Examples Foe Advanced Steel Design.
Examples Foe Advanced Steel Design.
Example: Post-Tensioned
Deck Parking Garage
Note: The slab thickness selection will be shown in the slab From Table 3-5 the maximum temp. spacing = 33 in.
design. Therefore the minimum required number of tendons is:
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 87
1 / 14
Mild Reinforcing Steel 55'-0" 55'-0"
55'-0" 55'-0"
STRUCTURAL
BAR C (BOT.) BAR C (BOT.)
18'-0"
SPAN OF SLAB
BAR D (TOP) BAR D (TOP)
TEMPERATURE PLUS
SHRINKAGE TENDONS
Span length, L = 55 ft
The four typical bars required are:
Beam spacing, s = 15 ft
Bar "A" #4 × 13 ft-4 in. @16 in. Slab thickness, to = 5 in.
Bar "B" #5 × 9 ft-6 in. @16 in. Concrete, f c′ = 5 ksi
Bar "C" #4 × 9 ft-6 in. @16 in. n=7
Bar "D" #4 × 9 ft-6 in. @16 in. Steel, Fy = 50 ksi
Studs, 3/4 in. dia. × 3 in.
Refer to Figure 3-10, which illustrates placement and loca-
tion of reinforcing bars.
Loading—Service
Please also note: Always include two #4 bars continuous at
Dead Loads:
all anchorages.
5 in. post-tensioned slab 5/12 (150) = 63 psf
self-weight of beam—assume 94 lb/ft
Uniform Dead Load:
w = 15(0.063) + 0.094 = 1.04 k/ft
Live Load:
code: 50 psf
uniform live load = 18(0.05 ksf) = 0.9 k/ft
Y2
Service Load Condition
ENA
Assume that the fresh concrete load moment is equal to the
service dead load moment, with Ixx of 2100 in.4
d
YENA 394(55) 2
∆ DL = = 3.5 in. Too High
161(2100)
Switch to W27×84
394(55) 2
∆ DL = = 2.59 in.
161(2850)
Assume a = 2 in. Y2 = 5 in. − (2 in./2) = 4 in.
From composite beam tables for Fy = 50 ksi and Y2 = 4 in.
Specify a camber of 21/2 in.
Possible selections
From composite beam tables use Y2 = 4 (from above)
W27×84 or W24×76
Y1 = 3.44 in.
Try W24×76 Qn = 456 kips
φMn = 1270 k-ft
From composite beam tables
Number of studs = 2(456)/26.1 = 35 studs
Y1 = 0.34 φMn = 1270 k-ft > 1097 k-ft
Qn = 814 kips
For W27×84 with Y2 = 4 and Y1 = 3.44 the lower bound
φMn = 1180 k-ft
moment of inertia can be found in the lower bound moment
Comparing Y2 for ΣQn = 814 kips of inertia tables: Ilb = 4860 in.4
b ≤ 2 × L/8 = 2 × 55 ft/8 = 13.75
≤ spa. = 18 ft 348(55) 2 L L
∆ LL = = 1.34 = < ok
b = 3.75 × 12 = 165 in. 161(4860) 490 240
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 89
3 / 14
Check Shear Final Selection
Vu = 2.7(55/2) = 7.5 kips
Use W27×178 Fy = 50 ksi camber = 11/2 in.
φV = φ(Fyw)(Aw) = 0.6(50)(26.71×0.46)
= 368 kips > 80 kips ok
BUMPER RAIL
Final Selection
Geometry
Use W27×84 Fy = 50 ksi with 36, 3/4 in. dia. shear stud con- Span ≈ 18ft
nectors.
Design Load
(18 shear stud connectors on each side of midspan)
P = 10,000 lb
END BAY GIRDER
Note: Codes do not define the bumper load as service or
Design Parameters ultimate. Also, the barrier member can fail in bending yet
still restrain an automobile.
Note: In order to minimize cracking, adjacent ramps should
not be connected. Thus, this girder should be non-composite.
Calculate Bending Moments
Girder Span = 45ft (Ref. to Figure A1-1A). P( L) 10(18)
M = = = 45 k-ft
Concentrated Loads at 1/3 points 4 4
Calculate Min Sy
W P P 45(12)
Min S y = = 17.8 in. 3
0.66(46)
Use HSS 10×6×5/16
Sy = 17.8 in.3
619(45) 2 L L
∆ LL = = 1.11 = < ok
161(6990) 484 240
@Seismicisolation
@Seismicisolation
90 / DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES
4 / 14
ASD DESIGN PROCEDURE @ Actr = 100 in.2 < 118 in.2
Bending Moments (Unshored)
From Property Tables
Construction Loads Ss = 213 in.3
A = 24.8 in.2
MD = 1.04(55)2/8 = 393 k-ft
I = 2850 in.4
Loads applied after concrete is hardened tf = 0.64 in.
d = 26.71 in.
