Earned Value Management For Enterprise Resource Planning Implementations
Earned Value Management For Enterprise Resource Planning Implementations
Abstract
ERP implementations are a special breed of projects. They
are often characterized by aggressive timelines, high
budgets and involvement of diverse teams. This
emphasizes the need to have a reliable tool to measure
the performance of ERP implementations throughout the
execution phases.
Earned Value Analysis, with its basis in cost, benefit and
timeline is a good financial tool for Project managers. This
paper starts by establishing the key concepts of Earned
Value analysis. Metrics such as EV, PV, AC, CPI, SPI are
explained at an overview level. Earned value analysis is
then applied to the individual phases of a typical ERP
implementation using an illustrative project. Each phase of
the implementation such as, requirements gathering, is
then analyzed by giving an overview of the phase,
describing the major activities and then describing the
EVM(Earned Value Management) activities that need to
take place in that phase.
June 2008
Introduction
Enterprise Resource Planning (ERP) Implementations – A special breed of
projects
Embarking on ERP implementation is a daunting task for any enterprise due to its inherently
complex nature. The process often involves big budgets, long durations and large teams across
multiple organizational units (IT, Business, Infrastructure, etc.). This places a great amount of
stress on the IT and Business leadership involved. They are also a special breed of projects; they
are part technology and part business. The primary differentiating factor is the heavy involvement
of business and IT. Often, the primary reason for implementing a packaged ERP application is to
redesign the existing business processes into industry standard best-of-breed processes, with the
ability to scale up to the enterprise’s growth plans.
Given this unique nature of ERP implementations, the project management team assumes critical
importance in measuring, monitoring and reporting the project status accurately. Most project
managers engulf themselves in project plans, resource plans, risk registers, status reports and
more status reports. What is often missing in those reports is a standard way of measuring,
monitoring and reporting the status. In such a situation, project managers need all the tools and
techniques they can get. The earned value technique, tailored for ERP implementation, offers one
such performance measurement tool.
2. Assign values to each WBS Item, also called Planned Values (PV)
Allocate the total budget into the individual items
Pg 2
Once these basic steps are achieved, a project plan can be created to track the project. As the
tasks are started, the value earned can be tracked. Some of the common metrics available for
measurement are:
Planned Value (PV): is the Budgeted Cost for Work Scheduled (BCWS/ BAC) to be
completed on an activity or WBS Item up.
Actual Cost (AC): is the total cost incurred in accomplishing the work scheduled. This
must correspond to what was budgeted.
$250,000
$200,000
$150,000 Time
AC
EV
$100,000 PV
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
The chart above shows the interplay between the three components of the EV analysis.
Pg 3
$250,000
$200,000
SV In $
$150,000
Time
PV
In Time
EV
$100,000
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
$160,000
$140,000 CV
$120,000
$100,000
Time
$80,000 AC
EV
$60,000
$40,000
$20,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
The first two set of indicators measure the cost and schedule variance of the work accomplished.
The next two are efficiency indicators that can be used for forecasting the cost and schedule
performance.
Pg 4
ERP Implementation Phases Overview
Note: This section refers to the Infosys Package implementation methodology (Intrak), explaining the various
phases for a typical ERP Implementation.
Strategic Stage
Planning Phase
– Business Case preparation
Package Evaluation Phase
– Package solution options are generated and finalized
Organizing Phase
– Project organization, methodology and change management processes finalized.
This stage is the precursor to the project organization being formed. It is at this point that the
Budget for the entire implementation is usually identified at the high level.
Project Stage
• Project scoping
• Requirements Gathering
The individual phases and the nature of EVM for each phase has been discussed in the sections
below. For this purpose, an illustrative ERP project has been used.
Pg 5
Phase wise duration split
Scoping 2
Requirements 4
To Be Design 4
Total 18
Let us assume that these values were finalized during the strategic phase of the ERP
implementation.
Overview
The activities in this phase are directed towards a clear-cut definition of the project with respect to
its scope, requirements and resources.
Major Activities
Project Manager (Client) and scoping team selection
Project Scope definition
Project team formation
Project team requirements identification
Orientation Workshops
Project planning and sign-off
Formal kick-off
Pg 6
Earned Value Analysis Activities
This phase is key in establishing the basic building blocks for the EVM.
• WBS has to be built from the project scope definition
• WBS level, at which tracking will be done, has to be established.
Note: At this point in time, the project management does not have the detailed information for all the tasks.
