Date : August 10, 2021
Project : GLORIETTA 4
Subject : PROPOSAL FORM FOR SUPPLY AND APPLICATION OF INTERIOR PAINTING WORKS(STEEL COLUMN & TRUSSES@ WELLNESS)
Project Location: Glorietta, Ayala Center, Makati City
Attention : Mr. Derek Palisoc
MDC-Area Manager
Thru : Mr. Drexler M. Escorial
MDC-Quantity Surveyor
PARTICULARS Qty Unit Total Unit Cost Amount
I.General Requirements
1.00 Mobilization/Demobilization lot 1.00 30,000.00 30,000.00
2.00 Temporary Facilities lot 1.00 8,000.00 8,000.00
3.00 Site Sanitary-General Cleaning lot 1.00 5,000.00 5,000.00
4.00 Safety Provisions
PPE including New Normal Requirement lot 1.00 35,000.00 35,000.00
Signages lot 1.00 3,000.00 3,000.00
Working Platforms w/ complete accessories to be supplied by MDC & installed by MDC
5.00 Permits/Bonds and Insurances lot 1.00 - -
6.00 Project Supervisions
Project In Charge lot 1.00 44,000.00 44,000.00
Safety Supervisor lot 1.00 40,000.00 40,000.00
7.00 As-built Plans N/A
SUBTOTAL GENERAL REQUIREMENT 165,000.00
II.Measured Works
A.1 To Steel Column 660.00 m2 -
A.2 To Trusses 3,991.32 l.m -
A.3 To Purlins 1,034.69 l.m -
SUBTOTAL-MEASURED WORKS -
GRAND TOTAL 165,000.00
Warranty : 1 year after substantial completion
Completion : as per project requirement
Submitted by: PZL CONSTRUCTION, INC.
Terms & Conditions :
1. Ten percent ( 10% ) down payment.
2. Progress billings shall be every 30 days.
3. The schedule of completion shall be as per your project requirements.
4. Water and power requirements shall be equitably charge to us.
5. Any changes in plans shall be considered as change orders.
6. VAT Inclusive
Prepared by:
GLENDA M.VALENZUELA
QS
Date : August 10, 2021
Project : LEPANTO REDEVELOPMENT PROJECT
MAKATI DEVELOPMENT CORPORATION
Subject : Supply and Application of Fire Rated Paints
Project Location: CALAMBA, LAGUNA
Attention : Mr. Romel Jan Erick Villacampa
MDC-Project In Charge
Thru : Ms. Fina Kamille A. Pel
MDC-Quantity Surveyor
PARTICULARS Qty Unit Total Unit Cost Amount
I.General Requirements
1.00 Mobilization/Demobilization lot 1.00 250,000.00 250,000.00
2.00 Temporary Facilities lot 1.00 150,000.00 150,000.00
3.00 Site Sanitary-General Cleaning lot 1.00 50,000.00 50,000.00
4.00 Safety Provisions
PPE including New Normal Requirement lot 1.00 50,000.00 50,000.00
Signages lot 1.00 30,000.00 30,000.00
Working Platforms w/ complete accessories & scaffoldings lot 1.00 1,350,000.00 1,350,000.00
Additional requirements due to Pandemic lot 1.00 150,000.00 150,000.00
5.00 Permits/Bonds and Insurances lot 1.00 167,616.13 167,616.13
6.00 Project Supervisions
Project In Charge lot 1.00 300,000.00 300,000.00
Quality Control lot 1.00 300,000.00 300,000.00
Safety Officer lot 1.00 264,000.00 264,000.00
7.00 As-built Plans N/A
SUBTOTAL GENERAL REQUIREMENT 3,061,616.13
II.Measured Works
A. Supply & Application
1 Intumescent Paint for B14 Steel Structural Framing 7,712.14 m2 6,968.72 53,743,739.12
2 Intumescent Paint for B12 Steel Structural Roof Framing 878.09 m2 6,968.72 6,119,162.76
SUBTOTAL-MEASURED WORKS 59,862,901.88
GRAND TOTAL 62,924,518.00
Warranty : 1 year after substantial completion
Completion : as per project requirement
Submitted by: PZL CONSTRUCTION, INC.
Terms & Conditions :
1. Ten percent ( 10% ) down payment.
2. Progress billings shall be every 30 days.
3. The schedule of completion shall be as per your project requirements.
4. Water and power requirements shall be equitably charge to us.
5. Any changes in plans shall be considered as change orders.
6. VAT Inclusive
8.Intumescent Paint Jotun Brand-Delivery Availability:60 days
Prepared by:
GLENDA M.VALENZUELA
QS
Date : August 10, 2021
Project : METAL FORMING AND FITOUT CENTER
MDC BUILD PLUS
Subject : Supply & Application of Fire Rated Paints
Project Location: BRGY. SAN FELIX, SANTO TOMAS BATANGAS
Attention : Mary Joy Andal
Procurement Specialist
PARTICULARS Qty Unit Total Unit Cost Amount
I.General Requirements
1.00 Mobilization/Demobilization lot 1.00 100,000.00 100,000.00
2.00 Temporary Facilities lot 1.00 70,000.00 70,000.00
3.00 Site Sanitary-General Cleaning lot 1.00 30,000.00 30,000.00
4.00 Safety Provisions
PPE lot 1.00 10,000.00 10,000.00
Signages lot 1.00 30,000.00 30,000.00
Additional requirements due to Pandemic lot 1.00 80,000.00 80,000.00
5.00 Permits/Bonds and Insurances lot 1.00 4,651.92 4,651.92
6.00 Project Supervisions
Project In Charge lot 1.00 125,000.00 125,000.00
Quality Control lot 1.00 125,000.00 125,000.00
Safety Officer lot 1.00 110,000.00 110,000.00
7.00 As-built Plans N/A
SUBTOTAL GENERAL REQUIREMENT 684,651.92
II.Measured Works
A. Supply & Application of Intumescent Paint
1.00 Plate m2 3.63 6,020.00 21,852.60
2.00 Side Column m2 121.10 6,020.00 729,046.08
3.00 Inner Column m2 30.16 6,020.00 181,563.20
4.00 Cantilever m2 23.76 6,020.00 143,035.20
5.00 Rafter m2 18.59 6,020.00 111,881.70
6.00 Strut m2 18.59 6,020.00 111,881.70
7.00 Steel Beam m2 81.39 6,020.00 489,937.70
SUBTOTAL-MEASURED WORKS 1,789,198.18
###
GRAND TOTAL 2,473,850.10
Warranty : 1 year after substantial completion
Completion : as per project requirement
Submitted by: PZL CONSTRUCTION, INC.
Terms & Conditions :
1. Ten percent ( 10% ) down payment.
2. Progress billings shall be every 30 days.
3. The schedule of completion shall be as per your project requirements.
4. Water and power requirements shall be equitably charge to us.
5. Any changes in plans shall be considered as change orders.
6. VAT Inclusive
8.Intumescent Paint Jotun Brand-Delivery Availability:60 days
9. Scaffolding-Provided and Installed by MDC Build Plus
10.Quantity is Provisional,subject for recon
11. Considering area of rafter, .7 meter strip from column
12. Area of column that was covered by double wall is excluded
13. Girder of overhead crane is excluded
Prepared by:
GLENDA M.VALENZUELA
QS