Doleh Sufian ch10 p23 Build A Model PDF Free
Doleh Sufian ch10 p23 Build A Model PDF Free
CSU ID 2356325
Chapter 10. Solution for Chapter 10 P23 Build a Model
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:
a. If each project's cost of capital is 12%, which project should be selected? If the cost of capital is 18%, what
project is the proper choice?
At cost of capital of 12 percent, Project A should be selected. But if the cost of capital rises to 18 percent, then
Project B should be accepted instead.
Before we can graph the NPV profiles for these projects, we must create a data table of project NPVs relative to differing costs
of capital.
NPV
Project A Project B NPV Profiles
$1,000
$226.96 $206.17
0% $951.00 $565.00
2% $790.31 $489.27 $800
4% $648.61 $421.01
6% $523.41 $359.29 Project A
$600
8% $412.58 $303.35
10% $314.28 $252.50
12% $226.96 $206.17 $400
14% $149.27 $163.85
16% $80.03 $125.10
$200 Project B
18% $18.24 $89.54
20% ($36.98) $56.85
$0
22% ($86.39) $26.71 $0
24% ($130.65) ($1.11) 0 0.05 0.1 0.15 0.2 0.25
26% ($170.34) ($26.85)
-$200
28% ($205.97) ($50.72)
30% ($237.98) ($72.88) Cost of Capital
-$400
c. What is each project's IRR?
IRR A = 18.64% Note in the graph above that the X-axis intercepts are equal to the two projects' IRRs.
IRR B = 23.92%
Cash flow
Time differential
0 $200
1 ($490)
2 ($390) Crossover rate = 13.14%
3 ($290)
4 $410 The crossover rate represents the cost of capital at which the two projects
5 $410 have the same net present value. In this scenario, that common net present
6 $736 value, at a cost of capital of 13.14% is: $182
7 ($200)
e. What is each project's MIRR at a cost of capital of 12%? At r = 18%? (Hint: Consider Period 7 as the end of
Project B's life.)
Project A
Time period 0 1 2 3 4 5 6
Cash flow (375) (300) (200) (100) 600 $600 $926
Cumulative cash flow (375) (675) (875) (975) (375) 225 1,151
Payback 4.625
Project B
Time period 0 1 2 3 4 5 6
Cash flow (575) 190 190 190 190 $190 $190
Cumulative cash flow (575) (385) (195) (5) 185 375 565
Payback 3.026
g. At a cost of capital of 12%, what is the discounted payback period for these two projects?
WACC = 12%
Project A
Time period 0 1 2 3 4 5 6
Cash flow (375) (300) (200) (100) 600 $600 $926
Disc. cash flow (375) (268) (159) (71) 381 340 469
Disc. cum. cash flow (375) (643) (802) (873) (492) (152) 317
Discounted Payback 5.40
Project B
Time period 0 1 2 3 4 5 6
Cash flow (575) 190 190 190 190 $190 $190
Disc. cash flow (575) 170 151 135 121 108 96
Disc. cum. cash flow (575) (405) (254) (119) 2 110 206
Discounted Payback 3.98
h. What is the profitability index for each project if the cost of capital is 12%?
, what
explained in this
the range does not
dded separately.
18 percent, then
st of Capital
ojects' IRRs.
e two projects
mon net present
the end of
7
($200)
951
7
$0
565
7
($200)
(90)
227
7
$0
0
206