PU-D-ROA0915422512-EX-CS-CAL-005-01-B - Tender Book
PU-D-ROA0915422512-EX-CS-CAL-005-01-B - Tender Book
DETAIL DESIGN
PROIECTARE DE DETALIU
Issued for
comments /
01 01.2021 I. DAMIAN L. SOARE J. NAN C. STAN
Emis pentru
comentarii
Project
Date Description Prepared Checked Manager Approved
Rev.
(Data) (Descriere) (Intocmit) (Verificat) (Sef (Aprobat)
Proiect)
CONFIND
1 OF 53
EPCC BARBUNCESTI CBARB
COMPRESSOR STATION (PR. 1220/2020)
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
3 of 54
no.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
4 of 54
no.
CONŢINUT/CONTENT
1 General prescriptions................................................................................................................... 7
1.1 Objective................................................................................................................................. 7
2 Marking........................................................................................................................................ 9
2.4 Tolerances............................................................................................................................ 10
4 Foundations............................................................................................................................... 16
4.3 Characteristics...................................................................................................................... 16
4.4 Technology........................................................................................................................... 16
4.5 Applicable............................................................................................................................. 18
4.6 Checks.................................................................................................................................. 18
4.7 Materials............................................................................................................................... 18
4.8 Quantity................................................................................................................................. 18
5 Concrete works.......................................................................................................................... 19
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
5 of 54
no.
5.3 Characteristics...................................................................................................................... 20
5.4 Technology........................................................................................................................... 20
5.5 Applicable............................................................................................................................. 21
5.6 Tests..................................................................................................................................... 21
5.7 Materials............................................................................................................................... 21
5.8 Quantity................................................................................................................................. 21
6 Materials.................................................................................................................................... 22
6.1 Concrete............................................................................................................................... 22
6.1.4 Characteristics.............................................................................................................. 24
6.1.5 Technology................................................................................................................... 26
6.1.5.1 Concrete preparation and transport 26
6.1.5.2 Preparation conditions on cold weather 26
6.1.5.3 Preparation conditions on hot weather 26
6.1.5.4 Concrete pouring28
6.1.5.5 Striking 31
6.1.5.6 Imperfection remedial 32
6.1.5.7 Deviation and tolerances at element’s casting 34
6.1.6 Applicable..................................................................................................................... 34
6.1.7 Checks.......................................................................................................................... 34
6.1.7.1 Quality control 34
6.1.7.2 Quality control of the hardened concrete 36
6.1.8 Materials....................................................................................................................... 37
6.1.9 Quantity........................................................................................................................ 37
6.2 Formwork.............................................................................................................................. 37
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
6 of 54
no.
6.2.4 Characteristics.............................................................................................................. 38
6.2.5 Technology................................................................................................................... 38
6.2.5.1 The Formwork’s Lubrification 38
6.2.5.2 The Storage 38
6.2.5.3 Erection Specifications 38
6.2.5.4 Tolerances 39
6.2.6 Applicable..................................................................................................................... 39
6.2.7 Checks.......................................................................................................................... 40
6.2.8 Materials....................................................................................................................... 40
6.2.9 Quantity........................................................................................................................ 40
6.3 Reinforcement....................................................................................................................... 40
6.3.3 Characteristics.............................................................................................................. 40
6.3.4 Technology................................................................................................................... 41
6.3.4.1 Delivery 41
6.3.4.2 Storage 41
6.3.4.3 Shaping 41
6.3.4.4 Erecting 41
6.3.4.5 Joining of the reinforcement bars 42
6.3.4.6 Tolerances 42
6.3.4.7 Concrete cover 42
6.3.5 Applicable..................................................................................................................... 42
6.3.6 Checks.......................................................................................................................... 42
6.3.7 Materials....................................................................................................................... 43
6.3.8 Quantity........................................................................................................................ 43
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
7 of 54
no.
6.4.2 Technology................................................................................................................... 43
7.2 Materials............................................................................................................................... 45
8 Structure maintenance............................................................................................................... 47
12 Final provisions.......................................................................................................................... 51
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
8 of 54
no.
1 GENERAL PRESCRIPTIONS
1.1 Objective
This specification establishes the conditions for quality of execution, verification and acceptance of
work covered by the project.
Quality control check will be done according to the valid prescription requirements, ”Standard for the
quality inspection and acceptance of structure works and related facilities” – indicative C56-85. The
scope of the quality verification is to examine how the project requirements are accomplished, as well
the technical specifications in valid during the project execution.
The norms list contained in the specification will be updated by the contractor (builder) with new or
revised standards that will appear until and during the project execution.
The designer can add or make changes to the content of this specification throughout the execution,
which will become mandatory after taking notice by the contractor and customer.
The performer is required to take organizational measures for implementing the required quality
requirements in terms of project execution, ensuring compliance with the provisions included in this
Tender book and also for all the valid standards, norms and technical instructions that are related to
the project execution.
This Tender book does not replace the provisions of valid regulations, but it completes here
provisions and specifies certain details and how to interpret them.
The fulfill of the valid regulation provisions and the Tender book is mandatory and is the base for the
intermediate and final acceptance for a part or for the whole project.
The builder (contractor) will instruct all working staff, at the production factory and on the site,
regarding the project, regulations and technical instructions and of the present Tender book, so that
each of those who contribute to the project to know perfectly their tasks and duties in compliance with
the technical quality conditions of this project.
In order to ensure quality of the project, the supplier can complete this Tender book with other
provisions that he considers necessary for building/making the constitutive elements, subassemblies
and assemblies at the factory and mounted on the site.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
9 of 54
no.
