Chapter One: 1.1 Motivation
Chapter One: 1.1 Motivation
2014
CHAPTER ONE
INTRODUCTION
1.1 Motivation
Electric energy demand in Hawassa city is over increasing every year .So the previously installed power
transformer in distribution network of the city was not capable of carrying this over increased load. While
we practice six month industrial internship in southern region distribution; we saw many malfunction or
burnt power transformers that stored in the store of the office. Most of these malfunction happened due to
overload and over current. To combact this problem many option are there .Of these we come up with the
most cost effective and efficient project entitled ―automatic load sharing of power transformer using
microcontroller based relay in Hawassa city‖. In this project, a sharing transformer in the case of shares
the load of main transformer over load and over temperature. A sensor circuit is designed to log the data
from the main transformer and if it is found to be in over load condition, immediately the sharing
transformer will be connected in parallel to the main transformer and the load is shared.
To ensure increase market service value in terms of adequate quality and reliability, reduce cost of
operation and service interruptions, there is a need for an optimal solution or technique. This technique is
to ensure continuous dynamic load balancing along the low voltage secondary feeder thereby relieving
overload in the feeder with minimal service interruption; and reduced real power losses. The main duty of
this investigation is how unbalance due to uneven distribution of single-phase loads at the secondary side
of the distribution network can be minimized using automatic load sharing in Hawassa city.
The existing system presently is done manually by technician this result in damage of transformer. This is
a heavy loss to any grid or industries, here are even chances for the equipment to get damaged and power
interruption. There is a need for an optimal solution or technique for this problem.
Sub-Problem 1
The present method of reducing the degree of unbalance is the trial and error approach. In this method
take time and efforts are made to distribute single phase loads among the phases as uniformly as possible.
Most often this only ensures balance for a brief period since the loads supplied by each phase vary in a
random manner due to use at the point of utilization. The resultant effects of this approach are:
Inadequate service quality and reliability;
Power losses;
Voltage drop and high cost of operation.
Sub-Problem 2
To balance the phase currents in every segment and reduce the neutral line current is a very difficult task
for the distribution engineers considering that they do not have control over power utilization by the
This thesis describes about, how to use power supply when critical load happened. Using this module
someone can protect the transformer form the over load. This thesis describe how will connect and
disconnect the transformer automatically. Therefore, the following objectives are proposed to be achieved
during the course of this thesis:
Design of automatic load sharing of power transformer using microcontroller-based relay scheme
To test unwanted conditions (over current or overload) and when such conditions arise to share
overload condition in the shortest time possible
Investigate how rearrangement of consumers load can be carried out among the phases
Evolve techniques or system for ensuring continuous dynamic on-line load rearrangement with
minimal service interruptions; reduced power losses, and voltage drop.
Eliminate or reduce manual operations approach for improving load balancing on secondary
distribution network feeder.
Reduce the frequent blackout of the power system that severe the reliability of the system.
Create a simulation model and consequently carryout a study of the proposed technology and its
operation.
Provide low cost and reliable system
CHAPTER TWO
LITERATURE REVIEW AND FIELD SURVEY
2.1 Introduction
This chapter will discuss the study about significant effect of overload in Hawassa distribution system
network and some cite on this area.
At present load sharing of transformer is done in factory like Hawassa textile by paralleling the
transformers. This may causes increasing short-circuit currents that increase necessary breaker capacity,
the risk of circulating currents running from one transformer to another transformer, circulating currents
that diminish load capability and increased losses. This method is following on olden days also. The
challenge in paralleling modular supplies is to insure predictable, uniform current sharing-regardless of
load levels and the number of modules. It provide enhanced system reliability through complete
redundancy such that the failure of one or more modules could be tolerated as long as the total remaining
capacity is equal to or greater than the demands of the load.
2.2 Citation
Automatic transformer load sharing issues and remedies are relevant project topics and a lot of advanced
researches are being carried out in this area. These issues are mainly due to increased usage of power
system utility and unbalanced loads occur in power system. Dynamic loads cause power quality problems
usually by voltage or current variations such as voltage dips, fluctuations, momentary interruptions.
Various publications define transformer load sharing in different aspects.
The project entitled "power transformer protection using microcontroller designed with peripheral
interface controller (pic 16f877a)".This project is mainly used to protect transformer from getting worn
out due to electrical disturbances. The electrical parameters like current, voltage of the transformer are fed
as base values, using a keypad to the peripheral interface controller and the output signal is provided to
operate a relay comparing the base value with the operation electrical parameters.
