Module 2-Task 1.2
Module 2-Task 1.2
Melwin
Diploma of Building & Construction
1.1. Objective
The main objective of this demolition management plan is to create and document the required
procedures and the legal framework for the physical work to be undertaken in the demolition
process and ensure that they meet the legal, safety and health specification in accordance with
Legislation, regulations, standards and codes of practice that govern the demolition of Class 2-9,
type “B” construction buildings of AS 2601-2001.
1.2. References
1
AS/NZS ISO 19011:2003 Australian/New Zealand Standard Guidelines for quality and/or
environmental management systems auditing;
Environmental Protection Authority Publication Environmental Guidelines for Major
Construction Sites (1996);
AS 1885.1 – 1990: Workplace injury and disease recording standard.
The building structure for demolition is an existing brick factory which covers an area of 1600
sq. meters. It is comprised ground floor and the first floor only and is contained in a site which
covers an area of dimensions; 55082 mm by 49943 mm. The property is fenced and is neighbors
to storey buildings such as adjacent double Storey Concrete/ Concrete Block Retail Shop
2
1.4. Demolition Tasks Summary
Demolition Method/Procedure
Task No. Building/Structure Description of the work Photos
performed
1 The whole site Before the demolition works starts Refer to the plan
disconnection activities will be
performed on the site and they
include;
Degassing, disconnection
and removal of air
conditioners.
Disconnection and removal
of still useful electrical
devices and appliances.
Disconnection and removal
of factory machines safely.
Disconnection of electricity
and possible removal and
reallocation electricity
equipment such as poles and
electrical cables.
Also, ensure use of protective gear
for the persons undertaking the
demolition work.
3
excavator after blowing it using
explosives as it is made up of
Bituminous Membrane roof with
50mm insulation and 200mm of
River pebble ballast.
4
2. Preliminary Demolition Activities
The preliminary activities have been accomplished and the following are the main preliminary
demolition activities;
The identification of run-off water and stormwater outlets and sealed accordingly to
protect them from sediments and building material sediments that can led to the closure
of the outlets.
Clear mapping and location of all the operational pathways and available roads for
transportation of the demolished structure.
Clear mapping and identification of the adjacent and surrounding buildings and structures
such as the shop and the perimeter wall.
The following underground essential services infrastructure was identified for disconnection and
protection prior to demolition work commencement;
An existing sewer system was identified and work was undertaken to barricade and
protect the sewer pit within the boundaries of the site.
Existing water supply system pipe was identified and work was undertaken to barricade
and protect the sewer pit within the boundaries of the site.
Existing stormwater conduit pipe was identified and work was undertaken to barricade
and protect the sewer pit within the boundaries of the site to ensure machines can move
on the ground freely.
The following aboveground essential services infrastructure was identified for disconnection and
protection prior to demolition work commencement;
5
There is overhead electricity power to the northern part of the premises which is within
meters from the building structure. The Electricity grid providers were engaged to
perform Tiger Tail installation work on the site.
The Hazardous waste management plan has been prepared which ensures proper handling and
disposal of hazardous wastes such as asbestos and industrial chemicals. In addition hazardous
building material survey has been conducted and proper disposal procedures outlined.
Items Yes No
Requirements and Procedures
Demolition Permit
Council required documents such as A copy of the title for the
property, Plan of subdivision also known as the title plan and
site plan
Planning permit
Demolition commencement permit
6
4. Identifying what technique would be used for the
demolition and why
The technique that can be used in this case is the use of excavators and wrecking balls.
This techniques are preferred because of the small size and height of the building and the
small space available for loading the debris into the earth movers.
7
8
6. Where the drop zones would be. (Indicated on the site
plan)
The drop zone is supposed to a third of the working height. The height of the
building is 7620 mm which equates to 7.62 meters. And thus the drop zone radius
is 2.54 meters. In the plan section below the black part the drop zone.
9
7. Where hoardings, fencing and shoring maybe used
Fencing, hoarding and shoring is erected around construction sites to create a barrier to
confine any risk during demolition, excavation of the site, and when construction’s
underway.
They will installed around the perimeter distance of the whole site.
Activities Yes No
Disconnect services, power, water, gas etc.
Determine stormwater and sewer drains locations and seal at point
of discharge.
Undertake any adjoining property protection as determined and
agreed by building surveyor and provide temporary wall bracing
and shoring where required.
Remove loose and attached equipment, fittings and built in fixtures,
internally and externally
Remove wall cladding external chimneys, attached outbuildings
and lean-to structure
10
10. Complete a Form 7 Protection Work Notice for one
of the neighboring properties
FORM 7
Regulation 113
Building Act 1993
Building
Regulations 2018
Postal address: Mrs Smith 98 Shirley Street PIMPAMA QLD 4209 AUSTRALIA
Telephone: 011-61-2-2434-0650
11
Adjoining owner's property details (the adjoining property)
Municipal district
From: _________________________________
Owner/Agent:
__________________________ Owners
Name: ____________________________
ACN/ARBN:
_______________________________
Postal Address: ____________________________ Postcode:
Municipal district
NOTICE
In accordance with section 84 of the Building Act 1993, I give notice of my intention to carry out the
following building work on my property and request your agreement to the proposed protection
work which affects your adjoining property.
12
Details of proposed building work:
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Location of works:
___________________________________________________________ Time and
duration of protection: _______________________________________________
If the proposed protection work is agreed to by the adjoining owner or determined as being
appropriate by the relevant building surveyor under section 87(1) of the Building Act 1993 or by the
Building Appeals Board under section 141 of the Building Act 1993 (as the case requires), the owner
must—
13
i. ensure that a contract of insurance is in force in accordance with section 93 of the Building
Act 1993 against damage by the protection work to the adjoining property and other
liabilities described in that section; and
ii. make a full and adequate survey of the adjoining property in accordance with section 94 of
the
Signature:
Date: ____________________________________________
14