110 G90 GHX 00001 007 Project HSSE Plan (Approved)
110 G90 GHX 00001 007 Project HSSE Plan (Approved)
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 1 / 154
REVISION LOG
REV. NO DATE PAGE DESCRIPTION
TABLE OF CONTENT
1.0 GENERAL..................................................................................................................... 10
2.0 DEFINITION ................................................................................................................. 10
3.0 ACRONYMS................................................................................................................. 15
4.0 REFERENCE DOCUMENT .............................................................................................. 16
5.0 SCOPE ......................................................................................................................... 20
6.0 PURPOSE .................................................................................................................... 21
7.0 PROJECT HSSE PHILOSOPHY ........................................................................................ 21
8.0 LEADERSHIP AND COMMITMENT ................................................................................ 21
9.0 TEAM LEADER OBJECTIVES .......................................................................................... 22
10.0 POLICY, OBJECTIVES AND KPI’S ................................................................................... 22
10.1 HSSE Policy .............................................................................................................22
10.2 Strategic Objectives and KPI’s ................................................................................23
11.0 HSSE GOLDEN RULES AND NO TOLERANCE.................................................................. 26
11.1 Golden Rules for Life Saving ...................................................................................26
11.2 Golden Rules for Safe Driving .................................................................................26
11.3 Zero Tolerance........................................................................................................27
12.0 HSSE ORGANIZATION AND RESPONSIBILITY ................................................................ 27
12.1 Organization ...........................................................................................................27
12.2 Responsibility .........................................................................................................28
12.2.1 Project Manager .................................................................................................... 28
12.2.2 HSSE Manager ....................................................................................................... 28
12.2.3 Engineering Manager ............................................................................................ 30
12.2.4 Procurement Manager .......................................................................................... 30
12.2.5 Construction Manager........................................................................................... 30
12.2.6 Construction Discipline Superintendent or Supervisor ......................................... 31
12.2.7 Pre-Commissioning and Commissioning Manager ............................................... 31
12.2.8 Discipline Leads ..................................................................................................... 32
12.2.9 Deputy HSSE Manager ........................................................................................... 33
12.2.10 Chief HSSE / HSSE Superintendent ........................................................................ 33
12.2.11 HSSE Engineer........................................................................................................ 33
12.2.12 Enviromental Engineer .......................................................................................... 34
12.2.13 Inspector ................................................................................................................ 34
12.2.14 HSSE Training Coordinator .................................................................................... 34
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 4 / 154
List of Tables
Table 1. HSSE Key Performance Indicators.................................................................. 25
Table 2. MOC Risk Assessment Requirements............................................................. 40
Table 3. MOC Authorization Level Required................................................................ 41
Table 4. Classification of Work Areas.......................................................................... 41
Table 5. Matrix Approval Authority Greenfield-Brownfield Onshore & Offshore............ 43
Table 6. Personal Protective Equipment (PPE) Standard............................................... 57
Table 7. List of Required Authority to Certify Heavy Mobile Equipment......................... 63
Table 8. Requirements for Respirable and Non-Respirable Confined Space................... 70
Table 9. Colour Code Period....................................................................................... 79
Table 10. Records and Reports Retentions Periode........................................................ 96
Table 11. Emergency Siren Tones................................................................................. 98
Table 12. Disciplinary Action to be Taken up to The Penalty Points ................................. 107
List of Figures
Figure 1. Classification of Work Areas.......................................................................... 42
Figure 2. Calculation for Potential Fall Distance............................................................ 64
Figure 3. Danger Tag tagging and padlocked (Red colour) ............................................. 71
Figure 4. Out of Service Tags (yellow colour) ............................................................... 72
Figure 5. Distribusi muster point and Assemble Point................................................... 100
Figure 6. CSMS Process Flow....................................................................................... 111
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 10 / 154
1.0 GENERAL
PT PERTAMINA (PERSERO), hereinafter referred to as the OWNER, places prime importance
health, safety and environmental issues and shall require the CONTRACTOR Subscribe to and
actively pursue the highest standards of Health, Safety, Security, and Environment in the course
of project execution.
CONTRACTOR shall therefore observe, adhere to and comply with HSSE provisions as required by
this HSSE document and applicable local HSSE Laws and Regulations.
This Project HSSE Plan is established to provide all CONTRACTOR Management and employees,
SUBCONTRACTORs, visitors, and other persons involved in the project a clearly defined plan to
ensure that CONTRACTOR takes every possible action to protect Health, Safety, Security and
Environment.
All CONTRACTOR management and employees and SUBCONTRACTOR personnel shall be familiar
with their responsibilities to Health, Safety, Security and Environment. For this purpose, this
Project HSSE Plan and other documents required such as OWNER’s HSSE Guidance, if any, will be
located at work areas and be readily available to all personnel.
2.0 DEFINITION
Unwanted or undesired event resulting from the occurrence of
ACCIDENT one or more fault incident that have negative impact on the
system, product, equipment or personnel.
Siren is a sign with a certain sound and duration for emergency or
ALARM
unsafe condition
is a study of the major and significant impacts of a business and /
or planned activity on the environment required for the decision-
AMDAL
making process regarding conducting business and / or activities in
Indonesia.
Assembly point are considered safe place to congregate the
ASSEMBLY POINT
workers or the third parties in case of evacuation
A systematic and independent review of a HSSE system or element
for its compliance, effectiveness and degree of implementation to
AUDIT
the system undertaken by a person other than those who have a
responsibility within the activity being audited
A property team, project team or SUBCONTRACTOR who are
AUDITEE
executing an activity
Persons of EPC Of Lawe-Lawe Facilities RDMP Ru-V Balikpapan
AUDITOR Project who have proper qualification (National/ International
certified) and authorization to perform a HSSE audit
Employees of CONTRACTOR, Pertamina or any of its
SUBCONTRACTOR or Vendors, Who are scheduled for work or has
AUTHORIZED PERSONNEL other official business on site. Authorized personnel may also
include non employees who have been formally invited to the
project or who have been formally invited to the project or who
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 11 / 154
OFFSHORE WORK is practices of work conducted under, on, over and near water.
a doctor who was accomplished and located at the site project of
ON SITE DOCTOR a particular activity or concern on site medical treatment for
accident victim
OWNER PT PERTAMINA (Persero) RDMP RU-V Balikpapan
PERMIT SYSTEM Safe system of work for the control of activities in hazardous area.
is entry or inclusion or organism, Substance, energy and/or other
component into environment by human activity, result the quality
POLLUTION
decreased to a certain level and caused the environment
malfunction
Engineering, Procurement and Construction (EPC) for the scope of
PROJECT work for the Lawe-Lawe Storage Terminal defined within and in
referenced documents and drawings (RDMP Lawe-Lawe Project)
RDMP RU V Balikpapan Refinery Development Master Plan Refinery Unit V Balikpapan
RESTRICTED WORK Where the employee cannot fulfill his normal work, the day
ACTIVITY CASES following an incident.
Effect of uncertainty on objectives. It could refer to positive
RISK
consequences of uncertainty, as well as negatives one.
Safety Task Analysis Risk Reduction Talk A meeting conducted
SAFETY TASK ANALYSIS RISK before a task between field supervisors/PA and their work crew
REDUCTION TALK which focuses methodically on the hazards of the task and its
associated precautionary measures
SUBCONTRACTORs/ CONTRACTOR's employee engaged in the
SCAFFOLDER
erection and dismantling of scaffolds.
Simultaneous Operations, is two different or more activities which
SIMULTANEOUS have occurring in almost same time and area. Close enough to
OPERATIONS each other that there is a risk of interference, clashing, or risk
transfer.
SITE is Project Location where the facilities will be installed
SITE DOCTOR A qualified medical practitioner who attends the project site.
SPECIFICATION is technical requirement which has not been included in standards
the base used for prayer, in the form of carpets etc. small in size,
PRAYER MAT
approximately 80 x 120 cm
Person or persons, firm, partnership, corporation or combination
thereof engaged by the CONTRACTOR, (not being the employee of
SUBCONTRACTOR
CONTRACTOR, (not being the employee of CONTRACTOR) for
supplying services to CONTRACTOR
All sudden, suspicious, unexpected, unexplained and accidental
death or missing person (presumed dead). It can be classified at
SUDDEN DEATH
the work place or in an area other than the workplace i.e.
accommodation, travel, smoking area, etc.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 15 / 154
3.0 ACRONYMS
ALARP As Low as Reasonably Practicable
Analisis dampak lingkungan / Analisis mengenai dampak
AMDAL
lingkungan (Environmental Impact Analysis)
BAPETEN The Nuclear Energy Supervisory Agency is a non-ministerial
government institution that is under and responsible to the
President
BATAN The National Nuclear Energy Agency (BATAN) as a Non-
Departmental Government Institution carrying out tasks in the
field of research, development and utilization of nuclear energy in
accordance with the provisions of the applicable laws and
regulations intends to hold a 2015 Nuclear Science and
Technology Seminar.
BBSO Behavior Based Safety Observation
CFCs Chlorofluorocarbons
COSHH Control of Substance Hazardous to Health
CPR CARDIO PULMONARY RESUSCITATION (CPR)
Joint Operation of China Petroleum Pipeline Engineering co., ltd.
CPPHK
and PT. Hutama Karya (Persero)
CPR Cardio Pulmonary Resuscitation
CSMS CONTRACTOR Safety Management System
CTR CONTRACTOR
DAFW Days Away from Work Cases
e-COP Electronic Construction Observation Programs
EMS Environmental Management System
ERT Emergency Response Team
FAC First Aid Case
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 16 / 154
Government Regulation No. 101 of 2014 regarding Management of Hazardous and Toxic Waste
Materials
RI-Goverment Regulation No. 17 Year 1974 about Supervision Of Implementation Of Oil
Exploration And Exploitation And Earth Gas In The Beach Regions
Regulation of Indonesian Government No. 50 / 2012 regarding Implementation of
Occupational Health and Safety Management System Law No. 1/1970 regarding Occupational
Health
Regulation of Indonesian Government No. 81 / 2012 regarding Management of Household
Waste and Similar to Household Waste;
Regulation of Indonesian Government No. 74 / 2001 regarding Hazardous Material
Management
Regulation of Indonesian Government No. 41 / 1999 regarding Air Pollution Control;
RI - Labor and Transmigration Minister Regulation No. PER/01/MEN/1980 about Safety and
Health on Building Construction
Minister of Labor Regulation No. 2 Year 1992, about the Procedures for Appointment of
Obligations and Authority of Occupational Safety and Health Experts
Decree No. 51/MEN/1999 Ministry of Manpower regarding the physical threshold values at
work sites
Regulation of the Minister of Manpower and transmigration No. Per.03/Men/1982, on Medical
Services
Manpower Ministry standard No. 37 Year 2016 Pressure Vessel and Storage Tank
Minister of Environment Decree No.127/2002, Environmental Evaluation Performance
Program
Minister Regulation No. PER. 05/ MEN/ 96 about Occupational Health and Safety Management
System.
Minister of Environment Decree No.42/1994, General Guidance for the Implementation of
Environment Audit
Minister of Energy an Mineral Resources Regulation No. 26 of 2018 Concerning Good
Implementation of Mining Rules and Supervision of Mineral and Coal Mining
Decree of the Minister of Energy and Mineral Resources Number 1827 K /30 /MEM /2018
Concerning Guidelines for Implementing Good Mining Engineering Rules
Decree of the Minister of Energy and Mineral Resources No. 1457K/38/MEM/2002 regarding
Technical Guidelines on Environmental Management in the Mines and Energy Field
Decision of the Minister of Manpower, No. KEP-612/MEN/1989 regarding the supply of data
on dangerous Substances affecting occupational safety and Health.
Minister of Manpower Decree No.05/1996, Health Management System
Head of Police RI Regulation No. 24 year 2007 about Organization Security Management
System, Company and or Government Institute.
Decree of the Chairman of BAPEDAL No. Kep-01/BAPEDAL/09/1995 regarding Procedures and
technical Requirements for Storing and Collecting of Hazardous and Toxic Waste Materials
Regulation of the Minister of Manpower and Transmigration No. 05/ 2018 regarding
Occupational Health and Safety of Workplace Environmental
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 18 / 154
Regulation of the Minister of Manpower No. 15/MEN/VIII/2008 regarding First Aid for
Workplace Accidents
Regulation of the Minister of Environmental No. 18/2009 regarding Guideline of Hazardous
Waste Management Permit
Regulation of the Minister of Environmental No. 14/2013 regarding Symbols and Labelling of
Hazardous Material and Toxic Waste
Regulation of the Minister of Environmental No. 13/2009 regarding Quality Standards for
Stationary Sources of Emissions and / or Activity Oil and Gas Business
Regulation of the Minister of Environmental No. 51 / 1999 regarding Decision of Threshold
Value for Physical Factors in the Workplace
Decree of the Minister of Health No. 492 / 2012 regarding Requirements for Drinking Water
Quality
Decree of the Minister of Health No 1096 / 2011 regarding Sanitation Hygiene Requirements
for Catering Services
Decree of the Minister of Health No. 70 / 2016 regarding Standard and Requirement of
Occupational Health Industrial Work
Decree of the Minister of Environmental No. 48/MENLH/11/1996 regarding Noise Level
Standard
Decree of the Minister of Environmental No.35/MENLH/10/1993 regarding Standard of Vehicle
Emissions
Decree of the Head of Environmental Impact Control Agency No. 255/BAPEDAL/08/1996
regarding Procedures and Requirements for Storage and Collection of Used Lubricating Oil
Decree of the Head of Environmental Impact Control Agency No. 02/BAPEDAL/09/1995
regarding Hazardous Waste Manifest
Decree of the Head of Environmental Impact Control Agency No. 03/BAPEDAL/09/1995
regarding Technical Requirements of Hazardous Waste Management
Decree of the Head of Environmental Impact Control Agency No. 205/BAPEDAL/07/1996
regarding Technical Guidelines for Air Pollution Control Stationary Sources.
Regulation of Manpower Ministry No. 09 Year 2016 regarding Working at Height
Regulation of Manpower Ministry No. 37 Year 2016 regarding Pressure Vessel and Storage
Tank
Regulation of Energy and Mineral Resources Ministry No. 18 Year 2018 regarding Installation
and Tools Inspection for Oil and Gas Activity
Regulation of the Minister of Manpower No. 01/MEN/I/2007 regarding Guidelines for HSSE
Award.
Environmental Impact Analysis (EIA) of RDMP RU V Balikpapan Project.
Local Regulation of East Kalimantan No. 02 Year 2011 regarding Water Quality Management
and Water Pollution Control
Local Regulation of Balikpapan No. 03 / 2012 regarding Permit for Building
Guidelines of CONTRACTOR Safety Management System (CSMS), A-001/ K00100/2015-S9 Rev-
3, June 2015.
Pertamina HSSE Plan Project Guidelines No. A-002 / V00100 / 2018-S9.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 19 / 154
5.0 SCOPE
This document defines the Health, Safety, Security, and Environment (hereinafter referred to as
“HSSE”) requirements that CONTRACTOR shall apply during the execution of the Project.
The Project HSSE Management System implementation activities described in this plan apply to
the Project Management, Procurement, Construction, Commissioning, Start-up and operations
take and take-over, and HSSE functions performed by CONTRACTOR.
CONTRACTOR shall take all necessary action steps to ensure all employees including
SUBCONTRACTORs comply with all applicable HSSE Regulation and guidance from OWNER’s HSSE
Regulation.
This document shall apply to all project activities carried out by the CONTRACTOR and its
SUBCONTRACTORs
This document shall be revised and updated as necessary to reflect any changes to the project
scope of work.
Within the Brownfield operation all PERTAMINA procedures and policies which are in line with
MIGAS requirements must be followed and are under the absolute authority of the Chief Engineer
(KTT).
The MIGAS regulations apply only to Brownfield areas (Oil and Gas Production facilities or projects
undertaken within the operating site).
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 21 / 154
In compliance with MIGAS regulations, the Greenfield area shall be clearly partitioned from the
Brownfield area, such that it is not possible for persons to arbitrarily cross between
6.0 PURPOSE
The purpose of Project HSSE Plan is a specific plan to ensure all job activities in this project has
complied with OWNER standards, CONTRACTOR standards, and applicable government rules and
regulations in order to get the best quality for Health, Safety, and Environmental to prevent the
adverse (human, property, and environment) incident. In addition, Project HSSE Plan described
the detail of HSSE schedule (based on project requirements) to support all of project activities. It
is a working document, Subject to ongoing review, and possible revision during the lifetime of the
project.
LAGGING INDICATOR
1 Fatality Total case number 0
2 Lost Time Incident Total case number 0
Lost Time Incident Frequency Ratio
3 <1
Rate (LTIFR)
Lost Time Incident Severity Ratio
4 <1
Rate (LTISR)
Incident impacted to
5 Total case number 0
Environmental pollution
Incident impacted to fire /
6 Total case number 0
asset damage
Total Recordable Injury Rate
7 Ratio < 0.15
(TRIR)
Total manpower
8 First Aid Case Total case number 4%
on board
LEADING INDICATOR
1 HSSE Meeting MoM / Attendant list Min. 1 / month
2 HSSE Talk / briefing / toolbox Attendant list Daily
Report Submission
3 HSSE Reporting Weekly
record
4 HSSE Management Visit/ MWT MWT record Quarterly Level PMT
Follow up action
5 Closure Action 100% Closed
report
Audit/ Inspection
6 Inspection / audit Monthly
report
PPE compliance
7 PPE Compliance 100%
report
Compliance on Waste Waste management
8 100% Comply
Management report
Compliance on Hygiene Hygiene Industry 100% Comply
9
Industry report
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 25 / 154
The progress of KPI and program shall be updated regularly. CONTRACTOR shall submit, on a
weekly basis, a formal report summarizing CONTRACTOR and SUBCONTRACTORS HSSE
performance to the Owner representative. The report will be including total man-hours, leading
and lagging indicator as stated on HSSE Objectives, Target, Programs, and any related additional
data.
To achieve the above mentioned HSSE objectives and KPIs, the following actions will be taken in
terms of Safety, Health, Environment and Security:
Occupational Safety:
Effective leadership and accountability for the performance of own and SUBCONTRACTOR
/vendors’ personnel
Identification, safety risk assessment and appropriate controls of the project’s unique hazards
Ongoing behavior and observation based training and education, including sustainable
development
Provision of safe systems of work and risk-free facilities.
Establishment of barrier-free communication system
Establishment of a “blame-free” culture
Establishment of emergency preparedness and incident reporting procedures
Application of incident/accident investigation and analysis for recurrence prevention
Monitoring and auditing with management participation
Establishment of safety promotion schemes
Occupational health and hygiene
Conduct health risk assessment
Supply appropriate site medical staff/facilities and emergency vehicle(s)
Provide a suitable and adequate amount of fresh water
Supply of sufficient number of site toilets
Provision of site resting shed
Prevention of heat stress
Protection from any epidemics
Environmental:
Conservation of natural resources
Minimization of adverse environmental impact
Fostering of waste reduction, reuse, and recycling
Open communication with public and local community
Awareness of “zero emission initiatives”
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 26 / 154
Security:
Strict management of goods, materials, vehicles, equipments and personnnel movement on
and off the RDMP Lawe-lawe Project
Ensure that all personnel entering the project site have valid ID or are issued with a visitor ID
Review relevant management plans for continual improvement
Promote compliance with the project 8 Golden Rules and the Golden Rules for Safe Driving Full
compliance with the Site Security Regulation
Never make a call and/or wear ear phone as well as smoking while driving
Do not drive when tired and do not allow an unfit driver to drive
Do not drive at night unless authorized to do so
Warn drivers of safety concerns or unsafe behavior
All drivers will be received the “7 Golden Rules for Safe Driving” after completion of
CONTRACTOR Defensive Driving Training
11.3 Zero Tolerance
A “Zero Tolerance Policy” for designated HSSE violations will be strictly enforced, ANY person
who knowingly and intentionally violates the Zero Tolerance Policy will be TERMINATED from
working at the RDMP Lawe-lawe. Zero tolerance offences shall include but not be limited to the
following:
Under influence of Alcohol and Consumption of Prohibited drugs
Fighting
Stealing
Gambling (cash money)
Using ID of another person to gain site access
Willful damage to equipment of property belonging to the Project
Not 100% tie off when working at height 1.8m above (double hook)
Without fall protection system when working at height
Unauthorized entry into confined space
Driving without accreditation card (inside project area)
Violation red tags on scaffolding working platform
7 Golden Rules for Safe Driving and Zero Tolerance Policy will be prominently displayed at the
project site in English and language understood by the majority of workers i.e. Bahasa Indonesia.
List Penalty System can be seen on Attachment 4 – PENALTY SYSTEM
12.2 Responsibility
The responsibility of Key Personnels are refer to 26076-110-G01-GAM-00001 “Project Execution
Plan”.
12.2.1 Project Manager
The Project Manager has overall responsibility for HSSE management and performance
of the project covering engineering, procurement, construction, pre-commissioning
and commissioning throughout the project execution period.
His/her major roles and responsibilities for HSSE management are to:
1) Establish the project HSSE Policies and targets.
2) Establish the project organization and assign competent personnel to the
organization.
3) Define and assign individual’s roles and responsibilities.
4) Participate in setting up the project HSSE strategy just after project award
5) Arrange necessary resources of people, things and funds
6) Incorporate the requirements of HSSE into the SUBcontracting scheme.
7) Be responsible for the selection of SUBCONTRACTORS according to their attitude
toward HSSE, past record of HSSE performance, etc., as well as their experience and
ability to do the work, proposed price and conditions.
8) Propose to assign HSSE Manager, Engineering Manager, Procurement Manager,
Construction Manager, Pre-commissioning & Commissioning Manager and other
managerial personnel who are competent and highly experienced in their designated
roles and responsibilities.
