Design Basis For Nht/Unit 02: Snamprogetti

This document provides a design basis for the Naphtha Hydrotreating Unit (NHT)/Unit 02 of the Bandar Abbas Gas Condensate Refinery Project. It refers to the process design basis in the Axens Process Books document, with an exception specifying the battery limit conditions and flow rates of incoming and outgoing fluids. Utilities conditions and other site information are to be found in document 3034-00-ED-PM-DBS-AA002.

Uploaded by

mohsen ranjbar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
468 views2 pages

Design Basis For Nht/Unit 02: Snamprogetti

This document provides a design basis for the Naphtha Hydrotreating Unit (NHT)/Unit 02 of the Bandar Abbas Gas Condensate Refinery Project. It refers to the process design basis in the Axens Process Books document, with an exception specifying the battery limit conditions and flow rates of incoming and outgoing fluids. Utilities conditions and other site information are to be found in document 3034-00-ED-PM-DBS-AA002.

Uploaded by

mohsen ranjbar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

CONT. No.

:
REF.No.:3034-PR-DBS-AA013 (A1)
PERSIAN GULF 316800 / 02-ZA-E-02004008
STAR OIL
COMPANY DOCUMENT CODE PAGE 1 OF 2

BAGCR JV PROJECT:
PLAN/PRJ UNIT PHASE DISC. DOC. TYPE SER. No. REV. No DATE
BANDAR ABBAS
Snamprogetti GAS CONDENSATE
REFINERY PROJECT 3034 02 ED PR DBS AA013 A1 09 JUN ‘08
Bina Golden Group
Consulting EP GmbH
Engineers

DESIGN BASIS FOR


NHT/UNIT 02

A1 09 JUN ‘08 FINAL ISSUE L.F. G.C. A.C.


A0 17 APR’ 08 IFA L.F. G.C. A.C.
REV. DATE DESCRIPTION PREPARED CHECKED APPROVED
BAGCR JV REF. No.:3034-PR-DBS-AA013
316800 / 02-ZA-E-02004008 (A1)
Snamprogetti
PROJECT:
BANDAR ABBAS GAS CONDENSATE PAGE 2 OF 2
Bina
Consulting
Engineers
Golden Group
EP GmbH REFINERY

For the Process Design Basis For Naphtha Hydrotreating Unit (NHT)/Unit 02, refer to the Axens
Process Books Doc.No 02/EB-PR/PRO-OO-0001-0, Paragraph 1.1.1 with the following exception:

Axens Paragraph 1.1.1.4: Battery limit conditions

Origin or Operating Operating


Fluid Destination pressure temperature
(barg) (oC)
Income
Stripped water Refinery 6.9 45
Caustic Soda Refinery 11.7 40
Outgoing
Sour water SWS unit 7.2 40
Light Naphtha ISOM unit 8.5 40
Medium naphtha Storage 7.2 40
Heavy Naphtha Gasoline pool 6.2 40
LPG Merox unit 8.0 40

Axens Paragraph 1.1.1.5: “Utilities conditions and site information”

Refer to the document 3034-00-ED-PM-DBS-AA002 (contractor number 00-ZA-E-00009002) - Basic