Are Binding' Dab Decisions Enforceable?: Taner Dedezade
Are Binding' Dab Decisions Enforceable?: Taner Dedezade
Taner Dedezade
Corbett & Co
International
decisions enforceable?
Construction Lawyers
Ltd, London
inappropriate devices to allow enforcement money. The employer issued an NOD and
but suggests, obiter, that an interim award failed to pay the sum determined as due by
might be effective. the DAB. The contractor applied directly to
• The sole arbitrator in ICC Case 16949/GZ the ICC arbitral tribunal for a final award
concluded that damages could not include enforcing the DAB’s decision on the basis
the sum adjudged as due by the DAB and that there had been a breach of the fourth
so declined to enforce. paragraph of Sub-Clause 20.4. NB the
contractor did not first refer the failure to
pay as a second dispute to the DAB, nor did
The problem
the contractor refer the merits to arbitration.
The fourth paragraph of Sub-Clause 20.4 A majority of the arbitral tribunal gave a
of the FIDIC 1999 Red Book provides: ‘The final award finding the sum awarded by the
[DAB’s] decision shall be binding on both DAB to be due without considering the merits.
Parties who shall give effect to it unless The contractor applied to set aside the arbitral
and until it shall be revised in an amicable award. The High Court set aside the award on
settlement or an arbitral award.’ the basis that failure to pay (the second
If no ‘notice of dissatisfaction’ (NOD) is dispute) did not go to the DAB prior to
issued under Sub-Clause 20.4 within 28 arbitration. Other obiter comments were also
days of receiving the DAB’s decision, that made by Judge Ean in relation to whether the
decision becomes ‘final and binding’. The arbitral tribunal could enforce without a
General Conditions make express consideration of the merits. The contractor
provision via a referral to arbitration for appealed to the Court of Appeal and the
the enforcement (specific performance) appeal was dismissed on the basis that:
of DAB decisions that are final and binding ‘There appears to be a settled practice, in
in Sub-Clause 20.7. arbitration proceedings brought under
By contrast, the ‘general conditions’ make sub-cl 20.6 of the 1999 FIDIC [Red Book],
no provision permitting the enforcement of for the arbitral tribunal to treat a binding
binding DAB decisions, that is DAB but non-final DAB decision as immediately
decisions where a notice of dissatisfaction enforceable by way of either an interim or
has been given by a party. Professor Nael partial award pending the final resolution
Bunni identifies this as a gap in the contract of the parties’ dispute. What the Majority
conditions in his article ‘The Gap in Sub- Members did in the Arbitration – viz,
Clause 20.7 of the 1999 FIDIC Contracts summarily enforcing a binding but non-
for Major Works’ [2005] ICLR 272 and final DAB decision by way of a final award
suggests that: without a hearing on the merits – was
• there is no remedy offered by Clause 20 of unprecedented and, more cr ucially,
the 1999 FIDIC Red Book, other than that entirely unwarranted under the 1999 FIDIC
of treating the non-compliant party as being [Red Book].’
in breach of contract and, accordingly, The Court of Appeal reasoned that:
liable for damages; and • A reference to arbitration under Sub-Clause
• Sub-Clause 20.7 of the 1999 FIDIC Red Book 20.6 in respect of a binding DAB decision
is of no assistance to the aggrieved party in this is in the form of a rehearing so that the
scenario as it applies only to DAB decisions entirety of the parties’ dispute(s) can finally
that have become final and binding. be resolved afresh.
• Sub-Clause 20.6 requires the parties fi nally
Singapore Court of Appeal to settle their differences in the same
arbitration, both in respect of the non-
On 13 July 2011, the Singapore Court of compliance with the DAB decision and in
Appeal dismissed an appeal of the decision respect of the merits of that decision. In
of the High Court in the case of CRW Joint other words, Sub-Clause 20.6 contemplates
Operation v PT Perusahaan Gas Negara (Persero) a single arbitration where all the existing
TBK [2011] SGCA 33. differences between the parties arising
The case concerned a pipeline project from the DAB decision concerned will be
under the FIDIC 1999 Red Book. Various resolved. This observation is consistent
disputes arose that were referred to the DAB. with the plain phraseology of Sub-Clause
The DAB decided, inter alia, that the 20.6, which requires the parties’ dispute in
‘employer’ owed the contractor a sum of respect of any binding DAB decision that