Method Statement - Earthing & Lightning Protection

This document provides a method statement for installing an earthing and lightning protection system for a tower project in Qatar. It outlines the scope, purpose, references, quality control, materials, storage, tools, safety procedures, installation process, and testing and inspection requirements. The installation process will follow approved shop drawings and specifications to properly install earthing pits, lightning protection rebar, and ensure all equipment is grounded and bonded. Upon completion, testing will check earth resistance values and continuity of all conductors and connections.

Uploaded by

Khaled Badawy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
583 views6 pages

Method Statement - Earthing & Lightning Protection

This document provides a method statement for installing an earthing and lightning protection system for a tower project in Qatar. It outlines the scope, purpose, references, quality control, materials, storage, tools, safety procedures, installation process, and testing and inspection requirements. The installation process will follow approved shop drawings and specifications to properly install earthing pits, lightning protection rebar, and ensure all equipment is grounded and bonded. Upon completion, testing will check earth resistance values and continuity of all conductors and connections.

Uploaded by

Khaled Badawy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

1 PAGE :-

METHOD STATEMENT

FOR

INSTALLATION OF EARTHING & LIGHTNING


PROTECTION SYSTEM

AL SHAHAD TOWER
5B+G+38
DOHA, THE STATE OF QATAR

Rev. Date Prepared By Reviewed By Approved By Description

0 05/01/16
EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

2 PAGE :-

This Cover Page is a record of all revisions of the document identified above by numbers and title.
All previous Cover Pages are hereby superseeded and are to be destroyed.

- INDEX -

.Item No Page No.

1.0 SCOPE.........................................................................3

2.0 PURPOSE.....................................................................3

3.0 REFERENCE.................................................................3

4.0 QUALITY CONTROL......................................................3

5.0 MATERIAL USED..........................................................3

6.0 STORAGE AND HANDLING............................................3

7.0 TOOLS AND EQUIPMENT..............................................4

8.0 SAFETY........................................................................4

9.0 INSTALLATION PROCEDURE........................................4

10.0 TESTING AND INSPECTION


EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

3 PAGE :-

1.0 SCOPE

The scope is to cover the method required for the installation of earthing
.and lightning protection system

2.0 PURPOSE

The purpose of this procedure is to define the method of installation for


.earthing system for the above project

3.0 REFERENCE

The following are to be used as references for the installation of earthing &
lightning protection system

3.1 Approved Material Submittal

3.2 Project Specification (Division 16 ref:16744 & 16060)

3.3 Approved Shop Drawing

4.0 QUALITY CONTROL

Quality of installation at site shall be ensured by project team of Engineer’s,


.Supervisor and QA/QC

The supervisor shall supervise the installation work and the engineer’s shall
check and approve the installation according to specifications and approved
.shop drawing for installation of earthing and lightning protection

5.0 MATERIAL USED

Materials to be used shall be as per the approved material and should be


.inspected prior to use

6.0 STORAGE AND HANDLING

6.1 Materials must be stored in a dry place and they must be handled
carefully.
EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

4 PAGE :-

6.2 Materials must be protected from direct sun light by placing them in
sun shades.

7.0 TOOLS AND EQUIPMENT

The following tools and equipment shall be used for installation of earthing
:system

7.1 Welding Machine

7.2 Hand tools

7.3 Testing Equipment: Earth Resistance Megger

8.0 SAFETY

8.1 Safety equipment like Hard hats, Safety shoes, Coveralls, Gloves
Goggles when necessary etc. to be worn at all times.

8.2 Ensure work area is clean and tidy.

8.3 Ensure adequate workface lighting is available.

9.0 INSTALLATION PROCEDURE

9.1 Check approval of the material submittal. Confirm materials supplied


to site are as per contract requirements.

9.2 Install earthing and lightning protection system in full compliance


with the requirements of Local authorities, and project specification.

9.3 Check the complete earthing and lightning protection system is


electrically and mechanically continuous to provide an independent
fault current return path to the earthing source.

9.4 Check earthing terminal connectors and brazing equipment and


bolted connections carried out as per standards.

9.5 Check the impedance of equipment (earth loop) at any point in the
electrical wiring system, which has to be sufficiently low to limit the
voltage to earth and to facilitate the operation of the circuit protective
devices in the circuits.
EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

5 PAGE :-

9.6 Complete lightning protection rebar welded to the piles cap in


accordance with the piles layout. Location and approved shop
drawings.

9.7 Complete earthing pits buried under ground in accordance with the
project layout, location and drawings.

9.8 System earthing will be for non-current carrying metal part of the
electrical installation such items as cabinets, exposed metal parts
apparatus as well as enclosures, doors grilles, etc., protecting or
shielding electrical equipment from direct access to unauthorized
personnel.

9.9 All socket outlets, power apparatus, lighting fixtures, switches,


switchboards or panel boards, shells of all water heaters, etc., will be
earthed.

9.10 After completion of installation earthing resistance check to be done


as per regulation and required values.

9.11 Earthing System shall be installed as per project specification.

10.0 TESTING AND INSPECTION

10.1 On completion of the installation the following isolated and


combined measurement and / or checklists has to be made and
the results recorded in a lighting protection system checklist.

10.2 The resistance to earth of each local earth electrode and in


addition the resistance to earth of the complete earth termination
system.

10.3 Each local earth electrode has to be taken with the test point
between the down conductor and the earth electrode in the
disconnected position (isolated measurement)

10.4 A further measurement has to be taken with the test point in the
connected position (combined measurement).
EW/ELEC/MS-07 DOC.NO.

1 ISSUE :-
INSTALLATION OF EARTHING &
05/01/16 DATE :- LIGHTNING PROTECTION SYSTEM

6 PAGE :-

10.5 The resistance of earth electrode will be checked with the


calibrated earth resistance tester for the value of less than 5
Ohms as per specification .If the resistance is nor achieved further
earth electrode will be driven to the ground untill achieving the
specified earth resistance .System include

10.6 The result of visual check of all conductors, bonds and joints and
their measured electrical continuity

- END OF METHOD STATEMENT -