Earth Filling
Earth Filling
783370 Kokrajhar,BTR,Assam,INDIA
A Project Report
On
“EARTH FILLING”
Conclusion
Introduction
Earth filling is a task which is done with compacting the floor’s soil about 6 layers and
the layers should not exceeding 300 mm to 450 mm in thickness. The soil used for filling should
be free from grass, roots, leaves and other foreing material. It should better slightly moist
different material is used, each material will have different property and thus different effect in
the structure. The different filling material that could be use is red clayey soil, stone dust,
Backfilling shall be done after the foundation has completely set. Backfilling shall be carried out
in layers and each layer shall be thoroughly compacted. Inadequate compaction is likely to cause
1. Backfilling work should not start until the Site Engineer gives his approval to do so.
Material use for backfilling shall be any one or combination of different soil types.
compaction equipment and method. The soil layer should slightly moist which will help
3. After compaction of final layer of soil Site Engineer should test the soil at least from 3
cores and it should be tested in laboratory for the degree of compaction achieve.
4. If the soil is excessively wet, it shall be allow to dry sufficiently before compaction.
5. Compaction should be done with mechanize way but in some cases it should be done by
increased by compactive efforts. compaction means to press the soil particles to each other by
mechanical method. During compaction air is forced out from voids and hence density is
increased. Objective of compaction is to increase the density, bearing capacity, shear strength.
a) Rollers
b) Rammers
c) Vibrators.
CONCLUSION
Earth filling and Compaction should be done after properly complete the set up of foundation. It
should be done in layers properly as to prevent the failure of foundation and flooring of the structure. It
should be done by mechanically or hand operate to compact the soil on the site.