Concrete Volume and Estimate-HSD
Concrete Volume and Estimate-HSD
1 of
SUMMARY
2 of
MATERIAL QTY UNIT UNIT COST COST
1. Cement 143 bags 265.00 PHP 37,794.30
2. Sand 6.00 cu.m. 1400.00 PHP 8,400.00
3. Gravel 12.00 cu.m. 1300.00 PHP 15,600.00
3 of
vol of cement: ratio of cement / total ratio x dry volume
total ratio: 6
Vol of cement: 0.28 cu.m.
9.88 cf ; 1 cf = 1 bag (40kg)
say : 10 bags
W=1m
L=1m
COLUMN
b: 0.30 m.
d: 0.30 m.
h: 0.30 m.
h=0.3
vol 0.03 cu.m. ;bxdxh
qty. : 6 pcs.
Total vol.: 0.162 cu.m. ; vol x qty.
SUMMARY
cement (40kg.) 2 bags ; Total vol x 8
sand: 0.07 cu.m. ; Total vol x .44
gravel: 0.14 cu.m. ; Total vol x .88 d = 0.3
b = 0.3
BEAM
L: 5.00 m.
b: 0.30 m.
d: 0.40 m.
vol 0.60 cu.m. ;bxdxh
qty. : 6 pcs.
4 of
Total conc. vol.: 3.6 cu.m. ; vol x qty.
SUMMARY L=5
cement (40kg.) 36 bags ; Total vol x 8
sand: 1.51 cu.m. ; Total vol x .44
gravel: 3.02 cu.m. ; Total vol x .88
FOOTING
L: 1.00 m.
w: 1.00 m.
t: 0.35 m.
vol 0.35 cu.m. ;bxdxh
qty. : 6 pcs.
Total conc. vol.: 2.1 cu.m. ; vol x qty. L=1
SUMMARY
cement (40kg.) 21 bags ; Total vol x 8
sand: 0.88 cu.m. ; Total vol x .44
gravel: 1.76 cu.m. ; Total vol x .88
SLAB
L: 8.00 m.
w: 6.00 m.
t: 0.13 m.
vol 6.00 cu.m. ; bxdxh
qty. : 1 pcs.
Total conc. vol.: 6 cu.m. ; vol x qty. L=8
SUMMARY
cement (40kg.) 60 bags ; Total vol x 8
sand: 2.52 cu.m. ; Total vol x .44
gravel: 5.04 cu.m. ; Total vol x .88
WALL FOOTING
5 of
L: 20.00 m.
w: 0.60 m.
t: 0.20 m.
Total conc. vol.: 2.40 cu.m. ; bxdxh
SUMMARY
6 of
H=1m
d=0.4
7 of
b=0.3
t=0.35
w=1
t=0.125
w=6
8 of
t=0.2
w=0.6
L=20
9 of
vol101
https://www.youtube.com/channel/UCZOgAMxZ_
https://www.youtube.com
YouTube Channel? YES Thank you.
outube.com/channel/UCZOgAMxZ_kb3s5s_9psMZA
Thank you. If you are using my program with
b3s5s_9psMZAA/
GRAVEL
y program without subcribing, SHAME ON Y
GRAVEL
HAME ON YOU.!!