Transformer Design
Transformer Design
TRANSFORMER DESIGN
& MANUFACTURING.
1
TRANSFORMER :DEFINITION
• A transformer is a static piece of apparatus
used for the transferring power from one
circuit to the other without change in
frequency. It can raise or lower the voltage
with a corresponding decrease or increase
in current.
2
• Primary winding
• Secondary winding
• Linkage of the two by Mutual Inductance
3
Voltage transformation ratio
• E1 = 4.44* f *N1* Øm
E2= 4.44* f *N2* Øm
E2 / E 1 = N1/N2
4
LOW VOLTAGE WINDING
DESIGN
• Since voltage is less ,hence turns will also
be less.
• Phase Current = MVA/(√3*line voltage in
kV) if winding is star connected.
Phase Current = MVA/(3*line voltage in
kV) if winding is Delta connected.
This indicates current in Low voltage
winding shall be high.
5
HELICAL WINDING
• To carry high current the area of cross
section of the conductors should be
high.This is accomplished by adopting
more no. of conductors per turn.
• Helical winding which is spring like,suits
most for the LV windings.
6
HIGH VOLTAGE WINDING
• Large no. of turns
• Less current.
• Disc coils are the best choice for the HV
windings where a single disc can have
turns as high as 25 nos.
7
Type of Windings
COIL
INTERLEAVED DISC
WINDING 10
INTERLEAVED DISC WINDING
11
(4 discs per group)
L.T
. H.T.
Line
Shields
14
Transposition
17
Insulating Area
18
A: Vertical Area B: Horizontal Area C: Area between
Leakage Flux
19
Flux entering the tank
20
Flux enters the Shunt
Insulation
21
MATERIAL USED FOR
WINDING
• P.I.C.C.
• C.T.C.
• Bunched P.I.C.C.
• Glued C.T.C.
22
MAGNETIC CIRCUIT
• Magnetic circuit is formed by ‘CORE’
• CORE is a three or five legged
construction providing the .
• Coils which are of cylindrical shape are
assembled over the legs.
23
OTHER CONSIDERATIONS
• After designing the windings they are
suitably placed over the core legs keeping
in mind the electrical stresses.
• Windings are designed for impulse
withstand and short circuit forces also.
• This is followed by the cooling design.
24
WHAT IS A CORE?
• ANY TRFR. CONSISTS OF CORE AND
WINDING. CORE IS THE MAGNETIC CIRCUIT
THROUGH WHICH FLUX FLOWS.
25
MATERIAL USED IN CORE
• The material used for core making is low
reluctance magnetic steel containing silicon.This
is called “CRGO” i.e cold rolled grain oriented
steel.
• The grain orientation is technology which
ensures that the flux flow through the
laminations with minimum resistance,resulting in
low core loss.
26
TYPE AND CONSTRUCTION OF
CORE
• THERE ARE FOLLOWING TYPES OF CORE
AVAILABLE:-
– A. THREE LIMB CORE
– B. TWO LIMB CORE
– C. FIVE LIMB CORE
– D. CORE WITH ELLIPTICAL YOKE SECTION
– E. CORE WITH FLAT YOKE
THERE CAN BE SOME MORE VARIATION
KEEPING THE BASICS SAME.
27
Core Nomenclature
TOP YOKE
• L= Leg
Length
• C= Distance L A A W
between leg
centres
• W=Main leg
width BOTTOM YOKE
C C AUXILIARY
LIMB
C
28
Section through
Section through 'A-A'‘A-A’
Cooling Duct
Cooling
C
Duct
L
W
L
C
30
Single Phase, Core type 2 legs
W/2 SM
W/2
W/2
W
INSIDE YOKE
LENGTH
W/2
W W
W W
W
W W W
W
0.43W
0.57 W
35
DESCRIPTIONS CONTINUED….
• LEG CENTRES: THIS IS THE DISTANCE
BETWEEN THE CENTRELINES OF MAIN
LEGS OF A CORE.
