CVS 447 - Chapter5
CVS 447 - Chapter5
0 DESIGN FLOWS
5.1 Introduction
Hydrologic design may be grouped in two categories namely, design for water control and design for water use. Both
categories will be considered.
Water control is concerned with mitigating the adverse effects of high flows (floods) and the major task is to determine the
flood flow for flow conveyance structures (storm, sewers, drainage channels, etc) as well as for flow regulating structures
(e.g. detention basins, flood control reservoirs, weirs, etc).
The purpose of flow conveyance structures is to safely convey the flow to downstream points where the adverse effects of
the flows are controlled or minimal while that of flow regulation structures is to smooth out peak discharges thereby
decreasing downstream flood elevation peaks.
Water use is concerned with the development of water resources to meet human needs alongside the conservation of the
natural environment. The increasing water demand must be balanced against the finite supply provided by nature and the
need to maintain a healthy animal and plant life in water environments.
In contrast with hydrologic design for water control, which is concerned with mitigating the adverse effects of high flows,
hydrologic design for water use is directed at utilizing average flows and with mitigating the effects of extremely low
flows.
An adequate and properly functional storm water drainage system is one of the basic facilities needed in a built
environment.
The design approach is governed by standards of regulating authorities which incorporate the following constraints and
assumptions:
1. The sewer is designed for gravity flow.
2. The sewers are of commercially available circular sizes no smaller than 8 inch/200mm.
3. The design diameter is the smallest commercially available pipe having flow capacity
equal to or greater than the design discharge e.g., 200mm, 300mm, 400, 450mm.
4. Storm sewers must be placed at a depth such that they will drain basements and will have sufficient cushioning to
prevent breakage due to surface loading or soil pressure. Minimum cover depths must therefore be specified.
5. The sewers are joined at junctions such that the crown elevation of the upstream sewer is no lower that of the
downstream sewer.
6. Minimum permissible flow velocity at design discharge must be specified to prevent excessive deposition of
solid material in the sewers (0.6 - 0.76 m/s). This is the self-cleansing velocity. This is achieved by ensuring that
when the pipe is flowing half full, a minimum velocity not less that the cleansing velocity is maintained.
7. At any junction (or manhole) the downstream sewer must be larger than any of the upstream sewers at that
junction.
8. The sewer system is a branching network converging in the downstream direction without closed loops.
where C = coefficient of runoff = (runoff/rainfall), A = area of the catchment and i = intensity of rainfall.
Using the commonly used units, Eq. (5.1) is written for field application as”:
The rational formula is found to be suitable for peak-flow prediction in small catchments up to 50 km2 in area.
It finds considerable application in urban drainage designs and in the design of small culverts and bridges.
Example 5.1: An urban catchment has an area of 85 ha. The slope of the catchment is 0.006 and the maximum length of
travel of water is 950 m. The maximum depth of rainfall with a 25-year return period is as below:
If a culvert for drainage at the outlet of this area is to be designed for a return period of 25 years, estimate the required peak-
flow rate, by assuming the runoff coefficient as 0.3.
Solution
The time of concentration is obtained by the Kirpich formula [Eq. (5.3)] as:
. .
𝑡 = 0.01947 × (950) × (0.006) = 𝟐𝟕. 𝟒 𝒎𝒊𝒏𝒖𝒕𝒆𝒔
By interpolation,
Maximum depth of rainfall for 27.4-min duration
Exercise 5.1: A 750 ha watershed has the land use/cover and corresponding runoff coefficient as given below:
The maximum length of travel of water in the watershed is about 3000 m and the elevation difference between the highest and
outlet points of the watershed is 25 m. The maximum intensity duration frequency relationship of the watershed is given by
i = intensity in cm/h, T = Return period in years and D = duration of the rainfall in hours. Estimate the
(i) 25 year peak runoff from the watershed and
(ii) The 25 year peak runoff if the forest cover has decreased to 50 ha and the cultivated land has encroached upon
the pasture and forest lands to have a total coverage of 450 ha.
