150 KV Substation Cost Estimation
150 KV Substation Cost Estimation
NO ITEM SCOPE
1 Land Preparation
2 Civil Works
3 Substation Equipments
4 Substation Automation and Control
5 Commissioning
6 Training
7 PLN Cost
8 150 kV Transmission Line
9 20 kV Transmission Line
150 KV LINE I 150 KV LINE II
S B 144
LA 150 KV 110 V LA 150 KV 110 V
150 KV 3 3 3 3
150 KV
10 KA
10 KA
1250 A 1250 A
170 KV 170 KV
2000 A S2DA 2000 A S2D A
40 K A 40 K A
400-800/5/5A 400-800/5/5A
170 KV 170 KV
3150 A GL 313 3150 A GL 313
40 K A 40 KA
A
170 KV S2DA 170 KV S2DA 170 KV S2DA 1 70 KV S 2DA
2000 A 2000 A 2000 A 2 000 A
150k V 40 K A 40 KA 40 K A 4 0 KA
B
170 K V 170 K V
3150 A 3150 A
GL 313 GL 313
40 K A 40 KA
200/5A 200/5A
Y Y
d1 30M VA d1 3 0M V A
Yo 1 5 0 /2 0 k V Yo 1 5 0 /2 0 k V
300/5A 300/5A
200/5A 200/5A
40 ohm 40 ohm
24 KV 24 KV
1250 A 1250 A
12,5 KA 12,5 K A
20kV
AEMCO
SUMMARY
COST ESTIMATION
150/20 KV 30 MVA SUBSTATION
PT ASIA PACIFIC FIBER - KARAWANG
MUHAMMAD FAJAR
ELECTRO-MECHANIC WORKS SUMMARY
150/20 KV 30 MVA SUBSTATION
PT ASIA PACIFIC FIBER - KARAWANG
TOTAL COST
NO. DESCRIPTION
(IDR)
A SWITCHYARD EQUIPMENTS
I 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, EARTHING Rp 3,767,800,000
II 150 KV LINE BAY : 2 BAYS FOR LINE I & II Rp 6,152,800,000
III 150 kV TRANSFORMER BAY : 2 BAY Rp 4,727,400,000
IV 150 KV BUS-COUPLER BAY : 1 BAY Rp 3,632,700,000
V ENERGY METER PANEL Rp 312,000,000
VI 150 KV SUBSTATION AUXILIARIES EQUIPMENT Rp 1,011,000,000
VII 150/20 KV POWER TRANSFORMERS AND AUXILIARIES Rp 17,596,800,000
VIII 20 kV SWITCHGEARS AND POWER CABLES Rp 4,294,700,000
B SUBSTATION AUTOMATION
I SUBSTATION AUTOMATION HARDWARE Rp 900,000,000
II SUBSTATION AUTOMATION SOFTWARE Rp 800,000,000
III AC SUPPLY EQUIPMENT FOR SUBSTATION AUTOMATION Rp 128,200,000
IV POWER LINE CARRIER FOR 150 KV SUBSTATION Rp 1,600,600,000
V DC POWER SUPPLAY Rp 265,900,000
VI TELECOMUNICATION EQUIPMENT Rp 1,024,200,000
C MISCELLANEOUS Rp 517,800,000
D TRAINING Rp 50,000,000
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
3,767,800,000
6,152,800,000
4,727,400,000
3,632,700,000
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
20 KV INCOMING COMPATIBLE WITH AMR EXISTING 1 SET (COMPLETE WITH 6 SETS METERING
PER-PANEL AS REQUIRED) INCLUDING ETHERNET SWITCH FOR CONNECTION TO WAN AND
MISCELLANOUS EQUIPMENT MATERIAL, RACK, CABINET, CABLES, CLAMPS, CONNECTORS,
COMPRESSION TERMINAL, CONNECTION TO INDIVIDUAL ITEMS OF EQUIPMENT, TEST TERMINAL,
AUXILIARY RELAY, INTERIOR LAMP HEATER ... ETC
312,000,000
1,011,000,000
17,596,800,000
4,294,700,000
41,495,200,000
B SUBSTATION AUTOMATION
I SUBSTATION AUTOMATION HARDWARE
1 SERVER AND OPERATOR WORK STATION PACKAGE 1 lot
2 LONGGER PRINTER. 1 set
3 COLOUR LASER PRINTER 1 set
4 GPS TIME REFERNCE CLOCK 1 set
5 GATE WAY 1 set
6 MODEM 2 sets
7 ETHERNET SWITCH FOR INTER-BAY SYSTEM-1. 1 lot
8 ETHERNET SWITCH FOR INTER-BAY SYSTEM-2. 1 lot 900,000,000 900,000,000
9 ETHERNET SWITCH FOR CONNECTION TO WAN. 1 set
10 OPTICAL CABLE FOR INTER BAY CONNECTION CORD. 1 lot
11 UTP CABLE TO CONNECTION IED FOR ETHERNET SWITCHES IN THE SAME CUBICLE 1 lot
12 RACK FOR SERVER, GATE WAY AND ETHERNET SWITCH. 1 set
13 FURNITURE 1 lot
14 ENGINEERING TOOLS AND TEST EQUIPMENT 1 set
15 MISCELLANOUS EQUIPMENT AND MATERIAL FOR AUTOMATION HARDWARE 1 lot
900,000,000
