks and resources, delegate tasks and allows you to
share responsibilities.
Executing Phase:
This phase is where all the actions happen. The team members co-ordinate and execute
their tasks. Generally, a project manager oversees the whole project, communicating with
the team about the progress, adding resources if needed and basically ensuring that
execution phase complies with the planning phase. Ideally planning phase is the blueprint
for the execution phase; however, in real world, due to un-anticipated events and external
forces, it is reasonable that execution phase might go tangent from planning phase.
Therefore, it is important to ensure that some buffer time for these events is considered
during the initiation and planning phase of the project. This is also why you should actively
update your Project Gantt chart to keep your progress on track and accurately record the
accomplishment of the tasks, sticking with the timeline.
Controlling Phase:
This phase occurs simultaneously with the executing phase as execution and controlling/
managing projects go hand in hand. Handling unexpected hurdles and also keeping the track
of the project according to the planning are involved in ensuring the project is a success. It
can get frustrating to balance both during this phase especially as we are time, budget and
resource constrained. It is important to keep the team’s morale high during this phase. This
is why celebrating ‘milestones’ is good to lift up team spirit. Gantt Chart Excel allows you to
create milestones and even break the primary tasks into child tasks so that responsibilities
can be further shared and delegated thus reducing the burnout that team might experience
during this balancing phase of execution and control.
Closing Phase:
As we come close to the end of the project, it is said that the momentum is often lost during
the last 10% of the project. The team feels like everything is finished and they forget to find
details that take a lot of time. This is where a Gantt chart can actually help the team to track
every detail of the project and also keep the motivation high so that you don’t miss out on
details as they say, ‘the devil is in the details.
“Voila! Our project is now complete.” It is also recommended that you revisit your project
details from conception to the closing phase to see what worked and what didn’t and what
can be learnt. This is the time to review the Gantt chart to go back and revisit the project
details with every detail recoded precisely and accurately.
1. Finish-to-Start (FS)
2. Start-to-Start (SS)
3. Finish-to-Finish (FF)
4. Start-to-Finish (SF)
Finish-to-Start (FS)
This is the most common and logical type of dependency in project management and the
real world. In this scenario, the predecessor task must finish before the successor can start.
It follows the natural flow and progression from one task to another. Task A must finish in
order for Task B to start.
This dependency means that if there are 2 tasks TASK A and B, the dependent task (B)
cannot begin until the task that it depends (A) on is complete… In other words, if TASK A is
delayed by a day, then B will also be delayed and will begin a day later.
Example: If you are building the foundation for your house and you have two tasks,
“Excavate” and “Pour concrete,” the “Pour concrete” task cannot begin until the “Excavate”
task is complete
Start-to-Start (SS)
The “Start to Start” dependency says that a task cannot start before the predecessor task
starts. This dependency means that if there are 2 tasks TASK A and B, Task B can’t start until
Task A starts. They don’t have to start at the same time: Task B can begin any time after Task
A begins.
Example: To save time, you want to level concrete at one end of the foundation while it is
still being poured at the other end. But Level concrete (B) can’t start until Pour concrete (A)
has also started.
Finish-to-Finish (FF)
In this case, a task cannot end before the predecessor task ends. This dependency means
that if there are 2 tasks TASK A and B, Task B can’t finish until Task A is completed. They
don’t have to end at the same time: Task B can end anytime after Task A ends.
Example: Your team is adding the wiring to the building and inspecting it at the same time.
Until Add wiring (A) gets done, you won’t be able to finish Inspect electrical (B).
Start-to-Finish (SF)
One peculiar dependency, which is rarely used, is “start to finish”. In this case, the
predecessor task must start before the successor task can finish. Task B can’t finish until
Task A begins. Task B can finish any time after Task A begins. This type of link is rarely used.
Example: The wooden window frames for your house are built off-site. You can’t
finish Assemble windows (B) until Window frame delivery (A) begins.
As a rule of thumb, a good practice is to stick with the common Finish to Start dependency
or else you run into the risk of creating a very confusing gantt chart.
2. Stack Tasks
Its good practice to stack the dependent tasks on top of each other in the order in which
they should be completed. The predecessor task should ideally be placed on top and the
successor task below.
Gantt Excel allows you to move tasks up and down easily.
3. Set Dependencies
Task dependencies can be easily set in Gantt Excel. You have to just double click a task to
set task dependencies. Please watch the video tutorial below to set task dependencies.
There are different types of dependencies in project management that can be categorized in
many ways depending on relationships, conditions, and other factors.
Causal Dependencies
These dependencies are found in the natural flow of tasks within a project. For example, to
bake bread you need to first buy the ingredients, then mix them together, then put it in a
oven and finally wait for it to bake. Each task is dependent on the completion of the
previous and avoiding one step or task in the process will lead to a failed project.
Resourced Based Dependencies
These are based on constraints and have no causal dependency. Meaning, if all resources
are present, all tasks and activities can be completed together. For example, within
technical user stories, there could be internal constraints with lack of skills of not
understanding technical terms or processes.
Preferential Dependencies
These are dependencies determined by best protocols, practices, and preferred processes.
They are institutionalized to focus on the quality of the product. For example, when painting
the interior of a house, the order in which the rooms and walls are painted is chosen based
on a various factor such as the furniture removal, current needs and preferences.
Cross-Team Dependencies
In larger companies, cross-team dependencies pose a serious challenge. This dependency
tends to exist when two or more teams are needed for the completion of a project.
External Dependencies
These dependencies are outside the control of project managers or teams and rely on 3rd
parties or outside vendors for completion.
Lead and Lag times - Space tasks out with a predefined lag or lead
Lead and lag are two terms associated with the task relationships that may occur between
two or more tasks. Lead and lag are both used in the development of the project schedule.
Lag time is a delay between tasks that have a dependency. This time interval can be set
between dependent tasks to allow for required delays. For example, in a construction
project, you need to let the foundations set before building the walls. In this case, lag time
should be set for concrete to set. A successor task can only start once the defined lag time
(specified in days) has elapsed.
Lag is the delay of a successor activity.
Lead time is overlap between tasks that have a dependency. For example, if a task can start
when its predecessor is half finished, you can specify a finish-to-start dependency with a
lead time for the successor task. You enter lead time as a negative value.
Lead is the acceleration of a successor activity.
Both types are available in any work breakdown structure that includes dependent
activities. Dependency rules between tasks determine which of the tasks are predecessors
and which ones are successors. Graphically it can be presented as a tree-like structure in
which every higher level is the successor of its lower level, and vice-versa – every lower level
is the predecessor of its higher level.