The contractor (builder) will appoint a technical officer for building quality certified by the law, which
will be responsible for the proper quality level of the project performance requirements.
After the receipt of technical documentation, the contractor (builder) will provide knowledge of the
project to all the factors that compete for work performance.
The control and acceptance program for the determinant phases of the project is attached to the
technical documentation. The program will also indicate which factors should participate in the
mentioned different stages.
At the structure site is necessary to find: complete documentation of execution, the register records of
the hidden works, records of site communications, the main rules governing the execution and
technology.
If operations that are not covered by technical regulations legally approved are approached, the
supplier/producer of the materials or parts will prepare a specification of the sequence of
technological steps and special requirements.
NOTE:
All standards, norms and procedures specified in the list of technical regulations in force under the
Decision no. 48834 EC/24.06.2011 by the Ministry of Regional Development and Tourism (MDRT) will
be applied, valid at the date of preparing the documentation. In the situation in which during the
execution of the project changes will be made to the technical regulation list the new regulation will be
used.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
10 of 54
no.
2 MARKING
NE 012/2-2010 Standard for the production and execution of concrete, reinforced concrete and
prestressed concrete.Part 2: Concrete works execution
Detail marking is based on projects in relation to landmarks points and level with the draw
materialized on the ground for the location of the building.
Detail marking for formworks and the marking for installing precast , reffers mainly to the following
categories of assets:
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
11 of 54
no.
The marking for elements that repeat vertically ( for example , succesive floors of a building) or
horizontaly (for example , strings of columns ) , will be for each one , as the basic reference points not
to the precedent element.
In cases where deviations between successive elements are found( one existing and one which is
made marking) higher than allowable , it let you know the designer to determine how to deal with
non-compliance.
For marking will use appropriate equipment for field use and precision.
Equipment precision will be a class higher than the required for marking tolerances.
2.4 Tolerances
Marking settlement tolerances according to STAS 9824/1-75 are the following:
Td1 ±2 ±2 ±3 ±4 ±5 ±5
Td2 ±3 ±4 ±5 ±6 ±7 ±8
In which:
Td1 rectangular coordinates marking tolerances for horizontal placement of buildings [cm];
S 0 25 50 100
In which:
Position tolerance of ±0,00 af building is ±1cm, for angles marking tolerance is 1o.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
12 of 54
no.
Detail marking tolerances should be a class lower than for those items after execution of
installation.Marking tolerances of concrete elements are presented in Appendix C of NE 012/2-2010.
- Identification and position coordinates and benchmarks materialized on the ground level with
the location mark of the building which led to the detail marking;
- Equipment used to perform detailed marking and , where appropiate, procedures used ( type
and name of equipment accuracy and the documentation of metrological control, procedure
codes, etc.);
- Way of seeing the marking made;
- delivery and reception betweent the performer of the detail marking and subsequent work
performer( formworks and assmbling precasted), parts of plotting evidenced made;
- executor obligation to intervene where noncompliance appear on the detail marking of
subsequent work performance;
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
13 of 54
no.
C169-88 „Standard for the execution of earthworks ,for the achievement of the foundations
of civil and industrial buildings.”
STAS 2914-84 „Road works . Earthworks. General technical requirements for quality”.
Topsoil,depth of about 40cm will be removed from the entire area of future construction before
excavation for foundations.Topsoil can be stored for reuse,but it will be stored separately from other
materials.Maximum transporting distance is 60m.Topsoil shall not be used as filler(in the
embankment).
The excavation will start from the bottom edge of the upper elevation earth,with permanent monitoring
of adjacent buildings and support system.The excavation will be done according to the dimensions,
levels and profiles indicated in the plans.Before starting work, must be checked the marking on the
ground.
On reaching the foundation levels from the project , before concreting the equalization, will performe
to identify the nature of the soil under determinante phase control program attached to this
documentation, in the presence of geotehnician engineer, designer engineer ,representative of the
beneficiary, the executor.In the event that differences will arise from the project , they will be recorded
in the minutes of the reception of the soil nature, and the comitee will decide how the work will
continue.The works will be resumed only after the notification in writing of the changes to the project
by the designer egineer or geotehnician engineer.
Excavation to a depth of 1,50 m can manually run without support, or at angle of slope of 2/1, to
greater depths (see Geotechnical study attached).
Excavating the highest vertical slope of 1,50m is necessary to provide support works slopes.Support
work will be sized according to the amount of active pushing the earth(natural land and overload the
(natural ground level, taking into account the horizontal and vertical pressure transimitted by
neighboring buildings) in static and dynamic conditions.Vertical slope must be covered with PVC film
and protected with plywood OSB type to conserve natural wetness.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
14 of 54
no.
Mechanized excavation stops at 20cm from the final elevation.Next 15cm must be digged
manualy.The foundation soil is compacted under the project , to obtain the degree of compactation of
98%.In this case the leveling concrete must be thicker than 5cm.If necessary , the compactation can
be done with ballast or can choose increasing concrete leveling.Excavation works will be executed on
short and sunny time.In case of interruption of work shall take measure to prevent entry water into the
building area( plate basement execution, channel water installations, drains, filling perimeter and
sidewalks).
Also on-site stormwater will be directed outward, and what will be accumulated in the feet of the
foundation will be evacuated immediately.It recommends gravitational rainwater leakage outside the
excavated area (for keeping the foundation soil land even if it’s nature will allow natural drainage)
operation will be accompanied by the provision of ancillary works(canals, ditches) by precluding the
direct inflow of water within the excavation.If it detects other water sources and losses of neighboring
networks , underground springs ,will stop work and shall notify the designer engineer to take the
necessary measures.Land on the slopes and the excavation will be protected from any
disturbance(mechanical or due to climatic factors).Also there are not allowed overloads greater than 2
kN/m2 over a distance of at least 2m from the edge of excavation( ie will not store materials and
equipment , not moving and no stationary machines).