"Transformer protection and monitoring" this project uses the distance protection function which is
used as back-up protection for faults within the transformer. This solution provides efficient protection
and control in facts installations. The distance protection function can also be used as back-up protection
for faults in the connected lines. The parameters related to line distance protection are mostly set as
primary ohms, which significantly reduce the need to re-calculate the current and voltage values. This
allows the IEDs to be quickly taken into operation.
Furthermore in 2007 S.M. Bashi et al, ―designed and built a microcontroller based system for power
transformer protection‖. The system includes facilities for discrimination between internal fault current
Overload: The city is on fast growing and its population increase rapidly from time to time. This is due
to establishment of different industries, and hotels resorts and public services. All mentioned above need
reliable and sustainable power to run their function properly. However, most of the transformer mounted
in the city cannot capable of carrying the over increasing load of the city. In addition the transformer
phases are loaded unequally to satisfy the customer need as customer desired. So, this over load that
comes from different utilities customer damage many of the city transformer.
Line-line or ground: This happened due to short circuit of the line in distribution net work. Most of the
city‘s network exposed for this faults. Since there are less trimming, sagging and animal and wind
protection in the network. On other hand, lightening is also the cause to this damage in the case of surge
failure.
Insulation failure: The two reasons explained so far is the causes for the insulation failure. This occurred
when internal temperature of the transformer increased and transformer over heated result in the
breakdown of dielectric strength (insulation) of the transformer.
Oil level decrease: Most of the time oil level of transformer checked by distribution technicians and
filled. But sometimes due to a number of transformers some transformers may not checked. As a result,
the transformer oil level drop and the cooling system fail. So the transformer over heated easily and
insulation break down that result in transformer internal damage.
Based on the above causes, we perform field survey on transformer overload in Hawassa city distribution
network.
IR IS IT IN IR IS IT IN
Atote Back trfo 200 25/03/06 2:16 226 171 147 152 31 80 99 52
AWA o4-T033 26/03/06 12:31 233 246 183 210 38 155 135 110
Back of Samuel market 315 26/03/06 2:25 301 347 280 140 75 121 102 76
Sileshi sefer 315 27/03/06 1:27 240 335 268 267 45 244 220 167
AWA 04T-o14 10/04/06 1:20 265 321 220 221 70 230 172 121
24/04/06 1:15 302 314 195 211 107 223 147 111
Konboni 200 5/04/o6 1:25 355 241 153 144 160 150 105 44
AWA 01T-056 20/06/06 2:30 350 264 235 224 155 173 187 124
Dato Giyorgis tapela 100 28/03/06 1:55 305 251 158 180 110 160 110 80
AWA 06T-055
The transformer to function properly, without any defect its phases, boxes and pillar must be equally
loaded (balanced) i.e. IR=IS=IT. The current in neutral line also have to be zero (no current flow in the
neutral line i.e. IN=0). As shown on the table from collected data all transformer phases are unbalanced.
Each phases of transformer carrying different value of current. And the two boxes of the transformer also
Depending on the collected data above many transformers are burnt out and being out of service. Of these
transformers some are explained while they are checked by MEGGER.
N.B 1. When meager transformer high tension with high tension, high tension with ground and high
tension with low tension. We set adjust (calibrate) the Meagher at 5KV.
2. When low tension with low tension, low tension with ground and low tension with neutral we set
adjust the Meagher at 0.5KV.
For instance, the transformer mounted around dato area by rehabilitation was burnt on the 02th
April 2006 EC. We went with the technique group and investigate the following events.
The Meagher result shows that the transformer S-phase low voltage side has no output and the
transformer low voltage side grounded with transformer body. Consequently, the transformer damaged
(burnt). It must be replaced by other transformer to give service for the customer.
We have gather data like what we have discussed so far on different area of transformer such as 2-07
kebele sefere selam, 1-01 kebele regional finance office, 2-07 kebele new market(Addis Gebeya)
traditionally begtera etc. All shows their major cause of damage is over load. So we came with this
critical (essential) project to combact this problem.
Fault impose hazard to both user and the system itself and when it comes to user, life is the concern and
when it concern the system it is merely to provide stable Electrical power system on top of that prevent
damage to the expensive equipment used. In summary, the needs of power protection are explained in
table 2.2 below. Table 2.2 Protection system
Equipment Safe guard the equipment from over current, over voltage and frequency drift th
can cause damage
General safety Prevent secondary accident that result from power system fault such as fire
Power supply stability Ensure that continuous and stable electrical power supplied by the system/grid
Operation cost Ensure that the system is operating at optimal efficiency and reduce equipme
maintenance
CHAPTER 3
DESIGN OF AUTOMATIC LOAD SHARING OF POWER TRANSFOMER
3.1 Introduction
Automatic load sharing of transformers is an integral part of the power system control process, allowing
smooth and immediate transfer of electrical current between multiple sources and the load. Here we are
using two transformers TF1 Main transformer and TF2 sharing transformer. The transfers switch senses
when utility power increases more than rating of transformer1, then starts up the transformer TF2 which
acts as a sharing transformer. The transfer switch continues to monitor utility power, and when it is less
than the rating of TF1 then sharing transformer will cut off from load and switches the load from the
Transformer TF2 back to the Main transformer TF1. Once the Transformer TF2 is disconnected, it goes
through a cool-down routine and is automatically shut down.
