Rec Erc 78 08
Rec Erc 78 08
Bureau of Reclamation
August 1978
MS-290 (l-76)
Bureau of Reclamation
TECHNICAL Rf EPORT STANDARD TITLE PAG
3. RECIPIENT’S CATALOG NO.
August 1978
Low Froude Number Stilling Basin Design
6. PERFORMING ORGANIZATION CODE
Same
S. SUPPLEMENTARY NOTES
6. ABSTRACT
Hydraulic model investigations were performed to supplement existing data and to develop
general design criteria for low Froude number stilling basins. A generalized basin design for
Froude numbers from 2.5 to 5.0 was developed from model tests and existing low Froude
number designs. The recommended design is a relatively short stilling basin with chute blocks,
baffle piers, and a dentated end sill.
). IDENTIFIERS--
by
Robert L. George
August 1978
Hydraulics Branch
Division of Research
Engineering and Research Center
Denver, Colorado SI METRIC
Page
Introduction ................................................................. 1
Previousstudies.. ......................................................... 1
Current Bureau studies .....................................................
Summary ................................................................... :
Laboratory model description .................................................
Test procedures .............................................................. f
Measurements and criteria for evaluation ......................................
Basin length and flow patterns .............................................. :
Waves ....................................................................
Efficiency ................................................................. i
Preliminary tests .............................................................
Natural basin tests ......................................................... 1
SAF basin test ............................................................ 5
Bureau Type IV ............................................................
Developmenttests.. ......................................................... 55
Basicflowpatterns ........................................................
Recommended design ........................................................ i
Chute blocks and baffle piers ............................................... 6
End sill and basin length ................................................... 7
Tailwater depth ............................................................
Energy dissipation ......................................................... ;
Design example ............................................................
Bibliography .................................................................
FIGURES
Figure
Current Bureau Studies A flume 760 mm deep, 760 mm wide, and 11.6 m
long was used for the study (fig. 3). An overflow
The foregoing generalized designs have not been crest was placed in the flume 330 mm above the
suitable for some Bureau applications and the floor. A 2:l inclined chute connected the crest to
increased use of low Froude number stilling the horizontal apron. The walls of the 8.5-m-long
basins has created a need for this information. center section of the flume were clear plastic to
This study was initiated to develop generalized allow visual observations from the side.
criteria for the design of low Froude number
hydraulic jump stilling basins. The criteria and
guidelines from the previous studies were The permanent piping in the laboratory supplied
combined with the results of this study to the water to the flume from the pump, and the
formulate the design guidelines recommended discharge was measured with venturi meters.
for low Froude number stilling basins. However, The discharge was varied for each test to obtain
it should be noted that a hydraulic jump stilling the desired Froude number. The theoretical
basin is not an efficient energy dissipator at low depth was 152, 68, and 24 mm for Froude
Froude numbers; that is, the efficiency of a numbers 2,3, and 5 respectively; the q(unit dis-
hydraulic jump basin is less than 20 percent for charge) for the same Froude numbers was0.371,
F<2.7. Alternative energy dissipators, such as 0.165, and 0.058 (mJ/s)/m, respectively.
the baffled apron chute or spillway, should be
considered for these conditions.
Depth measurements at the toe of the chute
(section 1 of fig. 3) were not possible for all
SUMMARY discharges because the tailwater covered the
lower portion of the sloping chute when the
This study was undertaken to consolidate the chute blocks were in place. Measurements were
knowledge of low Froude number stilling basins, made immediately upstream from the toe of the
and to supplement this with model tests to jump and were correlated to measurements at
develop design criteria for a stilling basin for section 1 without any appurtenances in place so
Froude numbers between 2.5 and 5.0. The the proper depth at section 1 could be estimated
recommended design has chute blocks, baffle with chute blocks in place.