ML = 0.9(55)2/8 = 340 k-ft
tw = 0.46 in.
Maximum Moment
Calculate Section Properties
Mmax = MD + ML = 393+340 = 733 k-ft
From table, at Y2 = 2.5 and Actr ≈ 30 (partial comp)
Maximum Shear
Str = 285 in.3
V = (1.04+0.9)55/2 = 53.4 k
Itr = 6269 in.4
Effective Width of Slab 6269
yeff = = 22
b =1/4 (L) = 1/4(55 × 12) = 165 in. 285
b = s = 15 × 12 = 180 in. yt = (26.71 + 5) − 22 = 9.71 in.
h
∴ fb is ok
N.A. (full)
D
yeff yo
53.4
N.A. (partial) fv = = 4.34 ksi < 20 ksi ok
26.71(0.46)
Check Deflection
M L2 340(55) 2 span
Y2 = 2.5 in. +DL = D = 1.23 = 1.06 = ok
161I c (161)2850 570
Actr = (b/n)to = (165/7)5 = 118 in.2
Enter Composite Beam Tables (9th ED) Camber 21/4 in.
Pg. 2-270 for Str = 267 in.3 393(55) 2 span
+LL = = 1.18 < ok
Try W27×84
161(6269) 240
Str ≈ 301 (interpolate for Y2 = 2.5 in.)
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 91
5 / 14
Check B/Flange Stresses Calculate Required Section Moduli (Fy = 50)
393(12) 340(12) For MD+L make sure top flange is braced, if not reduce fb
fb = +
213 285 1651(12)
Ss R e q ' d = = 600 in.3
= 365 ksi < 0.9(50) ok 33
@Seismicisolation
@Seismicisolation
92 / DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES
6 / 14
Live Check Stresses
Code 50 psf (Assume 1 floor garage) KLx = KLy = 12 ft
PD+L = 18 ft × 55 ft (0.072 ksf + 0.05 ksf) = 121 kips Allowable load on W12×40 = 237 kips > 121 kips
(Ref. AISC pg. 3-28)
Select Trial Section
fa < Fa ok
Try W12×40 (12 in. × 8 in. for connection)
Use W12×40
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 93
7 / 14
Appendix A2
Example: Cast-In-Place
Concrete on Metal Deck
This exercise is an illustration of typical calculations in the Gravity 50 psf
design of a typical cast-in-place concrete on metal deck Wind Note "A"
steel framed parking structure. Seismic Note "A"
Note "A": Refer to local codes for wind + seismic loads.
45'-0"
PRECAST OR SIM.
NOTE A
(WITH END BAY PARKING)
ARCH. PANEL
Component Design
Slab
END BM. C
Slab Design
BM. A
END BM. C
1.5" min.
BM. A
BM. A
6"
THIS PARTIAL PLAN ILLUSTRATES TYPICAL COMPONENTS
FOR A CAST-IN-PLACE SLAB POURED ON METAL DECK GARAGE
d= 6 - 1.5 - .5 = 4"
Geometry
To begin with the geometry of this example is:
Uniform Load Case
Ramp width = 55 ft
– Mu = [0.163(10)2/12]12 = 16.3 k-in.
Beam Spacing = Filler Beams – 10 ft c/c
Concentrated Load Case
Girder Beams = 22 ft -6 in. or 25 ft
– Mu = [0.0784(10)2/12 + 3.4(10/8)/4*]12 = 20.6 k-in.
Design Loading governs
Dead Loads * Note effective width of slab for concentrated loads is 48 in.
6 in. slab (total thickness poured on Set a = 0.2 in.
3 in. × 20 ga. composite deck) 56 psf
Required As = 20.6/0.9 × 60 × (4-0.2/2) = 0.1 in.2/ft
Structural steel 10 psf
66 psf
Live Loads
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 95
8 / 14
Bottom Steel LRFD DESIGN PROCEDURE
Load Cases
2 1/4"
1.4(D) = 1.4(1.43) = 2 k/ft
1.2(D) + 1.6(L) = 1.2(1.43) + 1.6(1.125) = 3.52 k/ft
1.6(L) = 1.6 (1.125) = 1.8 k/ft
3/4"
6"
Bending Moment
3"
Mu = 3.52(55)2/8 = 1331 k-ft (factored)
MDL = 1.43(55)2/8 = 540 k-ft (service)
MLL = 1.125(55)2/8 = 425 k-ft (service)
d = 21/4 in.
Check Section and Determine Properties
Uniform Load Case
Assume a = 1 in. Y2 = 6-2/2 = 5 in.