9) Encourage the HSSE Manager, Engineering Manager, Procurement Manager,
Construction Manager, Pre-commissioning & Commissioning Manager and other
managerial personnel to establish and/or to implement HSSE management strategy,
programs and procedures for the project.
10) Visit the site, as frequently as possible, to confirm and evaluate the HSSE
management status and performance as well as the construction status.
12.2.2 HSSE Manager
General
1) Represent Project Manager (PM) in socialization, implementation, maintenance
and continual improvement of this Project HSSE Plan including its associated
reference documents refer to ISO 45001: 2018 and ISO 14001:2015 requirements
including OWNER’S, CONTRACTOR’S quality manual and other applicable
requirements
2) Represent Project Manager (PM) in socialization, implementation, maintenance
and continual improvement of the HSSE Key Performance Indicators (KPI)
contained in HSSE Monthly Report in cooperation with the project SUB-
organizations to ensure the Project HSSE Plan including its associated reference
documents for the engineering, procurement, construction and commissioning
are well socialized, implemented, maintained and continually improved.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 29 / 154
4) Delegate responsibilities for the various HSSE functions and authority for
departmental and craft HSSE promotion.
5) Require full HSSE compliance by all involved disciplines of CONTRACTOR and all of its
SUBCONTRACTORs.
6) Establish and/or encourage to implement the job HSSE rules with special attention
to unusual operations and HSSE requirements of OWNER.
7) Establish and/or encourage to implement the disciplinary action necessary to
develop an efficient, functioning HSSE Program.
8) Plan for prompt accident investigations, ensuring that adequate, informative reports
are completed and their distribution is accomplished.
9) Be directly concerned with the planning for those operations which have a potential
loss or hazard above that of normal construction activities.
10) Pursue improvements in HSSE performance. Prevent damage to the environment by
construction activities
12.2.6 Construction Discipline Superintendent or Supervisor
Construction Discipline Superintendent are Superintendents responsible in supervising
and coordinating disciplines apart from HSSE. E.g. Mechanical Superintendent, Piping
Superintendent, Civil Superintendent, etc. Their responsibilities are:
o Responsible to implement of HSSE Plan at site.
o To attend daily toolbox meeting and other HSSE meeting related with their
activities.
o Ensure the work team members under their supervision are aware of the
hazards associated with their work activities and required control measures to
eliminate or reduce the risks.
o Ensure effective instruction, training and supervision is given to the employees
under their supervision, particularly to inexperienced or new employees and
those of any SUBCONTRACTORs.
To develop safe work practices through method statements, work instructions which
applicable to their activities.
12.2.7 Pre-Commissioning and Commissioning Manager
The Pre-commissioning and Commissioning Manager is responsible for the
implementation of the Project HSSE Plan within pre-commissioning and commissioning
scope.
Specifically, the Pre-commissioning and Commissioning Manager shall be the driving
force behind the Project HSSE Program and shall take the following responsibilities:
1) Assume full responsibility for HSSE activities within pre-commissioning and
commissioning scope and maintain liaison with the Construction Manager as well as
with the CONTRACTOR Construction Management Department Manager / Process
Department Manager in Head Office, Jakarta.
2) In cooperation with HSSE Manager direct the HSSE Program for pre-commissioning
and commissioning scope.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 32 / 154
JSA will be required for all jobs performed On or Off site. Construction Superintendent or
Supervisor shall be responsible to provide JSA and understood by all the work team member. HSSE
are responsible to review the JSA. Normally during daily Tool Box Meeting (TBM). Employee shall
sign the JSA Attendance list and involving in any review of activity change. New hazard identified
in JSA shall be add on HIRAC register.
As minimum JSA shall described breakdown steps for the task and hazards identified for each step
including control measures.
The JSA process flow to be done at site is as follows:
Step 1. Identify the job to be done.
Work Leader or Discipline Superintendent involved, shall identify the sequence of the job,
including HSSE requirement for each of the sequence.
Step 2. Breakdown the job in to sequential steps.
Break the job down into sequential steps. Everyone should understand what is taking place and
where; what people are required; what equipment or plant is in use; and any other components
involved.
Step 3. Identify the hazards in each step.
To identify the potential hazards that could reasonably cause damage on each steps. Consider:
Obvious hazards that can develop into an unwanted event
Things that could go wrong. Discuss credible risks in terms of WHAT could happen, HOW it
could happen, and WHY it could happen
Things that have been known to go wrong elsewhere (relevant incident reports)
Weather conditions
Day or night
Experience of operators
Other operations in the area
Step 4. Identify the control measures for each hazard.
A whole range of controls (elimination, Substitution, etc.) should arise from such JSA, not just
procedural ones, as these are the least effective. Many of the non-procedural controls require
action before the job starts (E.g. purchasing of equipment (signs, harnesses etc.), training and
certification of workers, re-design of equipment, installation of barriers, etc.).
Step 5. Review the JSA with all workers on the works (Pre-Job Safety Meeting).
During Pre-Job Safety Meeting, work group will have a final discussion which includes HSSE and
Discipline Superintendent review on the JSA then approval to proceed with the Work. Pre-job
Safety Meetings will be conducted at each work site prior to the start of job activities. During these
meetings the contents of the JSA will be discussed in detail in such a manner to meet the
expectations. In this meeting, The Supervisor or Crew Lead facilitates the JSA and asks specific
questions of multiple workers to obtain their input regarding planning and conducting Work
safely. Each crew member shall offer input, asks questions, and actively listens during the JSA
discussion. After completing final JSA discussion, all components of the JSA are accurately
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 38 / 154
documented on the appropriate project JSA form. The JSA is reviewed and signed by each crew
member, and signature approval is provided by the Supervisor or Crew Lead.
13.4 Job Hazard Analysis (JHA)
Job Hazard Analysis will be focuses on following items:
1. Break the task down into a defined sequence of steps.
2. Identify the potential hazards which may come from the relationship between the worker, the
task, the tools, and the work environment.
3. Develop control measures to eliminate or reduce them to an acceptable risk.
Supervisor or Foreman shall be responsible to provide JHA and to ensure that the work crew aware
and understand all the associated hazards with the jobs they will be performing. and also know
what are the preventive measures to be taken to eliminate or reduce them into acceptable risk.
Supervisor and Foreman need to conduct periodical review to JHA to ensures that it remains
relevant to reduce workplace incidents.
Supervisor and Foreman shall be deliver and discuss about JHA with their work crews just before
starting the work (Pre-Job Safety Meeting).
During Pre-Job Safety Meeting, Supervisor or Foreman and their work crew will have a final
discussion to review on the JHA then approval to proceed with the Work. Pre-job Safety Meetings
will be conducted at each work site prior to the start of job activities. During these meetings the
contents of the JHA shall be discussed and confirmation/check to ensure all precaution already at
place. After completing final JHA discussion, JHA are accurately documented on the appropriate
JHA form. The JHA is signed by each crew member, and Supervisor or Crew Lead.
Refer to the Attachment 12. JHA Form
13.5 Toolbox Talk / Safety Task Analysis Risk Reduction Talk (STARRT)
Refer to document no. 26076-110-GPP-GHX-00041 “Toolbox Meeting Procedure / STARRT
Meeting”
The supervisor or Foreman shall use the STARRT process, with participation from his entire crew,
to identify potential hazards associated with the task, immediately prior to its commencement.
The STARRT process shall be used at the beginning of every shift and prior to starting any new
task. Supervisors shall ensure that their employees understand the purpose of, and participate in
the JSA and STARRT processes and shall use them as primary planning and lessons learnt tools.
Records of attendees will be retained.
13.6 Pre-Construction HSSE Activities
Where pre-construction work activities exist in CONTRACTOR’s scope of work such activities shall
be performed after the relevant Method Statements and JSA. These documents shall be
completed and approved. After the process completed, PTW will be issued by Approving
Authority. For Brownfield Approves by IPMT (PMC and Owner) and For Greenfield by
CONTRACTOR.
a) Site Visit
- Personnel visiting the Project site shall be briefed on the relevant HSSE issues and
thereafter shall fully comply with the requirements of OWNER and the project HSSE
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 39 / 154
procedures including the use of PPE. Visitors will be issued with a temporary site access
badge and in most cases will be accompanied by personnel with permanent
CONTRACTOR ID badge.
b) Temporary Facilities
CONTRACTOR will ensure that adequate office, welfare and accommodation facilities are
provided by themselves and by all SUBCONTRACTORs/vendors on the project.
These will include:
- Installation of facilities in a manner that recognizes access, egress and fire prevention
requirements;
- Providing utilities with special regard to the protection of underground and above
ground services;
- Consideration of adjacent process operations;
- Maintenance of standards of cleanliness and order;
- Ensuring that personnel are aware and are complying with the requirements of the fire
plan, and that adequate fire extinguishers have been provided
- Reporting any defect to relevant personnel;
- Ensuring that hazardous (e.g. flammable, etc) materials are stored and used in a
controlled manner, and adhering to electrical regulations
c) Site Preparation
Before commencing activities such as ground clearing, installation of temporary facilities, and
erection of batching plant CONTRACTOR will ensure that all relevant documents, including
Government licenses and Permits have been obtained. CONTRACTOR to issue Camp /
Canteen food health & safety plan
CHANGE RISK
RISK ASSESSMENT REQUIREMENTS
CATEGORY
1. JSA to be re-reviewed and re-written to incorporate with the
Low
change occur.
2. Requirements 1 and method statement may need to be
Medium
provided and approved.
3. Requirements 2, Conduct a Risk Assessment Workshop and
High
Prepare Action Plan.
Table 2. MOC Risk Assessment Requirements
Step 3 Details of the change
This step requires the Change Initiator to detail the following:
o Describe the reasons for change, providing hard evidence to support the need/opportunity.
o Describe the benefits of this change.
o When does the change need to take place and why?
Step 4 Commitment and Application
This step requires the Change Initiator to detail the following:
o List any Technical Expert who needs to be consulted about / approve the proposed change.
o List the people / groups who need to be consulted on the proposed change.
o List systems, policies, procedures, plans, schedules, competencies, etc which affected by these
changes.
A Technical Expert is generally the person who may own legal obligation/business accountability in the
area covering the change and may not necessarily be the Change Authorizer.
The Change Initiator is required to seek approval from the Technical Expert for the proposed change if
the risk is deemed to be High.
Step 5 Action Plan
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 41 / 154
This step requires the Change Initiator to develop an Action Plan for the successful implementation of
the proposed change.
It is required to review the effectiveness of the change at an agreed period following the change.
Step 6 Approval
o The Risk Category for the requested change is the highest risk rating from Step 2. That is, if one
category has a risk rating of Medium, but another has a risk rating of High, the overall risk rating is
High.
o This step is break down into two stages. The first stage, if required, is the review and approval by a
Technical Expert. This shall apply for all High-risk changes.
o The second stage is the approval by the Change Authorizer. The Change Authorizer is identified by
completing Step 2 Risk Assessment of the Change Management Request Form. The Change
Authorizer depends on the level of risk as defined in the following table.
5A Lawe-Lawe Facilities √
5B Tanked Area √
6 Receiver 52” √
7 Site Office √
9 Offshore 52" √
The detailed location can be shown on 26076-110-G3-GHX-00001 Plot Plan Greenfield &
Brownfield Area Lawe Lawe Terminal. Including GREENFIELD areas such as Area 1, 2, 3, 4 Incl. Deep
Well area, 7 and 8 and all between gate 3 and 3A as well as all OFFSHORE project facilities and
construction sites / barges / vessels etc. Also, transportation or pedestrian moving between Area
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 43 / 154
8 (gate 3A) and areas 1, 2, 3,4 incl. Deep Well and area 7 is GREENFIELD areas. While the others
are BROWNFIELD areas (for example Area 5, 6, etc.). In BROWNFIELD areas, CONTRACTOR shall
follow all the rules and requirements of PERTAMINA RDMP and RU V as well as compulsory full
PPE according to the work activities carried out.
Following are JO CPPHK General Rules in the site greenfield areas:
Gate 3:
- Security Check is required
- Must use ID Badge (Greenfield)
- For all workers who will carry out HSSE Induction shall have received complete personal
equipment from CPPHK or subcontractor.
- Cellphone is allowed
- Cigarette and matches is allowed
- Weapons, drugs and alcohol not allowed
Gate 3A:
- Security Check is required
- Must use ID Badge (according to the destination area, Greenfield or Brownfield)
- PPE Mandatory is required (Coverall, Safety Helmet with chinstrap, Safety Shoes, Safety
Glasses, and hand gloves). Used special PPE for specific activities.
- Cellphone is not allowed
- Matches is not allowed
- Diesel fuel vehicles, equipped with flame arrestor, fire extinguisher & first aid kit, SIMPER /
IMDK and Vehicle must have pass entry sticker.
Gate 3B :
- Security Check is not required
- Must use ID Badge (Greenfield)
- PPE Mandatory is required (Coverall, Safety Helmet with chinstrap, Safety Shoes, Safety
Glasses, and hand gloves). Used special PPE for specific activities.
- Cellphone is not allowed
- Matches is not allowed
Site Office (Area 8):
- Must use ID Badge (Greenfield)
- For every working/maintenance activies refer to 26076-110-GPP-GHX-00016-000 Permit to
Work Procedure
- Inspection for camera and PC is not required.
Warehouse/Workshop and Genset area:
- Must use ID Badge (Greenfield)
- PPE mandatory is required
- For every working/maintenance activities, 26076-110-GPP-GHX-00016-000 Permit to Work
Procedure
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 44 / 154
o Pedestrian crosswalk will have an interface with vehicles access. CONTRACTOR must treat
adequate control for this area such as put proper sign to stop their vehicles and give priority
to pedestrian to cross the road, provide dedicated signal man, speed limit, etc.
o Identified blind spot with potential crash between pedestrian and vehicles shall provide with
mirror and adequate safety sign. E.g. pedestrian walkways at warehouse, workshop.
o Indoor workplaces where employees generally work in enclosed areas with central air-
conditioning: –Any microorganism breeding inside the air-conditioning system or cooling
towers may spread in the workplace through the air-conditioning system.
o Employees who work with animals.
Biological hazards likely to affect workers in specific workplaces will be vary according to the type
of occupation, the location, the weather, the nature of the work, species known to occur in the
region and the environment. Liaison with specialist advisors may be required to document the
type and extent of the Biohazards relevant to a workplace and to prepare a risk assessment and
mitigation plan based on that assessment.
Control of Biohazards requires systematic, analytical application of a hierarchy of control that
takes account of the nature of biohazards agent, the workplace, the nature of work, and the
workers.
If the contact with Biohazards cannot be prevented, the employees must use PPE and adhere
strictly to the practice of personal hygiene. PPE will be including masks, gloves, protective clothing,
eye shields (safety googles), face shields, and shoe covers.
This animal has a very strong jaw, which can bite with extraordinary strength, making it the
animal with the greatest bite strength
Crocodiles prey on fish, birds, mammals, and sometimes other crocodiles that are smaller and
even the bodies of adult crocodiles. These reptiles are ambush predators, it waits for its prey
land animals or fish to approach, then pounces it abruptly. As cold-blooded animals, these
predators can survive long enough without food, and rarely really need to move to hunt their
prey. Although it seems slow, crocodiles are the top predators in their environment, and some
species have been observed to attack and kill sharks. The exception is the Egyptian plover, which
is known to have a symbiotic relationship with crocodiles.
Snake bites can occur while working, especially when working in fields where there is still a lot
of grass
Ensure medical facility have appropriate anti venom available.
All people who are bitten by a snake must be transported to a medical facility immediately
Stomach aches, vomiting, headaches, are often the first symptoms.
Signs of muscle weakness due to bite (envenomation) may only occur after 24 hours
The most important thing is to stop the spread of poison from the bite site
That must be done immediately
Do not let the patient move - carry the transport to the patient
Try to keep the patient calm and not moving.
Do not wash the bite marks. Maybe a special test will be done to find out the type of snake
that has bitten the patient, based on the poison left in the skin.
Wrap / wrap all limbs, use the same pressure as for a sprained ankle
Wrap the arms or legs so they cannot move at all.
If the bite is on the body or on the head, give bandages only on the bite marks.
All food handlers shall be rigorous in matters of personal hygiene, washing hands before
touching food after having touched something else. All food handlers shall wear fresh and clean
uniforms with aprons, head cover and safety shoes. They shall maintain a clean, neat and tidy
appearance, with short finger nails and hair. The wearing of jewelry, especially rings, whilst
working is strictly prohibited.
The HSSE Manager shall implement a system of monthly checks and inspections of the catering,
food storage and preparation areas to ensure compliance with hygiene standards.
18.4.2. Fatigue Management
o CONTRACTOR must provide adequate rest periods for employees. It is recommended that
rest periods between shifts be at least 10 hours. In the event that an employee is required
to work longer than the normal allocated, consideration should be given to their start time
for the next shift.
o Where employees are required to work an extended shift, (i.e.: greater than 12 hours),
consideration should be given to:
- Maximum overtime on site is 15 (fifteen hours) in one day work cycle.
- At least 10 hours break should be given taking into consideration travel time, eating,
socializing, relaxing and sleeping.
- Adequate rest breaks should be given during the work shift.
o Where an employee is required to change shift from day to night shift, and vice versa, they
should be given a full 24-hour rest period prior to commencing the new shift.
o All employees shall not work more than thirteen (13) days straight without taking a day rest.
o To effectively manage fatigue caused by on call work, consideration is to be given to:
- Limiting the number of consecutive 24-hour periods that an individual is on call.
- Rostering more than one person to be on call at any time so that someone who is not
well rested is not required to work.
- Make arrangements to have workers transported to and from site.
18.4.3. Housekeeping
o Refer to document no. 26076-110-GPP-GHX-00033 “Housekeeping Procedure”
o A planned, clean, orderly project site is mandatory. Worksites, shop areas and lay down
areas shall be kept clear of scrap and unnecessary materials. Materials necessary for work
shall be properly stacked and kept out of roadways to allow proper access for firefighting
equipment. Lay down areas shall be planned and laid out in sections with access roadways
adequate for fire-fighting and materials handling equipment.
o Housekeeping practices and clean-up of all project facilities will be maintained by
Construction Team.
o The work area shall be maintained to a high standard of cleanliness, and supervisors will be
expected to review and rectify their respective work areas as required on a daily basis.
o Waste material shall not be burned in site and shall be segregated when disposed of in the
bins.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 52 / 154
2. If the STS persists, ear protection will be upgraded to one with a greater Noise Reduction
Rating (NRR). The minimum NRR will be 26 dBA.
3. The employee will be counselled, and information will be obtained regarding the
employee's possible noise exposure away from the workplace or existing ear pathology.
4. Qualified medical personnel will review the audiograms. This group will determine the
need for a medical referral.
5. The employee and employee’s supervisor will be notified of the shift in hearing threshold
in writing by HSSE within 21 days of determination.
6. If the employee who has experienced an STS is exposed to 85 dBA for 8 hours or 80 dBA
for 12 hours, mandatory use of ear protection is required.
7. Temporary employees will receive audiograms during their exit physicals if they have
worked around heavy equipment or have received an exposure to noise levels in excess
of 85 dBAs.
18.4.6. Respiratory Protection
- CONTRACTOR will comply with industry standards for the specification and provision of
respiratory protection. Disposable respirators for nuisance dust shall comply with BS or
ANSI standard
- Where a Risk Assessment identifies the need, CONTRACTOR and SUBCONTRACTORs will
ensure the provision and use of appropriate respiratory protective equipment,
manufactured to a recognized international standard.
- Appropriate training shall be provided to the wearers on the inspection, use, sanitary care,
and limitations of the equipment. Records of such training shall be maintained by
CONTRACTOR
- Supervisor will be responsible to provide Respiratory protection base on assessment of the
job. The respiratory protection type shall be in accordance with the PPE standard.
- Any employee who requires respiratory protection to perform the work shall be trained,
medically qualified, and fit-tested.
- CONTRACTOR must ensure that respiratory protection equipment cleaned and stored
properly
18.4.7. Radiation Protection
Radiation protection will be under Construction Manager’s responsibility. At the minimum, the
Construction Manager will ensure the following:
o Provide special room / bunker for Radioactive storage complete with sign and according
regulation and standard radiation storage system.
o Provide Sign, Barricade, Orange & Red rotary lamp and other equipment/tools to alert
that dangerous activity being conducted.
o Provide qualified personnel to conduct radiation activity. The personnel shall be certified
by BATAN for conducting the activity.
o NDT (RT) without collimators are prohibited.
o Emergency procedure for Radioactive shall be provided.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 54 / 154
CONTRACTOR must provide sufficient and adequate illumination for night work activities.
Illumination intensities shall comply with minimum requirement as defined in OSHA Safety &
Health Regulation for Construction, Subpart D, and Standard Number 1926.56(a) table D3.
Perform lifting activities that classified as critical lift is not allowed at night.
According to the construction condition of RDMP Lawe lawe Project that the high intensity of the
construction activity become trigger the need to accommodate the work at night. Especially for
critical activities at night must be equipped with a checklist (as attached in attachment 13) who is
reviewed and approved by the RDMP Lawe lawe Manager on duty.
Recommendations regarding the requirements that must be met before the start of critical
activities at night including monitoring for work and sometime after the work are completed. This
includes night time critical works, such as:
Working at height
Critical lifting work
Working aboard a barge
Confined space
Equipment repair work
Hot works
Etc.
Next, we have to make sure the checklist work at night consistently implemented seriously and
responsibly. The checklist is part of the Permit To Work (PTW) document for night work.
Detail of Working at Night Procedure is described on document 26076-110-GPP-GHX-00048.
