Soil Investigation Quotation Comparision

The document compares quotes from 5 different companies for soil investigation work involving borehole drilling and testing. The work involves drilling 50 boreholes to depths of up to 30 meters. The table lists the rates quoted by each company for different aspects of the work like boring charges per meter for different soil/rock types, mobilization costs, equipment shifting charges, testing costs etc. It also calculates the total amount for each company based on their quoted rates. VR Geotechnical from Erode provides the lowest total quote of Rs. 997,500, while Mars Synergy from Chennai provides the highest quote of Rs. 2,445,000.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
119 views1 page

Soil Investigation Quotation Comparision

The document compares quotes from 5 different companies for soil investigation work involving borehole drilling and testing. The work involves drilling 50 boreholes to depths of up to 30 meters. The table lists the rates quoted by each company for different aspects of the work like boring charges per meter for different soil/rock types, mobilization costs, equipment shifting charges, testing costs etc. It also calculates the total amount for each company based on their quoted rates. VR Geotechnical from Erode provides the lowest total quote of Rs. 997,500, while Mars Synergy from Chennai provides the highest quote of Rs. 2,445,000.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Soil investigation Quotation Comparision

VR Geotechnical (Erode) Geo Engineering (Chennai) Velciti (Chennai) Time institute (Trichy) Mars Synergy (Chennai)
Sr.No Description Unit
Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount

1 Boring Charges per  'm' for soil from Rmt 1750 5 50 437,500.00 850 5 50 212,500.00 3650 5 50 912,500.00 1500 5 50 375,000.00 4750 5 50 1,187,500.00
Ground level to 10 m

2 Boring Charges per  'm' for soil from 10m  Rmt 2500 - 900 - 3650 - 1500 - 1750 -
to 20m

3 Boring Charges per  'm' for soil from 20m  Rmt 2750 - 950 - 3950 - 2000 - 2150 -
to 30m

Boring Charges per  'm'  for soft rock (RQD


4 less then 10%)   Rmt 3000 1.5 50 225,000.00 3000 1.5 50 225,000.00 5500 1.5 50 412,500.00 2000 1.5 50 150,000.00 5500 1.5 50 412,500.00

Boring Charges per 'm'  for dense medium


5 rock(RQD varies from 10% to 30%)  Rmt 3200 1 50 160,000.00 4000 1 50 200,000.00 5700 1 50 285,000.00 2500 1 50 125,000.00 5500 1 50 275,000.00

Boring Charges per 'm'  for Hard rock(RQD


6 Greater than 30%)  Rmt 3500 1 50 175,000.00 5000 1 50 250,000.00 5900 1 50 295,000.00 3500 1 50 175,000.00 6500 1 50 325,000.00

7 Mobilization &Demobilization Ls - 45000 45,000.00 - - 45000 45,000.00

8 Shifting charge per shifting - 2000 1 50 100,000.00 - - 1500 1 50 75,000.00

9 Analysis of field test results Per bore - - - - 2500 1 50 125000

10 Working water for drilling Per bore - 2500 1 50 125,000.00 - - - -

11 Conducting tests Per bore - 3000 1 50 150,000.00 - - - -

Analysis of field test results and


12 Ls - 75000 75000 - - - -
submission

Total Amount (Rs.) 997,500.00 Total Amount (Rs.) 1,382,500.00 Total Amount (Rs.) 1,905,000.00 Total Amount (Rs.) 825,000.00 Total Amount (Rs.) 2,445,000.00