Contract Sum Analysis: Total Carried To Form of Tender
Contract Sum Analysis: Total Carried To Form of Tender
MENYELENGGARA RUMAH TERES MAMPU MILIK 1 TINGKAT ( 220 UNIT ) SERTA KERJA -
KERJA BERKAITAN DI ATAS TANAH KERAJAAN DI BANDAR SERI BANDI, DAERAH
KEMAMAN, TERENGGANU DARUL IMAN
……………………………………………………………………………………………………………………….
…………………………………………………. ……………………………………………….
Signature Of Contractor Signature of Witness
………………………………………………….. ………………………………………………
( Company's Name & Address ) ( Company's Name & Address )
………………………………………………….. ………………………………………………
………………………………………………….. ………………………………………………
………………………………………………….. ………………………………………………
Date :………………………………….. Date : …………………………………
CSA/1
MEREKABENTUK, MEMBINA, MENYIAPKAN, MENGUJI, Ringkasan
MENTAULIAH DAN
MENYELENGGARA RUMAH TERES MAMPU MILIK 1 TINGKAT ( 220 UNIT ) SERTA
KERJA-KERJA BERKAITAN DI ATAS TANAH KERAJAAN DI BANDAR SERI BANDI ,
DAERAH KEMAMAN, TERENGGANU DARUL IMAN
RINGKASAN HARGA
A PRELIMINARIES 1,047,800.00
B EARTHWORK ( Provisional Quantity ) 1,908,000.00
C PILING WORKS ( Provisional Quantity )
0.00 0.00
D BUILDING WORKS area cost/m2
Rumah Teres Mampu milik 1
i. tingkat ( 220 unit, area 1 unit = 16,643.00 820.00 13,647,260.00
75.65.m2)
F INRFASTRUCTURE WORKS
Infrastructure inside boundary 6,647,048.00
1 Site Clearance 84,000.00
2 Slope Protection 307,562.00
3 Roadworks and Hardstanding 1,861,725.00
4 Surface Water Drainage 1,464,000.00
5 Water Reticulation 539,000.00
6 Elevated Water Tank ( RC ) 684,000.00
7 Sewerage Work 733,000.00
8 Landscaping Works & Turfing 148,000.00
9 Refuse Bin ( 1.5m3 ) 42,000.00
10 Fencing and Gate 613,761.00
12 Playground Equipment 50,000.00
12 TNB Substation (Single Chamber ) 120,000.00
1
Ringkasan
RINGKASAN HARGA
J MISCELLANEOUS 36,000.00
Soil Investigation 36,000.00
2
MEREKABENTUK, MEMBINA, MENYIAPKAN, MENGUJI, MENTAULIAH DAN
MENYELENGGARA RUMAH TERES MAMPU MILIK 1 TINGKAT ( 220 UNIT ) SERTA
KERJA - KERJA BERKAITAN DI ATAS TANAH KERAJAAN DI BANDAR SERI BANDI,
DAERAH KEMAMAN, TERENGGANU DARUL IMAN
DATE: 25/07/2013
TOTAL EARTHWORKS
(To be carried to Item 2.0, Contract Sum Analysis Table) 1,908,000.00
APPENDIX 4c
1 . WBLFF 2,200,000.00
2 . APRON AND PERIMETER DRAIN 683,100.00
3 . FRAME 880,000.00
5 . ROOF CONSTRUCTION & FINISHES 3,685,000.00
6 . EXTERNAL WALL 836,000.00
7 . INTERNAL WALL AND PARTITION 550,000.00
8 . DOORS 506,000.00
9 . WINDOWS 683,320.00
10 . EXTERNAL WALL FINISHES 484,220.00
11 . INTERNAL WALL FINISHES 1,144,000.00
12 . EXTERNAL FLOOR FINISHES 88,000.00
13 . INTERNAL FLOOR FINISHES 286,000.00
14 . EXTERNAL CEILING FINISHES 66,000.00
15 . INTERNAL CEILING FINISHES 1,181,400.00
16 . SANITARY FITTINGS 261,800.00
17 . SUNDRIES 112,420.00
PDA/EWOB/1/1
MEREKABENTUK, MEMBINA, MENYIAPKAN, MENGUJI, MENTAULIAH DAN
MENYELENGGARA RUMAH TERES MAMPU MILIK 1 TINGKAT ( 220 UNIT ) SERTA
KERJA - KERJA BERKAITAN DI ATAS TANAH KERAJAAN DI BANDAR SERI BANDI,
DAERAH KEMAMAN, TERENGGANU DARUL IMAN
c Planner 50,000.00
1 PRELIMINARIES 1,047,800.00
2 PILING/ SPECIAL FOUNDATION
Type and Size 0.00
0.00
0.00
3 BUILDING Drawing No. Floor Area M2 Cost/m2 13,647,260.00
a. Rumah Teres Mampu Milik 1
Tingkat (220 Unit) 16,643.00 820.00 13,647,260.00
PDA/1/3
PRELIMINARY DETAILED ABSTRACT 0.00 25/07/2013
BREAKDOWN OF PRELIMINARY COST ESTIMATE (Cont'd) COST RM
SUB-TOTAL brought forward 16,988,296.00
5 INFRASTRUCTURE WORKS 10,255,148.00
5.1 Infrastructure Work Within Lot Boundry
a. Earthwork 1,908,000.00
b. Site Clearance 84,000.00
c. Slope Protection 307,562.00
d. Roadworks and Hardstanding 1,861,725.00
e. Surface Water Drainage 1,464,000.00
] Water Reticulation 539,000.00
g. Elevated Water Tank ( RC ) 684,000.00
h. Sewerage Work 733,000.00
i. Landscaping Works & Turfing 148,000.00
j. Refuse Bin ( 1.5m3 ) 42,000.00