18.13 Prevention the spread of Corona Virus Disease (Covid-19) for Workers, Partners and Families.
JO CPPHK must be managing the lowest possible risk according to the spreads of COVID-19 in all
lines of the operational activities of EPC Lawe-Lawe Facilities Project and to ensure the operational
activities runs well in order to complete the project on schedule. Work mechanism will be arranged
by JO CPPHK to handle prevention the spread of COVID-19 which includes the following details:
1. Daily checkup (Body temperature) using thermogun for all workers when entering the work
areas and the result will be reported.
2. If the body temperature >37.5°C and with the symptoms like Cold / Cough / sore throat /
shortness of breath shall be taken to nearest hospital immediately for further checking
according to the applicable government procedures.
3. Provide prevention facilities, includes:
a. Wash Hands Facilities including clean water and soap.
b. Hand sanitizer on site.
c. Provide drinking water and maximizing to use personal tumblers or disposable glasses.
d. Provide face masks.
e. Distribute vitamins and supplements for maintain immune and stamina.
4. Daily education to all workers including subcontractors with conducting Toolbox Meeting,
General Safety Talk, and Posters / Banners to increase personal awareness (workers &
families) against the transmission of COVID-19 through the following efforts, such as:
1) Avoid crowds (Public Area)
2) Avoid direct interaction between personnel, such as: Handshaking, hugging, etc.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 58 / 154
Availability and has been applied standing area marking on lift by considering the safe
distance between user (not facing each other, the space is sufficient according to the
physical distancing protocol).
Ensure that provided seats has been complied for physical distancing requirements
(separate and 1.5 meters minimum distance and has been marked).
Ensure that all personnel use masks properly
Disinfection 7 cleaning of work spaces in the lobby and reception area must be carried out.
C. Receiving package from outside Management
Ensure the body temperature of couriers has been checked an passed physical checking.
Couriers may not allow to entering the gate, and package placed at the drop off point.
Ensure on every package that entering JO CPPHK work area has sprayed with disinfectant.
Ensure the package that has been sterilized is delivered by internal personnel to the
recipient.
Ensure the body temperature of couriers has been checked a passed physical checking.
Couriers may not allow to entering the gate, and package placed at the drop off point.
D. Workspace and Meeting Management
Ensure that tables and chairs in work spaces and meeting room comply with physical
distancing requirements (minimum distance of 1.5 meters which can be marked with a
marker, workers are not allowed to face each other, or there is a dividing bulkhead, the
maximum occupancy of the meeting room).
Provide the sign or a text stating "the maximum number of occupancies in the meeting
room" and "maximum duration of 60 minutes".
Make sure the meeting conducted using by MS. Team. Attempted to avoid face-to-face
meetings.
The worker must be do physical / social distancing.
Workspaces and meeting rooms are cleaned (at least 2 times a day) and disinfected (once
a week) on a regular basis.
Make sure the workers always wear a mask.
E. Management of Breakout / Pantry / Canteen / Mess Area
Ensure all places has implemented physical distancing
Ensure that tables and chairs in breakout/pantry comply with physical distancing
requirements (minimum distance of 1.5 meters which can be marked with a marker,
workers are not allowed to face each other, or there is a dividing bulkhead).
The worker has been informed to bring their own tableware.
The worker should be worn mask properly, Chef and the food presenters also use gloves
and mask properly.
Ensure to provide wash basin facilities and hand sanitizer
Proper trash bins are available.
F. Public Facility Management
Public facilities (smoking area, musholla, toilet, parking area etc.) comply with physical
distancing requirements (minimum distance of 1 meter which can be marked with a
marker, workers are not allowed to face each other, or there is a dividing bulkhead).
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 60 / 154
Note: For musholla management, every worker must bring their own prayer mat. The
public facilities to be used interchangeably.
The workers use their own prayer mat and do not left it in the musholla
G. Toilet Management
Must provide soap for hand washing and tissue.
Proper trash bins are available.
Toilet users always wear a mask
H. Trash Management
Plastic bag bins must be provided and always closed.
I. Drop Off point Management
Availability facility and drop off point protocol for catering, food and stuff delivery.
J. Pool and shuttle Point to Point Management
Vehicle must be disinfected and cleaned regularly before it used.
Shuttle point to point must be provided for the transportation of workers and partners.
Passengers must be limited to a capacity of 50% capacity, and apply the concept of
physical distancing and other health protocols (must wearing a mask and washing hands
also using a hand sanitizer).
Availability vehicles must be suitable for workers who do not use private vehicles
Drivers and passengers who are WFO must have had the Rapid Test and the results are
Non-reactive.
Driver and passengers must use masks.
Personnel no longer use public transportation.
Provide hand wash facility and hand sanitizer at the parking area
K. Arrival Workers from their Origin Management (Mess)
Ensure workers from outside mess, must pass the Rapid Test (internal Balikpapan) or
SWAB Test (for those from outside Balikpapan)
L. Entering Mess Protocol
Provide a place to put shoes, sandals before entering the house.
Provide laundry basket.
Provide hand sanitizer in every strategic place at the mess (living room, dining room, etc.).
M. Bedroom Management at the Mess
The Limitation on the number of occupants. The distance between the beds is 2 meters. 1
room does not exceed 10 peoples.
Do not allowing the guests to come during pandemic
Provide the special room for self-isolation or quarantine and its occupants are limited.
There is sufficient distance between isolation rooms and another room.
Daily needs of people in the isolation room (food, drink. MCK) are separated from people
in another room and be served.
N. COVID-19 Prevention Inside Vehicles Requirements
Regarding the COVID-19 Prevention Program in All CPPHK Operational Vehicles, Ensure:
COVID-19 prevention barriers on vehicles are installed
Hand sanitizer and cleaning wipes are available in each compartment
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 61 / 154
All passengers have cleaned their self before entering the vehicle and wiped their seats
when exiting
Air conditioning must not be used during occupation of the vehicle and all windows shall
remain open during driving and occupation for full ventilation
O. Protocol for New Comer Employee or After Temporary Leaving Site
New Worker, after business trip, or after temporary leaving site for holiday need to be get
Medical Clearance from Doctor on Site, as for the requirements as follows:
1. Active Workers (Have ID Badge)
From Outside EAST Kalimantan:
- PCR/Swab Test
- Rapid Test Self Quarantine (min. 14 days) Rapid Test
From EAST KALIMANTAN, Outside Balikpapan & PPU:
- PCR/Swab Test
For every worker that used public transportation.
- Rapid Test
For every worker that used private transportation
Protocol as above applies also to every worker that have ID Badge and have traveled
from outside Balikpapan or PPU (Example: Business trip to Head Office, Survey/Visit
Vendor, etc.).
*NOTE:
PCR/Swab Test and Rapid Test Result need to be clearance by Doctor on Site.
PCR/Swab Test and Rapid Test Result valid for 14 days after result announced.
Workers can return to work after get Medical Clearance from Doctor on Site.
2. New Workers (Have no ID Badge)
From Local Balikpapan & PPU:
- Valid MCU and attached Screening Covid-19 Letter from Clinic/Hospital.
From Outside Balikpapan & PPU:
- Valid MCU and attached the Result of PCR/Swab Test
- If attached Rapid Test Result must be Self quarantine (min.14 days) and fulfilled
Self Quarantine Form.
others compulsory hand gloves PPE especially when working at height for example. Inherent
hazard when working at height and during night time could results in unwanted fatal incident.
All personnel who work in RDMP Lawe-Lawe project must be worn mandatory PPE. The standard
PPE that must be worn are:
Table 6. Personal Protective Equipment (PPE) Standard
Head protection All head protection with chinstrap shall meet requirements set
out in EN 397, ANSI Z89.1 – 2003
Colour requirements of safety helmet
CONTRACTOR’s Supervisor and above: White colour
SUB-CONTRACTOR helmet: Yellow colour
CONTRACTOR & SUB-CONTRACTOR HSSE Personal: Red colour
Eye and face protection All eye and face protection shall meet the requirements set out in
EN 166, ANSI Z87.1 – 2003
Respiratory protection All respiratory protection shall meet the requirements set out in
ANSI Z88.2 – 1992, filter respirator set out in BS EN 4275, 1997;
Airline mask BS EN 139, 1995; Self Contained Breathing
Apparatus (SCBA) BS EN 137, 1993
Hearing protection All hearing protection shall meet the requirements set out in ANSI
S3.19 – 1974, all type of hearing protective shall be used
appropriately depend on noise level to protect noisy as state limit
Hand protection All hand protection shall meet the requirements set out in BS
EN 420:2003 + A1 2009 and Super Duty gloves for specific activity
Body protection One-piece coverall (grey colour) with CONTRACTOR name and
personnel name
Foot protection All foot protection shall meet the requirements set out in BS EN
345, 1993 ANSI Z.41
Fall protection All fall protection shall meet the requirements refer to ANSI
A10.14
PPE inside Gate 3 Lawe-Lawe are Safety Helm, Safety Shoes & Two Piece. PPE Inside Gate 3A Lawe-
Lawe are Safety Helm, Safety Shoes, Coverall, Safety Glasses and Gloves. Used special PPE for
specific activities.
20.2 Safety Sign, Color Coding and Barricade
Refer to 26076-110-GPP-GHX-00034 Barricade Procedure, 26076-110-GPP-GHX-00010 HSSE
Inspection Procedure, 26076-110-GPP-GHX-00004 HSSE Sign and Color-Coding Procedure.
The boundaries of critical work areas, excavation and others hazard must be clearly delineated
by visible barricade and signage.
Hazard signage shall be posted in conspicuous place to warn workers about any hazard that is
present in the surrounding areas.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 64 / 154
CONTRACTOR shall ensure that employees understand with safety sign, colour coding and
barricade.
Signage shall be well illuminated so that it could serve its purpose. Broken signage shall be
replaced immediately and maintenance of all hazard signage shall be performed accordingly.
Excavation and floor openings shall be barricaded with hard barricades instead of barricade
tape.
CONTRACTOR and SUBCONTRACTORs/vendors will ensure that employees understand and
comply with barricade and barrier procedures (i.e. prohibited entry into barricaded or taped
areas).
No road shall be closed off without CONTRACTOR approval (OWNER when required).
20.3 Chain Blocks and Come-A-Longs
Refer to 26076-110-GPP-GHX-00024 Lifting and Erection Procedure.
Chain blocks and Come-a-longs shall have valid test certificate.
Pre-use check for Chain blocks and Come-a-longs shall be done in daily basis by the rigger.
Chain block shall never use for tensioning, pulling or anchoring loads.
Chain block and Come-a-longs shall be inspected every three month and change the colour
code.
It is prohibited to use rejected or out of service chain blocks and Come-a-longs. In case of
“out of service” for maintenance, chain blocks and Come-a-longs could be used only after
pass the inspection.
The use of Chain Blocks and lever blocks must pay attention to the following matters:
Make sure the lever / chain block is attached to the beam using standard shackle and lifting
lugs.
Be sure to use pad eyes made specifically for connecting hooks from the lever / chain block.
It is forbidden to swing a load that is hanging or pulling against the floor.
Do not use a lever / chain block if the hook has changed shape. (crooked or wide open)
Do not use a lever / chain block if the name plate is unclear or missing.
Make sure to place the top and bottom hooks at a standard lifting point.
Be sure to use webbing sling to tie the pipe and hook it to the hook.
Make sure the lever / chain block is neatly stored in the storage area.
Ensure that annual inspections and load capacity tests of the levers / chain blocks are carried
out routinely.
Make sure the lever / chain block has a number
Serial and WLL (working load limit) & the availability of valid certificates.
Make sure the lever / chain block color code (quarterly) is still valid.
Do not be under the load position of the chain block
It is forbidden to use a chain lever / chain block as a binder / binding material.
It is prohibited to link the lever / chain block in the scaffolding pipe as a point of lifting.
Do not use a lever / chain block if the chain is damaged, elongated or bent.
Do not use levers / chain blocks that do not have safety latches or conditions are damaged.
Immediately replace the safety latch with a new one.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 65 / 154
Do not lift loads beyond the capacity (SWL) specified in the chain / lever block.
It is prohibited to build a load on the end of the hook lever / chain block.
Hook lever / chain block is prohibited from being connected to the beam.
20.4 Lifting and Rigging
Detailed procedure for crane and lifting refers to document 26076-110-GPP-GHX-00024 Lifting
and Erection Procedure.
20.4.1 Crane Requirements
CONTRACTOR will ensure that all cranes used for this project either provided by
SUBCONTRACTOR and/or directly by CONTRACTOR shall have valid certificate from MIGAS.
All cranes shall pass the CONTRACTOR’s standard and can only be used after get an
approval from CONTRACTORs.
All lifting Crane shall have:
- Valid MIGAS certification in line with the lifting requirements
- Its identification numbers
- Safe Working Load (SWL) marking
- Current color code, transit slings are permitted to be of a different color to that in
use during the current color period. This is to identify them as “transit slings” which
is less confusing
- Load chart put in the cabin
- An adequate safety factors
- The current color code must be posted and all slings with different color must be
moved from the location
- Certification of Lifting Crane shall be managed.
In case of intending to use lifting crane in an unusual way, suitability must be indicated by
the manufacturer / supplier and the advice sought before any change of use is attempted.
20.4.2 Lifting Gears Requirements
All lifting gears will be inspected by qualified inspector from CONTRACTOR and have valid
MIGAS certification.
Lifting gears will be inspected regularly by CONTRACTOR Inspector and follow the colour
code inspection system.
All lifting gears shall have:
- Valid MIGAS certification in line with the lifting requirements
- Its identification number
- Safe Working Load (SWL) marking
- Current color code, transit slings are permitted to be of a different color to that in
use during the current color period. This is to identify them as “transit slings” which
is less confusing.
- Regular inspection by CONTRACTOR inspector before change color code
- An adequate safety factor
- The current color code must be posted and all slings with different color must be
moved from the location
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 66 / 154
2 Truck Mounted Crane (TMC) MIGAS / OIL & GAS (Government agency)
Vehicles shall not be older than 5 years for light vehicles and 10 years for trucks and another
heavy vehicle.
All vehicles and heavy equipment’s must have reverse alarm installed.
CONTRACTOR shall ensure that all vehicle drivers and heavy equipment operators are fit to
work and shall have a valid license for driving and/or operating issued by Government or
authorized institution.
All heavy mobile equipment and vehicles must be in a safe operating condition at all times.
They are to be checked at the beginning of each shift. All heavy mobile equipment and
vehicles shall be attached by fire extinguisher, first aid equipment, seat belt and flame/spark
arrestor.
The number of passengers of vehicles or equipment’s must follow the availability of seat belt
and it is prohibited to utilize the bed of truck and/or vehicles for passengers.
Inspection to all heavy mobile equipment and vehicles will be done regularly. Inspection
Sticker will be attached to the heavy mobile equipment and vehicles after pass the Inspection.
With this sticker, equipment’s and/or vehicles permitted to be used at greenfield and
brownfield area.
All heavy mobile equipment and vehicles to be used at RDMP Lawe-Lawe CPPHK will be manage
to be complied with RDMP Lawe-Lawe CPPHK Inspection procedure No. 26076-110-GPP-GHX-
00010 HSSE Inspection Procedure.
20.6 Working at Height /Fall Protection
Refer to document no. 26076-110-GPP-GHX-00020 “Working at Height Procedure”
Working ≥ 1.8m is mandatory to use safety full body harness complete with double lanyard.
Shock absorber will be required to be attached to the full body harness by consider the
potential fall distance (with 3 ft safety factors). Below the picture illustration for the
calculation of potential fall distance.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 70 / 154
The standard of scaffolding that must be following: OSHA standard with material of the frame
scaffolding must be galvanized.
Work platforms must be equipped with standard guardrails, mid-rails and toe boards.
Drop bars must be installed on all scaffolding deck/platform.
Detail of scaffolding pipe specification and materials shall be followed Construction Execution
Plan (CEP) and in accordance with Contract.
The uses of frame scaffolding for working at height platform are strictly prohibited.
Movement of materials, tools, equipment, etc. to higher or lower levels will be affected by
hand line or hoist apparatus.
Open sides and ends of platform 6 feet (1.8 meters) or more above will be guarded by top rails,
mid rails and toe boards with the top railing 42 inches (1.1 meters) above the platform levels.
Scaffolds must be erected plumb and on a solid foundation. Loose bricks, boxes, concrete
block, scrap lumber, etc. must not be used to level or support scaffolds or planks.
All scaffolds must have an inspection tag placed at the point of access/egress by a competent
person.
Employees, materials and tools must not ride on mobile scaffolds.
Ensure toe boards are in place and secured down to prevent tools and materials from falling
off and provide buckets/boxes to store small material
Ensure safe access to and from the scaffold is provided with no obstruction.
Keep the platform tidy and remember only LIMITED materials are allowed on the platform.
NEVER modify components of a scaffold for your job, only SCAFFOLD CREW is authorized to
modify the scaffold.
Visually inspect the scaffold at all points to ensure safety every time you are planning to use
it.
Weekly inspections of scaffolds are done to ensure the scaffold is still safe for use. Scaffold
Tags identifies the condition of the scaffold
Regarding scaffolding platforms for offshore activities:
- Where practicable, a scaffold is the best method of ensuring safe offshore activities.
- The scaffold should be designed for the task so that it is stable and of sufficient size for the
proposed work.
- Guardrails and toe boards should be fitted to prevent falls of persons or materials
20.8 Falling Objects Protection
The most effective way to eliminate/minimize the potential personnel exposure to falling tools,
materials and/or debris is to never allow employees to work and walk below others in that are
working at an elevated work area.
Whenever possible, to secure below area of an elevated work location with barricade.
Tools, equipment, material, etc., will be kept and arranged in an orderly manner and good
housekeeping will be practiced throughout the work day.
Controlling/restricting the amount of material taken to the elevated work areas; only
stage/store what is needed to perform the task.
Minimize hand carrying or handing material from person to person by hands.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 72 / 154
Safe access must be provided into all excavations by means of ladders, ramps or stairs.
Access ladders or other means of access shall be placed at regular distances (max. 7.5m) so
that workers only have to travel a short distance to escape if there any emergency situations.
Access ladders shall be placed at least 1 m protruding over surfaces and must be tied off to
prevent any movements.
Climbing into or out of excavations using the waling and struts is prohibited. In narrow trenches
use vertical ladders.
Walkways, bridges or ramps with standard guardrails must be provided where workers or
equipment are required to cross over excavations or trenches.
At the edges of all excavations where a worker fall could occur ≥ 1.2 m, rigid barriers must be
erected or the excavation covered and clearly visible.
Particular care is required where the public are required to cross over excavations. In a case
such as a footbridge, rigid hand railing must be provided with appropriate warning signs
advising of the hazards.
Dewatering is necessary if the water table is less than 0.5m from the bottom of the intended
maximum depth of the excavation (i.e. more than 1.7 m depth)
If the excavated pit or trench is deemed to be a Confined Space, the pit / trench shall be treated
as such and all Safe Working in a Confined Space shall be strictly adhered to.
Detailed of Excavation and Trenching refer. 26076-110-GPP-GHX-00019 “Excavation and
Trenches Procedure”.
20.11 Confined Spaces Entry
Refer to document no. 26076-110-GPP-GHX-00021 “Confined Space Procedure”
Confined Space means a space which:
Is not intended as a regular workplace (i.e. continuous employee occupancy)
Has restricted means of entry or exit;
Is large enough and so configured that an employee can bodily enter and perform assigned
work and is at atmospheric pressure during occupancy.
All excavation activities more than 1.5-meter depth
Has limited air circulation
In addition, this space has at least one of these characteristics:
It contains or has a potential to contain a hazardous atmosphere;
It contains material (solid or fluid) that has potential for engulfing an entrant;
It has an internal configuration such that an entrant could be trapped or asphyxiated by
inwardly converging walls or by a floor which slopes downward and tapers to a smaller cross-
section; or
It contains any other recognized serious safety or health hazards, for example exposed rotor
blades, noise etc.
Examples of confined spaces are:
Process vessels and related equipment (vessel tower skirts and flare stacks), boilers, water
storage tanks, other tanks including pontoons on floating roof tanks, tank cars and trucks;
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 74 / 154
Spaces located below ground or deck level, such as drain pits, sewage pits and associated
tunnels, ducts, trenches, wells, shafts, cellars, vaults and unventilated rooms which may be
considered confined spaces under specific circumstances.
Entry into a confined space shall only be contemplated as a last resort, after all other possible
options have been ruled out. Tasks to be carried out in a confined space shall be Subject to a Risk
Assessment at the planning stage. If all other options for completing the work without confined
space entry are ruled out, task-specific controls shall be implemented to ensure it is safe to carry
out the work.
Before entering the confined space (sewer, drain, manhole, vessel, tank, or other enclosed area
with restricted entry and exit), workers must be trained and have an Entry into Confined Space
Permit.
CONTRACTOR shall identify the position(s) or person(s) responsible to coordinate entry operations
and permitting for the site(s). These people and their responsibilities shall be shown on the
Confined Space list. As a minimum confined space activity should have these following position (s)
or role (s):
Authorized entrants.
Standby Man/Person.
Authorize Gas Tester.
Entry Supervisor.
Standby Man/Person responsibilities are:
To monitor entrants during the job and during entry & exit to ensure their safety.
The standby person may not abandon his post for any reason while personnel are in the
space. In case he/she need to leave, he/she MUST contact their supervisor/foreman to be
replaced by another trained standby person.
To control access to the confined space.
To summon emergency assistance as needed.
To assess hazards in and around the space, and act on the same.
To keep records of confined space work, such as air test results, personnel entry/exit.
Standby person can ONLY watch one confined space at a time and shall have no other duties.
Authorize Entrants responsibilities are:
Understand the hazards involved with the job.
Know the mode, signs and symptoms of exposure to chemicals hazards that could be present.