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
- MODBUS
4 HMI SOFTWARE. 1 lot
5 CONFIGURATION AND SETTING SOFTWARE FOR IED 1 lot
800,000,000
128,200,000
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
3 TELEPROTECTION EQUIPMENT 2 sets 90,500,000 181,000,000
4 CUBICLE AND ACCESSORIES 2 sets 135,500,000 271,000,000
5 PARTY LINE 1 set 10,500,000 10,500,000
6 TELEPHONE TERMINAL. 6 sets 17,600,000 105,600,000
7 MISCELLANEOUS MATERIAL TO COMPLETE THE SYSTEM. 1 lot 70,500,000 70,500,000
1,600,600,000
V DC POWER SUPPLAY
1 48 VDC BATTERY SUITABLE FOR SUPPLYING ALL 48 VDC LOAD 1 set 103,600,000 103,600,000
2 BATTERY CHARGER FOR 48 VDC BATTERY COMPLETE WITH PANEL BOARD 1 set 111,500,000 111,500,000
3 48 VDC SWITCH FUSE DISTRIBUTION BOARD 1 set 50,800,000 50,800,000
265,900,000
VI TELECOMUNICATION EQUIPMENT
1 NODE SDH-ADM 2 sets 122,100,000 244,200,000
2 STM-4 LINE INTERFACE (2 PORTS) 2 ports 50,000,000 100,000,000
3 2 MB INTERFACE (8 PORTS) 2 ports 5,000,000 10,000,000
4 2 MB DIGITAL BRANCHING 2 sets 40,000,000 80,000,000
5 DIU DATA INTERFACING UNIT 64 KBPS (4 PORTS) 2 ports 55,000,000 110,000,000
6 VF 2/4 WIRE E/M INTERFACE (MIN 6 PORTS) 2 ports 7,500,000 15,000,000
7 VF/SUBSC INTERFACE (MIN 6 PORTS) 2 ports 10,000,000 20,000,000
8 MAIN DISTRIBUTION FRAME 2 sets 15,000,000 30,000,000
9 RACK/CABINET 1 lot 40,000,000 40,000,000
10 DIGITAL TELEPROTECTION 2 sets 90,000,000 180,000,000
11 PAX (8 TRUNKS - 8 SUBCRIBES) COMPLETE WITH TELEPHONE SET OF EACH SUBSCRIBER 1 set 180,000,000 180,000,000
12 MISCELLANEOUS EQUIPMENT AND MATERIAL INCLUDING CABLES, PATCH CORD, PIG TAIL, ETC 1 lot 15,000,000 15,000,000
1,024,200,000
4,718,900,000
COST ESTIMATION
150/20 KV 30 MVA SUBSTATION
PT ASIA PACIFIC FIBER - KARAWANG
ELECTRO-MECHANIC WORKS
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
C MISCELLANEOUS
1 CCTV SYSTEM 1 lot 49,800,000 49,800,000
2 MISCELLANEOUS EQUIPMENT AND MATERIAL REQUIRED FOR CCTV SYSTEM 1 lot 10,800,000 10,800,000
3 FAULT RECORDER EQUIPMENT 2 sets 202,000,000 404,000,000
4 INTERFACE MARSHALLING CUBICLE FOR SCADA 1 set 28,200,000 28,200,000
5 MISCELLANEOUS EQUIPMENT AND MATERIAL REQUIRED FOR FAULT RECORDING 1 lot 25,000,000 25,000,000
517,800,000
50,000,000
46,781,900,000
CIVIL WORKS SUMMARY
150/20 KV 30 MVA SUBSTATION
PT ASIA PACIFIC FIBER - KARAWANG
TOTAL COST
NO. DESCRIPTION
(IDR)
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
I PREPARATION WORK
1 Building Permit ( Ijin Mendirikan Bangunan / IMB ) ls 1.00 50,000,000 50,000,000
2
2 Site clearing m 200.00 40,000 8,000,000
3 Setting survey and installation of setting plan ls 1.00 12,500,000 12,500,000
4 Site office ( 4m x 6 m ) ls 1.00 48,000,000 48,000,000
5 Site storage ( 4 m x 10 m ) ls 1.00 80,000,000 80,000,000
6 Soil investigation for controle building :
- SPT, DCPT, Core Drilling and Test Lab ls 1.00 12,500,000 12,500,000
- Report Sets 3.00 2,500,000 7,500,000
II EARTH WORK
3
1 Excavation work m 360.00 80,000 28,800,000
3
2 Backfiil m 225.00 80,000 18,000,000
3
3 Sand layer ( compacted sand, thickness 10 cm ) m 6.00 300,000 1,800,000
IX CABLE DUCT
1 Concrete cable duct for cable duct type I m 20.00 3,923,000 78,460,000
2 Concrete cable duct for cable duct type II m 21.00 3,923,000 82,383,000
3 Concrete cable duct for cable duct type III m 21.00 3,923,000 82,383,000
