Net Present Value and Other Investment Rules

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Chapter 5

Net Present Value and Other Investment Rules

McGraw-Hill/Irwin Copyright © 2013 by The McGraw-Hill Companies, Inc. All rights reserved.

Chapter Outline
5.1 Why Use Net Present Value?
5.2 The Payback Period Method
5.4 The Internal Rate of Return
5.6 The Profitability Index

5-1

5.1 Net Present Value


 The Net Present Value (NPV) of an
investment is the present value of the
expected cash flows, less the cost of the
investment.
 NPV = –Cost + PV = Initial Investment +
Total PV of future CF’s

5-2

1
5.2 The Net Present Value (NPV)
Rule
The basic investment rule can be generalized to
(Independent investments):
 Accept a project if the NPV is greater than
zero.
 Reject a project if NPV is less than zero

Mutually Exclusive Investments (Ranking


Criteria): Choose the highest NPV and NPV>0

5-3

Questions
 1b (page 162)

5-4

5.2 The Payback Period Method


 How long does it take the project to “pay
back” its initial investment?
 Payback Period = number of years to recover
initial costs
 Minimum Acceptance Criteria:
 Set by management
 Ranking Criteria:
 Set by management
5-5

2
The Payback Period Method
 Disadvantages:
 Ignores the time value of money
 Ignores cash flows after the payback period
 Biased against long-term projects
 Requires an arbitrary acceptance criteria
 A project accepted based on the payback
criteria may not have a positive NPV
 Advantages:
 Easy to understand
 Biased toward liquidity
5-6

Questions
 1a (page 162)

5-7

5.4 The Internal Rate of Return


 IRR: the discount rate that sets NPV to zero
 Minimum Acceptance Criteria:
 Accept if the IRR exceeds the required return
 Ranking Criteria:
 Select alternative with the highest IRR
 Reinvestment assumption:
 All future cash flows are assumed to be
reinvested at the IRR

5-8

3
Internal Rate of Return (IRR)
 Disadvantages:
 Does not distinguish between investing and
borrowing
 IRR may not exist, or there may be multiple IRRs
 Problems with mutually exclusive investments

 Advantages:
 Easy to understand and communicate

5-9

NPV versus IRR


 NPV and IRR will generally give the same
decision.
 Exceptions:
 Non-conventional cash flows – cash flow signs
change more than once
 Mutually exclusive projects
 Initial investments are substantially different
 Timing of cash flows is substantially different

5-10

Questions
 5,6

5-11

4
5.6 The Profitability Index (PI)

 Minimum Acceptance Criteria:


 Accept if PI > 1

 Ranking Criteria:
 Select alternative with highest PI

5-12

The Profitability Index


 Disadvantages:
 Problems with mutually exclusive investments
 Advantages:
 May be useful when available investment funds
are limited
 Easy to understand and communicate
 Correct decision when evaluating independent
projects

5-13

Questions
 8

5-14

5
Summary – Discounted Cash Flow
 Net present value
 Difference between market value and cost
 Accept the project if the NPV is positive
 Has no serious problems
 Preferred decision criterion
 Internal rate of return
 Discount rate that makes NPV = 0
 Take the project if the IRR is greater than the required return
 Same decision as NPV with conventional cash flows
 IRR is unreliable with non-conventional cash flows or mutually exclusive
projects
 Profitability Index
 Benefit-cost ratio
 Take investment if PI > 1
 Cannot be used to rank mutually exclusive projects
 May be used to rank projects in the presence of capital rationing

5-15

Summary – Payback Criteria


 Payback period
 Length of time until initial investment is recovered
 Take the project if it pays back in some specified period
 Does not account for time value of money, and there is an
arbitrary cutoff period
 Discounted payback period
 Length of time until initial investment is recovered on a
discounted basis
 Take the project if it pays back in some specified period
 There is an arbitrary cutoff period

5-16