piers, and a dentated end sill. All data are
presented in dimensionless form. The length is
rather short, approximately three times D2 (the TEST PROCEDURES
conjugate depth after the jump). The size and
spacing of the chute blocks, and baffle piersarea After reviewing the available data from refer-
function of D1 (incoming depth) and the Froude ences [l] through [5], preliminary tests were run
number. The dentated end sill is proportioned for a natural hydraulic jump stilling basin
according to 02 and the Froude number. The end (Basin I), a SAF stilling basin, and the Bureau
sill is placed at’or near the downstream end of the low Froude number basin (Basin IV).
stilling basin. Erosion tests were not included in
the development of this basin. Observations of
flow patterns near the invert downstream from The designs for the Palmetto Bend and SAF
the basin indicated that no erosion problem stilling basins recommend that baffle piers and
should exist. However, if hvdraulic model tests end sills be used. The SAF design recommends
are performed to confirm a design based on this that chute blocks be used in addition to baffle
2
piers and end sill. These designs were compared Basin Length and Flow Patterns
to Basins Ill and IV designs. The Basin Ill design,
for a Froude number of 5, was similar to the SAF Both the length and theflowpatterns in the basin
design and the Palmetto Bend design, both of are subjective observations and will vary from
which worked well. Therefore, a stilling basin observer to observer. The L (length of basin) was
was built according to the Basin Ill criteria for a taken as the longer of (1) the distance from the
Froude number of about 6.0, which performed toe of the chute to the point at which the high-
very well. Data extrapolated from the Basin Ill velocity jet leaves the floor, or (2) the ‘distance
design were used as the initial design for lower from the toe of the chute to a point immediately
Froude number tests. The size and location of the downstream from the surface roller. These
chute blocks, baffle piers, and end sills were criteria were used for the length of the jump both
varied from this extrapolated design to obtain the in EM25 and in this study.
best configuration for Froude numbers from 2.5
to about 6.0. The optimum size and placement of
the chute blocks were established first, and then The distribution of flow was observed with
various sizes and locations for the baffle piers particular attention to the velocity along the floor,
were tested. After the location and size of the The best flow pattern was the flow which had a
baffle piers and chute blocks were determined, stable jet that hit the baffle piers directly, re-
different sizes and shapes of end sills were tested sulting in:
near the end of the basin to determine the best lower velocities along the floor
size and location. the upstream toe of the jump locating near
section 1 (fig. 3).
a “smooth” water surface immediately down-
MEASUREMENTS AND CRITERIA stream from the hydraulic jump.
FOR EVALUATION
The parameters used to evaluate the perform- Specific energy at section 1 and section 2 (fig. 3)
ance of the various stilling basins tested were: was determined by measuring the depth and
discharge and computing E (specific energy)
basin length above the bottom of the flume from
energy dissipation
observed wave heights
tailwater depth near 0,
even distribution of flow throughout the basin (1)
with no stagnant or high-velocity flow
areas.
where
3
Efficiency of the stilling basin is defined as the discharge. These data were combined to form
difference of specific energy between sections 1 dimensionless ratios and are plotted as functions
and 2 divided by the energy at section 1. of the Froude number (fig. 4, 5, and 6) for the
basins tested.
The initial tests were performed on a natural (1) The front of the jump may have been main-
hydraulic jump stilling basin (Basin I) and on tained more completely on the sloping chute
stilling basins designed according to the SAF and during this study than the previous studies,
Bureau Basin IV criteria before tests were run to which would decrease the length of the hy-
develop a low Froude number stilling basin. The draulic jump.
eight Basin I tests were for Froude numbers from
2.7 to 6.0; the tests for the SAF and Basin IV
designs were for a specific Froude number. The (2) The differences between observations
existing basins were tested togain experience on made by different people may account for
performance of existing designs and to obtain some of the difference between the current
data to compare with later tests. data and the dashed line because each set of
data appears to be consistent within itself.
