Suitecommerce Advanced: Project Plan
Suitecommerce Advanced: Project Plan
SuiteCommerce Advanced
TGW 2021
PROJECT INFORMATION
Cross-Reference Documents
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
TABLE OF CONTENTS
PROJECT INFORMATION........................................................................................................................2
DOCUMENT VERSION HISTORY.............................................................................................................2
Planning Basis.......................................................................................................................................4
Scope.................................................................................................................................................4
Milestones.........................................................................................................................................4
Phases...............................................................................................................................................4
Activities............................................................................................................................................5
Tasks..................................................................................................................................................5
Effort.................................................................................................................................................5
Resources..........................................................................................................................................6
Project Plan...........................................................................................................................................6
Schedule............................................................................................................................................6
Dependencies....................................................................................................................................6
Assumptions......................................................................................................................................6
Constraints........................................................................................................................................6
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Planning Basis
Scope
The activities and tasks defined in the project plan must be undertaken within the scope of
the project.
Milestones
Phases
A phase is “a set of activities which will be undertaken to deliver a substantial portion of
the overall project”.
List and describe the major project phases within the following table.
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Go Live phase
TGW Project Laying down the plan for the Phase # 2
Execution SuiteCommerce Implementation including
meeting clients for basic requirements
gathering
TGW Project Customizations required that were not Phase # 2
Customization finished on the first project execution
TGW User The stage where a list of users will be doing Phase # 2
Acceptance Testing and applying testing on the whole website
and End User Testing process
TGW Go Live TGW SuiteCommerce Advanced Go Live Phase # 2
phase
PTI and TGW Go Live Post Go Live Support Phase #1 and #2
Support
Activities
Phase Activity
Project Initiation Initial Meeting
Pre-Kick Off Call
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Tasks
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Extensions Creation of Backend Extensions for the 1st
Creation Webstore
PTI User See UAT and
Acceptance Go Live
Testing and Worksheet
End User
Testing
PTI Go Live See UAT and
Go Live
Worksheet
Effort
Task © Effort
in hrs
Identify Business Case .30
Identify Current Need .30
SuiteCommerce Advanced Introduction 1
Identifying Project Managers, Developers, and Consultants .30
Presentation of Workbook and introduction 1
Confirmation of Fields in SCA Workbook .30
Filling out of the Workbook 3
Review of SCA Workbook Details 1
Finalization of SCA Workbook 1
Official Project Kick Off Call with Consultants and Stakeholders 1
Items, Website Categories import 2
SCA Workbook setting application on the Configuration 3
Domain Setup 1
Field Set Setup .30
Shopping and Checkout Setup 2
Images .30
SSP Application Setup 1.30
Subsidiary Setup 1
Extension and Theme Management Setup 1
Theme installation
Theme installation 1
Extensions Installation and Setup 2
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Identification of Payment Methods Available 1
Setup of Payment Methods 2
Setup of Payment Processing Profiles 2
Items Showing On Webstore 2
Cart Adding of Items 1
Checkout Processing 2
Placing of Order .30
NetSuite Verification of Order Placed
All Customizations Identified Development 36
Application of Front end requirements for theme 24
Extensions Creation 40
Resources
For each task identified, list the resources allocated to complete the task.
Task © Resource
Identify Business Case PTI and TGW
Identify Current Need
SuiteCommerce Advanced Introduction CWGP
Official Project Kick Off Call with Consultants and Stakeholders PTI, TGW and
CWGP
Items, Website Categories import PTI
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
Images CWGP
Project Plan
Schedule
The timeline and project outline is presented in Timeline_ProjectOutline
Dependencies
Dependencies will be discussed solely by the parties themselves.
Assumptions
It is assumed that:
Constraints
• The project must operate within the funding and resource allocations approved
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.
• The project team must deliver the software with no requirement for additional
hardware
The information contained in this document is proprietary and confidential information of CW Global Partners. Any unauthorized
reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document and information are intended
solely for the internal use of authorized CW Global Partners or its customers, for the limited purposes set forth herein.