37
PURPOSE OF TRFR.TANK
38
MOST BASIC CLASSIFICATION
A. CONVENTIONAL
B. BELL TYPE
• CONVENTIONAL TANK:
A TANK IN WHICH THE COVER IS FLAT AND
TANK TO COVER JUNCTION IS AT THE TOP
OF THE TANK.
39
• BELL TYPE TANK
• A TANK IN WHICH THE COVER IS NOT
FLAT IN SHAPE AND THE TANK AND
COVER JUNCTION IS NEAR THE
BOTTOM OF THE TANK .
• THUS THE TANK HAS GOT TWO PARTS
– ‘TOP TANK’ AND ‘BOTTOM TANK’
40
TRANSFORMER FITTINGS
• COOLING EQUIPMENTS
• TERMINAL ARRANGEMENT
• CONSERVATOR
• O.L.T.C.
• INSTRUMENTS
• BREATHERS ETC.
41
TRANSFORMER COOLING
• WHEN THE TRANSFORMER IS IN SERVICE
THE WINDINGS GET HEATED UP. IN OIL
FILLED POWER TRANSFORMERS OIL IS THE
COOLING MEDIUM FOR WINDINGS. OIL IS IN
TURN COOLED BY MEANS OF RADIATORS
/INTEGRAL COOLERS WITH WATER/AIR AS
COOLING MEDIUM.
42
TYPE OF COOLING
• ONAN COOLING
• ONAF COOLING
• OFAF COOLING
43
ONAN COOLING
• OIL FLOW IS THROUGH NATURAL
CONVECTION
• AIR FLOW IS ALSO NATURAL(NOT FORCED)
• COOLING EQUIPMENT USED:
– RADIATORS
44
ONAF COOLING
• OIL FLOW IS THROUGH NATURAL
CONVECTION
• AIR FLOW IS NOT NATURAL BUT FORCED
• COOLING EQUIPMENT USED:
– RADIATORS AND FANS
– ONAF COOLERS
45
OFAF COOLING
• OIL FLOW IS FORCED BY MEANS OF INLINE
OIL PUMPS.
• AIR FLOW IS FORCED BY MEANS OF FANS
/BLOWERS
• COOLING EQUIPMENTS USED:
– RADIATORS,FANS AND PUMPS.
OR
– INTEGRAL OFAF COOLERS.
46
RADIATORS
48
PUMPS
• PUMPS ARE NORMALLY INLINE TYPE.
• PURPOSE IS TO PUMP OIL THROUGH THE
TRANSFORMER TO CREATE FORCED FLOW
OF OIL.
49
MOUNTING OF RADIATORS
• RADIATORS CAN BE DIRECTLY MOUNTED
ON THE TANK WALL, IF THE NO. OF
RADIATORS IS NOT LARGE.
• RADIATORS CAN BE MOUNTED IN A BANK
FORMATION I.e. GROUP OF RADIATORS ARE
MOUNTED ON HEADERS AND ARE PLACED
SEPARATELY FROM TANK.
50
HEADER
• HEADERS ARE PIPES OF SQUARE
CROSS SECTION.
• THERE SHALL BE ONE TOP HEADER
AND ONE BOTTOM HEADER FOR A
GROUP OF RADIATORS.
• THE HEADER AND RADIATOR ASSY. IS
SUPPORTED OVER “A”
FRAMES(NAMED SO BECAUSE OF
RESEMBLANCE WITH ALPHABET “A”)
51
HEADER PIPE WORK
52
• ARRRNGEMENT OF FANS / INLINE PUMPS
ALONG WITH THEIR SUPPORTS ARE ALSO
SHOWN IN THE HEADER PIPE WORK
DRAWING.
53
CONSERVATOR PIPE WORK
54
CONSERVATOR
• A CONSERVATOR IS A CYLIDERICAL VESSEL
WHICH PROVIDES SPACE FOR EXPANSION
OF OIL INSIDE THE TRANSFORMER OR
SUPPLIES OIL TO THE TRANSFORMER
WHEN THE TRANSFORMER OIL COOLS AND
CONTRACTS IN VOLUME.