4 Concrete cable duct for cable duct type IV m 23.00 3,923,000 90,229,000
5 Concrete cable duct for cable duct type V m 20.00 3,923,000 78,460,000
XI LIGHTNING PROTECTION
1 Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories Lot 1.00 12,500,000 12,500,000
clamps steel plate, material support and pole, grounding system for
controle building
XII FIRE ALARM
1 Alarm bell 6'' ( 150 mm ) diameter included installation wiring No 1.00 1,250,000 1,250,000
2 Smoke detector included installation wiring No 6.00 1,250,000 7,500,000
3 Fixed and rate of rice temperature detector included installation wiring No 2.00 1,250,000 2,500,000
4 MCFA ( Master control fire alarm ) included indication lamp, battery. Etc No 1.00 37,500,000 37,500,000
TOTAL 2,129,474,000
COST ESTIMATION
150/20 KV 30 MVA SUBSTATION
PT ASIA PACIFIC FIBER - KARAWANG
CIVIL WORKS : CONTROL BUILDING FOR 200 KV ROOM
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
I PREPARATION WORK
1 Building Permit ( Ijin Mendirikan Bangunan / IMB ) ls 1.00 50,000,000 50,000,000
2
2 Site clearing m 320.00 40,000 12,800,000
3 Setting survey and installation of setting plan ls 1.00 12,500,000 12,500,000
4 Site office ( 4m x 6 m ) ls 1.00 48,000,000 48,000,000
5 Site storage ( 4 m x 10 m ) ls 1.00 80,000,000 80,000,000
6 Soil investigation for controle building :
SPT, DCPT, Core Drilling and Test Lab ls 1.00 12,500,000 12,500,000
Report Sets 1.00 2,500,000 2,500,000
II EARTH WORK
3
1 Excavation work m 600.00 80,000 48,000,000
3
2 Backfiil m 400.00 80,000 32,000,000
3
3 Sand layer ( compacted sand ) m 10.00 300,000 3,000,000
IX CABLE DUCT
1 Concrete cable duct for cable duct type I m 40.00 3,923,000 156,920,000
2 Concrete cable duct for cable duct type II m 12.00 3,923,000 47,076,000
3 Concrete cable duct for cable duct type III m 3.00 3,923,000 11,769,000
XI LIGHTNING PROTECTION
1 Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories Lot 1.00 12,500,000 12,500,000
clamps steel plate, material support and pole, grounding system for
controle building
XII FIRE ALARM
1 Alarm bell 6'' ( 150 mm ) diameter included installation wiring No 1.00 1,250,000 1,250,000
2 Smoke detector included installation wiring No 10.00 1,250,000 12,500,000
3 Fixed and rate of rice temperature detector included installation wiring No 2.00 1,250,000 2,500,000
4 MCFA ( Master control fire alarm ) included indication lamp, battery. Etc No 1.00 37,500,000 37,500,000
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
1 Earth Work
a. Site Clearing m2 5,000 40,000 200,000,000
b. Common Excavation m3 100 80,000 8,000,000
c. Back fill with selected material m3 - -
d. Import fill with selected material m3 - -
e. Slope protection (stone masonry) m3 - -
f. Soil Disposal m3 - -
g. Plank name project unit 1 2,500,000 2,500,000
h. Fence security of project 2 m high m' - -
i. Bouwplank m' 350 80,000 28,000,000
2 Road (new)
a. Prepare compacted subgrade m2 - -
b. Macadam surface course m2 - -
c. Base structure (Sub base & Base coarse) m2 500 500,000 250,000,000
d. 50 mm Asphalt hot mix m2 500 150,000 75,000,000
e. 50 mm Asphalt penetration m2 - -
TOTAL II 3,643,000,000
III Site and Road Lighting
ESTIMATED COST
NO DESCRIPTION QUANTITY
UNIT PRICE PRICE
(IDR) (IDR)
II 20 kV TRANSMISSION LINE
TOTAL -