Natural Basin Tests The curve for the conjugate depth ratio, &/O, =
‘ii ( m - l), is a function of the Froude
The flow downstream from the Basin 1 design number and is plotted on figure 6. The data points
was quite smooth at low Froude numbersand the are bounded by the curves which correspond to
jump was maintained in the basin if the tailwater tailwater depths of 1 .l and 0.9 times 4.
depth was at least equal to 4. Sweepout
occurred (the hydraulic jump moved downstream
from the toe of the chute) in a natural basin when Tests that had ratios of ‘TW (tailwater depth) to 0,
the tailwater was about 3 percent lower than 4. higher than those shown, (fig. 6) had very little
energy dissipation even though the flow was very
smooth. Tests with a high TW/D, were observed
Two main disadvantages of using a Basin I design and the efficiencies computed; however, these
for low Froude number flows are: (1) the basin data were not recorded because of the small
length, 6 4, and (2) the relatively high-velocity amount of energy dissipation. if the tailwater
jet that exists along the floor may extend intoand depth was reduced below 02, a rough wavy
erode the downstream channel. surface developed and eventually the hydraulic
jump would sweep out of the stilling basin. The
best conditions for energy dissipation and flow
Preliminary test data included upstream and existed when the tailwater was at or slightly
downstream depths, length of the jump, and above 0~.
4
In summary, the following were characteristic of tests of this structure. The upper data point on
the natural basin (Basin I) design: (1) The length figure 5 is with the end sill and the lower point is
of the jump was about six times D2 and tailwater without the end sill.
was nearly equal to 02 (2) The velocity was
distributed uniformly over the depth except for
the high-velocity jet near the floor. (3) Usually, The flow approached critical depth across the
minimal waves occurred downstream from the solid end sill proportioned according to EM25. As
jump; however, surging waves occurred down- a result the flow alternately accelerated,
stream when the high-velocity jet oscillated reducing the depth, then raised back up to the
between the floor and the water surface. As a tailwater height immediately downstream from
result, channel erosion is likely to occur for a the end sill. This alternate decrease and increase
Basin I design because higher velocity flow in depth caused a very rough water surface .
stayed close to the floor. downstream from the end sill, which required a
longer stilling basin than would be required
without the end sill. The water surface was not as
SAF Basin Test rough and turbulent without the end sill. Ap-
parently, the end sill was too high for the Froude
A stilling basin was built and tested for a Froude number tested. The full conjugate depth was
number of 3.5 according to the SAF design required to keep the jump from sweeping out of
criteria [3]. The upstream face of the hydraulic the basin. The efficiency of the type IV basin was
jump was very rough. Waves and large slightly lower (fig. 4) than that for Basin I.
fluctuations in velocity occurred immediately
downstream from the baffle piers and caused a
rough wavy surface. The rough turbulent flow DEVELOPMENT TESTS
continued some distance downstream from the
end sill and much of the energy dissipation
occurred there. Consequently, the potential for The development of a low Froude basin design
scour downstream from an SAF stilling basin is started with the Basin Ill design and modified
high. Ribrap or other protection must be provided according to the results of model tests. Data
unless a scour hole is permissible. obtained during these tests included basin
length, upstream depth, tailwater depth, and
discharge. These variables were used to create
The length of the SAF stilling basin was shorter the dimensionless plots for the design criteria on
than the natural basin for the same Froude figures 5, 6, and 8.
number (fig. 5). but higher waves were observed.
The SAF basin is about 5 percent more efficient
(fig. 4) than the other basins. However, the SAF Basic Flow Patterns
basin is generally not more efficient than a
natural hydraulic jump stilling basin. The Several different types of flow patterns were
increased efficiency shown was mainly caused observed in the stilling basins. Without chute
by the inadvertently lower tailwater set during blocks the jet hit the floor at a downward angle,
the SAF test. At section 1 most of the energy is deflected off the basin floor, and almost jumped
velocity head, while at section 2 most of the compl.etely over the baffle piers, making them
energy consists of pietometric head. As a result, ineffective. When chute blocks (fig. 7) were
higher energy losses than normal were com- placed at the toe of thechute, the jet wasdirected
puted between sections 1 and 2 (fig. 6) because toward the vertical face of the baffle piers, which
the tailwater was slightly less than D2 for the test. increased the energy dissipation. However, if the
baffle piers were too close to the toe of the chute,
rough turbulent flow occurred between the chute
. Bureau Type IV blocks and the baffle piers, and the jet was
deflected upward along the upstream face of the
Oversize def;sctor blocks on the chute and an baffle piers. This vertical flow caused a boil above
optional solid r;nd sill characterize the Bureau the baffle piers and rough turbulent waves
Basin IV. The reccmmended length of the stilling downstream. As the baffle piers were shifted
basin for this structure is the same as for stilling downstream, a much smoother flow occurred and
Basin I. Two data points were recorded from the the downstream waves diminished. At the other
5
extreme, when the baffle piers were too far hit the channel floor, consequently, a dentated
downstream they were ineffective, and the jet- end sill is recommended instead of a solid end
,
like flow from the chute blocks oscillated sill to minimize erosion and provide a smoother
between the water surface and the floor of the flow downstream for a wider range of conditions.
