PATOQ - Concrete Works

This document provides an agenda and procedures for pouring quality concrete works. It outlines ensuring equipment is functional for pouring ready-mixed concrete within 3.5 hours and testing concrete strength at 7 and 28 days. The procedure lists items to consider like rebar and formwork checklists as well as concrete accessories needed. It also gives cement factors based on required strength and ratios for sand and gravel per cubic meter of concrete. Finally, it states to clean and clear areas after stripping by sorting materials and removing unsuitable items.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
200 views6 pages

PATOQ - Concrete Works

This document provides an agenda and procedures for pouring quality concrete works. It outlines ensuring equipment is functional for pouring ready-mixed concrete within 3.5 hours and testing concrete strength at 7 and 28 days. The procedure lists items to consider like rebar and formwork checklists as well as concrete accessories needed. It also gives cement factors based on required strength and ratios for sand and gravel per cubic meter of concrete. Finally, it states to clean and clear areas after stripping by sorting materials and removing unsuitable items.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PRE-ACTIVITY TRAINING AND ORIENTATION ON QUALITY

CONCRETE WORKS
CONCRETE WORKS

Agenda

• Scope of Work Background and Description


• Procedure
CONCRETE WORKS

In pouring/placing of ready mixed concrete make sure all the equipment such as pump
crete, tower crane, vibrator and other accessories needed are functionally accordingly. As our
requirements from the batching plant all ready mixed concrete shall be placed and poured on
or before 3.5 hours Testing of concrete shall be required for seven (7) days and twenty eight
(28) days until it attained the required strength. Hence there are some items of to be
considered hereunder
CONCRETE WORKS
1. Approved rebar checklist
Procedure 2. Approved formworks checklist
3. Structural slab / Finish floor line reference and Floor level depression
4. Floor finish (rough or straight to finish)
5. Construction joint location should be established
6. Required Beam & slab shear bars
7. Provide Concrete accessories
Concrete epoxy bond
Water stop
Curing compound
Integral waterproofing
Sufficient quantity of tools / equipment / manpower
Concrete vibrator
Shovels and pails
Trowel / power trowel / floats / spreaders
Manpower (skilled and labor)
Leveling laser equipment
CONCRETE WORKS

CEMENT FACTOR TO BE CONSIDERED

SAND (S1) AND


CEMENT FACTOR
REQUIRED STRENGTH GRAVEL(3/5’’) PER
(BAGS)
CU.M

3000 PSI 11.0 11.0 : 2 : 4

4000 PSI 12.5 12.5 : 2 : 4

CLEANING CLEARING THE AREA

After stripping the areas, all material for rebars and formworks shall
be sorting and segregates accordingly. All unsuitable materials shall be
spread or removed at the proposed building. The contractor should assigned
sufficient manpower for cleaning on this matter.