• A CONSERVATOR IS ALWAYS PLACED
ABOVE THE TRANSFORMER.
55
CONSERVATOR CONTD...
• WHEN THE CONSERVATOR IS USED
FOR THE MAIN TRANSFORMER IT IS
CALLED MAIN CONSERVATOR AND
WHEN IT IS USED FOR THE OLTC IT IS
CALLED AUXILIARY OR OLTC
CONSERVATOR.
56
TERMINATION
• TRANSFORMERS ARE CONNECTED IN THE
SYSTEM BY ANY OF THE THESE METHODS
AS DEMANDED BY OUR CUSTOMERS.
• OVER HEAD BUSHINGS
• CABLE BOXES
• BUS DUCT
• A COMBINATION OF ABOVE
57
OVERHEAD BUSHINGS
• HIGH VOLTAGE, LOW VOLTAGE AND IN
SOME CASES THIRD WINDING
“TERTIARY” OR “STABILISING” LEADS
ARE BROUGHT OUT THROUGH
BUSHINGS. THEY ARE CALLED HV
BUSHING, LV BUSHING AND TERTIARY
BUSHING.
• THESE BUSHINGS CAN BE MOUNTED
ON THE TANK COVER(OR TOPMOST
HORIZONTAL PLANE IN THE TANK) OR IN
SOME CASES SOME BUSHINGS ARE
MOUNTED ON VERTICAL END WALLS. 58
CABLE BOXES
• IN SITES WHERE CUSTOMER HAS LAID CABLES
INSTEAD OF OVERHEAD CONDUCTORS THE
TERMINATION (CONNECTION) IS THROUGH CABLE
BOXES.
• CABLE BOXES ARE ENCLOSURES ATTACHED
EXTERNALLY TO THE TRANSFORMER TANKS.
• THEY CAN BE ON THE LV WALL,HV WALL OR ON
BOTH LV AND HV WALLS. SIMILARLY INSTEAD OF
WALLS THEY CAN BE ATTACHED ON THE COVER
ALSO.
59
BUS DUCT
60
COMBINATION OF
TERMINATION METHODS
• TERMINATION OF DIFFERENT WINDINGS
CAN BE THROUGH DIFFERENT
COMBINATIONS. FOR EX.
• HV-BUSHING, LV-CABLE BOX
• HV-BUSHING, LV-BUS DUCT
ETC.
61
TANK BASE
• BASE CAN BE WTH OR WITHOUT
ROLLERS
• ROLLERS OF 4 TYPES AND ARE OF
STANDARD DESIGN
• SKID BASE
• BASE SUITABLE FOR PLACEMENT ON THE
PLINTH
62
OLTC
63
BUCHHOLZ RELAY
64
BUCHHOLZ RELAY contd….
• Buchholz relay is a protective relay .When
the accumulation of the gases rise above
a certain level then the float in the
buchholz relay rises activating a mercury
switch which gives the alarm
• When the gas accumulation is still higher
then another float activates the trip switch
disconnecting the transformer from the
circuit.
65
M.O.G . WITH LOLA
• Magnetic Oil Gauge with low oil level
alarm.
• This is used with conservator
• It's purpose is to indicate the oil level in the
conservator vessel and to give alarm when
the oil level falls below a threshold limit.
66
OIL SURGE RELAY
• This is similar to MOG but used in On load
tap changer oil compartment.
67
PRV
• Pressure Relief Valve
• When transformer experiences excessive
pressure due to extreme heating on
account of faulty operation or conditions
then this valve saves the transformer by
releasing the excessive pressure and
simultaneously disconnecting the
transformer from the lines.
• This equipment is of spring loaded type.
68
OTI
• OTI: Oil Temp. Indicator: This consists of a
bulb dipped in a oil cup on the cover of the
transformer tank cover. This bulb is
connected to the meter placed in the
marshalling box meant for housing the
equipment electrical controls by means of
a capillary. This indicates the temperature
of the top part of the transformer oil which
is the hottest part.
69
WTI
• Similar in construction to the OTI.
• This reads the temperature of the winding
in an indirect way.