stilling basin immediately upstream from the
baffle piers.
RECOMMENDED DESIGN
Baffle piers that ‘were too high caused a
secondary jump to occur downstream from them. This design was developed from the tests of the
If the baffle piers were too short; there was current study and from design criteria that have
insufficient energy dissipation. Placing the baffle been used successfully in previous applications.
piers downstream from the openings in the row The recommended design is a relatively short
of chute blocks produced a smoother flow than stilling basin (L equals approximately 3 4). with
when the baffle piers were not offset. As a result, chute blocks, baffle piers, and dentated end
the width and spacing of the baffle piers and sill (fig. 7).
chute blocks must be the same to obtain the exact
offset.
Chute Blocks and Baffle Piers
Changes in tailwater significantly affected the The recommended height and width of both the
flow downstream from the baffle piers. If the baffle piers and the chute blocks are equal to DI
tailwater depth was much below the conjugate and 0.70 0,. respectively. The recommended
depth, a high-velocity jet existed along the floor spacing between these piers or blocks is equal to
but did not increase the efficiency above the the width, that is, S = W = 0.70 &.
dashed line of figure 4. These high velocities
decreased as the tailwater approached the
conjugate depth and most of the kinetic energy in
The following relationship can be used to obtain
the flow was dissipated by turbulence in the
N (the total number of blocks and spaces):
tailwater. Maximum energy dissipation resulted
when the tailwater was equal to oz. Energy
dissipation decreased as the tailwater was raised N _ Width - 2kW
above D2. As a result of the above, a tailwater (3)
W
slightly above the conjugate depth is preferred to
a low tailwater condition at the sacrifice of a where
slight decrease in efficiency.
k = fractional width of block equal to side
clearance, 0.375_<k$0.50
Either a solid or dentated end sill is often used to Width = total width of stilling basin
lift the high-velocity flow away from the floor of W = 0.70 0,
the channel downstream from the end sill and to
increase the stability of the hydraulic jump. End
sills that were too high caused rough flow and The N obtained should be rounded to the nearest
waves downstream. Small end sills generally odd number and then adjusted values of either or
allowed more erosion because the water flowed both Wand k can be computed.
over the end sill, turned downward, and
eroded the channel downstream from the basin.
The baffle piers should be placed in line with the
openings between the chute blocks to increase
Rougher flow occurred with a solid end sill than their effectiveness and to decrease the waves.
with a dentated end sill of the same height. The The clear space between the sidewall and the
dentated end sills tended to improve the mixing of chute blocks should not be less than 0.375 W nor
the higher energy water with the surrounding greater than 0.50 W. Usually, no baffle piers will
water and produced a better velocity distribution be placed within 1.375 W of the sidewall.
downstream from the end sill. Also a dentated However, if the blockage (summation of the
end sill reduced the tendency for the flow to widths of baffle piers divided by the width of the
6
channel) is less than 0.40, then partial sections of Tailwater Depth
the baffle piers could be placed along the sidewall
to obtain approximately 0.50 blockage. Any A tailwater depth of D: maintained the jump at
configuration with less than four baffle piers will the intersection of the horizontal apron and the
need partial baffle piers placed along the chute. However, sweepout did not occur for the
sidewalls to obtain the necessary blockage. recommended design when the tailwater was
Blockage should be kept between 0.45 to 0.55. 0.8 of Dz. The TW (tailwater depth) should be
When more than four baffle piers were tested, no maintained at or slightly higher than D2(five per-
difference in performance was noted when cent or less). The additional depth increases the
partial side piers were in place, thus the partial factor of safety against sweepout and decreases
side piers would usually not be needed. the flow velocity.