Automatic load sharing of Transformers is to satisfy the above needs with an extent. The present system
is designed around two transformers. One transformer TF1 is used as the main supply and the other
transformer TF2 is used as sharing transformer. These two transformers are connected with the relay
which is controlled by the embedded controller. The loads are connected to the main line TF1 and as well
as to the TF2 through relay.
Initially TF1 is connected to the load, the loads run with this power. If the load on transformer 1 is
increase beyond its rating then controller will find out that and it will connect the sharing transformer
parallel to the main transformer. And controller will continuously monitor the current flowing in the load
and when the load current decreases below the TF1 rating then it will turn off the sharing transformer.
Here we are using current transformer CT for measuring and protecting the load current, and the output of
CT is given to ADC for converting analog output of CT into digital data. That ADC output is given to
microcontroller for monitoring purpose. When current are beyond certain limit then we are going to
sharing transformer.
While most modern-day power supplies can be paralleled for higher currents, the load current will not
share equally between modules without some extra effort in the design process. With unequal load
sharing, the stress placed on the individual modules will be unequal; resulting in some units operating
with higher temperatures contributor to reduced reliability .Therefore, the challenge in paralleling
modular supplies is to insure predictable, uniform current sharing of modules. Another major goal should
be to provide enhanced system reliability through complete redundancy such that the failure of one or
more modules could be tolerated as long as the total remaining capacity is equal to or greater than the
demands of the load.
Power supply
LCD
Microcontroller
Transformer1
Relay
ADC
sharingTransfor
mer2
3.2.4 IC Regulator
An IC regulator is an electrical regulator designed to automatically maintain a constant voltage level. A
voltage regulator may be a simple ―feed-forward‖ design or may include negative feedback control loops.
Negative voltage regulators are available, mainly for use in dual supplies. Voltage regulator ICs are
available with fixed (typically 5, 12 and 15V) or variable output voltages. They are also rated by the
maximum current they can pass.
Most regulators include some automatic protection from excessive current ('overload protection') and
overheating ('thermal protection').It may use an electromechanical mechanism, or electronic components.
Depending on the design, it may be used to regulate one or more AC or DC voltages.
Basic operation
The EMRs have three components: the coil, spring and contacts. A digital +5V can control a 220Vac
transformer 2, without any physical contact between them. When current flows through the coil, a
magnetic field is created around the coil (the coil is energized), which causes the armature to be attracted
to the coil. The armature‘s contact acts like a switch and closes or opens the circuit. The relay serves as
the protective device of the entire system. The relay receives trip signal from the microcontroller and
thereby connect the transformer 2 secondary from the input ac to the load.
For example, the transfer of electricity efficiently over a long transmission line requires the use
of high voltages. At the receiving end where the electricity is used, the high voltage has to be
reduced to the levels required by the consumer. Transformers enable these changes in voltage to
be carried out easily, cheaply and efficiently. We normally use the step down transformer that
converts 15kv to 220v AC supply.
A transformer consists of two coils electrically separate but linked by a common magnetic circuit
of low reluctance formed by a laminated soft iron core. If one coil (the primary coil) is connected
to an AC supply, an alternating magnetic flux is set up in the iron core. This alternating magnetic
flux passes through the secondary coil and induces and alternating voltage in the secondary coil.
The magnitude of the secondary voltage is directly proportional to the ratio of the number of
turns in the secondary and primary windings and to the primary voltage.
Assume no-load voltages EA and EB are identical and in phase. Under these conditions if the primary and
secondary are connected in parallel, there will be no circulating current between them on no load.
The Figure shows two impedances in parallel. Let RA, XA and ZA be the total equivalent resistance,
reactance and impedance of transformer A and RB, XB and ZB be the total equivalent resistance, reactance
and impedance of transformer B.