+M = (0.163(10)2/24)12 = 8.2k-in From composite beam tables for Fy = 50 ksi
+M = (0.0784(10)2/24)12+(3.4(10)/8 × 4)12 = 16.7 k-in and Y2 = 5 in.
Set a = 0.2 in.
Possible Selections
As = 16.7/0.9 × 60 × (2.25 × 0.2/2) = 0.143 in.2/ft
W27×84 or W30×90
Final Selection
Try W27×84
Draped Wire Fabric
From Composite Table
Use WWF 4 × 4/W3.0 × W3.0
Y1 = 0.32
As furnished = 0.14 in.2/ft
Qn = 921 kips
φMn = 1500 kips
Rebar
Use #4 @16 in. c/c Top & Bottom Compare Y2 for ΣQn = 921 kips
As = 0.2(12/16) = 0.15 in.2/ft
b ≤ 2(L/8) = 2(55/8) = 13.75 ft
≤ spa. = 22.5 ft
TYPICAL BEAM A
b = 13.75 × 12 = 165 in.
Span Length = 55 ft ΣQn 921
a= = = 1.31 in.
Spacing = 22 ft-6 in. 0.85 ( f c′)b 0.85(5)(165)
Y2 = 6-1.31/2 = 5.34 in.
Service Loading
Compute number of studs required.
Dead Loads (Service)
Qn = 26.1 kips/each (Table 5.1)
6 in. slab on 3 in. deck 56 psf
steel filler beams 3 psf Number of studs = (2)ΣQn/Qn = 2(921)/26.1 = 70.6
Total 59 psf
Use 71 shear stud connectors
Uniform Dead Loads
Construction Phase Check
w = 22.5(0.059)+0.1 (self wgt.) = 1.43 k/ft
A construction phase live load will be assumed from LRFD
Live Loads (Service) Specification (Section A4.1). The relevant combinations
are:
Code 50 psf
Uniform Live Loads 1.4(D) = 2 k/ft
w = 22.5(0.05) = 1.125 k/ft 1.2(D)+16(L) = 1.2(1.43)+1.6(0.02 × 22.5 ft) = 2.44 k/ft
Mu = 1331 k-ft
From composite beam tables for W27×84
@Seismicisolation
@Seismicisolation
96 / DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES
9 / 14
With an Fy = 50 ksi
PD+L
φMn = φMp = 1500 k-ft > 1331 k-ft
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 97
10 / 14
ASD DESIGN PROCEDURE From Property Tables
TYPICAL BEAM A Ss = 245 in.3 A = 26.4 in.2 I = 3620 in.4
tf = 0.611 d = 26.4 tw = 0.47
Composite Beam
Bending Moments Calculate Section Properties
Construction Loads From Table with a = 4.5 in. and Actr ≈ 30 in.2
MD = 1.43(55)2/8 = 540 k-ft Itr = 8834 in.4
Loads applied after concrete is set. yeff = 8834 / 353 = 25 in. yt = 6 + 29.5 − 25 =10.5 in.
ML = 1.125(55)2/8 = 425 k-ft
Max. moment
Check Concrete Stresses
MD+L = 540 ft + 425 = 965 k-ft
I 8834
Max. shear St = tr = = 841 in.
3
yt 10.5
VD+L = (55/2)(1.43+1.125) = 70.3 kips
fc = 965 (12 in./ft) / 841 × 7 = 1.97 < 0.45(5 ksi) ok
Effective Width of Slab
b = 1/4 (L) = 1/4(55 ft × 12 in./ft) = 165 in. governs Check Steel Stresses
= spa. = 15(12) = 180 in.
Total load Str = 353 in.3 > 350 in.3
Required Section Modulus (Fy = 50 ksi) Dead Load Ss = 245 in.3 > 196 in.3
For MD+L ∴ fb is ok
Str = 965(12)/33 = 350 in.3 fv = 47.7/(0.46 × 26.71) = 3.89 ksi
For MD
Check Deflection
Ss = 540(12)/33 = 196 in.3
∆DL = MDLL2/161(Is) = 540(55)2/161(3620)
b
= 2.85 in., camber 23/4
∆LL = MLL(L2)/161(Itr) = 425 (55)2/161(8834)
span span
= 0.9 in. < ok
to 730 240
yT y2
Check B/Flange Stress
N.A. (full) h fb = [540(12)/245]+[425(12)/353] = 40.9ksi
D
yeff yo < 0.9 (50 ksi)
N.A. (partial)
B/flg stress ok
@Seismicisolation
@Seismicisolation
98 / DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES
11 / 14
Max. Str = 385 in.3 with y = 4.5 Check Stresses
Seff req'd = 350 in.3 Bending
Ss = 624 in.3 > 609 in.3 ok
Seff − Ss 350 − 245
2
Vh′ = Vn = 66.0 385 − 245 = 371 kips ∴ fb is ok
Str − Ss
Check Deflection
N = Vh′ / q = 371/13 / 3 = 28 Per 1 2 span
PD = 55(22.5) 0.066 = 81.7 kips
∆D = PA3/48EI = 81.7(45)3 1728/48(29000)(8870)
Use 56, 3/4 in. dia. × 3 in. shear stud connectors = 1.04 in.
