Material Requirements Plan

The document contains a product structure with three levels for a product called S. S is at level 0 and requires components T and U at level 1. T requires components V, W, and X at level 2, while U requires Y and Z. The document also includes lead times for each component and uses this information to construct a time-phased product structure and gross material requirements plan showing the requirements for each component over seven weeks to meet a demand of 100 units of S in week 7.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views

Material Requirements Plan

The document contains a product structure with three levels for a product called S. S is at level 0 and requires components T and U at level 1. T requires components V, W, and X at level 2, while U requires Y and Z. The document also includes lead times for each component and uses this information to construct a time-phased product structure and gross material requirements plan showing the requirements for each component over seven weeks to meet a demand of 100 units of S in week 7.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Nama : Nuricha Fajariani NIM : 20808141017

No : 16 Kelas : Manajemen A20

TUGAS MATERIAL REQUIREMENTS PLANNING


MATA KULIAH MANAJEMEN OPERASIONAL

14.5 The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of
T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally,
each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It
takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks
to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
a) Construct a product structure. Identify all levels, parents, and components.

Product Structure

T(1) U(2)

V(1) W(2) X(1) Y(2) Z(3)


Identification
Struktur produk ini memiliki tiga level (0, 1, dan 2) dengan S berada di level 0, T dan U berada
di level 1, dan V, W, X, Y, dan Z berada di level 2. Selain itu, struktur ini memiliki tiga orang
tua (S, T, dan U) dimana setiap orang tua setidaknya memiliki satu level di bawahnya, dan 7
komponen (T, U, V, W, X, Y, dan Z) karena setiap item memiliki setidaknya satu level di
atasnya. Pada struktur ini, T dan U berperan ganda, yaitu sebagai orang tua dan komponen.

b) Prepare a time-phased product structure.


Waktu Tunggu Setiap Komponen

COMPONENT LEAD TIME


S 2
T 1
U 2
V 2
W 3
X 1
Y 2
Z 1

Time-phased Product Structure

2 minggu
V
1 minggu
W T
3 minggu
X
1 minggu

2 minggu

Y
2 minggu

1 minggu 2 minggu U
Z

1 2 3 4 5 6 7
Waktu dalam minggu
14.6 Using the information in Problem 14.5, construct a gross material requirements plan.
Gross Material Requirements
WEEK LEAD
TIME
1 2 3 4 5 6 7
(WEEKS)
S. Required date 100
2
Order release date 100
T. Required date 100
1
Order release date 100
U. Required date 200
2
Order release date 200
V. Required date 100
2
Order release date 100
W. Required date 200
3
Order release date 200
X. Required date 100
1
Order release date 100
Y. Required date 400
2
Order release date 400
Z. Required date 600
1
Order release date 600

14.7 Using the information in Problem 14.5, construct a net material requirements plan using
the following on-hand inventory.
ON-HAND ON-HAND
ITEM ITEM
INVENTORY INVENTORY
S 20 W 30
T 20 X 25
U 40 Y 240
V 30 Z 40

Tabel Net Requirements Plan terlampir di spreadsheets.