k. Fencing and Gate 613,761.00
l. Playground Equipment 50,000.00
m. TNB Substation (Single Chamber ) 120,000.00
Sub-Total 8,555,048.00
5.2 Infrastructure Work Outside Lot Boundry
a. Surface water drainage 906,000.00
b. Water reticulation 13,700.00
c. ACDC Lane 780,400.00
Sub-Total 1,700,100.00
6 PRIME COST AND PROVISIONAL SUM 142,100.00
a. Land Surveyor work including survey for quit Title 142,100.00
SUB-TOTAL 27,385,544.00
7 VARIATION OF PRICES -
8 CONTRIBUTION FEE TO LOCAL & UTILITY AUTHORITY 248,000.00
a. Sumbangan TNB 168,000.00
b. Sumbangan TELEKOM 10,000.00
c. Sumbangan SATU 10,000.00
d. Sumbangan MPK - Bangunan & civil 60,000.00
9 MISCELLANEOUS 36,000.00
a. Soil Investigation Works 36,000.00
10 CONTINGENCIES 0.00
ALL IN UNIT RATES (of Total items 1 to 10) TOTAL (items 1 to 10) 27,669,544.00
Total Flr Area m2 : 16,643 Cost/m2 : 1,662.53 cost/ft2 154.51
Total Flr Area per unit m2 : 75.95 cost per unit: 90,423.35
11 SUPERVISION 0.00
PDA/2/3
PRELIMINARY DETAILED ABSTRACT 0.00 25/07/2013
12 PROFESSIONAL FEES 2,411,377.33
a Architect
b. Civil & Structural Engineer
c. M & E Engineer 8.00% 2,213,563.52
d. Quantity Suurveyor
e Planner 50,000.00
f Lanscape Architect 15,000.00
g Government Servis tax 6% from fee 132,813.81
PDA/3/3
NOTES ON FILLING OF PRELIMINARY DETAILED ABSTRACT FORM (PDA)
1.1 The information given on this Detailed Abstract is for Government use only
1.2 No portion of the form is to be left blank. Item not applicable in any particular case shall have a dash inserted
against then. If any item is included under 'BUILDING' this shall be stated in the 'COST' column
2.1 Total Provision shall be the amount given by the Client Department as the amount approved for the project
and which shall be given together with the project brief. If this information is not available it shall be left blank.
3.1 Provision for Construction shall be the Total Cost of Project as shown. For revised PDA, Provision for
Construction Shall be the Total Cost of project in previously approved PDA
4.1 The following abbreviations shall be used in completing the 'Brief description of Building' :
CR - Cement GWB - Glass wool Board Pqt - Parquet TSM - Timber Framed
Rendering Screen Wall
Both the base material and the finish shall be given in the case of floors, wall and flat roofs, thus :
Con./VT RC/WCR
Both the base material or the type of suspension/framing and the finish shall be given in the case of ceilings,
thus :
T/WCB A1./WFB
4.2 The standard of the building relates to the general standard of finishes rather than to concsturction and shall
be given as one the following three categories :
5.1 Each type and size of Piling/Special Foundation and its cost shall be stated separately
6.0 BUILDING
6.1 The cost for the building shall be exlusive of all services
6.2 The building to be listed under item 3 shall refer to the some buildings as listed under 'Brief Description of
Building'.
6.3 The Floor Area Shall mean the Gross Floor Area of all enclosed spaces fulfilling the functional requirements
of the building measured flat on plan to the internal face the enclosing walls.
6.4 The Drawing Numbers to be stated shall only be those of the Architectural floors plans, section and
elevations. Structural and other detailed drawing numbers need not be stated
7.1 The cost for internal services shall be inclusive of Profit and Attended and all builders work in connection
therewith where applicable
8.1 The amount to be allowed for Variation of Price shall be based on the projected increase in the relevant
building cost index as issued by the Department of Statistics, or 5% of the Buider's work
9.0 CONTINGENCIES
10.1 The amount of Professional fees for each Consultant shall be inserted in the "Cost" column.