Slopes condition will be monitored continuosly (inclination , degree of cracking).If it will be detected
cracks parallel to the slope , the works will stop immediate, the personnel and the equipment will be
immediate evacuated and the designer engineer will be announced.No excavation work shall be
performed during periods of freezing and/or rain.
- Identification of possible airborne or ground and the unit holders to establish the conditions under
which this work can be performed safely;
-Tracing works;
-Organizing and supplying the working point with the necessary materials in a proportion of 50%;
-Do not jeopardize the safety of construction and existing facilities , visible or buried and execution of
works in the vecinity;
-Daily , before starting work and at the end of the day must be checked the state support land around
the excavation to take appropiate measures to prevent any subsidence and accident hazards.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
15 of 54
no.
Excavations runs with vertical walls without support , manually or mechanically ,with the following
conditions:
-Excavation is kept unopened and filling operations are performed on the same day;
-Excavation depth is relatively small, ie 10m in plastic and sands soil and 1.5 m in the land of hard
consistency;
When running mechanized excavation and filling draining technology implementation does not require
lowering workers digging under the conditions mentioned above , the depth can be increased to a
maximum of 2.0 m.
When excavation depth exceeds 1.0 or 1.5 m, excavation slope runs without support of up to 2.0m
deep or vertically with the walls supported in depth.
Excavations with vertical slope, in plastic and sands soil or hard soil, runs at the shelter of horizontal
supports based according with an execution project that adapts to actual conditions in the field.
The land affected by instability, difficult soil (loess, clay contractile ,etc.) at any depth , the support is
based on execution project with vertical cabinet frame(optionally piles), wich form a continous wall
and a waterlight manner.The piles are beaten (0.5...0.75m) in advance.
Digging earth store will be placed at least 1.0m from the wall of the excavation and the materials must
be disposed of at least 5.0m.The distances can be reduced to half digging drains for drainage, wich
usually have depths below 2.0m.In areeas where there are burried cables, pipelines, archaeological
land etc.the digging runs carefully with instructions in writing , tutorial unit installations , wich may
delegate supervision of the unit.
If it is discovered during construction excavation underground facilities, the work must be stopped
immediately and proceed to their identificitation and referral unit guardianship.Work can be resumed
only after the elimination of danger and supervision delegate guardianship unit.
Note:
Since the execution of the works is done inside the rafinery the following aspect must be
considered:
Do not allow the existence of routes or utility installations below the foundation in the
area affected by the construction;
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
16 of 54
no.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
17 of 54
no.
4 FOUNDATIONS
4.3 Characteristics
According to the specifications of Technical Documentation.
4.4 Technology
Preparing:
Foundations works will begin after the reception of the natural ground and the tracking of
the foundations.
The formworks for foundations and its supports must be made in such a way to ensure
the following:
the shape and dimensions that are specified in the technical documentation;
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
18 of 54
no.
The support of the formwork will be erected and fixed in a way that will not allow
deflections or deformations of the formwork while the concrete is casted.
It is necessary, before casting the concrete, to check the final position of the formworks.
The striking of the formworks will be made according with the specifications of standard
“NE 012/2-2010”.
The storage of the formworks will be done without its degradation or deformation (due to
moisture, dirt, rust or decay).
It is forbidden the storage of the formwork directly on the ground or the storage of other
materials on the formworks.
To ensure the right cover of concrete, it will be used spacers made by plastic
Before casting the concrete, it will be checked all the reinforcements from the point of
view of the numbers, the position, lengths, spacers.
The foundations will be made according to the specifications from the chapter about
concrete works.
The foundations will be casted continuous, without stopping; in case that this
specification cannot be applied, the following steps will apply:
the maximum admitted delay will be 1.5 – 2 hours (depends on the type of
cement used); if the delay is longer;
if the delay is longer, it will be made a joint at a distance of 1.00 m from the edge
of the columns or from the intersection of the beams.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
19 of 54
no.
4.5 Applicable
According to the specifications in the Technical Documentation.
4.6 Checks
All the foundations works will be checked and tested, and all results will be written in
“Account of proceedings for hidden works”.
4.7 Materials
According to the specifications in the Technical Documentation.
4.8 Quantity
According with the quantity specified in the Technical Documentation.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
20 of 54
no.
5 CONCRETE WORKS
C 11-74 Technical specifications for using and making the formworks from
wood panels.
The reinforced concrete beams will be casted in formworks made of wood panels,
metallic or mixed ones.
the elements of the formwork must have enough strength and stability to sustain
the pressure that comes from the green concrete.
The order for realizing the reinforcement of the girders is the following: tracking the
position of the ties on the formwork; placing the ties with the open side on top; placing
the longitudinal reinforcement bars and joining them with the ties; closing the ties.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
21 of 54
no.
5.3 Characteristics
According with the Technical Documentation.
5.4 Technology
The phases of the execution process for the reinforced concrete works, will be hidden
works, so the quality checking will be mentioned in ”accounts for proceeding” which will
be signed by the beneficiary’s and constructor’s delegacy. The “account for proceedings”
it is not valid if it is signed only by the constructor.
It is not allowed to proceed with the works before this document is signed and stamped.
In this documents will be mentioned all checks that were made, the results, and if it is
allowed to continue with the works.