• A current transformer injects current into
the heating coil of the equipment giving
the extra temperature gradient over the
top oil temp. which normally a winding is
expected to have.
70
SILICA GEL BREATHERS
• Moisture is an enemy of transformer insulation
system
• Whenever oil contracts transformer breaths in
through breathers.
• With air lot of moisture which is present in the air
also go inside.
• The silica gel present in the breathers absorb
moisture and only dry air goes inside.
• After a certain level of absorption the color of
silica gel crystals change from blue to pink when
these particles should be recharged or replaced.
71
AIR CELL
• When transformer breathes in air oxygen also
gets in touch with the oil.Oxygen oxides the
insulating oil and contaminate it in terms of the
electrical properties.
• Air cell is rubber bag compatible with the
transformer oil and is fitted inside the
transformer conservator.When oil in transformer
contracts ,it sucks air into the this bag and when
oil expands it expels air. Thus Air Cell prevents
atmospheric oxygen to come in contact with the
oil.
72
PRINCIPLES OF
TRANSFORMER TESTING,
ERECTION &
COMMISSIONING.
73
TRANSFORMER TESTING
• A. Routine tests
• B. Type tests
Routine tests are conducted on each and
every transformer of the lot/order .
Type tests are conducted on one
Transformer of a particular design and on
successful passing of this test the design
of the transformer is said to be validated.
74
Routine tests
• RATIO TEST
• VECTOR GROUP VERIFICATION
• WINDING RESISTENCE
• CORE LOSS
• LOAD LOSS
• IMPEDANCE MEASUREMENT
• SEPARATE SOURCE VOLTAGE WITHSTAND
TEST
• INDUCED OVER VOLTAGE WITHSTAND TEST
75
TYPE TEST
• TEMPERATURE RISE TEST
• LIGHTENING IMPULSE TEST
• VACUUM AND PRESSURE TEST
76
TEST REQUIREMENTS
• IN ORDER TO ENSURE THE SUITABILITY OF TRANSFORMER
FOR VARIOUS POSSIBLE TRANSIENTS/OVERVOLTAGES OF
SYSTEM, VARIOUS NATIONAL STANDARDS LIKE IS 2026
(PART-III) & INTERNATIONAL STANDARD LIKE IEC 60076-3
DEFINE THE TEST LEVELS & TEST METHOD REQUIREMENT
FOR DIFFERENT TESTS.
• THE MAJOR DIELECTRIC TESTS APPLICABLE FOR EHV
CLASS TRANSFORMERS ARE:
1. LIGHTNING IMPULSE WITHSTAND
2. SWITCHING IMPULSE WITHSTAND
3. INDUCED OVERVOLTAGE WITH OR WITHOUT PD
MEASUREMENT
4. SEPARATE SOURCE VOLTAGE WITHSTAND TEST
77
TEST REQUIREMENTS
• RECENTLY, IEC 60076-3 HAS BEEN REVISED TO
INCORPORATE MORE STRINGENT TESTING
REQUIREMENTS. THE MAJOR CHANGES wrt
EARLIER EDITION OF 1980 ARE:
PARAMETER EARLIER REQT. AS PER IEC-
60076-3(2000)
ACLD NA SPECIAL TEST
FOR Um=72.5-
170kV. ROUTINE
TEST FOR
Um>170kV
LI ROUTINE FOR ROUTINE FOR
Um300kV Um>72.5kV
78
TEST REQUIREMENTS
PARAMETER EARLIER REQT. AS PER IEC-
60076-3(2000)
SI ROUTINE FOR ROUTINE FOR
Um300kV Um>170kV
ACSD WITHOUT NA ROUTINE FOR
PD Um72.5kV
80
ERECTION AT SITE : INSPECTION
82
OIL FILLING CONTINUED…
• If the oil is not having the properties as
recommended by the standards,it must be
filtered with filters with built in heaters and
vacuum pumps for improving the quality of
oil.
• For transformers dispatched gas filled ,oil
filling must always be done under vacuum.
83
PRECAUTIONS DURING OIL FILLING
84
THANK
YOU !
85