Use the required PPE correctly.
To inform the standby person when noticing a warning indication of exposure to a hazard.
Sign the entry log when entering or exiting the confined space.
Will evacuate the space when any of the following conditions occur:
- An order to evacuate is given by the standby person
- Entrant recognizes a warning indication of hazard exposure
- The evacuation alarm is sounded
To assure that the space has been adequately ventilated, isolated, emptied, or otherwise
made safe for entry.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 75 / 154
To immediately exit a space, without question, upon word of the standby person, no matter
what the reason.
To follow all HSSE rules and procedures that applies to the job.
All workers involved in confined space entry must be adequately trained to acquire the
understanding, knowledge, and skills necessary for the safe performance of the duties and to
ensure that safe work procedures are followed.
CONTRACTOR shall identify the training required to comply with this procedure and provide
training to ensure employees have the necessary understanding, knowledge, and skills to safely
perform Confined Space duties.
This training as a minimum shall:
Address safe work practices,
Address roles and responsibilities of employees,
Address the use of applicable safety equipment,
Effectively communicate work conditions within the Confined Space and identified potential
and corrected hazards.
The training shall develop qualified employees and shall be continually improved to address
changes in the Confined Space program.
Confined space categorized as Gas Free/Respirable and Non-Gas Free/Non-Respirable Confined
Space. The conditions under which entry is permitted will depend primarily upon the results of
the atmospheric sampling using the table shown below.
Approved Entry Under Gas Free / Approved Entry Under NON-Gas Free /
NO
Respirable Condition NON-Respirable Condition
1 Breathing Apparatus NOT required Breathing Apparatus required
2 OXYGEN: 20% TO 20.9% OXYGEN: <20% OR > 20.9%
LEL: <1% AND Toxic vapors ≤ 50% of LEL: >1% but <10% AND/OR Toxic vapors >
3
PEL 50% of PEL
Remarks – (a) For Inert conditions - Refer to
Remarks – (a) Both conditions 2 & 3 PTS 60.2110 Working in Inert Space (b) BA
above must be met for entry without must be used if either condition 2 or 3 is
4 BA (b) Typical gas detectors will provide present (c) Higher presence of flammables
reading for presence of Oxygen, indicates presence of other gases which
Flammables, CO and H2S may not be detected using the typical gas
detector.
Table 8. Requirements for Respirable and Non-Respirable Confined Space
6. Continuous ventilation.
7. PPE & Tools.
8. Rescue Plan (for high risk confined space activity based on Risk Assessment).
9. Permit to Work.
A competent Rescue Team shall be available and on alert for high risk confined space entries
(based on Risk Assessment). Rescue Team members should have ready access to Breathing
Apparatus sets or airlines, harnesses, line rescue and any other equipment necessary for safely
retrieving injured or collapsed personnel from the confined space. The Rescue Team response
time must be considered during the Risk Assessment and Planning stages of the job preparation.
Specific Confined Space procedure with project site condition shall be provided to ensure all
Confined Space activities can be carried out safely.
The CONTRACTOR and SUBCONTRACTORs will ensure that all employees have the CONTRACTOR
in-house training regarding the hazards of confined spaces and the procedures to be followed.
Special training shall be provided to all entry supervisors, entrants, and attendants. The
CONTRACTOR will ensure that entry supervisors know, understand and execute their full
responsibilities
Assigned AGT (Authorized Gas Tester) will examine each confined space before initial entry to
evaluate the specific hazards and SUBCONTRACTOR’s safety precautions.
Prior to each entry into a confined space SUBCONTRACTORs will ensure, and the CONTRACTOR
will verify, that:
- Proper ventilation equipment is used to purge and/or supply air to the confined space
- All electrical services have been Earth Leakage Protection Device (ELPD) or Ground Fault
Circuit Interpreter (GFCI) protected
- No AC current equipment or lightings to be used within confined space.
- Adequate access/egress from the confined space is provided,
- A task specific rescue plan has been developed and reviewed with all involved employees,
and
- All external sources of atmospheric contamination are isolated.
- Ensure periodical gas check to be performed at all times of the confined space activity and
Subsequent gas test will be by the CONTRACTOR and all data must be recorded on the
permit.
The CONTRACTOR and SUBCONTRACTORs will evaluate each confined space for possible heat
stress conditions.
SUBCONTRACTORs will ensure that all personnel who will be responsible for safety watchers
(confined space attendants) are easily identified, properly trained and aware of the duties
associated with each emergency situation that may occur within the confined space.
The CONTRACTOR and SUBCONTRACTORs will ensure that an emergency response plan is
available for all confined space entries and that all employees know how to summon assistance.
20.12 Lock-Out and Tag Out Procedure (LOTO) – Energy Isolation
Refer to document no. 26076-110-GPP-GHX-00017 “Lock Out and Tag Out (LOTO) Procedure”
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 77 / 154
CONTRACTOR will ensure that all employees receive instruction on the specific lock-out/tag-out
procedure and comprehension testing shall be conducted to verify knowledge and understanding
of the procedure. Records of training and testing shall be retained.
Worker supervisor, SUBCONTRACTOR HSSE officer, CONTRACTOR disciplines supervisor in charge
and CONTRACTOR HSSE supervisor shall utilize and control their personnel key log and worker to
ensure that entire worker or work area have safe during LOTO working execution and termination
period.
LOTO system shall implement before performing repairs, adjustment of electrical, pneumatic,
hydraulic, thermal, gravity and radiations equipment.
Personal Danger Tag tagging and padlocked (Red colour) will be used for equipment that is being
repaired by someone.
Out of Service Tags (yellow colour) shall be attached to faulty equipment or out of service equipment
and shall be left attached until the equipment is repaired and ready for use.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 78 / 154
must be equipped with a drip tray to contain any accidental leak. The daily inspection
check list shall be kept for recording purposes.
- Isolation switches for machines and equipment shall be readily accessible.
- Terminals and live components shall be adequately protected and cables shall be
frequently inspected to ensure that insulation is intact.
- The welding return cable shall be secured onto the work piece, or as near as is practically
possible
- Approved cable connectors shall be used when connecting runs of cables and cables must
not be allowed to lie in water
2) Cutting and Grinding Works
- SUBCONTRACTORs shall ensure that any of their employees authorized to change abrasive
wheels have attended the vendor approved course of training, carried out by in-house
personnel, or have been appointed in writing by their Construction Manager. This
certificate must be with the employee at all times while on site. Training will include the
following: Grades, types and marking of wheels, the use, hazards, speeds, storage,
handling, inspection, testing, dressing, adjustments, and the functions of associated
components such as flanges, bushes, locking nuts etc.
- Details of each employee trained shall be entered in an Abrasive Wheels register retained
at site by each SUBCONTRACTOR. Machines used to drive abrasive wheels shall be in good
condition, inspected daily and properly guarded.
- Pedestal or bench mounted grinders shall have an emergency stop button and be fitted
with a properly adjusted tool rest. Pedestal grinders must be securely fixed to the floor to
prevent them from walking when in operation
20.16 Pedestal, Bench and Portable Grinders
Machinery, such as grinders or buffers, must be secured to a work bench or pedestal and the
bench or pedestal, in turn, must be secured to the floor to prevent walking or moving.
Pedestal or bench mounted grinders shall have an emergency stop button and be fitted with a
properly adjusted tool rest. Pedestal grinders must be securely fixed to the floor to prevent them
from walking when in operation.
Detail is described in 26076-110-GPP-GHX-00037 Welding and Cutting Procedure and 26076-110-
GPP-GHX-00038 Grinders Procedure.
20.17 Manual and Mechanical Handling
Refer to document no. 26076-110-GPP-GHX-00030 “Manual and Mechanical Handling Procedure”
Conduct manual duties referring to the related work procedures / work instructions and pay
attention to the HSSE Aspects determined during conducting HSSE aspect identification,
assessment, and control or job safety analysis.
When manually moving materials, personnel should seek help when:
The load is so bulky it cannot be properly grasped of lifted
They cannot see around or over it
Use mechanical devices/equipment when the loads are very heavy
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 81 / 154
During manual handling, personal should be wear required PPE (appropriate gloves, eye
protection, safety shoes and safety helmet), when use lumber must have protruding nails
removed before handling and prior to handling hazardous materials, make certain that a SDS is
reviewed and understood
Conduct mechanical duties referring to each equipment Operation Manual and pay attention to
the HSSE Aspects determined during conducting HSSE aspect identification, assessment, and
control or job safety analysis.
20.18 Permit to Work
CONTRACTOR will use Work Permit system for any activities consider as High Risk at green field
to comply with Regulation of Indonesian Government No. 50 / 2012 regarding Implementation of
Occupational Health and Safety Management System Law No. 1/1970, which mentioned to
establish Work Permit for High Risk activities. Also, Regulation of Indonesian Government No.
11/1979 regarding Work Safety at MIGAS Refinery, which mentioned any specific Hot Work
activities and conducted at hazardous area shall get written permission from “Kepala Teknik”
(Technical Manager).
At green field area, most of the routine and not high-risk activities will use general work permit
with area/discipline wise, however JSA will use activity wise and shall attached to the PTW.
The details of the CONTRACTOR Work Permit System for Green Field area will be described on
document 26076-110-GPP-GHX-00016 Permit To Work Procedure.
If required, during pre-commissioning and commissioning (including start up and performance
test) phases, permit to work system will be modified / adjusted to the work conditions (especially
associated with specific hazards when conducting pre-commissioning and/ or commissioning
activities).
CONTRACTOR activities carried out at brownfield area will follow the PERTAMINA SIKA procedure
No. A-005/E15500/2016-S9.
Any construction activity under the general or hazardous work procedure category, when
conducted under non-routine or other jeopardizing conditions, will be performed under PTW. All
project and SUBCONTRACTOR personnel will abide by the project PTW program and its affiliate
procedure. PTW-covered activities will not commence unless an accurately completed authorized
PTW is in effect. CONTRACTOR PTW system will be applied at Greenfield area. PERTAMINA’s PTW
system will be applied at existing (Brownfield) area.
The work permit system will incorporate checks and authorizations that are consistent with risk
or hazards involved.
The following points are contained in the permit system:
- The Permit to Work system contains pre-start checks to ensure that the work site is safe, that
necessary isolations are performed and verified, necessary bypasses are performed, and the
work does not present a hazard to other work in progress or planned. Those affected by the
work must be informed of the work and the possible affects upon their work, and appropriate
communication and coordination meetings are held and key decisions recorded.
- Work Permits are approved for a specific duration.
- Senior operations/construction management is responsible for ensuring an effective work
permit system and verifying that it is used correctly.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 82 / 154
- The type of work and work conditions that are managed with work permits are defined for
each site based on the risks involved.
- Each work permit has a description of the work to be performed and details specific
precautions to protect personnel, environment and equipment from potential hazards.
- Permit procedures require closeout checks to be performed at completion of the work to
ensure that: (a) the work was performed satisfactorily, (b) isolations and bypasses are
restored, (c) workplace and processes are returned to a safe condition, and (d) completion of
work is communicated to affected personnel.
- The authority to approve and closeout work permits is clearly designated and approved by
Head of Purification and Refinery. PTW shall be documented at each site.
- All personnel issuing or using work permits are trained in the application of the work permit
procedure.
- Work permit system and training effectiveness is audited periodically and results documented.
Work permits and records are retained to facilitate assessment.
- The JSA shall be provided in detail for each activity. The Supervisor will discuss the hazards of
the job with his/her employees while completing the JSA and determine all the appropriate
mitigations required to perform the job which will be implemented before the job is
authorized to start. Workers will use the JSA process at the commencement of each shift and
new work task.
All Construction work within live plant areas, or as dictated by OWNER, will be Subjected to
OWNER’s PTW Procedures. Ensure PTWs shall be prominently displayed at work area at all times.
20.19 Cameras (Security)
Detail of operational and deployment of CCTV camera is described on 26076-110-GPP-GHX-00025
Security Procedure.
To increase surveillance of important and high-risk area within CONTRACTOR’s premises,
CONTRACTOR has allocated CCTV cameras that operate 24 hours per day, live view, fully recorded,
and can be accessed by authorized users.
20.20 Hand and Power Tools
A portable hand and power tools shall be inspected prior to use. CONTRACTOR site
management shall ensure that all tools are maintained in a safe condition and used in a safe
manner by all personnel.
Defective tools must be removed from service until repaired or replaced.
Site Supervisor must ensure that workers understand how to use the tools correctly and care
about other workers.
Machine Guarding must be checked to ensure that it can be operated effectively.
Guards and safe protection of the devices must remain in place and in operable condition on
all tools. Wooden handles on tools must be free of cracks or other defects. Tape or other
coverings that will hide defects are not to be placed on these handles.
The colour code must be posted on the device to determine the condition of the equipment
(Good or Not Good).
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 83 / 154
Damaged or defects tools should not be used and removed from site. Re-inspection should be
done for these tools after repair.
Daily checks shall be done by tools user to ensure that tools is in good condition and safe.
Always use appropriate tools for every job. Do not use improvised or modified tools.
Non-spark, explosion proof or intrinsically safe tools are mandatory to be used at several
hazardous or flammable area.
Impact surfaces of tools including, but not limited to, hammers, wrenches, drift pins, chisels
must be kept free of mushroomed heads.
Refer to document no. 26076-110-GPP-GHX-00035“Tools Procedure”
SUBCONTRACTORs will provide and ensure that all tools are used in accordance with the
manufacturers’ recommendations, have required guards in place, and are maintained in good
working order.
All job made tools shall be Subject to inspection for approval by the CONTRACTOR HSSE Section
prior to use. A sticker after pass inspection should be implemented periodically. Generally,
handmade tools shall be prohibited on the project. All tools and equipment shall be used and
maintained in accordance with manufacturers’ recommendations. If exceptions to this rule are
needed (e.g. spreader beams), they will be brought to the OWNER attention for review and
acceptance prior to use.
20.21 Pneumatic Tools
Pneumatic tools include Chippers, Drills, Hammers, and Sanders. Pneumatic power tools shall be
secured by proper clamps and whip checks.
In addition to mandatory PPE, eye protection (goggles) or a face shield (with safety glasses or
goggles), and hearing protection are required for working with pneumatic tools.
Pneumatic tools may be used only by employees who are properly instructed and familiar with
these tools.
Employees must follow safe practices for operating pneumatic tools, including the following:
Before assembling the system, check all hoses for cuts, breaks, and loose connections.
Blow out all hoses before hooking up the equipment. If the connector has a rubber seal.
Remove it before (and replace it after) blowing.
When possible, run air lines through areas with little traffic. If possible, avoid laying lines
across roads. Protect air lines or hoses against trucks and pedestrians either by building
runways over the hose or suspending the hose overhead with the lowest part of the hose at
least 2.1336 meters above the ground.
Tighten hammer-joint connections with a hammer. Do not tighten them by hand. Hoses
equipped with special connections require special tightening techniques or equipment. One
example is hammer-union connections, which must be tightened with a hammer. Another
example is spanner-wrench connections, who must be tightened with a spanner wrench. Do
not tighten these connections by hand.
Do not turn on air valves until the hose connections are secure.
Do not point an open-air hose at anyone.
Compressed air shall not be used for cleaning purposes except where reduced to less than 30
psi, and then only with effective chip guarding and proper personal protective equipment.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 84 / 154
Unless the equipment has quick change connectors (with internal check valves), shut off the air at
the air supply valve ahead of the hose before breaking the connection.
20.22 Compressed Gas Cylinder
Refer to document no. 26076-110-GPP-GHX-00039 “Gas Cylinder Procedure”
The use of compressed gas will follow Manpower Ministry standard (Regulation of Manpower
Ministry No. 37 Year 2016 regarding Pressure Vessel and Storage Tank) in terms of: how to
storage, how to handle, how to transport and use. Compressed gases are stored using the rack
and fastened using chain.
CONTRACTOR must ensure that all gas cylinders are to be labelled to indicate the contents of
the cylinder.
Flammable and oxygen cylinders shall be fitted with flashback arrestor (adjacent to the
regulator) and reverse flow check valve (at the torch).
CONTRACTOR shall develop an inspection schedule of the gas cylinder.
All compressed cylinders must be kept clear of oil, grease or other hydrocarbons.
Cylinders must be inspected for leaks and/or defects prior to use.
Cylinders must not be exposed to sparks, slag, flame or other heat sources.
Cylinders must be secured in an upright position during use and storage. They must be secured
by the use of Chain, (never use barricade tape or rope).
Protective caps must be in place over valve stems when cylinders are in storage or when not
in use.
Cylinders must not be taken into confined spaces.
When cylinders are not in use, oxygen and fuel gas cylinders must be stored separately.
Storage area for cylinders must be designated with signs stating” Oxygen Full or Empty,”
Acetylene Full or Empty,” etc.
The detail procedure related with welding and cutting activities using compressed gas cylinder
describe in Document No. 26076-110-GPP-GHX-00037 Welding and Cutting Procedure.
SUBCONTRACTORs will provide cradles and/or cages for lifting compressed gas cylinders and
ensure that cylinders being transported are secured and in the upright position.
SUBCONTRACTORs will ensure that cylinders are provided with protective systems to prevent
damage to valves. This may include caps or protective collars.
Safety device such as a suitable flashback arrestor or any suitable device which prevent flame
flashback should be fitted at the pressure regulatory outlet of each gas cylinder.
A suitable check valve, non-return valve or any similar device which prevents the backflow of gas
into the hose should be fitted between each gas torch inlet and gas hose.
20.23 Electrical Works
Refer to document no. 26076-110-GPP-GHX-00023 “Electrical Work Procedure” and 26076-110-
GPP-GHX-00010 HSSE Inspection Procedure.
The CONTRACTOR will implement, and SUBCONTRACTORs will fully comply with, the Government
Electrical Equipment Inspection requirements, which include quarterly color code changes and
shall use Earth Leakage Protection Devices (ELPD) or Ground Fault Circuit Interrupters (GFCI) on
all temporary electrical applications.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 85 / 154
CONTRACTOR shall ensure grounding system are provided to protect personnel and installation
against ground fault current, lightning and static discharge.
Grounding system shall be installed and tested as per the standards.
Only competence/certified person shall carry out electrical testing activities.
PPE shall be used during working with electricity.
The CONTRACTOR or SUBCONTRACTOR will employ an Electrical Safety Supervisor (Usually
supported by Electrical Construction Section) to undertake and supervise SUBCONTRACTORs’
electrical inspections. The CONTRACTOR and SUBCONTRACTORs will maintain records of all
construction tools / equipment inspections. Colour Coding System need to be implemented for
electrical & power tools, equipment and also lifting gear as per inspection period.
The CONTRACTOR will ensure all tools are checked for electrical continuity after repairs are made.
The CONTRACTOR and SUBCONTRACTORs will ensure that personnel are isolated from electrical
distribution centers. This may include fencing and locking of transformers.
SUBCONTRACTORs will provide details in method statements prior to commencing Underground
and Overhead Electrical Installations.
CONTRACTOR will ensure that all electrical tools such as portable tools, hand tools, and other
portable electrical apparatus, meet standard safety requirement.
Temporary electrical installation including distribution boards, cabling, and switch gear shall
comply with the current wiring regulations. Hand lights carried into vessels shall not exceed 12
volts, unless protection is provided by a Ground Fault Circuit Interrupter (GFCI).
All required tests will be performed prior to first use and/or prior to the equipment is returned to
service following any repairs.
Colour code standard will refer to CONTRACTOR standard in monthly basis. Loose lifting
equipment shall be colour coded to indicate compliance with periodic inspection and / or re-
certification. The colour code will be affixed or painted onto the lifting gear.
The following four colours, blue, orange, green and yellow will be used in rotation.
Equipment
20.24 Hot Work
Refer to document no. 26076-110-GPP-GHX-00027 “Hot Work Procedure”
Hot work refers to any task uses (or could create) a flame, spark or other energy discharge that
might in turn ignite a fire or explosion. It is normal practice to consider two types of hot work:
High energy (open flame), Lower energy (spark potential)
Hot work shall be Subject to a JSA at the planning stage and task-specific controls implemented to
ensure that:
o all combustible materials within 15,24 meters have been removed, isolated, and/or protected
from the source(s) of ignition
o where relevant, control measures are in place to keep oxygen levels and flammable vapour
within acceptable limits
o in hazardous areas, the atmosphere affected by the hot work is regularly tested by a competent
person as often as the Risk assessment requires
o Suitable fire-fighting equipment is readily available and accessible at the hot work site.
A fire watcher must be present to monitor the work area while fire and gas system are inhibited
for naked flame hot work, e.g., welding and burning. The fire watcher is responsible for ensuring
that:
o He is in possession of a radio for immediate emergency communication, or he is aware of the
location of the nearest radio point for communicating with the facility control point.
o Fire fighting equipment is available and ready for immediate use
o He is trained and able to demonstrate his competence in handling relevant fire fighting
equipment
o Flammable materials are cleared away from the work site
o Drains remain covered and sealed
o Sparks and welding spatter are contained (by the use of fire blankets, water sprays etc.)
o The alarm is raised where a fire of gas release occurs in the area
o Upon completion of the task, all relevant fire fighting equipment is returned to its appropriate
storage location.
20.25 Hazardous Material
CONTRACTOR will ensure that all Substances classified as hazardous to health, which are
transported, used or created during activities, are controlled to minimize the risk to the health
and to the environment.
o The list of Chemical and Hazardous Materials to be used shall be available including Safety Data
Sheet (SDS).
o Required PPE as mention in SDS shall be used during handling with the chemicals.
o Required equipment and tools as mention in SDS to control any accidental release of hazardous
chemicals shall be provided.
o Before beginning a task where a hazardous Substance is to be used, the risks, the precautionary
measures to be taken and the actions to be taken in the event of a spillage (if applicable) or
injury will be explained during the Pre-Job Safety Meeting (PJSM).