CHAPTER 4
INTERFACING OF MICROCONTROLLER AT89C51 WITH ADC0804
AND LCD LM016
4.1 MICROCONTROLLER AT89C51
The AT89C51 is a low-power, high-performance CMOS 8-bit microcomputer with 4K bytes of Flash
programmable and erasable read only memory (PEROM). The device is manufactured using Atmel‘s
high-density nonvolatile memory technology and is compatible with industry-standard MCS-51
instruction set and pin out. The on-chip Flash allows the program memory to be reprogrammed in-system
or by a conventional nonvolatile memory programmer.
By combining a versatile 8-bit CPU with Flash on a monolithic chip, the AT89C51 is a powerful
microcomputer which provides a highly-flexible and cost-effective solution to many embedded control
applications.
A Micro controller consists of a powerful CPU tightly coupled with memory RAM, ROM or EPROM,
various I/O features such as Serial ports, Parallel Ports, Timer/Counters, Interrupt Controller, Data
Acquisition interfaces-Analog to Digital Converter ADC, Digital to Analog Converter (ADC), everything
integrated onto a single Silicon Chip. It does not mean that any micro controller should have all the above
said features on chip, Depending on the need and area of application for which it is designed, The ON-
CHIP features present in it may or may not include all the individual section said above. Any
microcomputer system requires memory to store a sequence of instructions making up a program, parallel
port or serial port for communicating with an external system, timer / counter for control purposes like
generating time delays, apart from the controlling unit called the Central Processing Unit.
Functions of micro controller
Sends appropriate commands to ADC to start conversion,
Collects the output of ADC for every 10 sec and stores in buffer,
After data gets transmitted sends command for disconnection
Sends appropriate information to the display unit as per status of the communication medium
RST:
Reset input. A high on this pin for two machine cycles while the oscillator is running resets the
device.
ALE/PROG:
Address Latch Enable output pulse for latching the low byte of the address during accesses to external
memory. This pin is also the program pulse input (PROG) during Flash programming.
PSEN:
Program Store Enable is the read strobe to external program memory. When theAT89C51 is executing
code from external program memory, PSEN is activated twice each machine cycle, except that two PSEN
activations are skipped during each access to external data memory.
EA/VPP:
External Access Enable (EA) must be strapped to GND in order to enable the device to fetch code from
external program memory locations starting at 0000H up to FFFFH. Note, however, that if lock bit 1 is
programmed, EA will be internally latched on reset. EA should be strapped to VCC for internal program
executions. This pin also receives the12-volt programming enable voltage (VPP) during Flash
programming, for parts that require 12-volt VPP.
XTAL1:
Input to the inverting oscillator amplifier and input to the internal clock operating circuit.
XTAL2: Output from the inverting oscillator amplifier.
V ref VDD
Sampling clock
ADC DTA
OUTPUT
Analog input
The reference input terminal of an ADC may be buffered as shown in Figure above in which case it has
input impedance (usually high) and bias current (usually low) specifications, or it may connect directly to
the ADC. In either case, the transient currents developed on the reference input due to the internal
conversion process need good decoupling with external low inductance capacitors.
The sampling clock input is a critical function in an ADC and a source of some confusion. It could truly
be the sampling clock. This frequency would typically be several times higher than the sampling rate of
the converter. It could also be a convert start (or encode) command which would happen once per
conversion. Regardless of the ADC, it is extremely important to read the data sheet and determine
exactly what the external clock requirements are, because they can vary widely from one ADC to another.
In ADCs, this line is variously called busy, end-of-conversion (EOC), data ready, etc. Regardless of the
ADC, there must be some method of knowing when the output data is valid—and again, the data sheet is
where this information can always be found.
Another detail which can cause trouble is the difference between EOC and DRDY (data ready). EOC
indicates that conversion has finished, DRDY that data is available at the output. In some ADCs, EOC
functions as DRDY—in others, data is not valid until several tens of nanoseconds after the EOC has
become valid, and if EOC is used as a data strobe, the results will be unreliable.
Our ADC0804 is a single channel analog to digital convertor i.e., it can take only one analog signal. An
ADC has n bit resolution (binary form) where n can be 8,10,12,16 or even 24 bits. ADC 0804 has 8 bit
resolution. The higher resolution ADC gives smaller step size. Step size is smallest change that can be
measured by an ADC. For an ADC with resolution of 8 bits, the step sizeis19.53mV(5V/255).
The time taken by the ADC to convert analog data into digital form is dependent on the frequency of
CHAPTER FIVE
SIMULATION AND RESULT
We use two most known software for simulation of our project; that compatible to design component of
automatic load sharing of power transformer. For construction of the schematic diagram of the project we
applied proteus and compile our code by keil.
5.1 Proteus
Proteus is a single application with many service modules offering different functionality (schematic
capture, PCB layout, etc.). The wrapper that enables all of the various tools to communicate with each
other consists of three main parts.
