Plumbing Work Program

This document outlines a project schedule for plumbing services at a factory in Malaysia from December 2018 through December 2019. The schedule includes tasks for mobilization, sanitary services like pipe sleeves and piping installation at different levels, cold water services such as pump installation and distribution piping, and testing and commissioning with a deadline of September 2019. Major tasks include provision of pipe sleeves from February to May 2019 and cold water distribution piping from April to June 2019.

Uploaded by

Mark Sim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
1K views1 page

Plumbing Work Program

This document outlines a project schedule for plumbing services at a factory in Malaysia from December 2018 through December 2019. The schedule includes tasks for mobilization, sanitary services like pipe sleeves and piping installation at different levels, cold water services such as pump installation and distribution piping, and testing and commissioning with a deadline of September 2019. Major tasks include provision of pipe sleeves from February to May 2019 and cold water distribution piping from April to June 2019.

Uploaded by

Mark Sim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May

Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19
19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9
1 TETUAN BAKELS (MALAYSIA) SDN BHD FACTORY 265 days Mon 12/3/18

2 PLUMBING SERVICES 209 days Mon 1/21/19

3 Mobilisation 7 days Mon 1/21/19

4 Sanitary Services 121 days Fri 2/1/19

5 Provision of Pipe Sleeves 80 days Fri 2/1/19

6 Level 1 3 days Fri 2/1/19

7 Level 2 3 days Fri 4/19/19

8 Roof 3 days Sun 5/19/19

9 Soil, waste & vent piping 74 days Tue 4/9/19

10 Grd. 18 days Tue 4/9/19

11 Level 1 18 days Thu 5/9/19

12 Level 2 18 days Sat 6/8/19

13 Roof 18 days Thu 6/20/19

14 Cold Water Services 150 days Tue 4/9/19

15 Incoming to suction tanks 21 days Thu 8/1/19

16 Pump feed Riser & Droppers 150 days Tue 4/9/19

17 Distribution piping 74 days Tue 4/9/19

18 Grd. 18 days Tue 4/9/19

19 Level 1 18 days Thu 5/9/19

20 Level 2 18 days Sat 6/8/19

21 Roof 18 days Thu 6/20/19

22 LG Transfer Pump 21 days Tue 5/28/19

23 Booster Pumpset @ Roof 14 days Mon 6/17/19

24 Harvesting Tank 20 days Tue 5/28/19

25 Testing & Comissioning 30 days Mon 9/23/19

Project: Bakels Plumbing Work Progra Task Progress Summary External Tasks Deadline
Date: Sat 2/23/19 Split Milestone Project Summary External Milestone