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 87 / 154
o It is recommended to use less harmful Substances to minimize the risk to health and to the
environment.
o Only trained personnel should handle hazardous materials using the precautionary measure
that have to be taken, as instructed in the SDS.
o Used containers of hazardous Substances/chemical will be disposed of as hazardous waste.
o Hazardous chemicals will be disposed as per the instructions available in the SDS. Never litter,
or scatter used/empty chemical containers or used it for other storage purpose or handling as
it may be harmful to life and environment.
o CONTRACTOR must provide adequate eye-wash, shower and first aid boxes with medicines at
locations were hazardous chemicals are stored and handled, if deemed necessary. Also, to
ensure that it is well maintained and inspected regularly for defects or malfunctioning.
o Employees are to be given information with regards to working with hazardous Substances and
use and maintenance of applicable PPE. At minimum this shall be given as part of the
individuals Induction Training.
Storage of Hazardous Substances/Chemical shall consider following requirements:
o All chemicals containers must be labelled.
o CONTRACTORs shall ensure that adequate storage cabinets/ store rooms are available for the
proper segregation and storage of different types of hazardous Substances/ chemicals.
o Incompatible chemicals shall be stored separately.
o Hazardous Substance storage areas are to be identified with the correct signage, indicating
contents of the storage area and ‘No Smoking’ signs.
o Spill kits shall be provided where hazardous Substances are being stored or used.
o Hazardous Substance storage areas will be well ventilated and kept in hygienic manner at time.
Appropriate portable fire extinguishers and safety shower shall be provided at the storage
facilities and employees will be trained to use them effectively during an incident with hazardous
Substances/chemical.
No hazardous Substances or materials shall be brought and used on the site before a suitable
COSHH assessment has been carried out by a suitably trained person. In addition to the
assessment, approval to use the hazardous Substances on site shall be sought from CONTRACTOR.
The hazards of the Substance shall be described and shall be obtained from the SDS. In
circumstances where the work involves exposure to more than one Substance hazardous to
health, the risk presented by exposure to each Substance in combination shall be assessed.
Control measures to be implemented shall be based on the principal of hierarchy of controls
where elimination is the most preferential method of prevention and personal protective
equipment shall be used as a last resort for control. Exposure shall be controlled to below the
relevant exposure limits. All control measures shall be maintained in an efficient state, in efficient
working order, in good repair and in a clean condition.
20.26 Hydrogen Sulfide (H2S)
CONTRACTOR shall provide H2S Gas Detector to monitor the presence of H2S.
Where H2S exists in concentrations greater than 10 ppm, employee protection shall be
ensured through following control:
- Engineering controls (ventilation, automatic tank gauging, etc.).
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 88 / 154
This will include all areas of the construction site and temporary facilities. CONTRACTOR will
include plans to ensure that fire protection equipment is placed and maintained in proper
location as work progress.
Prevention of fire is a goal. Identification of potential fire hazards and prevention and
protection will be an important factor in the job HSSE analysis performs for each specific
activity.
Fire prevention and fighting training will emphasize planning work in such a way that
potential fire hazards are removed or reduced to the greatest extent possible. Particular
emphasis will be on hot work permits, control of flammable gas, liquids and other material,
proper electrical wiring, and proper removal and storage of waste materials.
Refueling of mobile equipment and vehicles whilst running is prohibited.
The use of gasoline powered equipment such as dewatering pumps, concrete vibrators,
temporary lights is restricted and Subject to CONTRACTOR/OWNER approval prior to use.
Where temporary welding enclosures are required to prevent sparks flying or falling,
CONTRACTOR and SUBCONTRACTORs/vendors will ensure that these enclosures are
constructed with flame resistant materials (such as fire blanket)
CONTRACTOR will establish a smoking Policy for the Project as OWNER requirements. This
shall restrict smoking to designated areas.
Office areas shall be monitored to reduce and control storage of combustible materials.
CONTRACTOR and SUBCONTRACTOR’s/vendors personnel whose work tasks are in the
vicinity of fire cabinets and equipment, fire hydrants, and fire lanes shall keep them clear
and unobstructed.
CONTRACTOR and SUBCONTRACTORs/vendors will ensure that all combustible waste
containers are emptied regularly, equipment, tables, and floors are free from oil or oily rags
and oily rag containers are kept covered and emptied regularly. Janitor/storage closet shall
be maintained in an orderly condition and shall not be used to store quantities of hazardous
or toxic chemicals. Electrical, mechanical, and telegraphic rooms shall be kept in order and
free of combustible storage materials. Cable tray and raceways shall be free of combustible
material, debris, or trash.
2) Equipment
CONTRACTOR and SUBCONTRACTORs/vendors will ensure the provision of all fire protection
and prevention equipment necessary for their operations.
Each SUBCONTRACTOR/vendor will provide an adequate number of fire extinguishers of the
correct size and type for its work activities. Extinguishers shall be maintained per
manufactures recommendations, inspected monthly, and tasted annually.
Employees will be trained in the proper use of fire extinguisher.
The frames of arc-welding and cutting machines that incorporate a power outlet will be
adequately grounding.
20.28.1 Flammable Combustible Liquid Storage & Handling
Following are the requirements for flammable combustible liquid storage:
Since vaporization (the formation of vapor) increases when the temperature is raised or
when these liquids are more exposed to the air it is essential that they are stored in a
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 90 / 154
relatively cool place and in closed tanks, drums or cans. Open containers should never be
used for storing flammable and combustible liquids.
Storage in the open - in field conditions drums should be placed so that they are not
exposed to the direct rays of the sun, or any other source of heat.
The storage area should have a warning sign clearly displayed indicating that flammable and
combustible liquids are stored there and that no smoking or naked lights are permitted.
A shallow trench or dike should be constructed around the storage area to prevent any
spillage or vapor spreading to lower ground areas where they might contact a source of
ignition and cause a flashback fire.
The storage area must be at least 15,24 meters from any ignition source (e.g. open fire,
workshop area where grinding tools, or flame cutting equipment is used).
Storage indoors - ideally, storage of flammable and combustible liquids should be in a
separate isolated building. If this is not possible, they should be stored in a special room
with fire resistant walls, doors, ceilings and floors.
The storage indoor should be protected with an automatic fire-protection system
(sprinklers, foam, and carbon dioxide). The room should be well ventilated, be equipped
with explosion proof lighting and electrical fixtures and have a warning sign at the entrance
indicating that no smoking or naked lights are permitted.
Any storage area, whether in the open or indoors, should have a portable fire extinguisher
(approved for Class B fires) available outside the entrance. This extinguisher may be of the
foam type, carbon dioxide type, dry chemical type of liquefied gas (halon) type. Personnel
must be trained in the use of the extinguisher.
During flammable liquids are transferred from one container to another, there is a possibility
of static electricity build-up which is a dangerous ignition source. To prevent build-up of static
electricity, following requirements are required during handling of flammable liquids:
Flammable liquids storage shall be provided with grounding (earthing) and bonding facility.
This is to minimize potency of build-up static electricity during transfer of flammable liquids.
Grounding facility for storage must be periodically tested to ensure it is still working
properly.
Safety glasses, protective gloves and long sleeves uniform should be worn if there is any
chance of skin contact. Liquids should be washed from the skin with non-abrasive soap or
hand cleaner. It is recommended to provide safety shower facilities and/or proper water
supply near to storage area.
The liquids should be used only in well ventilated areas to avoid breathing vapours and
fumes. If ventilation is not possible (e.g. in confined spaces) an approved respirator must
be worn.
If any personnel are splashed with a harmful or burning liquid, they must be taken to a source
of running water immediately and the splashed area should be flushed with water for at least
15 minutes. Contaminated clothing should be removed and medical attention sought
immediately.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 91 / 154
Mobile phone will be returned back to the owner of mobile phone once he/she left the
brownfield area. To ensure the phone owner could get his/her phone back, he/she must
leave the brownfield through the same security gate when he/she entering the brownfield
area.
It is recommended to provide effective identification method for each of mobile phone kept
by security. E.g. using ID number for mobile phone, registration in log book, etc.
20.28.4 Fire Extinguisher and Fire Watcher
Journey Management Plan consist of all work necessary to provide turn the safe transportation
on the hazof personnel and materials between workshop and site, material and/or
lamp)"equipment transportation between harbor and site, including material and/or equipment
loading and offloading, movement of vehicle and protection of person and property at harbor as
well as construction sites.
20.30 Blasting and Painting
Refer to document no. 26076-110-GPP-GHX-00029 “Abrasive Air Blasting Cleaning and Painting”
Abrasive air blasting means propelling a stream of abrasive material at high speed against a
surface using compressed air to clean, abrade, etc. or otherwise change the original appearance
or condition of the surface.
Abrasive blasting operations can generate a variety of hazards to those directly involved, persons
in the vicinity and to the environment. Common hazards include dusts, hazardous chemicals and
risks associated with the use of plant and equipment.
Persons performing blasting works shall wear air supplied blasting helmets, blasting suits (heavy
canvas or leather), overall with hoods, gauntlet type leather gloves, safety boots, goggles, leather
aprons and hearing protection devices. Blasting helmets shall be positive air pressure type and
shall be rigged and used in accordance to the manufacturer’s recommendations.
The Supervisor will ensure the blast cleaning nozzle is equipped with an operating valve which
must be held open manually.
The Supervisor will ensure the abrasive blasting equipment and the object being blast cleaned is
grounded to eliminate static electricity.
The Supervisor will ensure appropriate respiratory protection is worn during the blasting
operation.
The Supervisor shall ensure the thickness of sand pot in good condition and inspect periodically.
No silica-based material will be allowed on site as storage or for use.
Containment will be maintained at all times including during use, for 100% cleaning and removal.
In this context, painting refers to spray painting. Spray painting is a process by which a liquid
coating of paint is converted into a mist of aerosol and applied onto an object or surface. The
Subsequent identify the minimum controls that need to be implemented to mitigate the hazards
inherent to spray painting operations which include:
Exposure to hazardous Substances contained in the paint
Fire and explosion
Noise and
Manual handling
Persons performing spray painting operations shall be provided and are required to wear airline
respirators of the right type or half face particulate respirators, safety glasses for eye protection,
hearing protectors, hand gloves, overalls and loose fitting hoods. Painters shall be trained on the
correct use, fitting and maintenance of PPE.
20.31 Marine Safety
Working in an offshore facility is known as one of the high-risk jobs. Potential hazards include
when traveling from / to facilities (helicopter crashes, vessel collisions, fires, natural conditions,
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 94 / 154
etc.) and when working at facilities (gas escapes / explosions, mechanical / structural failures,
natural conditions, etc.). The offshore activities covering survey activities, pipe laying, installation
of SPM / PLEM, piling, landfall, accommodation, transport, training requirements etc. There are
three hazards in the sea (offshore) that can threaten human lives, namely:
Drowning
Exposure to natural elements
Exposed back to the initial hazard
Any boat or small craft used to convey a person to and from a place of work must provide for his
safe transport and be suitably constructed, properly maintained and in the charge of a competent
person. Sea survival training for offshore workers are mandatory. Competent persons properly
qualified and experienced in their respective duties for safe and reliable BARGE operation shall
man the BARGE. The minimum qualification and experience standards for all crew members shall
be those set by the Marine Department of the BARGE’S flag state.
If there is any risk of persons falling into water and drowning, suitable steps should be taken to
prevent falling, and to ensure that suitable rescue equipment is provided
Where there is a risk of falling from an edge of adjacent land, a structure, scaffolding or a floating
stage, etc. guardrails or fencing must be provided. These can be removed temporarily for the
movement of materials but must be replaced promptly Safety nets can be used where it is not
possible to provide a proper scaffold or gangway with handrails and toe boards, provided that
everything practicable has been done in respect of providing a suitable platform
Full body safety harnesses with double lanyards can be used instead of nets provided that secure
anchorage points exist and the harness is constantly worn and attached.
Irrespective of the type of platforms or safety nets a full-body safety harness with double lanyards
must always be worn while working over, or adjacent to, water.
Although every effort should be made to prevent people falling into water, the risk of this
happening remains. In the event of a casualty, two things are of paramount importance:
The person must be kept afloat
Location and rescue must be achieved as quickly as possible
Regular practice drills so that the best method of rescuing, securing and landing a potential
casualty is known in advance.
All personnel working over or near water must wear some form of lifejacket or buoyancy aid. Both
are designed to keep the wearer afloat, there are, however, some important differences.
Buoyancy Aids are intended to provide a conscious person with enough extra buoyancy to stay
afloat. Lifejackets are designed to support an unconscious person face upwards, either by built-in
buoyancy or when fully inflated. Inflation may be by mouth or CO2 cartridge, activated manually
or automatically.
Where safety harnesses are worn in addition to floatation equipment, it is important to ensure
that each of these items functions effectively and will not interfere with the other.
Lifebuoys must be available wherever people are working on, over, or near water Standard 760
mm diameter lifebuoys with rope or cord lifelines (usually 30 meter) attached should be placed in
conspicuous positions near the water’s edge.
All diving operations shall follow PERTAMINA RU-V Permit as stipulated in TKO Under Water
Permit.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 95 / 154
The minimum requirement for the diver is shall have certificate of SCUBA Diver or Open Water
Diver which issued by LEMIGAS / IMCA / ADCI.
The minimum requirement for the standby diver is shall have certificate of Rescue Diver which
issued by LEMIGAS/IMCA/ADCI.
All employees who are assigned as divers or may be exposed to hyperbaric conditions shall have
successfully completed a physical examination and valid medical record by a licensed physician
prior to any diving or exposures.
20.32 SIMOPS
SIMOPS is define as execution of 2 or more operations with potential interaction that could lead
to an increase of risk or introduction of new hazards to each other’s.
SIMOPS procedure and SIMOPS matrix should be established as a guideline to identify and manage
simultaneous activities. Construction will provide the SIMOPS procedure and SIMOPS matrix with
the participation of HSSE and other required discipline.
Where there are major interfaces between CONTRACTOR, SUBCONTRACTORs and Operations,
these shall be managed by the Construction Management representative to ensure agreement
and clarity on SIMOPS.
CONTRACTOR need to arrange following but not limited to this meeting:
30 day and 90 day look ahead meeting.
Daily plan of the day meeting: attended by discipline Superintendents/Supervisor, HSSE,
Permit Coordinator and Project control teams.
Meeting to coordinate and prioritize simultaneous activities.
20.33 Site Office, Stores, Workshops, Living Accommodation and Canteen Facilities
CONTRACTOR must ensure that site office, stores, workshop, accommodation block and canteens
are designed in manner which prevents injury, damage or loss.
All such facilities shall contain adequate number of suitable fire extinguisher. CONTRACTORs
must conduct periodical inspection to ensure fire extinguisher and others emergency
equipment maintained in good condition.
Each facility shall have evacuation procedure posted at regular interval throughout. Shall
ensure that the facility evacuation procedures remain in clear view to all.
All facility occupants shall be made aware of the evacuation procedures and the relevant
assembly/muster points for that facility.
Lightning protection shall be provided to all such facilities. The electrical installation of such
facilities shall be approved standard and comply with the CONTRACTOR’s policy on electrical
installation.
All emergency exits, shall be clearly marked by an A4 sized poster/notice. All emergency exits
shall remain free from obstruction at all time. Any obstruction found shall be removed
immediately.
At no time will rubbish, refuse and combustible materials be permitted to accumulate within
any facility. All rubbish, refuse and combustible shall be removed from yard to a designated
tipping area. Open burning of rubbish, refuse and combustible material generated by such
facilities will not be permitted at any location within project boundary.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 96 / 154
CONTRACTOR shall provide adequate number of rubbishes, refuse and combustible materials
bins.
CONTRACTOR shall provide all the facilities with adequate ventilation and lighting to prevent
injury or damage.
All facilities must be kept clean and tidy at all time. Any spillage shall be cleaned immediately.
CONTRACTOR will provide Prayer room located at field and office area. Design and number of
Prayer room will be decided based on need at site. The Prayer room will be provided with
sufficient water for ablution tap and toilet. Cleanliness, hygiene and tap condition must be
maintained in good condition.
CONTRACTOR must provide safe and adequate transport to pick up people from living
accommodation to the working area and vice versa.
CONTRACTOR shall provide proper and adequate number of toilet and sanitation system.
CONTRACTOR shall ensure the cleanliness and waste management in accordance with the
national regulation.
20.33.1 Workshop Facilities
Prior to any site workshop becoming operational, risk assessment shall be completed and all
related personnel shall have addressed the following items:
All equipment used shall be maintained in a safe working condition.
Any cranes or lifting devices used have been certified by a recognized authority and shall
clearly state their Safe Working Load.
The lifting of heavy plant and equipment, by the use of the hydraulically operated plant, i.e.
Excavators or pay loaders, shall be prohibited.
Adequate and suitable fire extinguishers shall be provided throughout, with additional
extinguishers being provided around hot work areas such as welding/burning areas.
Adequate screens shall be placed around hot work areas to prevent eye flash.
All personnel working within the workshops are mandatory to follow PPE requirements.
All generators shall be properly earthed.
All electric within the site workshop shall be fused correctly.
Guards shall be fitted stored in upright drums. The drums shall be stored in an orderly
manner and shall be clearly marked to show their contents. Additional fire extinguisher shall
be located adjacent to lubricant storage areas.
Used lubricants and oils shall be disposed of at an approved temporary waste storage area.
All spillage shall be cleaned up immediately.
All used batteries, containing acids, shall be stored in an upright position and shall be
removed to temporary waste storage as soon as possible.
The workshop facility shall be maintained in safe working condition at all times
20.33.2 Living Accommodation
CONTRACTOR shall ensure that all accommodation blocks shall be provided with an adequate
number of suitable fire extinguishers and that adequate lighting and ventilation is provided.
Fire Exits shall be indicated as mentioned above.
Evacuation procedures shall be advised to all personnel living/sleeping within the blocks.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 97 / 154
Such accommodation blocks shall be erected as far away from the permanent works as
possible.
CONTRACTOR must provide safe and adequate transport to pick up people from living
accommodation to the working area and vice versa.
20.33.3 Ablution Facilities
CONTRACTOR will ensure that all site ablution facilities are designed, constricted and operated
in accordance with all statutory regulations. All such facilities shall be maintained in a clean
condition, at all times. Any defects found within the system shall be rectified immediately
The user of each site ablution facilities shall discharge into a suitable designed septic tank and
soak way arrangement. All septic tank shall be designed to meet demands from all site
conditions. If at any time, septic tanks are found to be full or overflowing they shall be pumped
into a suitable tanker, immediately. The resultant effluent shall be disposed of at an approved
facility.
20.33.4 Canteen Facilities
CONTRACTOR must ensure that canteen facilities shall be maintained in a sanitary and safe
working condition at all time.
All Pressure Gas Cylinder (LPG) containers shall be stored outside the buildings, except when
in use.
Fly mesh shall be used at all window locations in an attempt to keep insects away from the
food preparation areas and the displayed food.
Food preparation areas shall be cleaned before and after each mealtime.
21.2 Competency
CONTRACTOR develop HSSE Training Matrix based on required HSSE competencies for each Job
Task at project site. Refer to Attachment 2. HSSE Training Matrix for the detail.
To increase personnel awareness on working safely, Construction Manager with HSSE Manager
are responsible to ensure that all personnel have completed all training required as per Training
Matrix.
Special skills/competency required for a specific job shall be certified by government (Migas /
Depnaker). E.g. Scaffolding, Crane Operator, Rigger, etc. In House (at site) training deliver by
CONTRACTOR in accordance with this special skills/competency only for refreshment purpose.
21.3 Training Record and Tracking Method
Following are Training record which shall be documented and made available for auditing
purpose:
Training attendance record.
Database of employees training record. Include a record to verify all personnel who have
successfully completed the training.
Training assessment.
Approved Training material.
Training Sticker will be given to the participant who pass the assessment and this sticker must be
attached to their helmets. Database of employees training record shall be maintained and used
to track employee’s compliance to follow the required training.
21.4 Training Provider
Since CONTRACTOR will have activities at brownfield area, Owner will conduct in house training
for transfer knowledge of HSSE system and requirements to CONTRACTOR.
CONTRACTOR have responsibilities to deliver required HSSE Training at project site.
21.5 Training Key Performance Indicator (KPI)
CONTRACTOR’s Weekly Report contain Key Performance Indicator (KPI) related to training.
Progress against these KPI’s will be reported by weekly to IPMT (PMC and Pertamina RDMP RU V).
21.6 CONTRACTOR Internal Trainer
CONTRACTOR shall provide qualified trainers.
All CONTRACTOR’s HSSE Trainer must Certified as Training of Trainer (TOT).
CONTRACTOR will hire certified person to be assigned as HSSE Trainer for the special
skills/competencies required training. i.e. Rigger, Crane Operator, Scaffolder refreshment
training.
CONTRACTORs will provide HSSE Training centre to facilitate in house (at site) HSSE Training. This
training centre will be located at CONTRACTOR’s temporary office and have capacity for 50
participants/trainee.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 99 / 154
22.0 COMMUNICATION
Refer to document no. 26076-110-GPP-GHX-00005 “HSSE Communications Procedure”
22.1 Languages
It is CONTRACTOR policy that the major HSSE-related project publications, bulletins and general
communication notices will be printed in both English and the language of the base country. In
addition, for verbal communication purposes, an adequate number of bilingual (English and
Bahasa Indonesia) staff will be employed in the work area to facilitate communication between
the work force, CONTRACTOR, SUBCONTRACTORs/vendors and OWNER.