Therefore, these values can later be refined during the requirements gathering stage.
• PVs have to be assigned to the WBS Items at the level at which planning will be done.
This has to be discussed and agreed upon with the business users during the scope
discussions.
• Earning rules for the WBS Items also have to be established in this phase.
• Finally, the Project Plan is created in this phase and it clearly establishes all the phases
and the duration of the entire implementation. This project plan will be key to tracking the
actual cost and earned values to the planned values.
All of the above steps will be represented in the Project measurement plan, which is usually
discussed with the key stakeholders during the Formal kickoff.
At this point, most of the actual cost goes into establishing the cost, scope and operational
baselines. EVs will also be toward the same tasks. The chart given below gives a graphical
representation of the S- Curves, showing the AC, EV and PV values. We will continue to monitor
these S-curves through the rest of the implementation phases
$250,000
$200,000
$150,000 Time
PV
AC
$100,000 EV
SCOPING
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
Pg 7
Requirements Gathering
Overview
The Core Business Processes (CBP), identified during Project Scoping phase, are used to derive
the “As-Is” processes. The high level gap analysis is carried out.
Major Activities
• Business Process Mapping
• Identification of sources of information
• Environment installation
• Training to core team (client) on specific modules
• Prepare for workshop
• Workshop to capture business processes
• High level Process mapping and Gap Analysis
• System Status Mapping
EVM Activities
This is the first phase where tracking costs, schedule and quality start to assume greater
importance.
• Project Plan is being tracked and updated on a regular basis - usually on a weekly basis.
• Actual Cost starts to accumulate in this phase and can be obtained by combining the
timesheet data, from the time tracking systems, along with resource cost details and other
material costs from the project accounting systems.
• Most of the actual costs at this point are licensing, hardware and software costs that will be
used throughout the course of the project.
• Schedule variance can be tracked at this point, using the EVs against the PVs.
• Tasks which have begun will get 20% EV, and completed tasks will get 100% as per the
20-80 earning rule.
• Total EV can then be calculated as
Pg 8
• Due to the complex nature of ERP implementation, the requirements phase usually runs
over budget. The key reasons for this are:
– Scope Change, due to new work item identification
– Complexity change, due to difficulty of getting information on existing process
– Lower productivity, due to team dynamics – the various members of the team are
working together for the first time and this could lead to lower productivity at the team
level
• In the chart below, the project is shown to be ahead of schedule and over budget.
$250,000
$200,000
$150,000 Time
PV
AC
$100,000 EV
SCOPING REQUIREMENTS
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
To-Be Design
Overview
The To-Be Design Phase involves key activities such as “To-Be” Process Design of the proposed
solution, Data Migration Design, Configuring the proto-type, and conducting the Conference
Room Pilot (CRP).
Major Activities
• To-Be Process Design
• Functional Specifications for Custom Components, Data Migration Programs
• Configure the Proto-Type
• Conduct CRP
Pg 9
EVM Activities
This is the phase where schedule and cost overruns have to be tracked with the utmost care.
• WBS Updates, if required, are done in this phase.
• All WBS Items are broken to the tracking level and their PVs are finalized
This phase is also a good time to start predicting/ forecasting the cost and schedule performance.
• This SPI can be used to forecast the completing of the design stage
• Additional CPI can be used for tracking the cost performance.
• CPI and SPI combined together give a very good tool to the project manager to tack
corrective actions.
In addition to tracking, correcting cost and schedule overruns, this phase also involves estimating
the total budget at cost.
END OF PROJECT
BAC = ΣPV
BEGINING
• The Budget at Completion (BAC) indicates the total PV for the project at completion
• Using the CPI and BAC, we can calculate the Expected Budget at Completion (EAC).
• The Estimate to Complete (ETC) is another key indicator to indicate the estimate of work
left to be completed before the project can go live.
Pg 10
• In the chart below, the project is shown to be tracked closer to the PV of the budget. Both,
the AC and EVs are approaching the PVs.
$250,000
$200,000
$150,000 Time
TO BE DESIGN
PV
AC
$100,000 EV
SCOPING REQUIREMENTS
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
Overview
Pg 11
Major Activities
• Technical Design and Development of all Custom components
• Final Configuration
• Training
• System Integration Testing
• User acceptance
• Data Migration of Master Data
EVM Activities
• This phase involves configuration of the actual application along with component
development
• This phase has peculiar characteristics as most of the work is technical in nature and
tracking such work becomes even more critical.