It is mandatory to elaborate “accounts for proceedings” for the following phases of the
process:
when striking.
- length ±10 mm
- section’s dimensions ± 3 mm
- concrete cover ± 3 mm
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
22 of 54
no.
- dimensions ±10 mm
- surface’s dip:
o partial ±3 mm/m
o total ±5 mm
o partial ±3 mm/m
o total ±5 mm
5.5 Applicable
According with the Technical Documentation.
5.6 Tests
The constructor is forced to make the checks that is specified in this document and to
keep the results.
5.7 Materials
Concrete in foundation C35/45, XC2, XF3.
5.8 Quantity
According with the Technical Documentation.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
23 of 54
no.
6 MATERIALS
6.1 Concrete
Concrete composition;
Conditions for preparing, transport, cast-in work and further treatment of the
concrete;
CEMENT
At temperatures >25°C, CEM III A 42.5 N-LH sau CEM II B-M (S-V) 42.5 N-LH.
Technical conditions for reception, delivery and control of cement shall conform to the
provisions of STAS 3011-83.
Change of cement type can be made only with the written notice of the designer.
During the transport from the manufacturer to the concrete plant, and the storage, the
cement should be protected from moisture and contamination with different materials
(soil, coal, organic substance, plaster, hydrated lime etc).
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
24 of 54
no.
The constructor will make in his own laboratory the tests from table 1, point 1.
It’s forbidden the use of the cement in the concrete preparation that doesn’t meet the
conditions for setting of concrete and volume constant.
If the period between the delivery from the manufacturer and the use of the cement
exceeds 30 days, the cement will be used only if after 7 days at a new check the
mechanical resistances correspond to the standard conditions.
The constructor is forced to have a clear evidence of each introduced batch of cement,
also of the daily consumption.
AGGREGATES
At the concrete preparation will be used aggregate sorts: 0-3, 3-7, 7-16, 16-31 mm,
supplied from the nearest ballast-pit.
The aggregates will correspond to the technical conditions from STAS 1667-76, the
determination methods of the characteristics are from STAS 4606-80.
For the quantity delivered in one transport, the supplier is forced to send the quality
certificate along with the sending document.
MIXING WATER
The water used for preparing the concrete will be water from the potable system. If its
used water from other sources it should correspond to the quality conditions from STAS
790-82.
ADDITIVES
Additives like water reducer and plasticizer will be used for the exposed elements in
intense and very intense aggression conform to NE 012-1-2007.
CHLORIDE CONTENT
Table no.1.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
25 of 54
no.
At supply
2.5. - granularity Once per day The results use for the
and each network correction.
time is
considered
necessary
2.6. - moisture
6.1.4 Characteristics
Each type of concrete will be defined by it’s: class, workability and eventual, degree of
water-tightness.
TECHNICAL CONDITIONS
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
26 of 54
no.
The concrete used for elements of foundation, girdle and columns, will have the classes
specified in the project.
Workability
Temperature
The maximum temperature will be of +25 0C. The checks will be made according table
no.6.
CONCRETE COMPOSITION
In table 2 the parameters of concrete composition for some currently used classes are
presented:
Table no.2.
No. Concrete Cement Max. Admixtures Area of
crt. proportioning w/c type(1/m3) granularity
CEM II A
1. C35/45 - L3/L4 300 kg/m3 0.50 Water reducer Table 3
plasticizer
2. C8/10 – L3/L4 180 kg/m3 0.50 - Table 3
Used admixture proportion will be according with the supplier’s specifications.
The minimum compression strength (on cubs with side of 15cm) at the age of 28 days
will be: C25/30 – 30 N/mm2
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
27 of 54
no.
6.1.5 Technology
The concrete plant must be certified conform to the Normative C 140-86 and for this
case the constructor is forced to the measures.
The proportioning of materials component of the concrete will be done gravimetric, with
admitting the following deviations:
Cement ±2%;
Aggregates ±3%;
Water ±1%;
Admixtures ±5%.
Proportion of admixtures will be made using proper batchers that allow more accurate
measurement of the admixture solution quantity settled in the concrete mixing ratio.
The constructor has to take the required methods for proper admixture’s preparation and
proportioning by taking into account the fact that deviations more in extra or minus then
the provided ones can have a bad influence on the concrete’s quality.
On cold weather special measures for the preparation of the concrete have to be taken
by the constructor, under the specified minimum temperature.
These measures are: removing the ice and the aggregates balls, covering with
tarpaulins the aggregates and heating them using steam or blown-in air through pipes,
using worm water etc.
If at the preparation of the concrete its used water with a temperature higher than 40 0C,
the direct contact of water and cement will be avoided. In this case, first the water will
mix with the aggregates and only after the temperature of the mixture will decrease
under 400C the cement will be added.
On hot weather special measures for the preparation of the concrete have to be taken by
the constructor, under the specified maximum temperature.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
28 of 54
no.
These measures are: spraying the storage of aggregates with cold water, protecting the
storage of aggregates and the water tanks against direct action of the sun, warm and dry
wind, using cold water for concrete preparation, concrete preparation when the air
temperature is lower or at night.
CONCRETE TRANSPORT
Transport of the concrete from the plant to the site will be made with auto-agitator or
tipper with tight clamshell.
The local transport of the concrete will be done using concrete pumps, clamshell,
troughs, carts etc.
Each concrete transport will have attached a transport bill where the following data will
be mentioned:
concrete mixer;
Information regarding the concrete plant will be filled by the chief plant, and information
from site will be filled by the work leader.