Note: Typical interior beam "B" and end beam "C" are Camber 1 in.
similar. PL = 55(22.5)(0.05) = 61.9
∆L = 61.9(45)3(1728)/48(29000)(8870) = 0.8 in.
END BAY GIRDER span span
0.8 in. = < ok
Design Parameters 675 240
Same as LRFD Example
Final Selection
Calculate Concentrated Load + Uniform Loads
Use W27×217 with 1 in. camber
PD+L = 55(22.5 ft)(0.066 ksf + 0.05 ksf) = 149 kips
w = 200 lb/ft Estimate or 0.2 k/ft BUMPER RAIL
For typical bumper rail calculations refer to Appendix A-1A.
Calculate Bending Moments + Shears
MD+L = 1490(45)/4 = 1676 k/ft TYPICAL INTERIOR COLUMN
V = 149/2 = 75 kips
For typical column calculations refer to Appendix A-1A.
Calculate Required Section Modulus (Fy = 50 ksi)
Ss Req'd = 1676(12)/33 = 609 in.3
Select Section
Try W27×217 Ss = 624 in.3 I = 8870 in.4
tw = 0.83 in. d = 28.43 in.
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 99
12 / 14
Appendix A3
Example: Precast—Twin Tee Deck
DESIGN STEPS:
BEAM D
BEAM B BEAM C 1.) CHECK BEAM FOR DEADAND LIVE LOAD - USING O/C
OF THE STEMS AS UNBRACED LENGTH.
12'-0" TYP.
BEAM D
6'-0" TYP.
BEAM E
BEAM D BEAM D BEAM D
BEAM A BEAM C
36'-0"
BEAM C
BEAM E
W = 2.7 KIPS/FT
BEAM D
BEAM B BEAM C
Design Example
The bumper rail and column designs are similar to those in
the previous examples and will not be repeated for this
Appendix.
For precast deck-beam design, check the construction
phase loadings of the beam as well as the final built condi-
tion. Figure A-3B illustrates these phases.
Since the beam design procedure is typical, only beam C
will be illustrated.
@Seismicisolation
@Seismicisolation
DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES / 101
13 / 14
BEAM C BEAM C
LRFD DESIGN PROCEDURE ASD DESIGN PROCEDURE
Design Loads
Design Loads
Uniform Loads
Uniform Loads
Dead: wD = 30(0.09) = 2.7 k/ft
Dead wu = 1.2(2.7) = 3.24 k-ft
Live: wL = 30(0.05) = 1.5 k/ft
Live wu = 1.6(1.5) = 2.4 k-ft
Total: wD+L = 4.2 k/ft
Total wu = 5.64 k-ft
Dead only
Load Unbraced
wu = 1.4(2.7) = 3.78 k-ft Moment
Case* Length
2
1** 4.2(36) /8 = 680 k-ft 6 ft
2*** 27(10.2) = 135 k-ft 24 ft+3 ft = 27 ft
Load Unbraced
Moment
Case* Length 3*** 13.2(16/2) = 34 k-ft 12 ft+3 ft = 15 ft
2
1 5.64(36) /8 = 914 k-ft 6 ft
Moments
2 1.4(135) = 189 k-ft 24 ft+3 ft = 27 ft
* See Figure A-3B
3 1.4(345) = 483 k-ft 12 ft+3 ft = 15 ft ** Load Case 1—Dead + Live Load
* See Figure A-3B *** Load Case 2 and Load Case 3—Dead Load Only
437.2(36) 2 437.2(36) 2
∆ DL = = 1.08 in. ∆ DL = = 0.88 in.
161(3270) 161(3990)
243(36) 2 span span
∆ LL = = 0.6 in. = < ok 243(36) 2 span span
161(3270) 722 240 ∆ LL = 0.5 in. = <
161(3990) 720 240
Check Deflection
Final Selection Check Deflection
Final Selection
Use W27×94 Fy = 50 ksi With 1 in. camber
Use W30×99 Fy = 50 ksi With 3/4 in. camber.
@Seismicisolation
@Seismicisolation
102 / DESIGN GUIDE 18 / STEEL-FRAMED OPEN-DECK PARKING STRUCTURES
14 / 14