All HSSE Training and education for the local workforce, including training material and booklets,
will be languages understood by the workers. All multi-national meetings will be facilitated by an
interpreter(s) and the record of minutes will be produced in bilingual (English-Bahasa Indonesia)
format as necessary.
CONTRACTOR will produce a multilingual HSSE handbook for participants who successfully
complete the project HSSE orientation course.
22.2 Communication Mediums
CONTRACTOR recognizes that HSSE objectives can be achieved with effective communication.
CONTRACTOR will utilize numerous mediums to educate, raise HSSE awareness, motivate and
stimulate participation. There may include all or some of the following:
HSSE Training
Bulletins and posters
Sign boards and banners
HSSE handbook
HSSE committees
HSSE awareness campaign
Toolbox meeting/STARRT
Submission of reports
Others
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 101 / 154
22.3 Meetings
a) CONTRACTOR-business partners kick off meeting
Kick off meeting of CONTRACTOR and business partners (OWNER / SUBCONTRACTORs /
priority vendors) is intended to ensure that business partners clearly understand the Project
HSSE requirements. It shall be conducted prior to start work, lead by relevant leads and
attended by related Sub-organization representatives
b) JSA Meeting
JSA meeting is a meeting for each construction job such as: heavy lift rigging, steel erection,
high elevation work, confined space work, hot work and any other works that need work
permit. This meeting shall be conducted by each group of SUBCONTRACTOR, lead by their
group leaders and attended by their group members to discuss HSSE aspect of the job. Job
sequences, accident prevention plan and safe work methods shall discuss in this meeting.
Each JSA group should not be more than 20 members in order to make effective two ways
communication and should not be more than 20 minutes. JSA records shall be prepared,
effectively used during the meeting, and field accordingly. Attendants’ list/equivalent shall
be maintained.
In accordance with Risk Assessment process, the high risk job may require the JSA meeting
as OWNER’s request.
c) Daily Group Toolbox Meeting
Daily Group TBM is a meeting for each SUBCONTRACTOR discussing hot issue specific to the
SUBCONTRACTOR or planned Subjects. This TBM shall be conducted by each
SUBCONTRACTOR, lead by their Site Manager/Equivalent and attended by all of their
members before starting their work on the day. Speakers of the TBM should be scheduled in
turn representing all disciplines and TBM reports & attendants’ list/equivalent shall be
maintained.
d) Weekly General Toolbox Meeting (General TBM)
Weekly General TBM is a meeting for all CONTRACTORs, SUBCONTRACTORs and other related
site parties members discussing hot issue specific to the project or planned Subjects. This
TBM shall be conducted by CONTRACTOR, lead by CONTRACTOR Site Manager/Equivalent
and attended by all site members on a scheduled day. Speakers of the TBM should be
scheduled by the Construction Manager (assisted by CONTRACTOR HSSE Manager) in turn
representing all disciplines (of CONTRACTORs, SUBCONTRACTORs, related parties) and TBM
reports & attendants list / equivalent shall be maintained by CONTRACTOR HSSE Manager.
The end of Week in every Month will become The General Monthly Toolbox Meetings with
OWNER’s involvement and the opportunity to held HSSE awards.
e) Weekly HSSE Coordination Meeting
Weekly HSSE coordination meeting is a meeting for all HSSE representatives of CONTRACTOR,
SUBCONTRACTORs and related parties discussing gaps between HSSE Lagging & Leading KPI
versus project requirements and its implementation. This meeting shall be conducted by
CONTRACTOR, lead by HSSE Manager/Equivalent and attended by CONTRACTOR and
SUBCONTRACTOR HSSE & Management representatives refer on a scheduled day. MOM and
attendants list of the meeting shall be maintained by CONTRACTOR HSSE Manager.
f) Monthly HSSE Coordination Meeting
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 102 / 154
All Project HSSE records shall be archived in accordance with OWNER’s Safety and Health
procedures. The CONTRACTOR HSSE Manager shall insure that records to be maintained
throughout project life, training records, inspection reports, testing records, etc.
3 min
1 Incident occurred 3 minutes wavy siren
Safe / normal
3 1 minute Continuous siren
condition
In the event of medical evacuation, the IP (Injured Person) will be taken to PERTAMINA
hospital in Balikpapan for minor injury assessment and treatment.
CONTRACTOR will provide the Ambulance and standby fulltime at site for emergency
cases.
CONTRACTOR will employ paramedics for site project. Paramedics will be assigned to
assist the CONTRACTOR’s site doctor. The paramedic will not be allowed to perform
any medical treatment without acknowledgement from the CONTRACTOR’s doctor.
Paramedic will be employed until final demobilization of all CONTRACTOR personnel.
The Paramedic will be assessed by CONTRACTOR’s Site Doctor or Medical Advisor.
24.5 Equipment
Emergency equipment will be inspected at regular frequencies as determined by the inspection
program. Records of inspections will be retained by CONTRACTOR HSSE Section. All marine and
heavy equipment certification are required as per MIGAS standard.
24.6 Muster Point and Assembly Point
When an emergency evacuation siren is activated, all employees gather to the nearest assembly
point. Assembly point as the first destination that is considered safe and becomes the pick-up
point for workers before heading to the muster point if needed.
Assembly points will be set at each point of work, if there are several work points in an area, it will
be agreed and marked as a flag with the initial’s "A" indicating the assembly point. Workers and
guests will be directed to the nearest muster point.
There is one muster point when an emergency occurs in the Lawe-Lawe area that is Gate 3.
CONTRACTOR shall provide and socialize to all employee the location of Assembly Point, Muster
Point and Wind sock. These location (map) shall be informed at HSSE Notice board located at site
and office area. For HSSE Notice Board reference to standard drawing No.: xxxx.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 106 / 154
25.0 SECURITY
Refer to document no. 26076-110-GPP-GHX-00025 “Site Security Procedure”
25.1 Security Control Areas
- Security control within SUBCONTRACTORs assigned areas and temporary lay-down facilities
etc. shall be the sole responsibility of each SUBCONTRACTOR.
- Security personnel engaged outside the OWNER Plant by the CONTRACTOR will only be
responsible for site office guardhouse/gate control and security in areas not assigned to
individual SUBCONTRACTORs. However, the CONTRACTOR security reserves the right to
enter/check construction CONTRACTOR’s assigned areas at any time, particularly during
routine site security patrols.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 107 / 154
26.0 ENVIRONMENT
Environmental Management refer to 26071-100-G01-GHX-000014 Environmental Control
Procedure.
CONTRACTOR shall provide Environmental Monitoring programs and measurements in
accordance with Environmental Impact Analysis (EIA (AMDAL)) of RDMP RU V Balikpapan Project
(RKL-RPL).
All project activities of CONTRACTOR in RDMP RU V Balikpapan has been included in construction
phase Environmental Impact Analysis (EIA) of OWNER. The potential impacts on the environment
of the CONTRACTOR activities on this project shall be assessed and stipulated with OWNER’S and
Government regulations particularly environmental regulations.
CONTRACTOR shall provide Policy, Procedure, and other document in line with OWNER’S
environmental management plan and EIA of Owner in construction phase.
The following environmental plan will be developed and implemented during the project by
CONTRACTOR:
o Comply with all applicable environmental laws, regulations, rules, and codes governing
environmental requirements.
o Provide all documentation required by all levels of governing authority concerning
environmental requirements.
Provide and maintain effective planning and field control measures for the following activities:
o Wastewater discharges to land, surface water, or groundwater,
o Spill prevention and response
o Erosion and sedimentation control
o Dust Control
o Noise control
o Waste & hazardous waste management
o Comply with EIA (AMDAL), Environmental Management Plan (RKL) & Environmental
Monitoring Plan (RPL).
26.1 General Environmental Requirement
The project shall be constructed and commissioned in accordance with the following:
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 109 / 154
- Sewage system shall be designed adequate to handle the sanitary waste of all project
personnel, with treatment facility according to the regulations.
- Regular inspection shall be conducted to ensure that waste management has been
done appropriately and not to cause any damage nor hazards to environment in the
area including it downstream up to the reasonable extent.
26.2.4 Hazardous Waste Management
Hazardous waste generated on site which meet the hazardous waste criteria are as follow:
o Flammable
o Combustible
o Reactive
o Toxic
o Infectious
o Corrosive
o Poisonous
CONTRACTOR shall ensure following requirements are implemented to manage waste of
hazardous chemical:
o Symbol and label shall be affixed on the hazardous chemical waste containers.
o The condition of the hazardous waste container/drum shall be inspected on a daily
basis.
o Containers intended for hazardous waste disposal should not be used for other
purpose.
o The waste should be kept at a proper temporary hazardous waste storage not more
than 90 days.
o The hazardous waste temporary storage should be provided with license/permit from
authorized body.
o CONTRACTOR will provide third-party (who have license) to handle medical/clinic
waste.
o Transfer of all hazardous wastes to a third-party should be accompanied by
manifest/document hazardous waste. Copies of document hazardous waste should be
maintained.
o Hazardous waste temporary storage shall comply with applied regulation and shall be
equipped with Fire extinguisher, PPE and spill kit equipment.
o CONTRACTOR shall provide Safety Data Sheet (SDS) for all waste of hazardous
chemicals.
o CONTRACTOR will conduct basic waste management training periodically; this training
must be followed by personal who involved with waste of hazardous chemicals.
o Waste such as empty containers or drums with residue of flammable liquid should be
stacked in isolated area away from building and installation. Have notice displayed
forbidding smoking or naked lights. These containers should be thoroughly steam-
cleaned or washed before use.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 111 / 154
26.2.5 AMDAL
- Environmental Impact Analysis (in Indonesia, known as AMDAL) is a study of the major
and significant impacts of a business and / or planned activity on the environment
required for the decision-making process regarding conducting business and / or
activities in Indonesia.
- CONTRACTOR shall provide Environmental Monitoring programs and measurements
in accordance with Environmental Impact Analysis (EIA (AMDAL)) of RDMP RU V
Balikpapan Project (RKL-RPL).
- All project activities of CONTRACTOR in RDMP RU V Balikpapan has been included in
construction phase Environmental Impact Analysis (EIA) of OWNER. The potential
impacts on the environment of the CONTRACTOR activities on this project shall be
assessed and stipulated with OWNER’S and Government regulations particularly
environmental regulations.
- Provide and maintain effective planning and field control measures for Comply with
EIA (AMDAL), Environmental Management Plan (RKL) & Environmental Monitoring
Plan (RPL).
- Environmental management issues shall be raised in the management review meeting
in finding the best solutions to address the problems. The achievement construction
environmental management performance also is associated with waste management
and it should be discussed through the Management Review Meeting to ensure all the
targets can be achieved
- All documented information of environmental management will be recorded and
tracked by CONTRACTOR and reported periodically to OWNER as required, includes
documentation of EIA (AMDAL) Monitoring as RKL / RPL report, every 6-monthly
- Air and water quality monitoring as the consequence of project activities include
waste management activities on site will be conducted at least every three (3) months.
Monitoring of hazardous waste balance in the temporary storage and reporting to the
project management include reporting to local government shall be conducted every
month
the appropriate management level as a check on the completeness and quality of the investigation
and to obtain agreement to the proposed actions.
All corrective actions listed in the incident investigation report shall be closed in a timely manner.
The report shall remain in the ‘open status’ until it is closed. A corrective action tracking register
shall be established to track the closure of all action items and issues that remains in the ‘open
status’ shall be Subjected to discussion and resolution in the Site HSSE Committee Meeting.
A copy of the investigation report shall be forwarded to the OWNER and a copy sent to the
CONTRACTOR Home Office.
The HSSE Manager shall maintain a log of all incidents on the project in an up to date manner.
Incidents shall be updated into the Incident/accident log.
In addition, all investigation reports including witness statements shall be maintained by the HSSE
Manager till the completion of the project.
START
By HSE
Preparation
Completed
Distribute to Subcontractor / Fabricator /
CSMS in 25
Forwarder
days
Vender Management
HSE
HSE HSE
Vendor Management
Clarification Recommended
Bidder List
30.2 Registers
The following registers will be retained on site:
- Personnel medical records
- Inspection of Excavations.
- Inspections of Lifting Gear
- Inspection of Electrical Powered hand tools
- Inspection of Pressure Vessels (e.g. air receivers)
- Scaffolding
- Inspection of Cranes and Lifting machines.
- Explosive Powered tools
- Pre-inspection of plant & equipment
- Vehicle inspection
30.3 Authorizations
The following persons shall be required to carry a site authorization card at all times while on
site:
- Crane Operators
- Riggers
- Drivers/Operators of mobile plant (mechanically propelled vehicles).
- Drivers of cars, trucks, vans, pick-ups
- Scaffolders
- Electricians
- Explosive Powered Tools Operators.
- Permit To Work Holders/Acceptors
- Confined Space Watcher
- Hot Work Fire Watchers
- First Aiders
- The review includes assessing opportunities for improvement and the need for changes to the
HSSE Management System, including the HSSE Policy and HSSE objectives
- The inputs to management review include:
o Results from internal audits and evaluations of compliance with legal and other
requirements
o The results of participation and consultation
o Relevant communication from external parties, including complaints
o The HSSE performance of the CONTRACTOR’s organization
o The extent to which the objectives have been met
o The status of incident investigations, corrective and preventive actions
o Follow-up actions from previous management reviews
o Changing circumstances, including developments in legal and other requirements related
to HSSE
o Recommendations for improvement
- The outputs from the management review include decisions and actions related to possible
changes to the HSSE policy, objectives, resources, HSSE performance and other elements of
the HSSE management system, and consistent with the commitment to continual
improvement
- The records of the management reviews are retained and made available for communication
and consultation
32.0 ATTACHMENTS
Attachment 1 CONTRACTOR HSSE Policies
Attachment 2 List of Regulation
Attachment 3 HSSE Matrix Training
Attachment 4 CSMS Questionnairre
Attachment 5 HSSE Program
Attachment 6 PPE Matrix
Attachment 7 Incident Process Flowchart
Attachment 8 HSSE Organization Chart
Attachment 9 Change Management Request Form
Attachment 10 Hazard Identification Risk Assesment & Control (HIRAC)
Attachment 11 Job Safety Analysis (JSA)
Attachment 12 Job Hazard Analysis (JHA)
Attachment 13 Penalty System
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 007
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 121 / 154
Primary CPPHK’s management is committed to providing a safe and healthful workplace in all of
CPPHK’s facilities, offices and work sites and to making every effort towards eliminating or minimizing
any environmentally adverse effects of CPPHK’s operations.
Thus, CPPHK will, promote the highest standards, health, safety and environmental preservation by
establishing and implementing an HSE Management System , in all of its operations and in all locations
where work is being carried out under its control, as well as , maintaining an HSE Management System that
will include such elements as targets and standards for HSE performance, HSE education programs and
motivational incentives, and assessments and accountability for achievement those targets and standards.
To meet this commitment, Joint Operation of China Petroleum Pipeline Engineering Co., Ltd. and PT.
Hutama Karya (Persero) in carrying out its operations, will in all cases, abide by the following principles:
1. Place the highest priority on the health and safety of personnel and on the preservation and
protection of the environment.
2. Give authority to all employees and workers to stop work due to unsafe behavior, unsafe
conditions, and involve them in the decision making process in matter of safety, occupational
health and environmental protection.
3. Provide plans that meet the highest standards for safety and operation, and place the minimum
burden on the environment.
4. Plan and perform work in accordance with the HSE Management System.
5. Hold employees, including those of Vendors and Subcontractors, responsible for their own HSE
and that of their colleagues.
6. Prohibit the usage of illegal drugs, alcohol and firearms
7. Provide HSE training for personnel to improve workers' HSE understanding and competence
through socialization and training and implementation of the HSE program
8. Implement a Reward and Punishment system related to HSE aspects
9. Review, monitor and measure HSE performance for continual improvement
10. Creating and maintaining harmonious relationships with the surrounding environment
and stakeholders
To achieve the above commitments, the CONTRACTOR Management, Sub-Contractors and every
personnel involved in the work must be aware of their contents and implement all the statements in the
Policy above for each of their work activities.
Cui Guojun
( Project Manager CPPHK )
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 122 / 154
As Joint Operation of China Petroleum Pipeline Engineering Co., Ltd. and PT. Hutama Karya
(Persero) which creates a more prosperous future for humans and the earth, CPPHK sets the
following environmental policies to contribute to the protection of the earth's environment.
1. To build, maintain and work through periodic reviews for continuous improvement of the
Environmental Management System that clearly states and provides for the implementation
of environmental targets for office operations and project implementation that contribute to
the prevention of environmental pollution.
2. To use our technical expertise to give our clients access to services that contribute to the
protection of the earth's environment.
3. To fully comply with environmental laws and regulations made to protect the environment
and with related agreements reached with clients and stakeholders.
4. To minimize the burden on the environment from office operations by reducing waste,
promoting reuse and recycling and limiting energy consumption.
5. To strictly pay attention to the following principles in carrying out engineering, procurement
and construction work for our projects.
In our design work for projects we must strive to minimize adverse impacts on the
environment through these steps including limiting the consumption of resources and
energy, and working to prevent air, water and soil pollution.
In procurement, we will encourage vendors who show a positive attitude towards the use
of environmentally friendly manufacturing policies.
In construction, we must minimize the use of resources and waste production, promote
recycling, and strive to protect the environment through the prevention of air, water and
soil pollution.
Cui Guojun
( Project Manager CPPHK )
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 123 / 154
Joint Operation of China Petroleum Pipeline Engineering Co., Ltd. and PT. Hutama Karya
(Persero) is committed to creating a safe, healthy and productive workplace for employees. The
CPPHK stipulates that the abuse of alcohol, illegal drugs, other addictive substances and weapon
is illegal and can endanger yourself and others, disrupt the productivity, efficiency and
performance of workers, business partners and business partners.
The CPPHK strictly prohibits and takes firm action, namely Termination of Employment to
anyone who while working in the activities of CPPHK:
1. Consuming alcohol, illegal drugs and other addictive substances which are prohibited by
the law
2. Circulating or selling alcohol, illegal drugs and other addictive substances within CPPHK
3. Abusing legal drugs or knowingly owning, distributing, selling drugs available in Health
Facilities and first aid kits provided by the CPPHK
4. It is strictly forbidden to carry any weapon for any reason inside the job site and office.
People who are suspected carrying any weapon should be suspended from the job site and
shall be prosecuted by the law.
The CPPHK will not provide health facilities for all health consequences due to the abuse and
dependence on illegal drugs, alcohol and other addictive substances.
All employees and worker of CPPHK are responsible for implementing and complying with HSE
policies and evaluating for continuous improvement.
Cui Guojun
( Project Manager CPPHK )
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 124 / 154
LIST OF REGULATIONS
HSEMS
NO REGULATIONS AND OTHER REQUIREMENTS ELEMENT / CLAUSE
SECTION
Requirements
Environment
General
Undang-Undang No. 32 / 2009 – Perlindungan dan Pengelolaan 1, 2, 3, 4, 13, 14, 20, 21, 53,
1 1 – 13
Lingkungan Hidup 54, 57, 58, 59, 60, 67, 68, 69
2 Peraturan Pemerintah No. 27 Tahun 2012 – Ijin Lingkungan 5 Pasal 53
3 PP No. 70 Tahun 2009 – Konservasi Energi 5 Pasal 7, BAB 3
Permen LH No. 13 Tahun 2010 - UKL - UPL dan Surat Pernyataan
4 5 Pasal 2 - 9
Kesanggupan Pengelolaan & Pemantauan Lingkungan Hidup
Hazardous Material
6, 8, 9, 12, 13, 15, 16, 17, 18,
Peraturan Pemerintah No. 74/2001 – Pengelolaan Bahan Berbahaya
5 5, 9 19, 20, 22, 23, 25, 27, 28, 29,
dan Beracun
30, 31, 39
Hazardous Waste
3, 4, 5, 7, 8, 9, 10, 11, 13, 14,
Peraturan Pemerintah No. 101/2014 – Pengelolaan Limbah Bahan
6 2, 5, 9 16, 29, 30, 31, 54, 55, 56, 57,
Berbahaya dan Beracun
58, 59, 60, dst.
Peraturan Menteri Lingkungan Hidup No. 14/2013 – Simbol dan Label
7 2, 5, 9 Poin B dan C
Limbah B3
8 Peraturan Menteri Lingkungan Hidup No. 18/2009 – Tata Cara PerIjinan 2, 5, 9 1, 2, 3, 4,
Keputusan Kepala Bapedal No. 01 Tahun 1995 – Tata Cara dan 1, 2, 3, 4, 5, Lampiran 1 No. 1,
9 Persyaratan Teknis Penyimpanan dan Pengumpulan Limbah Bahan 5, 9 2.1, 2.2, 3.1, 3.2, 4, 4.1, 4.2,
Berbahaya dan Beracun 4.3, 4.4,
Keputusan Kepala Bapedal No. 02 Tahun 1995 – Dokumen Limbah 1, 2, 3, 4, 5, Lampiran 1 No. 1,
10 5, 9
Bahan Berbahaya dan Beracun 2, 3, 4
Peraturan Menteri Lingkungan hidup - Simbol dan Label Limbah Bahan
11 5, 9 2, Lampiran
Berbahaya Dan Beracun
Peraturan Menteri Negara Lingkungan Hidup No. 03 Tahun 2008 –
12 5, 9 2,3, 4, dan Lampiran 1 No.
