Application For Accord of Administrative Approval For Construction of Bridge 1x40M Trussed Girder Foot Bridge

The document is an application for approval to construct a replacement footbridge near a girls' high school in Shopian district, Kashmir. The original footbridge was washed away in 2014 floods, cutting off the village. The proposed replacement is a 1x40m trussed girder bridge with a chequered plate deck to provide connectivity for 50,000 people. It will have open foundation RCC abutments, a steel girder superstructure, and asphalt wearing coat. The estimated cost is Rs. 91.84 lacs and it will take two working seasons to complete, subject to funding availability.

Uploaded by

hakim imtiyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views2 pages

Application For Accord of Administrative Approval For Construction of Bridge 1x40M Trussed Girder Foot Bridge

The document is an application for approval to construct a replacement footbridge near a girls' high school in Shopian district, Kashmir. The original footbridge was washed away in 2014 floods, cutting off the village. The proposed replacement is a 1x40m trussed girder bridge with a chequered plate deck to provide connectivity for 50,000 people. It will have open foundation RCC abutments, a steel girder superstructure, and asphalt wearing coat. The estimated cost is Rs. 91.84 lacs and it will take two working seasons to complete, subject to funding availability.

Uploaded by

hakim imtiyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Application for Accord of Administrative Approval

for
Construction of Bridge 1x40M Trussed Girder Foot Bridge
Name of work : Construction of 1x40 M Trussed Girder Bridge
Chequered plate Decked Bridge over Tongry Nallha
Near Girls high School
Constituency : Watchi
Name of District : Shopian.
Authority : Chief Engineer PWD (R&B) Kashmir
1). History & Necessity:- The RCC Footbridge at Tongry
Nallha Zanipora near Girls high School was washed away due to
floods of Sept. 2014. The village got cut off from the main road causing
great inconvenience to vehicular movement and general public. There
is urgent necessity of construction of Footbridge at Zanipora near Girls
school to give connectivity to mitigate the sufferings of inhabitants.
The footbridge will benefit about 50,000 souls.

2). Proposals:-
a). Sub-structure: There is boulder strata all along and
around the Bridge site, as such open foundation
and RCC abutments are proposed with proper
protection work both on the upstream as well as
downstream sides of Bridge.

b). Super-structure: The super-structure is proposed


to be steel Girder bridge laid over with chequered
plate decking.

. Asphaltic concrete wearing coat as per the clause 2702.1


of MORTH specifications with 2.5% slope on either
side of the centre of the bridge will be provided.
Railing is proposed to be provided in steel having a
clear height of 1.10 m supported over kerbs with
total width of 0.30m. Reinforced concrete approach
slab covering the entire width of the roadway shall
be provided having 0.30m thickness and 3.5m
length. Drainage along longitudinal direction shall
be ensured by drainage spouts.
3). Project Cost:-
The estimated cost of the project is Rs. 91.84 Lacs

4). Time of Completion:-


The project shall be completed in two working seasons
subject to availability of funds.

Asstt. Executive Engineer Executive Engineer


R&B Zainapora Sub Division R&B Division Shopian

Superintending Engineer Chief Engineer


(R&B) Circle Pulwama/ Shopian PWD (R&B) Kashmir