IMS Module 3 Part 1
IMS Module 3 Part 1
TECHNIQUES
MODULE 3
.1 PROJECT MANAGEMENT &
NETWORK ANALYSIS
A project is composed of jobs, tasks or functions and activities that are related to each
other a project is any human undertaking with a clear beginning and a clear ending.
planning, scheduling and controlling the work during any worthwhile project is the main
task for any project manager. Project planning calls for detailing the project into activities,
estimating resources requirements and time for each activity, and describing activity
interrelationships. Scheduling requires the details of starting and completion dates for
each activity. Normally for any project, we may be interested in answering questions like
if any activity is delayed , what effect will this have on the overall completion time of the
project?
if there are any additional funds are available to reduce the time to perform certain
activities, how should they be spent,
❑ One of the important technique used in project management is
Network analysis.
❑ Network analysis is a technique used for planning and
scheduling large projects in the field of construction,
maintenance, fabrication, purchasing, computer system
installation, research and development designs.
❑ Large projects are broken down to individual activities and are
arranged in logical sequence.
❑ It is also decided which task will be carried out sequentially and
which task will be performed simultaneously.
❑ Network analysis helps in designing, planning, coordinating,
controlling and in decision making in order to accomplish the
A number of network techniques have been developed. The most popular modem
project.
Any activity which does not consume either any resources or time is known
as dummy activity. These are imaginary activities. They are used to
preserve the logic of network. These activities are normally needed when
two or more activities in a network have same head and tail events or
when some activities in network have same predecessor activities. It is
represented as a dotted Arrow line
EFT (Earliest finish time)
This is the earliest possible time at which an activity can finish. This is
represented on the top right corner outside operation in a rectangle.
LFT (LATEST FINISH TIME)
It is the total time by which the operation must be completed so that the
schedule date for the completion of the project may not be delayed. It
may be represented in a triangle below the outside operation circle. In the
below network for the last operation E LFT=EFT,, this is true for every network.
CRITICAL PATH