The transport bill will be duplicate, one will remain on site and the other one will be
returned to the concrete plant.
Transport duration will be considered from the moment the unload starts until it finishes,
and it will not overcome:
The constructor will take measures for in time of transport the concrete quality will not
change (loss or segregation of concrete milk in case of transport using tippers, added
water, in case of transport using auto-agitators).
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
29 of 54
no.
The constructor will ensure the best conditions for the concrete transport in time of works
developed on cold or hot weather, by taking the safety measures for conservation the
quality of green concrete.
Elevation levels and cleaning state of the formwork surface used for the concrete
element done before;
Proper level of formwork in plan as in level with the ones specified in the project,
formwork’s verticality, existing measures for maintaining the shape, ensure
tightening and fixing of formwork with sustaining elements.
The resistance and stability of sustaining elements, the correct bearing and fixing
of the sustaining and other striking devices;
Correct placement of reinforcement and proper bar diameters and their number
as the ones in the project, solidarity of reinforcement, sufficient number of
distance-pieces etc;
If there are identified any mismatches from the project or the requirements for starting
the concrete pouring are not ensured, then proper measures will be applied.
After the checks are finished the constructor shall fill in the “Inspection report for
checking the concreting requirements”.
The concreting will be leaded by the chief of work. He will be present on the site at the
cast-in place and he will supervise the develop of works by taking any repairing
measures for mismatches that will be added in the “Inspection report for concreting” of
the element or elements made.
The concrete must be poured as soon as possible after its brought on the site, the cast-
in will be done with no interruption between the pouring joints.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
30 of 54
no.
Concrete pouring will be done in uniform horizontal layers, with max.30cm thickness.
The height from where the concrete is dropped will not be bigger than 1m when its
poured using the pump and 1.5m when other equipment is used.
The maximum admitted time between pouring two consequent layers will be appreciated
depending the concrete composition, environment conditions and element dimensions,
so that the new concrete layer can be vibrated along with the previous poured layer.
If the constructor believes that, from different reasons, the pouring cannot be done in the
proper time for ensuring the element’s continuity, then for concrete preparation, beside
used admixtures, will be used a delayer admixture (hexamethanphosphate, sodium).
Although the concrete poured in the previous layer has been strengthened or because of
high important reasons, the pouring is impossible, the surface of the concrete will be
considered a pouring joint and: clean the not compacted concrete, the cement milk, and
it will be created a rough surface that before repeating the pouring process will be blown
with compressed air and washed.
When pouring the concrete it will be carefully watched the complete including of the
reinforcement in the concrete and the right realization of the cover layer’s thickness.
Where the reinforcement is frequent, the complete filling with concrete and compaction
will be made with special care, and where its the case, there will be created access
possibilities from a side for the green concrete through spaces that allow also the use of
the vibrator or the metallic rods for concrete beating-up.
It will be avoided the reinforcement’s strain or displacement from the position specified in
the project, and its forbidden for the workers to walk on it.
The compaction of the concrete poured in elements will be done with vibration, during
this operation the constructor will take the following measure:
Personal training regarding the vibration technique, and the correct realization of
this operation’s importance;
Proper equipment for vibration for the workers and sufficient number of vibrators.
the vibrator will be vertical positioned, entering the base layer on a approximately
10…15cm depth;
pulling out the vibrator will be very slowly done, avoiding forming air gaps in the
extract points;
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
31 of 54
no.
optimum time of vibration from technical and economical point of view is between
5…30 sec, depending the concrete workability, element’s dimensions and the
reinforcement extent, also the type of vibrator that was used.
no more air bubbles appear on the concrete surface and their diameter reduces;
If the temperature of the surface that will be covered with concrete is lower than +5 0C,
the concrete pouring will not start.
For assuring favorable strengthening conditions, the concrete will be permanently kept
wet for 7 days, by permanent spraying, or by concrete covering surface with tarpaulins,
mats, sackcloth etc, kept permanently wet.
During time with hot weather, the concrete treatment will be done minimum 14 days after
casting.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
32 of 54
no.
Protection measures on cold weather will be taken when the environment temperature
(taken at 8 am.) is lower than +50C.
Concrete protection will ensure beside the normal strengthening conditions also:
concrete protection on the free sides will be done with mats or other thermal
insulator applied on a polyethylene sheet;
6.1.5.5 Striking
If its not different specified in the project, minimum striking deadlines will be the ones
specified in Code NE 012-99, tables no.14.1, 6.2 and 14.3.
Deadlines specified in table no.4 are for guidance, striking will be made after the
execution procedures when the elements have reached the minimum resistances
indicated at point 14.4 from NE 012-99 Code.
the process will be supervised directly by the work leader, in case of any
observed pouring imperfections (gaps, segregated area) that can have effect on
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
33 of 54
no.
the element bearing capacity, the sustaining element’s striking will be stopped
until remedial measures will be applied;
the formwork sustaining system will be loosen starting from the central zone of
the element openings and continuing symmetrical to the supports;
Striking will be done so that sudden load overtaking by the elements, broken
concrete edges or damaged formwork and sustaining material are avoided.
Right away after striking will be examined the concrete and signaled the areas with
inappropriate concrete ( not compacted segregated concrete, gaps, not allowed pouring
joint etc). In the same time the followings will be checked: position of passing gaps,
position of the reinforcement that will be embedded in further casted elements. All the
findings will be written in the “Account for proceedings of hidden works”.
Remedial solutions of the imperfections will be settled with the consent of the designer
depending the type of imperfection, by following Normative C149-87:
Concrete zone with gaps or not allowed concreting joints will be remedied by
pouring concrete in the damaged places conform point C4.
