METHOD STATEMENT FOR Paving - Rev 0

This document provides a method statement for laying unit pavers and interlocking tiles for the Khalifa Port Interchange project. It outlines the responsibilities of various parties, pre-laying activities such as material procurement and site preparation, and the step-by-step procedure for laying including spreading sand, placing tiles, compacting, and edge restraints. It also lists the manpower, material, and equipment requirements and confirms health and safety provisions will be followed.

Uploaded by

Osama MZ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
708 views7 pages

METHOD STATEMENT FOR Paving - Rev 0

This document provides a method statement for laying unit pavers and interlocking tiles for the Khalifa Port Interchange project. It outlines the responsibilities of various parties, pre-laying activities such as material procurement and site preparation, and the step-by-step procedure for laying including spreading sand, placing tiles, compacting, and edge restraints. It also lists the manpower, material, and equipment requirements and confirms health and safety provisions will be followed.

Uploaded by

Osama MZ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 7

Client Consultant Main Contractor Sub Contractor

METHOD STATEMENT FOR LAYING


OF UNIT PAVERS/INTERLOCKING
TILES

Project Name: KHALIFA PORT INTERCHANGE

Scope of Work.: LANDSCAPE/IRRIGATION AND STORM WATER

Client: DEPARTMENT OF TRANSPORT

Consultant: MOUCHEL MIDDLE EAST LT.

Main Contractor : LARSEN & TOUBRO

Sub Contractor: AL JURF DEVELOPMENT PROJECTS LLC

REVISION HISTORY

0 Hafez
23/04/2013
Makdissi - Issued forAhmad
Approval
Deeb JDP-KPI-MS-/R0
Osama Zarzour
Rev Section(s Reference No.
Date DescriptionQA/QC
of Change
.Technical Engineer ) Project Manager
Authorized to Submit
Originated By Reviewed By By
Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

CONTENTS

1. Scope 3
2. References 3
3. Responsibilities 3
4. Procedure / Method to be Employed 4
5. Manpower Requirement 5
6. Material Requirements 6
7. Equipment Requirement 6
8. Health and Safety Provisions 6
9. Attachments 7

Page 2 of 7

KHALIFA PORT INTERCHANGE LANDSCAPE/IRRIGATION&STORMWATER


Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

1. Scope

 The scope of this method statement is to ensure that Hard Landscape unit pavers and interlocking tiles is
carried out using the approved procedure, which complies with the contract specifications.

 This method statement determines the procedure to be followed through out the Hard Landscaping works.

2. References

 Contract Specifications
 DOT. Environment, Health & Safety Management System (EHSMS)
 Al Jurf QHSE Management System and Project Specific Safety Plan

3. Responsibilities

 It is the Project Manager’s duty to ensure that all necessary safety and protective equipment are provided
along with the properly trained and qualified personnel.

 It is the QA/QC Engineer’s duty to ensure that the Method Statement Procedure is adhered to by all
personnel.

 It is the Site Engineer’s and the Foreman duty to organize the work in a safe manner, and in accordance with
the standards.

 It is the duty of Safety Officer (assigned Foreman) to supervise and monitor activities and perform as per the
guidelines of HSE standards.

 It is also the duty of Safety Officers (assigned Foreman) to report any accidents, near misses, and dangerous
occurrences to Safety Engineer and participate in the investigation process.

 It is the Safety Officer’s (assigned Foreman) duty to initiate appropriate action for excellent safety
performance / repeated unsafe acts of personnel and implement safety measures as per HSE plan.

 It is the Engineer’s/Foreman duty to ensure that all the works are performed to the satisfaction of the
Company and as per the project specifications.

 It is the worker’s duty to adhere to all the safety rules. They must perform the work in accordance wit the
Method of Statement.

Page 3 of 7

KHALIFA PORT INTERCHANGE LANDSCAPE/IRRIGATION&STORMWATER


Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

4. Procedure / Method to be Employed


4.1 Pre Laying activities:

 After getting the approval for the Shop Drawings from client/consultant, arrangements will be made to
procure the Material to site.

 Surveying of areas and Setting out the Landscape areas.

 The approved material will be procured and delivered to the Site as per Schedule of works.

 Access will be provided to the work place by coordination with other contractors.

 Work area will be cleared totally from all other contractors.

 All debris and deleterious material shall be removed

4.2 Preparation of Sub Grade:


 Trim, fill and level the ground to the required level.
 Water and compact the leveled surface to achieve required MDD using Roller/Plate compactor.

4.3 Sand bed for Unit pavers /Interlocking Tiles

 The sand shall be procured from approved supplier.


 The material shall be stock piled in well protected area and it shall be protected from any dust.
 After completion of compaction and compaction test on sub base, laying of sand bed followed by
interlocking tiles shall commence.
 Sand bed shall be spread over the sub base maintaining an uniform thickness of 50 mm.

4.4 Laying of unit pavers/Interlocking tiles

 Approved interlocking tiles shall be procured from the approved supplier and it shall be stocked in site.
 For the car parking and service road area 80mm thick interlock tiles shall be used.
 Tile Pattern, Design and colors shall be followed as in approved shop drawings for walk and other areas.

Page 4 of 7

KHALIFA PORT INTERCHANGE LANDSCAPE/IRRIGATION&STORMWATER


Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

 Screened dune sand shall be spread on top of tile surface and compacted using plate compactor to
achieve flat well compacted interlocked tile pavement.

 Care shall be taken not to leave any un compacted areas of paving at the end of working periods, except
within 1 meter of unrestrained edges.
 Check paving after compacting first few meters, then at frequent intervals to ensure that surface levels
are as-specified.
 If it’s not compacted then brush sand into joints, re-vibrate surface and repeat as required to completely
fill joints and until pavers are uniformly level, true to grade and free of any movement.
 Avoid damaging kerbs and adjacent work during vibration. Edge restraint will be provided to all
perimeters of paved areas to eliminate the loss of bedding course material.

5 Manpower Requirement

 Project Engineer.
 Site Engineer
 Charge hands
 Surveyors
 Masons
 Electrician
 Skilled and Unskilled labours

6 Material Requirements

 Approved bedding sand


 Marking materials.
 Water.
 Approved paving materials
 Approved joint filling materials

Page 5 of 7

KHALIFA PORT INTERCHANGE LANDSCAPE/IRRIGATION&STORMWATER


Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

7 Equipment Requirement

 JCB
 Six Wheel
 Bobcat
 Trucks
 Roller Compactor
 Plate Compactor
 Water tanker
 Levels
 Air Compressors

8 Health and Safety Provisions

 All the works will be undertaken in accordance with site safety regulations as stated in the contract
documents.

 The site will be kept clean and tidy in accordance with site safety regulations, mainly at the time of soil
spreading and after spreading activities.

 All the machinery will be checked (daily routine maintenance) before starting the work by the operators and
then by Safety Officer.

 All the workers on site should abide to the HSE plan.

 All the machinery works will be performed in accordance with site safety regulations for utmost safety.

9 Attachments

 ITP
 Organization Chart

Page 6 of 7

KHALIFA PORT INTERCHANGE LANDSCAPE/IRRIGATION&STORMWATER


Client Consultant Main Contractor Sub Contractor

KHALIFA PORT ITERCHANGE Procedure No JDP-KPI-MS-

METHOD STATEMENT FOR LAYING OF UNIT 23/04/2013


Issue Date
PAVERS/INTERLOCKING TILES

 Risk Assessment
 Work Program
 Specification Reference

Page 7 of 7