Energy Dissipation
The location of the chute blocks and baffle piers is
shown in figure 7. The distance from the chute The energy loss ratio (EL/E,) is shown (fig. 4) as a
blocks to the baffle piers (X in fig. 8) varies from function of the Froude number. These data are in
1.3 to about 0.7 times Dz as the Froude number agreement with the theoretical curve for higher
varies from 2.5 to 5.6. Froude numbers and are slightly belowthis curve
for lower Froude numbers. The energy loss in a
hydraulic jump stilling basin is less than 20
percent for Froude numbers less than 2.7;
End Sill and Basin Length therefore, it may be better to use another type of
energy dissipator. For example, a baffled apron
spillway is a more efficient energy dissipator for
The dimension L&he distance from the toe of the
Froude numbers below three.
chute to the upstream side of the end sill) may be
obtained from figure 8. L, plus the length of the
end sill is somewhat shorter than L for Froude
Design Example
numbers greater than 3 and almost equal toL for
Froude numbers less than 3. The additional The following calculation describes the design
length beyond the end sill was required for
of a stilling basin according to the recommenda-
acceleration and deceleration of the flow.
tions of this report. The resulting structure is
However, the distance LI plus the length of the
shown (fig. 9) with dimensions.
end sill might be slightly longer than L for Froude
numbers less than 2.7. The stilling basin must be
extended to include the end sill for the latter.
Design of stilling basin for: Q = 62.77 (ma/@/m,
D, = 2.74 m, and a basin width of 112.8 m.
7
1. Lz3.1 D2 (from fig. 5) = 3.1 (15.8) = 49m Dentates should be placed against either
2. XsO.97 D2(fromfig.8)=0.97(15.8)=15.30m sidewall.
3. L1z2.24 D*(fromfig. 8)=2.24(15.8)=35.4Om
d. Therefore, the sill will have 49 blocks f
4. Design of chute blocks and baffle piers
and spaces, each 2.302 m wide.
a. height = 01 = 2.74 m
b. W= 0.70, = 1.92 m tentative value’ e. The top of the end sill piers = 0.2 times the .
c. The number of blocks and spaces end sill height = 0.2 (3.16) = 0.63 m.
8
D,- Depth of flow on chute / /
\
actional space
w= k~x. tooth width
20, ,minl Space=2.5 w
‘. .’.:-. .
..d . .~:\Jy.$i: ‘-‘o
:.‘~‘r:-:‘:‘a:‘:..::.:o:.‘...~:~:,~...~::ii:~$~::;&.
. . . . _. . ..* .,*. .
L . . ::.:. ::,
l-
3
hs
DI
2
9
rom loboratory recirculated
water supply
Tailwoter elevation
COlltl-0~ Q&O
/Wood heodbox side
d '.'O'.
.,. :,a.. .
:
‘.. :
‘, .' . . . ; :
0 . .
Sections .,
ELEVATION .4:
*so00
t
I
0 0 0
0 co
N 0
I 01
r :
Dimensions in mm
PLAN
6 8
7.0
V Design Ckve,‘Bweau
Basin I
-)- 1 --
6.0 /
0
/
/
/’
5.0 /I r7 e
/
/ 0
I/ 0 0 C
4.0
0”
\
-I
3.0
2.0
. - Test Data
I .o
0 - Natural Basin Tests
. v - Bosin IP USBR
o- SAF Basin
.O I I
0 2 5 6 7
12
V- Type IX USER
0 - SAF Basin -
0 I 2 3 4 5 6 7 a
!!L
F =$n,
13
El
El
El
I
End sill J
I
Chute blacks/ \ Baffle piers
hute blocks
Toe of chute
* ELEVATION
14
X/D2
”
% a in 0
0 r
h) .
PJ W P
b -0 b b
b/D2
Figure 9.-Example of recommended design.
, *