Not compacted or segregated concrete areas will be removed until it reaches the
“healthy” concrete layer, the reinforcement will be cleaned, compressed air will
be blown and it will be washed with pressured water. Washing the areas on
which the guniting will be applied will be done with 1-2 hours before the guniting
operation that will be done only after sammying of the surface;
At mixture preparation of guniting will be used cement Hz35 and sand 0-3mm in
ratio of ½, the water quantity will be settled by the constructor depending the
needed consistency at cast-in.
Guniting application will be done in successively layers until the remedial zone is
reached;
Surface finishing will be made at 30-45min. after guniting, first using the trowel
and reglet for removing the excess concrete then by smoothing with a metallic
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
34 of 54
no.
float or the trowel until its reached the same concrete surface as the near one; its
admitted for correction of the irregularities the use of fine mortar prepared from
the cement and fine sand 0-1mm in ratio of ½;
Protection of the redone areas will be made with polisol or sinolac solution, or
with permanent water spraying for 3 days and protection with sackcloth or
tarpaulin.
Imperfection remedial with concrete pouring its done by following the specifications
below:
Not compacted or segregated concrete areas will be removed until it reaches the
“healthy” concrete layer, the reinforcement will be cleaned, compressed air will
be blown and it will be washed with pressured water;
Concrete cast-in will be done by excess pouring in splay formwork, for one or all
sides of the element;
Fixed concrete composition its specified depending concrete class conform table
no.5.;
Table no.5.
Concrete class
Materials C25/30
sand 0 - 3 mm 600 1
sand 3 - 7 mm 600 1
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
35 of 54
no.
Protection of the redone areas will be made with polisol or sinolac solution, or
with permanent water spraying for 3 days and protection with sackcloth or
tarpaulin.
If it’s not specified in the technical documentation, the following deviations will be
allowed:
until 3 m ±3 mm
3....6m . ±20 mm
over 6 m ±25 mm
- the width and the height of the cross section of the reinforced concrete
flanges and columns
- until 50 cm ±5 mm
- over 50 cm ±10 mm
6.1.6 Applicable
6.1.7 Checks
The value of the concrete’s characteristics for every type of the concrete that is used, will
be made according with the specifications from the table nr. 6.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
36 of 54
no.
Table no.6.
The
determi-
Charac- Technical nations Checking place
teristic condition will be
made
acc. to:
Station Laboratory Study
At every evi- At each 20 cm, at
At the first char- dence that was each trans-port, if the
Workability p.C3 STAS ge, for establi- taken, for deter- condition of the
1759-80 shing the opti- mining the cha- commi-ssioning work
mum quantity of racteristics of the requires it
water casted concrete.
At every evi- At each 20 cm, at
At the first dence that was each trans-port, when
Temperature p.C3 charges to taken, for deter- there is a possibility
establish the mining the cha- to reach ex-tremes
temperature of racteristics of the values
the component casted concrete.
materials.
Only at the
preliminary
Occlusive air pct.C3 STAS checking, or
1759-80 when a new lot of
the additive is
brought
The result’s interpretation will be made in the following way:
- if the result of the checking is outside the admitted boundaries, the checking
will be repeated immediately;
- if neither this result is inside the admitted boundaries, the preparation of the
concrete will be immediately stopped and specific measures will be taken to
obtain the wanted product.
in site:
- if the required condition is not meet, for the same transport it will be done
another 2 checks and it will be calculated the average between this three
values;
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
37 of 54
no.
- if the admitted superior value of the compaction is exceeded, the concrete will
not be used immediately, but after a while.
- if the concrete’s compaction is lower than the admitted value, the workability
can be improved by adding plasticizer additive in the same time with the
concrete agitating with high speed.
- its admitted to exceed the maximum values with 2ºC, but only for one single
transport, or in very special cases for 4 consequently transports, in this time,
it will be taken the right measures for correcting the temperature of the
concrete.
The quality checking of the hardened concrete (compressive strength and degree of
water tightness) will be made on samples in the laboratory, the keeping and the checks
will be made according to STAS 3519-76.
The samples means at least 3 concrete cubes with the side length of 15 cm.
The samples will be taken with the frequency specified in table no. 7
The frequency samples collect for quality checks of the hardened concrete.
Table no.7.
Type of Characteristics
concrete Compressive strength Water tightness
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
38 of 54
no.
The evaluation of the quality of the concrete prepared and delivered, will be made
according with the specifications of the standard NE 012-2007, annex X.6, based on the
obtained results regarding the compressive strength, at the age of 28 days, made for
each kind of concrete, on samples kept in special condition.
In case that for one kind of concrete, its characteristics are not fulfilled, it will be re-
examined the composition based the quality of the materials and tuning the
technological procedure for preparing the concrete.
The concrete is considered proper from the point of view of the behaviour of the water
tightness if, after the checks at the specified pressure, the water cannot get in the
sample more than 10 cm.
The laboratory of the construction company will make a daily detailed log of the results
of the checks for each kind of concrete, to easily identify from a sample the concrete
from that element.
6.1.8 Materials
6.1.9 Quantity
6.2 Formwork
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
39 of 54
no.
The formworks can be realized by wood or products based on wood, steel or mixed
formworks. The materials used must ensure a proper concrete surface.
Choosing the formwork will be made regarding the type of the element, the dimensions
and the concrete casting technology.
