Critical Path Method
Critical Path Method
The activities timing are deterministic in nature that is why each and every activity only a single
duration will be given with that we have to proceed everything.
D I
2 5 8
E
B 3 6
1 J
F H
7
4
G
2) Calculate of the expected duration and variance of each activity
Formula: Mean te_expected duration
te = (to + 4tm + tp)/ 6
Variance formula:
Ᵹ2 = [(tp – to)/6]2
2 5 8
A (36)
E (34)
B (34)
3 6
1 J (34)
F (36) H
(36)
C (35)
7
4
G (34)
Earliest start time = forward pass
Esj = max (Esi + Dij)
Latest completion time = backward pass
Lci = min ( Lci – Dij)
72 105 141
36 69 141
D (33) I (36)
2 5 8
A (36)
37 71
0
34 71
0
E (34)
B (34)
3 6
1 J (34)
F (36) H
(36)
C (35)
7
4
G (34)
35 107
35 107
c) Critical path
i) Esi = Lci
ii) Esj = Lcj
iii) Esj – Esi = Lcj – Lci = Dij
Expected completion time: 35 + 36 + 36 + 34 = 141 Weeks
72 105 141
36 69 141
D (33) I (36)
2 5 8
A (36)
37 71
0
34 71
0
E (34)
B (34)
3 6
1 J (34)
F (36) H
(36)
C (35)
7
4
G (34)
35 107
35 107
d) What is the probability of completing of before 145 weeks?
Find probability:
P(x ≤ 22) = P [(x- u)/Ᵹ) ≤ (145 – 141)/2.56]
P(x ≤ 22) = P [ Z ≤ 1.56] = 94.06 %