Tentang Tata Cara Pemberian Simbol dan Label Bahan B3
Surat Edaran Nomor : 08/Se/02/1997 - Penyerahan Minyak Pelumas
13 5, 9 1 s.d. 6
Bekas
Radioctive
1, 5, 6, 12, 13, 14, 15, 16, 17,
14 Peraturan Pemerintah No. 61/2013 – Pengelolaan Limbah Radioaktif 5, 9
20, 26, 30, 35
15 KEPBAPETEN No. 01/Ka-BAPETEN/V-99 - Ketentuan Keselamatan
15 5 BAB II dan BAB IV
Kerja Terhadap Radiasi
Water Resources
16 Undang-Undang No.07/2004 – Sumber Daya Air 1 – 13 1, 7, 8, 9, 10
Peraturan Daerah Provinsi Kalimantan Timur No. 2/2011 - Pengelolaan
17 5, 9 BAB IV - VII
Kualitas Air dan Pengendalian Pencemaran Air
Peraturan Daerah Provinsi Kalimantan Timur No. 14/2012 – Pengelolaan
18 5 BAB II dan BAB III
Air Tanah di Kalimantan Timur
Liquid Waste
Peraturan Pemerintah No. 82/2001 – Pengelolaan Kualitas Air dan 7,8, 9, 10, 11, 12, 16, 17, 25,
19 2, 5, 9
Pengendalian Pencemaran Air 26, 34, 35, 37, 38, 41, 42,
Peraturan Menteri Lingkungan Hidup No. 19/2010 - Baku Mutu Air
20 5, 9 TBA
Limbah bagi Usaha dan/atau Kegiatan Migas Serta Panas Bumi
21 Keputusan Menteri Lingkungan Hidup No. 51/1995 – Baku Mutu
21 5, 9 1, 2, 5, 6, 8, Lampiran C
Limbah Cair Bagi Kegiatan Industri
Keputusan Menteri Lingkungan Hidup No. 122/2004 – Perubahan Atas
22 KepMenLH No. 51/1995 tentang Baku Mutu Limbah Cair Bagi Kegiatan 5, 9 Pasal 1, 2, dan Lampiran
Industri
23 KepMenLH No. 112 Tahun 2003 - Baku Mutu Air Limbah Domestik 5,9 4,6,8 dan lampiran
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 125 / 154
LIST OF REGULATIONS
HSEMS
NO REGULATIONS AND OTHER REQUIREMENTS ELEMENT / CLAUSE
SECTION
Air Pollution, Odor, and Noise
5, 9, 10, 20,22, 23, 24, 26, 28,
24 Peraturan Pemerintah No. 41/1999 – Pengendalian Pencemaran Udara 2, 5, 9 30, 31, 34, 35, 36, 37, 41, 42,
48, 49, 50, 51
Peraturan MenteriLingkungan Hidup No. 05/2006 – Ambang Batas Emisi
25 2, 5, 9 1, 2, 3, 4, 5, Lampiran No. B,
Gas Buang Kendaraan Bermotor Lama
Keputusan Menteri Lingkungan Hidup No. 48/1996 – Baku Tingkat
26 2, 5, 9 1, 2, 3, 5, 6, Lampiran 1, 2,
Kebisingan
1, 2, 3, 5, 6, 7, Lampiran 1 No,
Keputusan Menteri Lingkungan Hidup No. 49/1996 – Baku Tingkat 1, 2, Lampiran 2 No. 1, 2,
27 2, 5, 9
Getaran Lampiran 3, Lampiran 4, Lampiran
5
Keputusan Menteri Lingkungan Hidup No. 50/1996 – Baku Tingkat
28 2, 5, 9 1, 2, 4, 5, Lampiran 1
Kebauan
Waste Management
29 Undang-Undang No. 18/2008 – Pengelolaan Sampah 1 – 13 1, 2, 22, 23
Occupational Health and Safety
30 UU No. 1/1970 – Keselamatan Kerja 1 – 13 1 s.d 18
31 UU No. 36/2009 – Kesehatan 1 1, 10, 28, 38,44, 46, 56
32 PERMENKESNo 269/Menkes/per/III/2008 Rekam Medis 2, 5, 11 Bab I – Bab V
33 UU RI No. 22 Tahun 2009 – Lalu Lintas dan Angkutan Jalan 5 Bagian ketiga (Pasal 49 – 56)
34 UU 03/1992 – JAMSOSTEK 1 3, 6, 8, 10, 17, 20
35 PP No. 53/2012 – JAMSOSTEK 1 Pasal 9, 22, dan 26
PER 02/MEN/1992 – Tata Cara Penunjukan Kewajiban dan Wewenang
36 1 9, 10
AK3
37 PER 05/MEN/1996 – Sistem Manajemen K3 1 1 s.d. 8
38 PP No. 50 Tahun 2012 – Penerapan SMK3 1 1 s.d. 22
39 PER 04/MEN/1987 – P2K3& Tata Cara Penunjukan AK3 1 2, 3, 12,
PER 02/MEN/1980 – Pemeriksaan Kesehatan Tenaga Kerja dalam
40 5 9
Penyelenggaraan Keselamatan Kerja
41 PER 01/MEN/1976 – Kewajiban latihan Hiperkes Bagi Dokter Perusahaan 5 1
PER 01/MEN/1979 –Kewajiban Latihan Hygiene Perusahaan Kesehatan
42 5 1
dan Keselamatan Kerja Bagi Tenaga Para Medis Perusahaan
43 PER 02/MEN/82 – Kwalifikasi Juru Las di Tempat Kerja 5 3, 4 , 30, 31
PERMENAKERTRANS No.09 /2010 – Operator dan Petugas Pesawat
44 5 5, 6, 10, 12
Angkat dan Angkut
PER 03/MEN/1999 – Syarat – Syarat K3 Lift untuk Pengangkutan Orang
45 5 1, 3, 4, 5, 11, 12, 24, 27, 28
dan Barang
46 KEP 174/MEN/1986 – K3 pada Tempat Kegiatan Konstruksi 4 2
KEP 187/MEN/1999 – Pengendalian Bahan Kimia Berbahaya di Tempat
47 7 2, 4, 5, 9
Kerja
SK No. 261/MENKES/SK/II/1998 Persyaratan Kesehatan Lingkungan
48 5 BAB I. BAB II: A.1, B.1, C.1
Kerja
KEPMENKES 1405/2002 – Persyaratan Kesehatan Lingkungan Kerja
49 5 BAB VI: A, B. BAB XI
Perkantoran dan Industri
50 PERMENKES No. 492 / 2010 - Persyaratan Kualitas Air Minum 5 2, 6
PERMENKES No. 416 / 1990 – Syarat – syarat dan Pengawasan
51 5 2, 4, 9
Kualitas Air
PER 02/MEN/1980 – Pemeriksaan Kesehatan Tenaga Kerja dalam
52 5 1
Penyelenggaraan Keselamatan Kerja
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 126 / 154
LIST OF REGULATIONS
HSEMS
NO REGULATIONS AND OTHER REQUIREMENTS ELEMENT / CLAUSE
SECTION
2, 3, 4, 7, 18, 19, 20, 27, 37, 55,
53 PER 05/MEN/1985 – Pesawat Angkat dan Angkut 5
54, 55, 101
54 PER 09/MEN/2010 – Operator Pesawat Angkat dan Angkut 5 Bab 2 – 8
55 KEPRES 22/1993 – Penyakit Yang Timbul Karena Hubungan Kerja 7 2, 3
KEPMENAKERTRANS No. 609/2012 - Pedoman Penyelesaian Kasus
56 5, 6 2, 3
Kecelakaan Kerja dan Penyakit Akibat Kerja
PER 04/MEN/1980 – Syarat – Syarat Pemasangan dan Pemeliharaan
57 7 3, 5, 11, 12
Alat Pemadam Api Ringan
58 PER 02/MEN/1983 Instalasi Alarm Kebakaran Automatik 7 Bab 1 - 6
PERMENAKERTRANS No. 13/2011 NAB - Faktor Fisika dan Faktor Kimia 4, 5, 12, 14, 15, 16, 17,
59 5, 6
di Tempat Kerja Lampiran 1 dan 2
Electrical / Instrument
Deputy Manager/Chief
Carpenter / Mason
Mechanical Fitter
Superintendent
N o TRAINING INSTRUCTURE FREQUENCY
Administration
General Labor
Supervisor
Rebarman
Pipe Fitter
Scaffolder
Inspector
Surveyor
Engineer
Foreman
Manager
Riggers
Painter
Welder
Visitor
HSE Induction for CPPHK
1 Daily M M M M M M M M M M M M M M M M M M M M M M M M -
Employee (Level 1) HSE T rainer
HSE Induction for Visitor CPPHK
2 As required - - - - - - - - - - - - - - - - - - - - - - - - M
(Level 1) HSE T rainer
Basic First Aid for CPPHK Doctor
3 As required - O M M M M M O O O O O - - - - O O O O O O O - -
Employee (Level 2) /Paramedic
Basic Fire Fighting CPPHK
4 Biweekly O O M M M M M O M M O O O O O - M M M M M M O M -
(Level 1) HSE T rainer
Hand & Power T ools CPPHK
5 Monthly - O - - - M M - - - - - - - - - O O O O O O - O -
(Level 1) HSE T rainer
Permit to Work (PT W) CPPHK
6 As required O O M M - M M - - O O M - - - - - - - - - - - - -
(Level 1) HSE T rainer
Hazard Identification,
Risk Assessment, JSA CPPHK
7 Weekly O M M M M M M - - M M M M M M O M M M M M M M M -
(Job Safety Analysis) HSE T rainer
(Level 1)
Working at Height & Fall
CPPHK
8 Protection Equipment Weekly O M M M M M M - O O O M M M M - M M M M M M M M -
HSE T rainer
(Level 1)
Confined Space CPPHK
9 As required O O M O O M M - - - - M - - - - M O O - O - O O -
(Level 2) HSE T rainer
Scaffolder T raining CPPHK
10 Weekly - - - - M O - - - - - M - - - - - - - - - - - - -
(Level 2) HSE T rainer
BBSO/e-Construction
CPPHK
11 Observation Program Daily M M M M M M M M M M M M M M M M M M M M M M M M -
HSE T rainer
(Level 1)
Respiratory Protection CPPHK
12 Daily O M M M M M M - M O O O O O O O O O O O M O O M -
(Level 1) HSE T rainer
Safe Driving Course CPPHK
13 Quarterly O O O O O O O - O O O - - - - M - - - - - - - - -
(Level 2) HSE T rainer
CPPHK HSEM/
14 HSE Leadership (Level 1) Monthly M M M M M M M - - O O - - - - - - - - - - - - - -
DEPUT Y /Chief
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 128 / 154
Electrical / Instrument
Deputy Manager/Chief
Carpenter / Mason
Mechanical Fitter
Superintendent
No TRAINING INSTRUCTURE FREQUENCY
Administration
General Labor
Supervisor
Rebarman
Pipe Fitter
Scaffolder
Inspector
Surveyor
Engineer
Foreman
Manager
Riggers
Painter
Welder
Visitor
CPPHK
15 Hot Work (Level 1) Monthly - - M O O M O - - - - - - - - - M M M - M O - O -
HSE T rainer
Slinging, Rigging & Lifting
CPPHK
16 Refreshment T raining Monthly - - M O M M - - - - - - M M M - - - - - - - - - -
HSE T rainer
(Level 2)
Incident Investigation CPPHK
17 Quarterly O M M M M M O - O O - - O - - - - - - - - - - - -
T raining (Level 2) HSE T rainer
Excavation Work CPPHK
18 Bi-Weekly - - M O - M M - - - - - - - - - - - - - - - - O -
(Level 1) HSE T rainer
Emergency Preparedness CPPHK
19 Bi-Weekly O O M M M M M - M M M M M M M M M M M M M M M M -
& Response (Level 1) HSE T rainer
Waste Management CPPHK
20 Bi-Weekly - O M O O M M - - - - - - - - - - - - - - - - - -
(Level 1) HSE T rainer
Electrical Safety CPPHK
21 Bi-Weekly - O M O O M M - - M - - - - - - - - - - M - - - -
(Level 1) HSE T rainer
Mechanical Safety CPPHK
22 Bi-Weekly - O M O O M M - - - - - - - - - - - M - - - - - -
(Level 1) HSE T rainer
Chemical & Hazardous
CPPHK
23 Substance Handling Bi-Weekly - O M O O M M - - M - - M - - - - - - - - - - - -
HSE T rainer
(Level 1)
Industrial Hygiene CPPHK Doctor
24 Quarterly - O M O O M M - - - - - - - - - - - - - - - - - -
(Level 1) /Param edic
Lock Out T ag Out CPPHK
25 As required - O M O O M M - - - - - - - - - - - M - M - - - -
(LOT O) (Level 1) HSE T rainer
Safety Leader and CPPHK
26 Daily M M M M M M M M M M M M M M M M M M M M M M M M O
Awareness (Level 1) HSE T rainer
Basic Sea Survival
27 3rd Party As required M M M M M M M M M M M M M M M M M M M M M M M M O
(Level 1)
Working Above Water CPPHK
28 As required O O O O O O O O O O O O O O O O O O O O O O O O O
(Level 1) HSE T rainer
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 129 / 154
Electrical / Instrument
Deputy Manager/Chief
Carpenter / Mason
Mechanical Fitter
Superintendent
No TRAINING INSTRUCTURE FREQUENCY
Administration
General Labor
Supervisor
Rebarman
Pipe Fitter
Scaffolder
Inspector
Surveyor
Engineer
Foreman
Manager
Riggers
Painter
Welder
Visitor
CPPHK
29 SIMOPS (Level 1) As required O O M O O M M - - - O O O M M - O O O - O - - - -
HSE Trainer
H2S / Hazard Gas CPPHK
30 As required O O M O O M M - O - O O O O O O O O O O O O O O -
Awareness (Level 1) HSE Trainer
Banksman / Flagman CPPHK
31 As required - - - - - - O - - - - - O O O O - - - - - - - - -
(Level 1) HSE Trainer
CPPHK
32 STARRT (Level 1) As required O O M M - M M - - O O M - - - - - - - - - - - - -
HSE Trainer
CPPHK
33 Grating Activity (Level1) As required - O M O O M M - - - - M - - - - O O O - O - - - -
HSE Trainer
Note:
M: Mandatory
O: Option
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 130 / 154
CSMS QUESTIONNAIRE
Perkakas Tangan / Hand Tools Mesin Las / Welding Machine Mesin Pilling / Pilling Machine
Alat Berat / Heavy Equipments (Dozer, Excavator, Tangga / Stairs Pompa / Pumps
Compactor, Grader
Crane Scaffolding
4. Material yang Digunakan / Materials Used :
Nama / Name : :
Tgl / Date : :
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 131 / 154
CSMS QUESTIONNAIRE
CSMS QUESTIONNAIRE
Does your company have program and give Attendance list, copy of HSE training
HSE internal / external training? procedure, and training materials
(e.g. PPE training, chemical handling,
induction, etc.)
Apakah perusahaan Anda memberikan Matriks dan sertifikat pelatihan
pelatihan kepada karyawan sesuai dengan bidang keahlian kerja
2 lingkup pekerjaan? 0 2
Does your company give training to Matrix and training certificate of work
employee related to the scope of work? skill
NILAI TOTAL / TOTAL SCORE 0 6
IV MANAJEMEN SUBKONTRAKTOR / MANAGEMENT OF SUBCONTRACTO
Bagaimana perusahaan Anda mengelola Salinan prosedur pengelolaan
subkontraktor yang dapat mendukung subkontraktor / CSMS
program K3LL perusahaan?
1 0 2
How does your company manage Copy of subcontractor management
subcontractor for support company HSE procedure /CSMS
program?
Bagaimana perusahaan Anda memastikan Hasil evaluasi subkontraktor /
bahwa subkontraktor memahami dan dokumen kontrak yang memuat
melaksanakan program K3LL? aspek K3LL
2 0 2
How does your company ensure that Subcontractor evaluation result /
subcontractor understand and implement HSE contract document that mention the
program? HSE aspect
NILAI TOTAL / TOTAL SCORE 0 6
V HSE DLM DESAIN, KONSTRUKSI, DAN KOMISIONING / HSE IN DESIGN, CONSTRUCTION, AND COMISSIONING
Apakah perusahaan Anda memiliki prosedur Daftar dan salinan prosedur kerja
kerja sesuai dengan lingkup pekerjaan? sesuai dengan lingkup pekerjaan
1 0 2
Does your company have working procedure List and copy of working procedure
related to the scope of work? related to the scope of work
Apakah perusahaan Anda memiliki rencana Salinan rencana program K3LL
program K3LL untuk pelaksanaan proyek?
2 0 4
Does your company have HSE plan for Copy of HSE plan
project execution?
Apakah perusahaan Anda memiliki prosedur Salinan prosedur identifikasi bahaya
identifikasi bahaya dan penilaian risiko? dan penilaian risiko (JSA, RA)
3 0 2
Does your company have hazard Copy of hazard identification and risk
identification and risk assesment procedure? assesment procedure (JSA, RA)
Apakah perusahaan Anda memiliki contoh JSA Contoh JSA dan RA sesuai dengan
dan RA sesuai dengan detail / lingkup detail / lingkup pekerjaan
4 pekerjaan? 0 2
Does your company have an example of JSA Example of JSA and RA related to
and RA related to the detail / scope of work? the detail /scope of work
Apakah perusahaan Anda memiliki prosedur Salinan prosedur Izin Kerja Aman
Izin Kerja Aman?
5 0 2
Does your company have Permit to Work Copy of Permit to Work procedure
procedure?
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 133 / 154
CSMS QUESTIONNAIRE
CSMS QUESTIONNAIRE
CSMS QUESTIONNAIRE
Date:
Prepared by, Reviewed by,
(Name) (Name)
(Position) (Position)
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 136 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Communicate HSEpolicy and procedures to all employees, sub-Contractors, COMPANY and other stakeholders as appropriate to ensure them aware of their
obligations with respect to Contractor’S operation.
1 Conduct orientation / induction for HSEManagement Plan 1. Project All project Contractor Staff, Personal induction record is New hire CM, HSE Chief,
employees, SubContractors and visitors to and CSMS Requirement Induction SubContractor Staff and maintained. employees, HSEM
the site. Guideline. visitor T ransferred
2. Project Staff employees
Induction and visitor
Record.
2 Conduct regular meetings with Contractor Project HSE Plan related Daily T ool Box A HSE discussion for each Record of Daily T ool Box Every starting Site Supervisor,
staff, SubContractors and client to discuss Communication Meeting group on worker readiness, Meeting for attendance and of shift work Discipline
HSE issues. Procedure work plan for that day and topics. Superintendent
possible JSA. Site top management have
to attend this daily T BM
Weekly Construction progress Minutes of meeting record Weekly Construction
Construction coordination and discussion with HSE as the first agenda Manager
Meeting meeting, include HSE issues
Safety Discuss HSE issues and Minutes of Meeting of Monthly Construction
Committee Project progress record and attendance Manager
Meeting record
General safety A HSE discussion for All Make topics schedule and Weekly CM, HSE Manager
talk worker on project record for Attendance list
3 Ensure employees receive safety training Project HSE Plan Internal T raining T raining Nomination Form Form to signed off by Every time General
appropriate to their task and responsibility Course must be filled out prior to Project Manager prior to proposing to Superintendent /
any training taking place training taking place attend course CM
T raining Records have to be kept of T raining attendance sheet At every Project HSE
Attendance all persons attending training completed training Admin. or HSE
Sheet course Chief
T raining Records have to be kept of T raining attendance sheet At every Project HSE
Register all persons attending training completed training Admin. or HSE
course Chief
4 Establish Health, Safety, and Project HSE Plan, HSE Safety Notice Display all policies, Safety Safety notice boards are Monthly Project HSE
Environmental promotional material to Communication and Board minute of meeting, review placed in each work areas Admin. or HSE
improve the employee awareness T raining Procedure result of inspection, and displaying Coordinator
incidents, audits and others
Safety Display project performance HSE performance board Update Project HSE
Performance review against its objective placed in front of REK office Weekly Admin. or HSE
Boards and target and displaying project Coordinator
performance review result
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 137 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Safety Alerts A Safety Alert shall be Safety Alerts produced and Each occurrence PM, CM, HSE
produced for high actual or displayed Chief or HSEM
potential incidents
Follow up all relevant Follow up action incorporated As Job condition PM, CM, HSE
corrective action of incoming into the Project HSE Plan require Chief or HSEM
safety alerts from other
projects
Cautionary and Develop and display relevant Cautionary and warning Once when it's CM, Discipline
Warning Sign cautionary and warning sign signs developed and determined Superintendent
(list of warning sign like tape displayed on the hazardous
barricade, etc.) work places
Comply with all applicable HSE laws, regulations, and statutory obligations
5 Ensure that we are fully informed of all None Legal Gap Review all relevant legal Legal Gap Analysis is At start of CM, Discipline
applicable health and safety laws, Analysis aspects project such as: developed and reviewed. project and as a Superintendent
regulations, statutory obligations and relevant statutory Project procedures or result of any
Company Safety requirement and comply requirements, contractual working instruction may be amendments to
with those laws and regulation requirements and Company developed to fill the gap. legislations and
HSE requirements client
requirements
Ensure that health and safety management and practices are incorporated into all aspects of Contractor operations
6 We will analyze all areas of our activity and Project HSE Plan and JSA & Risk Identify all common hazards Conceptual Risk Assessment At start of Site Supervisor,
identify the risk level HSE Register Assessment and risks, which are is developed project /every Discipline
associated with each project starting of job Superintendent
activity
7 Where those procedures are not applicable Project HSE Plan and Job Safety JSA must be completed for Completed JSA Prior to start of Site Supervisor,
or suitable develop, implement and HSE Register Analysis new jobs and high-risk jobs. the jobs Discipline
maintain specific workplace procedures to Superintendent
ensure operations are conducted in such a JSA Review Ensure all JSA's are suited to JSA Review report During the job in HSE Chief
manner that eliminates the risk of injury, jobs carried out progress
illness or damage. Workplace Carry out workplace hazard Checklist of workplace As per schedule Project Supervisor
Hazard inspection for each project hazard inspection is and HSE Chief
Inspection work area completed, followed up and
closed out
Seek to achieve the personal commitment of all employees, sub-Contractors and suppliers to HSE workplace practices.