6.2.4 Characteristics
The formworks and their holdings will fulfill the following conditions:
to be stable and resistant under the load which appear in the construction
process;
6.2.5 Technology
For reducing the closure between the concrete and formwork, they will be lubricated on
faces that are in direct contact with the concrete, before each using, with special striking
solution. This substance must not stain the concrete elements, will not affect the
formwork and must not change its properties during the casting of the concrete or due to
the climatic conditions.
The storage of the formworks will be done without its degradation or deformation (due to
humidity, dirt, rust or decay). It is forbidden the storage of the formwork directly on the
ground or the storage of other materials on the formworks.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
40 of 54
no.
The links of the formworks will not let spaces or holes that may require additional repairs
of the reinforced concrete surface and will not lead to the concrete degradation.
It is recommended that after the remove of the formwork, no temporary steel element
should remain embedded in concrete at a distance smaller than 5 cm from the surface of
the concrete.
The support of the formwork will be erected and fixed in a way that will not allow
deflections or deformations of the formwork while the concrete is casted.
6.2.5.4 Tolerances
The formwork panels and the metallic parts for assembly will be in a good condition that
will allow the exact dimensions, shapes and position of the concrete elements.
- lengths ±4 mm
- widths ±3 mm
admitted tolerance for dip to the horizontal, of the edge and surfaces of the
formwork:
- on linear meter ±2 mm
6.2.6 Applicable
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
41 of 54
no.
In the last time it was developed formwork systems with superior performances to fulfil
the actual requirements and replace the old type of formworks.
Regarding this, it is recommended to use formwork with metallic structure, and special
panels with bond film.
6.2.7 Checks
6.2.8 Materials
6.2.9 Quantity
6.3 Reinforcement
STAS 438/1-89
STAS 438/2-91
STAS 438/3-89
6.3.3 Characteristics
The formworks and their holdings will fulfill the following conditions:
The reinforcement will be made using the materials specified in the technical
documentation. The reinforcement products must respect the specification of the
standards mentioned at pt. 6.3.1.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
42 of 54
no.
6.3.4 Technology
6.3.4.1 Delivery
Delivery of the reinforcement will be made according to the standards and must contain
the quality certificate issued by the producer. If the product is delivered by a local
supplier, they must provide a copy of the quality certificate of the entire lot of
reinforcement.
6.3.4.2 Storage
Reinforcement bars will be stored separately, by diameter and the following specification
will be followed:
6.3.4.3 Shaping
Before the shaping of the reinforcement, the bars must be straight and cleaned of dirt,
oil, paint or other impurities.
The shaping of the bars, making the reinforcement frame or reinforcement mesh will be
made according with the technical documentation.
The cut and shaped bars will be stored in labeled packages so they will not be confused
and they will be kept clean until erection.
If it’s used bending machines with 2 speeds, it is not recommended to bend the profiling
bars at high speed.
The designer will be noticed if the bars are cracking or breaking when they are bent.
6.3.4.4 Erecting
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
43 of 54
no.
To ensure the right cover of concrete, it will be used spacers made by plastic. It is
forbidden to use spacers made with other reinforcement bars.
If it’s not specified in the technical documentation the reinforcements will be tied with 2
steel wires with 1.5 mm in diameter (STAS 889-76).
The joining of the bars will be made by superposition them according to the specification
of the technical documentation.
It will be used the specification for joining the bars that is mentioned in standard NE
012/2-2010 - Standard for the production and execution of work in concrete,
reinforced and prestressed concrete - Part 2: The execution of the Concrete.
6.3.4.6 Tolerances
The following specifications will be fulfill at shaping and erecting the reinforcement bars:
the difference between the length specified in the technical documentation and
the cut length (if the length of the bars is greater than 10 m) is ±25 mm;
The concrete cover it is measured from the face of the concrete to the face of the
longitudinal reinforcement.
6.3.5 Applicable
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
44 of 54
no.
6.3.6 Checks
For each and type provided, according with standard NE 012/2-2010 the control
operation will have the following:
At the designer or owner request, or when there is any doubt regarding the quality of the
reinforcement, mechanical checks will be made according to standard STAS 6605-78.
6.3.7 Materials
6.3.8 Quantity
STAS 438/3-89
P 59-1986 – Technical instructions for designing and using welded mesh reinforcement
of concrete elements
6.4.2 Technology
The quality of the welded mesh: not show rust, dirt and grease;
Will be checked and received the formwork in which the mesh will be erected;
Elimination or replacement of the mesh will be done only if the meshes will have the
following imperfections:
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
45 of 54
no.
- Edges where the not-welded joints of the last transversal bars are in bigger number
than 5% of the total number of joints;
To ensure the correct position of the meshes when the concrete is poured, by following
the thickness of concrete layers from the technical documentation. For this, a number of
spacers will be provided, taking into account the position, diameter and distance between the
bars.
The bars of the mesh will be cut where are holes for the pipes that pass through the slab and
the edges of the holes will be additional reinforced with PC52 bars, that are fixed by welding
or tied with wire on the slab’s reinforcement bars.
The storage of the meshes will be on site in special and marked spaces, on horizontal and dry
places, not directly on the ground to avoid getting dirty or corrode.
The arrangement of the meshes will be done in horizontal stacks and vertical only in special
cases.
The transport and handling will be made with special machines and devices to avoid
deformation and degradation.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
46 of 54
no.
C169-88 Standard for the execution of earthwork fo laying the foundation for civil and
industrial constructions.
STAS 2914-84 Road works. Excavation. General technical requirements for quality.
7.2 Materials
Ballast fillings are made of continuous curve with maximum particle size of 63mm. Ballast must come
form rock stable , unalterable in air, water or frozen must not contain foreign bodies ( lumps of earth ,
coal , wood, crop residues) or altered items.
