Calculating Float
Calculating Float
Network Model
Supplemental Material for
Construction Management:
Planning and Scheduling
Early Start (ES) – the earliest time that an
The following information outlines the basic steps activity can start based on the latest of the Early
required to run calculations on a Precedence Network to Finish times of all its IPA’s
determine Early Start and Early Finish, Late Start and Early Finish (EF) – the earliest time that an
Late Finish, Float, and to identify the Critical Path. This activity can finish, calculated by adding the
discussion uses a beginning-of-day convention whereby activity’s Duration to its Early Start (EF = ES +
each activity starts and ends on the beginning of the Duration)
listed day; i.e. if an item begins on Day 10 and has a
duration of 1 Day, it will begin on Day 10 and end on Day Late Start (LS) – the latest time that an activity
11. All relationships used in this discussion are Start-to- can start without delaying the completion of
Finish relationships. the project, calculated by adding the Float of an
activity to its Early Start (LS = ES + Float)
1. Assign Early Start (ES) and Early Finish (EF)
a. Begin by assigning Day 1 as the Early Late Finish (LF) – the latest time that an activity
Start day of the first activity can be finished without delaying the
b. Calculate the Early Finish for this activity completion of the entire project, calculated by
by adding its Duration to its Early Start adding the activity’s Float to its Early Finish (LF
(EF = ES + Duration) = EF + Float)
c. The next activity on the network is Duration – the value assigned to an activity that
assigned an Early Start that is equal to represents the time it will take to complete that
the Early Finish of its Immediately activity
Preceding Activity (IPA)
i. In Figure 1 – The first activity Float – the amount of time that an activity can
begins on Day 1 and has a be delayed before it impacts the completion
Duration of 2 days, so its Early date of the project (also referred to as Total
Finish is the beginning of Day 3, Float)
meaning the next activity can
Lag – the amount of time that exists between
start at the beginning of Day 3 –
the Early Finish of an activity and the Early Start
remember when doing this by
of its successor activity (LAGAB = ESB – ESA)
hand to stick with a single
convention (in this case Critical Path – the sequence of linked activities
beginning-of-day) when for which the Float value of each activity in the
referring to activities path is zero