Application Framework: This is the framework or container which hosts all of the functionality of
Proteus. ISIS, ARES, 3DV all open as tabbed windows within this framework and therefore all have
access to the common database.
Common Database: The common database contains information about parts used in the project. A part
can contain both a schematic component and a PCB footprint as well both user and system properties.
Live Net list: Together with the common database the maintenance of a live net list allows all open
modules to automatically reflect changes. The most obvious example of this is wiring in ISIS producing
rats nest connections in ARES but it goes much further than that. The new Bill of Materials module
contains a live viewer and the 3D Viewer and Design Explorer are also linked into the live net list.
5.2 Keil cross C Compiler
KEIL can be used to create source files; automatically compile, link and covert using options set with an
easy to use user interface and finally simulate or perform debugging on the hardware with access to C
variables and memory.
Unless you have to use the tolls on the command line, the choice is clear. KEIL Greatly simplifies the
process of creating and testing an embedded application. The Keil Software 8051 development tools
listed below are the programs you use to compile your C code, assemble your assembler source files, link
your program together, create HEX files, and debug your target program. µVision2 for Windows™
Integrated Development Environment: combines Project Management, Source Code Editing, and Program
Debugging in one powerful environment.
C51 ANSI Optimizing C Cross Compiler: creates relocatable object modules from your C source
code,
5.3 Simulation
Figure 5.1 Simulation block diagram of the whole scheme of the project
CHAPTER SIX
CONCLUSIONS AND FUTURE RECOMMENDATION
6.1Conclusions
The project describes about how to use power supply intelligently under peak loads. The project
automatically connects and disconnects the sharing transformer thus protecting the main transformer from
overload. Current transformer plays an important role by sensing the current through the load and sending
feedback signal to the microcontroller through ADC. Microcontroller is so programmed that as soon as
the load exceeds a particular current limit it will soon generate a control signals and the signal is fed to the
electromagnetic relay. The switching process occurs in the Electromagnetic Relay which automatically
connects the transformer in parallel in accordance to the load sensed by the CT.
Through the transformer current analysis we can see that the current of the transformer rises as load
increases, whenever the load current goes above the transformer rated current, the microcontroller detects
an over current and it sends a trip signal to relay thereby the load shared automatically by transformer two
and protecting the transformer one from burning. As the load current goes below the rated current of the
transformer, the microcontroller detects normal there by sending an on signal to the relay to disconnect
the sharing transformer. The results indicate that the microcontroller based transformer automatic load
sharing achieves numerous advantages over the existing systems in use: 1) fast response, 2) better
isolation, 3) accurate detection of the fault. Finally, the results of simulation meet the aim and objectives
of the project and automated with no manual interface required.
REFERENCES
Books
Badri ram and D N Vishwakarma (1995); power system protection and switch gear New delhi:
Tata Mc Graw hill
Muhammad Ali Mazidi and Janice Gillispie Mazidi; The 8051 Microcontroller and Embedded
Systems; Chung-Ping Young Taiwan
Loading Considerations When Paralleling Transformers Application Guide(2007); Nashville, TN,
USA
Electrical Machines, Second Edition
Website
http://seminarprojects.com/Thread-automatic-transformer-distribution-and-load-sharing-system
http://www.asciitable.com/ Interfacing LCD with 8051 Microcontroller using Keil C - AT89C51.htm
http://embedded-microcontroller-project
http://Transformer_protection_monitoring_and_control.pdf
https://sites.google.com/site/coolembeddedlaboratory/home
APPENDIX
C Code for the whole thesis
#include <REGX51.H>
#include<stdio.h>
#include<string.h>
sbit INTR = P3^5;
sbit RD_ADC = P2^4;
sbit WR_ADC = P2^3;
sfr MYDATA = 0x80; //Port-0
sfr LcdData = 0x90; //Port-1
sbit RS = P2^5;
sbit RW = P2^6;
sbit EN = P2^7;
sbit relay=P2^0;
void lcdcmd(unsigned char value);
void lcddata(unsigned char value);
void lcdstr(unsigned char msg[]);
void Delay(unsigned int itime);
void SerTX(unsigned char x);
void SerTX_str(unsigned char msg[]);
unsigned char msg[] = "detect >";
void main()
{
unsigned int curr;
int hundreds,tens,ones;
unsigned char buffer[10];
TMOD = 0x20; //Timer-1, 8-Bit Auto Reload Mode
TH1 = 0xFD; //9600 Baud Rate When Crystal Used is 11.0592MHZ
SCON = 0x50;
TR1 = 1; //Start Timer
MYDATA = 0xFF; //Making P1 as Input Port
INTR = 1;