• The first half of configuration and development can be easily tracked using the ratios of
CPI/SPI, which is a good indicator of how the work is progressing.
• Any overruns are typical in nature, and the performance indicators are a good tool for the
project manager to predict the schedule and cost for this phase.
• Also, using the metrics of EAC and ETC, the estimated budgets can be forecasted
reasonably well.
• The second half of this phase is spent in testing. This phase too can be tracked using the
CPI/SPI indicators, since testing usually involves two critical activities -
– Test Execution
– Defect Resolution
• Both of the above activities are fairly predictable using the metrics available, such as
execution progress measured in test cases executed per day, or in case of defects -
defects resolved per day.
• The ACs and EVs start to approach closer to the PVs.
• Any deviations in this phase will result in overruns of cost and duration.
Pg 12
$250,000
$200,000
$150,000 Time
TO BE DESIGN
PV
AC
$100,000 EV
SCOPING REQUIREMENTS
$50,000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
Overview
The purpose of this phase is to ensure a smooth transition from the existing legacy system(s) to
the new system (installed package), and to establish a procedure for issue resolution. This
includes –
• Perform Freeze Period Activities and Cut-Over
• Verify that the activities in the ‘Go-Live Check List’ (system administration and
establishment of Help Desk activities that need to be communicated/ coordinated to the
client – including Go-Live Readiness) have been accomplished
• Go-Live and Post Production Support
• Project Closure and Sign Off
Major Activities
Pg 13
EVM Activities
This phase requires tracking all the costs and EVs to the PVs
Most of the costs for the project have been accrued and the values have been earned.
EAC will be approaching the BAC and ETC will be approaching zero
SPI/CPI over the entire project can be calculated for future projects
Lessons learnt throughout the project execution stages around earning rules, such as
what rules worked better for what system/team can be documented in this phase
Lessons learnt around the work breakdown structure, such as how much effort was
spent in breaking down a task to detail versus the benefit achieved in tracking the costs
at that level can be documented in this phase.
At this point, any contingencies in the budget will be utilized or released for other
projects.
$250,000
$200,000 C
U
T
O
V
$150,000 E Time
R
TO BE DESIGN
PV
A AC
N
$100,000 D EV
S
SCOPING REQUIREMENTS U
P
$50,000 P
O
R
T
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Months ->
Pg 14
Go live and Post Production Support
In this phase, the project goes live as per the cutover plan. Continuous monitoring is carried out
as per the established support process. All issues are captured using the production support
systems as opposed to the defect tracking systems used earlier in the project.
SPI and CPI, measured along the project duration, can be utilized for issue resolutions.
Additionally, any lessons learnt in measuring the performance of the entire project execution can
be passed on to the production support teams.
• Intimate all team members about the project closure date and obtain their concurrence
for the same
• Formally announce the closure of the project and take a sign-off from the PMO
Conclusion
Often, one of the biggest challenges in ERP implementations is the absence of a measurable
parameter for its success. EVM provides an excellent measurement tool that can not only help
during the implementation, but also in measuring the success of one project against another. An
area that EVM does not focus on is the quality aspect of the project. However, with a robust SEI
Capability Maturity Model (CMM) and a quality assurance at each phase, quality of the project
can also be closely monitored. EVM, along with the CMM assessments, can be a very helpful tool
in successfully implementing packaged applications.
Pg 15
About the Author
Venu Kotamraju
(Associate Business Manager, Enterprise Solutions, Infosys Technologies)
Venu has more than 8 years of experience in implementing packaged ERP solutions. His areas of
specialization include the package implementation methodology, ERP program management and
core financial, order to cash and procure to pay business process design. He has an exposure
to various industries such as Retail, Hi Tech and Financial services sectors. Presenting at the
Oracle Application User Group conferences in US and Australia, he has also co-authored Rapid
Retail Store Opening – An Oracle eBusiness Suite-based Solution.
He holds an MBA from IIM Bangalore, India and spent a term as an MBA exchange student at the
Kenan Flagler Business School at UNC, Chapel Hill. He also holds a degree in Electronics
Engineering from NIT (REC), Trichy.
Copyright in whole and in part of this document “Earned Value Management for Enterprise Resource Planning Implementations”
belongs to Infosys Technologies Limited. This work may not be used, sold, transferred, adapted, abridged, copied or reproduced in whole
or in part in any manner or form or in any media without the prior written consent of Infosys Technologies Limited.
Pg 16