There are several assumptions inherent to the Rational method:
1. The rainfall intensity is constant over a period that equals the time of concentration of the basin.
2. The rainfall intensity is constant throughout the basin.
3. The frequency distribution of the event rainfall and the peak runoff rate are identical (this assumption is true for all
event-based computations).
4. The time of concentration of a basin is constant and is easily determined (this assumption is also shared by other
event based methods).
5. Despite the natural temporal and spatial variability of abstractions from rainfall, the percentage of event rainfall that
is converted to runoff (the runoff coefficient, C) can be estimated reliably.
6. The runoff coefficient is invariant, regardless of season of the year or depth or intensity of rainfall.
.
5.3.1 Pipe Capacity using the rational method
Once the design discharge Q entering the sewer pipe has been calculated by the rational formula, the diameter of the pipe D
required to carry, this discharge is determined.
The diameter adopted should be the next larger commercially available size (i.e., 200mm, 250mm, 300mm, and so on).
It is assumed that the pipe is flowing full under gravity but not pressurized. The pipe capacity is thus computed for open channel
flow using the Manning’s equation,
𝑄 = 𝐴𝑅 𝑆 …………………………………………………………………… (5.6)
𝑄= 𝑆 …………………………………………………………… (5.7)
.
𝐷= / ………………………………………………………… (5.8)
The diameter for each pipe segment in the storm sewer layout is computed based on its tributary (drainage) area.
Note: For imperial units, (5.6) and (5.8) become
and
.
𝐷= / ……………………………………………………………… (5.10)
Once the diameter has been determined, it is necessary to check that the velocity is greater than the self-cleaning velocity:
𝑸
𝒗= ≥ 𝒗𝒎𝒊𝒏 = 2.0 - 2.5 ft/s or 0.6 - 0.76 m/s.
𝑨
Example 5.1: A hypothetical drainage basin comprising seven sub-catchments is shown in Fig. 53. Determine the required
capacity of the storm sewer EB draining sub-area III for a 5-year return period storm. This sub-catchment has an area of 4
acres, a runoff coefficient of 0.6, and an inlet time of 10 minutes.
:
Fig. 5.3: The drainage basin and storm sewer system for Examples 5.1 and 5.2.
The design precipitation intensity for this location is given by i = 3.05T0.175/(Td + 27), where i is the intensity in m/hr, T is the
return period, and Td is the duration in minutes. The ground elevations at points E and B are 151.92 and 151.04 m above
mean sea level, respectively, and the length of pipe EB is 137.2 m. Assume Manning's n is 0.015. Calculate the pipe diameter
and flow time in the pipe.
Solution
The time of concentration for flow into sewer EB is simply the 10-minute inlet time for flow from sub-catchment III to point
E. So, Td = 10 min and the design rainfall intensity with T = 5 years is
i = 3.05T0.175/(Td + 27)
. × .
= ( )
= 0.109 𝑚/ℎ𝑟
= 0.29 𝑚 𝑠
The slope of the pipe EB is the difference between the ground elevations at points E and B divided by the length of the pipe:
S0 = (151.92 – 151.04)/137= 0.0064.
3/8
3.21 × 0.29 × 0.015
=
√0.0064
= 0.52 m
The diameter is rounded up to the next commercially available pipe size, 500 mm.
The flow velocity through pipe EB is found by taking the nominal diameter (500 mm), and assuming the pipe is flowing full
3
with Q = 0.29 𝑚 𝑠.
Figure 5.4: Delineated catchment and sub-catchments with storm sewer layout
Sewer inlets are marked 1, 2, …. 8. Pipe segment 1-2 drains drainage area 1. The peak discharge 𝑄 and pipe diameter for pipe
segment 1-2 are determined as previously described with appropriate values for the composite runoff coefficient (C) and drainage
area (A) (shaded in Figure 5.5 (a)).
