Soil investigation Quotation Comparision
VR Geotechnical (Erode) Geo Engineering (Chennai) Velciti (Chennai) Time institute (Trichy) Mars Synergy (Chennai)
Sr.No Description Unit
Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount Rate One Bore No of Bore Total Amount
1 Boring Charges per 'm' for soil from Rmt 1750 5 50 437,500.00 850 5 50 212,500.00 3650 5 50 912,500.00 1500 5 50 375,000.00 4750 5 50 1,187,500.00
Ground level to 10 m
2 Boring Charges per 'm' for soil from 10m Rmt 2500 - 900 - 3650 - 1500 - 1750 -
to 20m
3 Boring Charges per 'm' for soil from 20m Rmt 2750 - 950 - 3950 - 2000 - 2150 -
to 30m
Boring Charges per 'm' for soft rock (RQD
4 less then 10%) Rmt 3000 1.5 50 225,000.00 3000 1.5 50 225,000.00 5500 1.5 50 412,500.00 2000 1.5 50 150,000.00 5500 1.5 50 412,500.00
Boring Charges per 'm' for dense medium
5 rock(RQD varies from 10% to 30%) Rmt 3200 1 50 160,000.00 4000 1 50 200,000.00 5700 1 50 285,000.00 2500 1 50 125,000.00 5500 1 50 275,000.00
Boring Charges per 'm' for Hard rock(RQD
6 Greater than 30%) Rmt 3500 1 50 175,000.00 5000 1 50 250,000.00 5900 1 50 295,000.00 3500 1 50 175,000.00 6500 1 50 325,000.00
7 Mobilization &Demobilization Ls - 45000 45,000.00 - - 45000 45,000.00
8 Shifting charge per shifting - 2000 1 50 100,000.00 - - 1500 1 50 75,000.00
9 Analysis of field test results Per bore - - - - 2500 1 50 125000
10 Working water for drilling Per bore - 2500 1 50 125,000.00 - - - -
11 Conducting tests Per bore - 3000 1 50 150,000.00 - - - -
Analysis of field test results and
12 Ls - 75000 75000 - - - -
submission
Total Amount (Rs.) 997,500.00 Total Amount (Rs.) 1,382,500.00 Total Amount (Rs.) 1,905,000.00 Total Amount (Rs.) 825,000.00 Total Amount (Rs.) 2,445,000.00