Method Statement - UPS System
Method Statement - UPS System
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
1 PAGE :-
METHOD STATEMENT
FOR
INSTALLATION, TESTING & COMMISSIONING
OF
UPS SYSTEM
AL SHAHAD TOWER
5B+G+38
DOHA, THE STATE OF QATAR
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
2 PAGE :-
This Cover Page is a record of all revisions of the document identified above by numbers and title.
All previous Cover Pages are hereby superseeded and are to be destroyed.
- INDEX -
1.0 SCOPE.....................................................................................................3
2.0 PURPOSE...............................................................................................3
3.0 REFERENCE.........................................................................................3
8.0 SAFETY...................................................................................................5
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
3 PAGE :-
1.0 SCOPE
2.0 PURPOSE
3.0 REFERENCE
The supervisor shall supervise the installation work and the engineer shall
check and approve the installation according to project specification,
manufacturer’s instruction and approved shop drawing for installation of
.UPS
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
4 PAGE :-
6.1 UPS must be stored in a dry place and they must be handled
carefully.
6.2 UPS must be protected from direct sun light by placing them in sun
shades and to be protected from any moisture condensation.
6.4 UPS must be checked for any defect or damage before installation.
: The following tools and equipment shall be used for installation of UPS
7.1 Crane
Ensure that all tools and equipment are in good working condition.
.Calibration and certification must be checked also prior to its use
EW/ELEC/MS-11 DOC.NO.
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
5 PAGE :-
8.0 SAFETY
8.1 Safety equipment like Hard hats, Safety shoes, Coveralls, Gloves
Goggles when necessary etc. to be worn at all times.
8.4 Good house keeping and protection to be done for all installed UPS
and accessories.
9.1 Installation
9.1.3 Using fork lift UPS and battery shall be moved to the place of
installation.
9.1.4 While positioning the Battery and UPS it shall be ensured that
clearence between them and walls as per approved drawings.
9.3 Inspection
EW/ELEC/MS-11 DOC.NO.
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
6 PAGE :-
9.3.2.1 The size of power cable for UPS input, output, bypass and
battery cabinets.
10.2 The cables of sufficient size shall be run to support the load
bank.
10.3 The final connections to the UPS shall be made at the output
point once it has been established that it is DEAD and safe to do so.
10.4 The load bank shall be energized with zero loads and checked for
functionality if satisfactorely the UPS shall be energized and switched
to support the load bank.
10.5 Load shall be applied to the KW rating of the UPS (assuming unit
power factor load bank) and the UPS allowed running for 15 minutes.
10.6 On starting the battery discharge test the mains shall be failed at
the closest isolation point upstream of the UPS to simulate mains
failure. Battery voltage and current will be recorded from the UPS
display at 60 seconds intervals until cut-off voltage is achieved.
EW/ELEC/MS-11 DOC.NO.
1 ISSUE :-
INSTALLATION, TESTING &
05/01/2016 DATE :- COMMISSIONING OF UPS
7 PAGE :-
10.7 The main supply shall be re-installed and the UPS allowed
restarting, recharge voltage and current shall be recorded and the
battery allowed recharging.
10.8 Before disconnecting the load bank it shall be allowed to cool off
load and then switched off. The output of the UPS will be isolated to
allow the load bank to be disconnected.
10.9 On completion of the load bank test all connections, power and
control shall be remade and checked.
10.9.a If the battery still requires re-charging the UPS shall be started
and left to recharge either supplying the load or isolated from it.
10.9.b The Load bank shall be packed for removal and stored safety
until dispatched.