The time of concentration is also calculated using the longest hydraulic path to inlet 1. Pipe segment 2-3 has a drainage area
composed of incremental drainage areas 1 and 2 and the peak discharge 𝑄 and pipe diameter are calculated for this combined
tributary area (Figure 5.5 (b)).
The travel time for segment 2-3 is the longest hydraulic path for the combined drainage area (Figure 5.5).
Thus, the drainage areas are cumulative of the entire area upstream of the inlet point being considered while time of
concentration is determined for the longest hydraulic path for the combined area.
The process is repeated for each pipe segment until the diameter of the outlet pipe is determined.
5. Flood Standards: The flood standard, sometimes expressed by return period is the size of flood adopted as the basis for
planning the protection of and controlling the development on flood-liable land. The appropriate flood standard should
reflect a realistic level of flood risk and take into consideration the social, economic and environmental factors associated
with a programme of flood loss reduction. The adopted flood standard will determine the trade-off between short term
costs and long term damages. Examples of flood standards adopted by some countries for the levee design. (Find out
Kenya’s practice in reference to dams- Refer Ministry of Water and Irrigation design manual):
COST_BENEFIT ANALYSIS
Cost
Benefit
Benefit
Or
Maximum
departure
Flood standard
COST-EFFECTIVENESS APPROACH
Fig. 5.6: Various alternatives for attaining specified goal (flood standard fixed)
10. Flood risk analysis and mapping: Essential to the formulation and implementation of appropriate flood loss prevention
and management strategies. The exercise involve flood mapping for different risk levels.
11. Flood Forecasting: Forecasting of floods in advance enables a warning to be given to the people likely to be affected
and further enables civil-defence measures to be organized. It is thus forms a very important and relatively inexpensive
non-structural flood control measure. Erroneous warning will cause the populace to loose faith in the system.
Flood forecasting technique can be broadly divided into 3 categories:
CVS 447 Page 10
Short range forecasts- This gives an advance warning of 12-40 hrs.
Medium range forecasts - This gives an advance warning of 2-5 days.
Long range forecasts- This gives much longer time than the above.
12. Flood forecasting methods: may include (1) multiple correlation methods e.g. H-upstream vs H-downstream, Q-
upstream vs Q-downstream Rainfall-upstream vs H-downstream (2) Rainfall-runoff models e.g. UH, conceptual models
(3) Routing models e.g. Muskingum, kinematic wave and dynamic wave approaches. When adequate data are available
and forecasts of complete hydrograph are required, rainfall-runoff relations are used to estimate the amount of water
expected to appear in the streams, while UH and stream flow routing procedures in one form or another are utilized to
determine the time distribution of this water at forecast point. Stage-discharge relation is then utilized to convert these
flows to stages. Computerized real time systems are nowadays in use in many points around the globe.
Detention reservoirs are also flood management reservoirs that smaller that retention reservoirs. They range from highway
culverts that provide backwater (Fig. 5.7), to fairly large reservoirs.
The primary purpose of detention reservoirs is to reduce the peak of the runoff hydrograph. This is called attenuation.
Detention reservoirs are designed to hold runoff for short periods of time and release it to the natural water bodies with
significantly lower hydrograph peaks. The slow release of water from detention reservoirs is achieved by providing it with
much smaller outlet weir or orifice than the inlet. A typical detention reservoir is depicted in Fig.5.8.
a) b)
Figure 5.10: a) On-site and b) regional detention reservoirs
In the figure, the numbers 1-12 show the potential locations for on-site detention basins while the portions designated R1 –
R3 show the potential locations of regional reservoirs that would be developed as alternatives to the on-site basins. A
combination of the two may also be considered. Careful consideration should be given to the impact of the detention
reservoirs constructed on the areas to be protected. The flow time to the point of interest should be considered to ensure that
the peak of the attenuated hydrograph does not coincide with the peak of the main hydrograph thus aggravating the flooding
instead of abating (Fig.5.11).
Detention basins may also be designed as infiltration basins to provide recharge to groundwater storage (Fig. 5.13).