8 Investigate a workforce safety Project HSE Plan Project Safety Safety Incentive criteria is Safety Performance is Monthly CM
performance incentive scheme Incentive established and monitored and reviewed by
Scheme communicated committee
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 138 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
9 Involve the workforce in the Project HSE Plan Project HSE Regular meetings, which Minutes of meetings is Monthly CM
implementation of the safety program Committee attended all member of produced and
through the formation of a workplace project safety committee. communicated
safety committee Regular inspection, which are A checklist for this inspection Monthly HSE Chief
to carried out by all member is developed and completed
of project safety
committee.
10 Provide Leadership on all issues of safety Project HSE Plan Workplace Carried out a workplace A checklist of this inspection Monthly Project Supervisor
management Hazard hazard inspection for their is completed, followed up Discipline
Inspection own area of responsibility and closed out by relevant Superintendent,
signatories, 85 % close out
action
Project HSE All signatories take a part in Signatories attended on Monthly Monthly
Committee Project Safety Committee, if meeting and recorded.
appointed as a member of it Take a part on inspection
Tool Box All signatories involved in this Signatories attended on Daily Site Supervisor,
Meeting meeting on their own area meeting and recorded. Discipline
of responsibility Superintendent
Safety Talks All signatories involved in this Signatories attended Weekly CM, HSE Chief
meeting. meeting and record
Weekly All signatories involved in this Signatories attended on Weekly CM
Construction meeting, with "safety" as meeting and recorded.
Meeting the first agenda of meeting.
Provide HSE risk management systems and procedures that are relevant to the nature and scale of work undertaken
11 Ensuring that operations are carried out Project HSE Plan and Standard Developing specific standard Standard Instruction is All works shall CM, HSEM
according to standard Contractor HSE Register Instruction instruction or review existing developed, communicated covered by
procedures or template standard and maintained standard
instruction to be suited to instruction
the works
Permit to Work A restriction and limitation Excavation Permit, Working As required CM, HSE Chief
to personnel in carrying out at Height Permit,
the works known as a high Radiography Permit, Hot
risk Permit to Work, Entry Into
Confined Space Permit,
Electrical Permit to Work,
Crane Permit, Cold Permit to
Work
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 139 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Job Safety JSA must be completed for Completed JSA (Job Safety Prior to Site Supervisor,
Analysis (JSA) new jobs, risk jobs, or jobs Analysis) commencement Discipline
that are not covered by of the jobs Superintendent
SOP or Standard Instruction
prior to commencement of
JSA Review Ensure all the jobs are carry JSA Review report, Updated During the job in HSE Chief
out in accordance to JSA JSA revision number progress
12 Risks to health, safety and environment Project HSE Plan Pre-start Inspection of all equipment Checklist completed Before mobilize CM, HSE Chief
will be dealt with by elimination, or removal, inspection must be carried out to site
substitution, design, redesign, or Preventive All plant and equipment are Checklist completed As per Schedule Project GSI and
separation, administrative and personal Maintenance scheduled for maintenance Mechanical
protection Inspection Supervisor
Workplace Carry out workplace hazard A checklist of this inspection Weekly Discipline
Hazard inspection regularly is completed and closed out Superintendent,
Inspection Project Supervisor
13 Provide risk identification and management Risk Register Job Safety JSA must be completed for Completed JSA Prior to Site Supervisor,
in their work areas Analysis new jobs, risk jobs, or jobs commencement Discipline
that are not covered by of the jobs Superintendent
SOP or Standard Instruction.
JSA Review Ensure all the jobs are carry JSA Review report, Updated During the job in HSE Chief
out suited to JSA JSA revision number progress
Hazard Supervisory staff to enforce Hazard report is produced. Every Day Site Supervisor,
Reporting the reporting of hazards Hazard register is Discipline
that may arise before, maintained. Corrective Sprntndnt, HSE
during and after the works Action is recorded. Superintendent
14 Ensuring that operations are carried out Project HSE Plan Standard Developing environment Standard Instruction is All works shall CM, HSEM
according to environmental standard Instruction (SI) standard instruction or developed, communicated covered by
and Work review existing or template and maintained standard
Instruction (WI) environment standard instruction
instruction to be suited to
the works
Set measurable targets and seek to continually improve our HSE performance
15 Set the Safety Performance targets for None Project Safety T o do better that the Safety Statistic T wice a Month CM
the project Performance corporate target: LT IFR <1, Performance, HSE
T arget LT ISR < 1.0, with Fatality = Evaluation
0, Medical T reatment =0,
Property Damages =0,
Environmental Damages =
0, HSE Performance min 90
(based on HSE Evaluation)
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 140 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Corporate HSE Audit T arget is reviewed and As per schedule CM
compliance rate minim. 90 communicated
Audit internal project T arget is reviewed and Monthly CM
minimum 1 sub- Contractor communicated
per month
Periodically review and revise our HSE Policy and procedure to maintain Contractor relevance
16 Conduct assessment and review of key None Assessment Formal review of the Action plan from the review Every 3 months HSEM
personal HSE in implementing HSE HSE Mngmnt implementation HSE or as required
Management System System Mngmnt System and
Checklist performance PM / HSE Chief
17 T he Project will be audited regularly Project HSE Plan Corporate HSE Corporate HSE audit shall be Corporate Audit Report As per schedule CM
Audit conducted on a regular basis
Internal Safety Every workplace shall be Internal site HSE audit Monthly CM, HSE Chief,
Audit audited against the HSE plan HSEM
by internal audit
Prepared for emergencies and response quickly, effectively and with care to incidents resulting form Contractor operation
18 Undertake and establish Emergency Project HSE PlanProject Emergency Develop emergency Plans are regularly reviewed. Every Six-Month CM, HSE Chief
Preparedness HSE Plan Response Plan response plan and maintain T he preparedness
its preparedness and emergency equipment is
equipment checked regularly
Emergency Ensure all personnel involved ERP T raining will be given to Before project HSEM, Owner
Response in Emergency Response Site Project T eam by Owner start HSEM
T raining T eam have been trained in
ERP
Emergency Practice the Plan by A written emergency Quarterly PM, CM, HSE
Rehearsal simulating an emergency rehearsal report Chief or HSEM
situation
Site Medical First Aid Facilities to manned Medical Kit is maintained and Every Week Paramedic
Services and per day (Working Hours) by completed
Ambulance trained medic / paramedic
Rehabilitation Ensure that rehab plan is Completed Rehab Plan Every CM, HSE Chief
Plan developed and agreed to by Rehabilitation
employee Case
Prepared for emergencies and response quickly, effectively and with care to incidents resulting form Contractor operation
19 Conduct Exercise Program None Gym or Exercise All signatories involved in this Signatories attended this Weekly CM, PM, HSE
Gym or Exercise Gym or Exercise Chief
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 141 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Rules and Regulations at Site
20 No smoking at office site and working Project HSE Plan Safety Notice All contractor Staff, Result of Monitoring Monthly CM, HSE Chief
area, use drug and alcohol and carry Board and SubContractor Staff and
weapon Project visitor
Induction
Drug Test Random drug test Drug test result Random HSE Chief & CM
(Weekly)
Selection of SUBContractor
21 Conduct selection our Sub-Contractor Project HSE Plan HSE Questioner All sub-Contractor Result of questioner High Validity every 2 PM, Project
(CSMS) Risk Category > 60, 35 – years Procurement Mgr
59: Low Risk Category and Project HSEM
Accident Investigation and Reporting
22 Conduct Accident Investigation Project HSE Plan Accident All Major Accident and Minor Completed Accident As per Event CM, HSE Chief
Investigation Accident (First Aid) Investigation Form
Form
23 Regular report Accident Project HSE Plan Accident All Major Accident and Car Completed Accident 1 x 24 Hours HSE Chief,
Reporting Form Accident Reporting Form Discipline
Superintendent
Safety Awareness Program
24 In encourage Safety Behaviour Project HSE Plan Unsafe Act and All unsafe act and unsafe Completed Unsafe Act and Every Day All Project Team
Awareness, will request to our employee to Unsafe condition Unsafe condition Form
report all unsafe act and unsafe condition Condition Form
In monitoring implementation HSE None HSE Report Implementation HSE Completed HSE Report Form Monthly HSE Chief
Management System at project site. Form Management System, Man-
Request project team to provide HSE Hours, Man- power, Total
Report Accident for all employee of
Contractor and All
SubContractor
Health Program of RDMP Project
25 Conduct General Medical Check-up for all Project HSE Plan General Medical All employee of Contractor Result of General Medical As required Project Manager
new employee of Contractor Check-up Form assigned to the Project Check-up and Construction
Manager, Health
Coordinator
26 Conduct General Medical Check-up for Sub Project HSE Plan General Medical All employee of Sub Result of General Medical As require CM, Medical
Contractor Supervisor to Up level Check-up Form Contractor Supervisor to Up Check-up Advisor
level who assign to the
Project
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 142 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
HEALTH & SAFETY PROGRAM
PROCEDURE / PRIMARY
HEALTH & SAFETY ACTIVITY PLAN
NO APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY RESPONSIBILI
/EXPECTATION
REFERENCE TY
Rules and Regulations at Site
27 Conduct General Medical Check-up for all Project HSE Plan General Medical All employee of All Result of General Medical As require CM, Medical
Sub Contractor employee Check-up Form SubContractor employee Check-up Advisor
who assign to the Project
28 Vital Check for high risk worker Project HSE Plan Vital Check Blood pressure check for Daily check for high risk Daily Medical Advisor &
high risk worker worker, no indication of high HSE Chief
blood pressure
Incident Injury Free® Program
To implement IIF® program to the entire Project HSE Plan IIF® Program Engage JMJ, start Activitities report (Training as required (see PM, CM, HSE
EPC RDMP Lawe-Lawe Project implement IIF ® Program attendees, observation etc) attached table) Chief or HSEM
at RDMP Balikpapan Project
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 143 / 154
HSE PROGRAM
RDMP LAWE-LAWE CPPHK
ENVRONMENTAL PROGRAM
PROCEDURE /
HEALTH & SAFETY ACTIVITY PLAN PRIMARY
NO APPENDIX WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY
/EXPECTATION RESPONSIBILITY
REFERENCE
1 Waste Management Control Project HSE Plan Control the schedule waste - Master List and inventory of As required CM, Discipline
management (Hazardous scheduled waste, - Storage of Superintendent, HSE
Chemical Material) and provide hazardous waste, - COMPANY Chief
MSDS at site. for handling waste schedule must
registered by Government.
Control the non-schedule waste Weekly monitoring form Weekly HSE Chief, Discipline
through organic and non-organic completed Superintendent
waste
2 Liquid Spill Control Project HSE Plan Provide oil container and oil traps Monitoring form completed Monthly CM, HSE Chief
by the site drainage
3 Communicate Contractor Environmental Project HSE Plan All project Contractor staff, Induction record, Record daily As required CM, HSE Chief
Policy & Procedure SUBContractor staff and visitor tool box meeting, minute of
meeting and attendance all HSE
Meetings
4 Ensuring that operations are carried out Project HSE Plan Developing environmental Standard instruction is developed, All works shall Site Supervisor, HSE
according to environmental standard standard instruction or review communicated and maintained covered by Chief
existing or template standard
environmental standard instruction
instruction to be suited to the
work
5 Conduct accident investigation and Project HSE Plan All major and minor accident Complete accident and As per event for CM, Discipline
reporting investigation form investigation and 1 Superintendent, HSE
x 24 hours for Chief
accident reporting
6 Rules & Regulation at site: use drug and Project HSE Plan All project Contractor staff, Result of monitoring Monthly CM, HSE Chief
alcohol and carry weapon SUBContractor staff and visitor
7 Encourage behavior awareness Project HSE Plan All unsafe act and unsafe Complete unsafe act and unsafe Every Day All Project Team
condition condition form
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 144 / 154
PPE MATRIX
PPE Minimum Welding Grinding Excavation Rigging Electrical Confined Space
ANSI Z89.1 - 2003, ANSI Z89.1 - 2003, T ype I ANSI Z89.1 - 2003, T ype I ANSI Z89.1 - 2003, ANSI Z89.1 - 2003, ANSI Z89.1 2003, T ype ANSI Z89.1 - 2003,
Helmet (yellow color)
T ype I class G and E class G and E class G and E T ype I class G and E T ype I class G and E I class E T ype I class G and E
Safety Glasses ANSI Z87.1 2003 ANSI Z87.1 2003 ANSI Z87.1 2003 ANSI Z87.1 2003 ANSI Z87.1 2003 ANSI Z87.1 2003 ANSI Z87.1 2003
SNI Standard or SNI Standard or AST M F SNI Standard or AST M F SNI Standard or SNI Standard or AST M F 2413-2005 SNI Standard or
AST M F 2413-2005 2413-2005 Impact 2413-2005 Impact AST M F 2413-2005 AST M F 2413-2005 Impact Resistance Class AST M F 2413-2005
Impact Impact Impact 75 (I/75) Impact
Resistance Class 75 (I/75) Resistance Class 75 (I/75) Resistance Class 75
Resistance Class 75 and Compression and Compression Resistance Class 75 Resistance Class 75 (C/75) with electrical Resistance Class 75
(I/75) and (I/75) and (I/75) and protection such as (I/75) and
Safety Shoes Compression Resistance Class 75 (C/75) Resistance Class 75 (C/75) Compression Compression o Electric shock Compression
resistance (EH) up to
Resistance Class 75 Resistance Class 75 Resistance Class 75 14,000 V or Resistance Class 75
(C/75) (C/75) (C/75) o Static Dissipative (SD), (C/75)
106 ohms - 1010 ohms
or
o Conductive (CD), 0-
- ANSI S3.19 - 1974 - ANSI S3.19 - 1974 for - ANSI S3.19 - 1974 for - ANSI S3.19 - 1974 - ANSI S3.19 - 1974 - ANSI S3.19 - 1974 for - ANSI S3.19 - 1974
for NRR labeling NRR labeling NRR labeling for NRR labeling for NRR labeling NRR labeling for NRR labeling
Ear Plug
- ANSI S12.6 – 1997 - ANSI S12.6 – 1997 for - ANSI S12.6 – 1997 for - ANSI S12.6 – 1997 - ANSI S12.6 – 1997 - ANSI S12.6 – 1997 for - ANSI S12.6 – 1997
for NRR testing NRR testing NRR testing for NRR testing for NRR testing NRR testing for NRR testing
- ANSI S3.19 - 1974
for NRR labeling
Ear Muff
'- ANSI S12.6 – 1997
for NRR testing
NIOSH T itle 42 CFR NIOSH T itle 42 CFR 84-
Respiratory Protection
84-1995 1995
ANSI Z87.1 - 2003 - High
Face Shield
Impact Level Protection
ANSI Z87.1 2003 - High
Welding Helmet
Level Protection
SCBA NIOSH T itle 42-1995
SABA NIOSH T itle 42-1995
EN407–2004 for EN407–2004 for AST M D 120–2006
flammability, contact heat, flammability, contact heat, Specification for Rubber
convective heat, radiant convective heat, radiant Insulating
Hand Protection N/A
heat, small splashes molten heat, small splashes molten Gloves (electrical)
metal or large splashes of metal or large splashes of
molten metal molten metal
ANSI Z359.1: Safety
Requirements for ANSI Z359.1: Safety Requirements for Personnel Fall
Fall Protection Personnel Fall Arrest
Systems, Subsystems Arrest Systems, Subsystems and Components (MANDAT ORY ONLY FOR WORKING ABOVE 6 FEET )
and Components
Coverall Coveralls Grey Color (100% cotton) with stripe scotchlight shall be worn by all worker and company Name (at front and back of coveralls)
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 145 / 154
1. VISIT SCENE 1. Check Investigator’s Safety All Wearing PPE, protect Information at scene, JSA of
investigation site Continue Collecting Evidence
2. PROTECT 2. Gather evidence that might disappear from rain of work activities
4. Information Collection
People, Equipment, Environment, Systems:
4
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 146 / 154
6. DEVELOP Y 6. Start with Stop when the information Keep asking: Record realistic
TREE “What is: What has causes
Happened” and Trivial changed? Review list of
repeatedly ask Too timely & costly to potential causes
Why? collect Be specific
Gone far enough to make a Cross link
realistic recommendation causes
Scrap potential causes if
not supported
7. PLAN FURTHER 7. Investigate undecided/unknown items that are from the Sequence of Events and the
INVESTIGATION Y Tree.
10. List actions for each contributing factors and By Who? And By When?
11. SITE REVIEW 11. Conduct review to ensure all the facts are correct and everyone is in agreement
with the findings and proposed actions
12
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V BALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 149 / 154
Aris Wahyudiono
2 PERSONS
4 PERSONS
HSE ENGINEER
2 PERSONS
PARAMEDIC
/NURSE
4 PERSON
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 150 /154
:
Describe the Proposed Change
Company/Department : Date: :
Change Initiator :
No. Determine nature of the change. Does the proposed change: Y N N/A
8 Alter or add processes, plant or equipment requiring new skills, knowledge or procedures.
If one or more “yes” boxes are ticked, then the change management form is to be completed.
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 151 /154
· Using the ADVERSE IMPACT OF CHANGE MATRIX, rank each impact type:
MEDIUM 2. Requirements 1 and method statement may need to be provided and approved.
HIGH 3. Requirements 2, Conduct a Risk Assessment Workshop and Prepare Action Plan.
Describe the reasons for change, providing hard evidence to support the need/opportunity.
List any Technical Experts that need to be consulted on the proposed change.
List systems, policies, procedures, plans, schedules, competencies, etc this change effects.
STEP 6: APPROVAL
STAGE 6.1
TECHNICAL EXPERT ( HIGH RISK )
STAGE 6.2
CHANGE AUTHORIZER: (BASED ON THE LEVEL OF RISK)
DISCIPLINE SUPERINTENDENT (LOW RISK)
Change
Minor Serious Major
Consequence Type
Impact on safety/harm to Low level Serious Permanent loss of Single or multiple
people symptoms injury/permanent working ability, fatalities or
requiring first aid disability or irreversible irreversible impacts
treatment only. impairment to one damage. Localised to multiple people.
Working conditions or more persons. outbreak of Widespread
causing discomfort Serious reversible infectious disease outbreak of
or strain. health effects infectious disease.
requiring medical
treatment.
Impact on Schedule < 1 day 1-4 weeks 4-12 weeks > 12 weeks
Impact on Reputation Minor technical Attention from Significant negative Prolonged negative
non-compliance media, negative attention, national international
resolved within local & regional publicity. publicity. Reputation
one week. No publicity. Moderate Reputation severely tarnished.
media coverage. or Serious breach tarnished. Legal
of regulations with action.
fine.
Impact on Community Local public Ongoing social Ongoing serious Very serious social
concern issues. Aggressive social issues. impacts. Irreparable
/complaints. No community Repairable damage damage to high value
compensation reaction. to high value items items of social
required. Suspension of of social significance.
project works. significance. Government
External arbitration intervention.
required.
LEGEND : LOW
MEDIUM
HIGH
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 154 /154
ACTION PLAN
· All agreed actions are to be entered into Code No. for tracking.
· Each action plan is required to have an action to review the effectiveness of the change at an agreed period following the change.
No. Change item Nature of item and change Action review effectiveness Who When Code No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 155 /154
HIRA Registration No. : Prepared by: Reviewed by: Reviewed by: Reviewed by: Approved by : Risk Category
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 156 /154
24-Sep-19
Pelaksana Pekerjaan
Checked Contractor SPV / Lead Eng
Job Responsible Person
Lokasi Pekerjaan
Approved Site Controller
Job Location
Aktivitas Pekerjaan JSA Team, confirm that the risks for the task described have been reviewed and the
control which are recomended reduce the risk to ALARP and they consider it is safe so
Job Activities
the task can proceed & confirm that a work site visit has been conducted prior to the
completion of the risk assessment.
JSA No :
Medical treatment required/work restriction, high financial loss, on site release contained
1-5 Low 3 - Occasional Will occur several time 3 - Moderate
with outside assistance
Unlikely, but it can
2 - Unlikely reasonable be expected to 2 - Minor First aid treatment, on site release immediately contained medium financial loss
occur
Unlikely to occur but
1 - Improbable 1 - Negligible No affecting work performance, No injury, low financial loss.
possible
Note : * : Without Control / Tanpa control ; *): With Control / Dengan control Remark :
Our Objectives are Zero Illness, Zero Injury, Zero Property Demage/Loss and Zero Environmental Damage
NOTE : IN EVENT OF EMERGENCY, STOP ALL ACTIVITY, TURN OFF ALL EQUIPMENT AND MAKE SAFE AND GO TO MUSTER POINT.
E : Elim ination Control Mn : Im pact to the pers on or hum an
S : Subs titution Control Fc : Im pact to the facilities or property dam age
G : Engineering Control En : Im pact to the environm ent
A : Adm inis tration Control
P : PPE control
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 158 /154
24-Sep-19
JSA HSE Job No. :
CPPHK ( Job Safety Analysis )
JSA No :
Job Location :
Date : Approved by :
(SV/Foreman
Revision : Signature)
In case of emergency condition and/or incident, the following people will be contacted:
1 Phone No. :
2 Phone No. :
3 Phone No. :
10
11
12
On what conditions, job changes or distraction will this activities temporarily stop?
EPC OF LAWE-LAWE FACILITIES RDMP
RU-V B ALIKPAPAN
Doc. No. : 26076-110-G90-GHX-00001 Rev No. : 006
PROJECT HSSE PLAN
Job No. : 26076 Page No. : 160 /154