AMC Process in Plant Maintenance: Kalyan Chakravarthi

1) The document describes the AMC process for preventive and breakdown maintenance in SAP plant maintenance. This includes creating service masters, outline agreements, maintenance task lists, plans, and releasing maintenance orders that trigger purchase requisitions and purchase orders. 2) For preventive maintenance under AMC, maintenance plans are scheduled which release preventive maintenance orders. These generate purchase requisitions and subsequent purchase orders to outsource the service. Service entry sheets are created against the purchase orders. 3) For breakdown maintenance, maintenance orders are created referencing the outline agreement, generating purchase requisitions and purchase orders as above for outsourcing the breakdown service.

Uploaded by

vadiraj tanjore
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views

AMC Process in Plant Maintenance: Kalyan Chakravarthi

1) The document describes the AMC process for preventive and breakdown maintenance in SAP plant maintenance. This includes creating service masters, outline agreements, maintenance task lists, plans, and releasing maintenance orders that trigger purchase requisitions and purchase orders. 2) For preventive maintenance under AMC, maintenance plans are scheduled which release preventive maintenance orders. These generate purchase requisitions and subsequent purchase orders to outsource the service. Service entry sheets are created against the purchase orders. 3) For breakdown maintenance, maintenance orders are created referencing the outline agreement, generating purchase requisitions and purchase orders as above for outsourcing the breakdown service.

Uploaded by

vadiraj tanjore
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

AMC Process in Plant Maintenance

November 14, 2013 | 2,264 Views |

Kalyan Chakravarthi
more by this author
PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)
 Enterprise Asset Management

 share   0  
 share   
 tweet  
 share   

Follow   RSS

Purpose: – In any SAP Plant Maintenance implementation, customer will ask about how to handle the
Annual Maintenance Contract Process (AMC Process) in SAP. People might follow different procedures,
here I have documented one process and this might be useful for the freshers.
AMC Process for Preventive Maintenance :
1.      Create Service Master.
2.      Create Outline Agreement
3.      Create General Maintenance Task list
4.      Create Maintenance Plan
5.      Schedule Maintenance Plan
6.      Release Maintenance Order
7.      Create Purchase Order against the Purchase Requisition
8.      Create Service Entry sheet against the Purchase Order
9.    Perform  TECO  for the Maintenance Order
Step 1:- Create Service Master by using the transaction code AC01.
Step 2:- Create Outline Agreement / Service Contract for AMC by using the Transaction
Code ME31K
Enter necessary data like Vendor, Agreement Type, Item Category as “D” and Acct Assignment Cat. as
“F”
Enter the service short text, here I have taken 4 visits for Preventive and two visits for Free Break Down.

Since system will not allow zero price, entered minimum amount as 0.01 USD for Free Break Down
Services.

Details of Service specifications for Preventive Maintenance are as below


Details of Service specifications for Free Break down Services.

SAVE the Outline Agreement after entering all the details. System will generate Outline agreement
number.
Step 3:- Create General Maintenance Task List by using the transaction Code IA05 and enter the control
key as PM03 and enter the Outline agreement number as shown below.
By using the service specifications button copy the services from the agreement

Step 4:- Create single cycle maintenance plan by using the transaction code IP41 and enter the Task List
which was created earlier.
Step 5:- Schedule Maintenance Plan and Release Maintenance Order

1. Maintenance Plan can be scheduled manually by using the Transaction IP10, in regular practice
these maintenance plans will be run on batch job in background.
2. Upon scheduling , Maintenance Orders will be triggered with reference to the intervals maintained
in Maintenance Plan  
3. The Maintenance Orders (Preventive) called will be released to process further
4. Purchase requisition will be triggered on release of Maintenance Order.

Step 6:- Process of Purchase Requisition to Purchase Orders


Use the transaction ME21n, Create Purchase Order with reference to the Purchase Requisitionnumber
which was created in the Maintenance Order.

Step 7:-Use the transaction ML81n, Create service entry sheet with reference to the Purchase Order
which was created from Purchase Requisition shown in the earlier screen shot.

After completion of the Service entry sheet service cost will reflect in the Maintenance Order and do the
TECO and other normal PM process like settlement and business completion of the order.

AMC for Breakdown Maintenance Process


Use the Transaction IW31 and create Break down Maintenance Order as like normal PM Process.
Enter the Control Key as PM03 for the Operation which is to be done by the vendor as per the Outline
Agreement and enter the Outline Agreement number with Item number 0020

Process of Breakdown Maintenance Order similar to Preventive Maintenance Order

1. Release the Maintenance Order


2. Purchase Requisition created from Maintenance Order is further processed to Purchase Order.

  3.  Create a Service Entry Sheet against the Purchase Order.  

4. Accept the Service Entry Sheet.


5. Perform Maintenance Order for Technical Completion and Settlement.

   6.   Perform Business Completion


Upon releasing of the Break Down Order system will create Purchase Requisition and with reference
to PR, PO has ben created.
Create Service Entry Sheet with reference to Purchase Order

Similarly for any Paid Break Down Services, we can create one more line item in the Outline Agreement and
process the same like Break Down Order.