Ballast must meet the qualitative characteristics specified in SR 662, pct. 2.3.4.2.
Optimal ballast may be achieved by mixing sorts 0-8, 8-16, 16-25, 25-63, or directly from ballast if it
meets the above conditions.
Supply filler will be made only after complete laboratory tests to check whether units meet the
requirements of these specifications, current regulations and only after the approval of the project
supervisor.
The executor shall keep records of quality materials in the form of certificates of quality issued by the
provider .
If the ballast is to be used in a number of sources, supply and storage will be such as to avoid mixing
materials supplied from different sources.
Compaction required ballast water may have come from the public or from other sources , but in this
case should not contain any particulate matter.
Quality materials control is done by the executor through his laboratory in accordance with STAS
4606-80.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
47 of 54
no.
Ballast will be litter layers and compacted to achieve 95% compaction degree and a minimum volume
weight on each layer γd= 21,5 kN/mc.
Furthermore, considering the specific of working, on the backfill at the foundation level will be realized
tests to provide dynamic parameters of the soil (shear moduluis, Poisson coefficient), one test on
each foundation. The tests can be SDMT, SRS, SRT or MASW. It will be realized a test on each
foundation and the results will be send to the designer in order to approve the carry on the
execution.
Checking fillers work will be done under program control attached decisive phases and Article 9 and
10 of this specification.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
48 of 54
no.
8 STRUCTURE MAINTENANCE
During operation, the client will ensure that the structure elements will not be loaded beyond the limit
values prescribed in the project.
Industrial dirt will be removed at regular intervals so that they do not exceed limits. Removal of dust
deposits will be made under an established program for that purpose by the client.
Periodically technical review will be done to check the state of the building. After events of exceptional
character (earthquakes, fires, explosions, damage caused by operation process, etc.) checking of the
structure technical condition is mandatory.
Steel surface coating system for corrosion protection maintenance of will be made in accordance with
technical specifications of the counting system producer.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
49 of 54
no.
Materials needed to achieve the designed solutions can be used only after obtaining technical
approval documents, certificates of conformity. Works contractor will be responsible for any checks,
inspections, certificates or other documents relating to quality of materials used.
Contractor shall appoint a certified technical manager who will directly and permanently overlook the
construction works.
Contractor will implement all quality control measures of works at no additional cost.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
50 of 54
no.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
51 of 54
no.
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
52 of 54
no.
12 FINAL PROVISIONS
During the execution of works all documents necessary for compiling the building book will be stored,
namely: the project that led to the execution, the on site provision issued during execution of works,
official reports of quality reception and hidden works made during execution and quality certificates of
materials used, testing bulletins, etc.
Any necessary correction works will be executed only with the approval or support of the designer.
Materials will be stored in minimum quantities and only after consulting with project supervisor. A
minimum number of containers will be installed, only the strictly necessary. Only containers and
similar mobile containers may be used. The use of wooden structures, tents, etc. is prohibited for
safety reasons.
Contractor shall inform in his offer of estimated space need for site organization. No changes to the
site organization can be done without the prior written consent of OMV-Petrom.
Gravel and other filling materials used for substructure must be approved by the beneficiary or his
representative before the installation or before excavation begins.
Contractor shall adjust the work program of work site to the required schedule. The normal duration of
working time on site is Monday to Friday from 7.00h to 20.00h.
Only personnel with work experience in refineries or specifically trained for this can be used in the
construction works inside Petrobrazi refinery.
All safety regulations and standards for working within a refinery will be followed by the contractor.
All the measures mentioned in this specification should be included in the lump sum offered price.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
53 of 54
no.
Besides measurements of safety and health at work legally valid, the entire area will be protected by
taking appropriate measures in accordance with internal rules on safety and health at work within
Petrobrazi refinery.
Besides legally valid fire protection measures, the entire area will be protected by taking appropriate
measures in accordance with internal rules on protection against fire in the Petrobrazi refinery.
Contractor will implement all measures for fire prevention works in hazardous areas without additional
costs.
Client PU-D-
EPCC BARBUNCESTI
Doc. ROA0915422512-EX-
COMPRESSOR STATION
no.: CS-CAL-005-01-B
Rev.
01
TENDER BOOK / no.:
CAIET DE SARCINI CONFIND Page
54 of 54
no.
The contractor declares that due to inspection of the construction site, he has knowledge about all
relevant conditions on site (e.g. access, necessary protection measures, underground facilities,
storage possibilities, scaffolding etc.) and these conditions are considered in the lump sum price offer.
All relevant works and materials, which are necessary to fulfil the scope described in the
specifications, are responsibility of the contractor. Therefore all related materials and works shall be
considered in the lump sum prices.
Unless otherwise provided for, all work described is inclusive of the supply of the pertinent materials
and products as well as unloading, storage and transport to the place where it is to be used. Any
packing material and transport aids shall be removed from the construction site and disposed without
any extra charge on the OMV-PETROM.
Execution periods will not be extended in case of winter- and adverse-weather conditions.
The contract prices shall be LUMP SUM prices, fixed and not subject to escalation for the whole
duration of works.
Overtime surcharges for weekend/holiday work and/or night work, shall only be applied on company’s
special demand to reduce agreed execution time.
If not indicated otherwise, the offered unit prices and rates LUMP SUM are valid on a possible
elevation. All necessary measures like scaffolding, lifting devices etc shall be included in the LUMP
SUM prices.
Waiting and idle times will not be reimbursed. This is also to be applied to any waiting times related to
getting work permits.