Program of Works and Detailed Estimates: Central Philippines State University

This document provides a program of works and detailed cost estimates for the construction of an annex classroom and library building at the Ilog Campus of the Central Philippines State University. It includes 13 items with quantities, units, unit prices, and amounts for each work component. The major work components include mobilization/demobilization, government fees, temporary facilities, safety measures, site works, excavation, backfilling, concrete works, steel reinforcements, and forms and falseworks. The total estimated cost for all 13 items is over 5 million pesos.

Uploaded by

Johnrey Garde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views7 pages

Program of Works and Detailed Estimates: Central Philippines State University

This document provides a program of works and detailed cost estimates for the construction of an annex classroom and library building at the Ilog Campus of the Central Philippines State University. It includes 13 items with quantities, units, unit prices, and amounts for each work component. The major work components include mobilization/demobilization, government fees, temporary facilities, safety measures, site works, excavation, backfilling, concrete works, steel reinforcements, and forms and falseworks. The total estimated cost for all 13 items is over 5 million pesos.

Uploaded by

Johnrey Garde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Republic of the Philippines

CENTRAL PHILIPPINES STATE UNIVERSITY


Kabankalan City, Negros Occidental 6111
Website: www.cpsu.edu.ph
E-mail add: [email protected] or [email protected]
Contact No.: 09173015565 (Mobile); (034) 702-9903 (Landline)

PROJECT MANAGEMENT AND MONITORING OFFICE


________________________________________________________________________

Project Title : ANNEX CLASSROOM AND LIBRARY BUILDING AT ILOG CAMPUS

Location : CENTRAL PHILIPPINES STATE UNIVERSITY - ILOG CAMPUS

PROGRAM OF WORKS AND DETAILED ESTIMATES

no. Items qty unit unit price amount


MOBILIZATION AND
1
DEMOBILIZATION INCL.

Mobilization 1 l.s @ ₱ 200,000.00 ₱ 200,000.00

Demobilization 1 l.s @ ₱ 200,000.00 ₱ 200,000.00

Subtotal ₱ 400,000.00

Labor and Equipment 1 l.s @ ₱ 240,000.00 ₱ 240,000.00

TOTAL ₱ 640,000.00
2
GOVERNMENT FEES

Building Permits 1 l.s @ ₱ 200,000.00 ₱ 200,000.00

Occupancy Permit 1 l.s @ ₱ 100,000.00 ₱ 100,000.00

Subtotal ₱ 300,000.00

TOTAL ₱ 300,000.00
3
TEMPORARY FACILITIES
Site office for engineer (with
aircon to be turnover) 1 l.s @ ₱ 50,000.00 ₱ 50,000.00
Temporary bunkhouse for
workers 1 l.s @ ₱ 60,000.00 ₱ 60,000.00
Temporary perimeter
enclosure 1 l.s @ ₱ 20,000.00 ₱ 20,000.00

Subtotal ₱ 130,000.00

TOTAL ₱ 130,000.00
OCCUPATIONAL SAFETY AND
4
HEALTH PROGRAM

Safety Signages 6 sets @ ₱ 950.00 ₱ 5,700.00

Barricades 5 sets @ ₱ 850.00 ₱ 4,250.00

PPE's 300 m.d @ ₱ 315.00 ₱ 94,500.00


Safety and Health Personell 300 m.d @ ₱ 595.00 ₱ 178,500.00

Subtotal ₱ 282,950.00

TOTAL ₱ 282,950.00
5
SITE CLEARING AND LAY-OUTING
Removing of unnecessary
objects 1 l.s @ ₱ 280,000.00 ₱ 280,000.00

Lay-outing 1 l.s @ ₱ 25,000.00 ₱ 25,000.00

Subtotal ₱ 305,000.00

Labor 1 l.s ₱ 91,500.00 ₱ 91,500.00

Equipment 1 l.s ₱ 183,000.00 ₱ 183,000.00

TOTAL ₱ 579,500.00
6
EXCAVATION AND DISPOSAL
Excavation for Footing and
Wall footing 681.072 cu.m. @ ₱ 500.00 ₱ 340,536.00
Disposal of Excavated
Materials 681.072 cu.m. @ ₱ 300.00 ₱ 204,321.60

Subtotal ₱ 544,857.60

TOTAL ₱ 544,857.60
7
BACKFILLING AND COMPACTION

Materials Backfill Materials 804 cu.m. @ ₱ 500.00 ₱ 402,000.00

Compaction 964.8 sq.m. @ ₱ 200.00 ₱ 192,960.00

Subtotal ₱ 594,960.00

Labor 1 l.s ₱ 178,488.00 ₱ 178,488.00

TOTAL ₱ 773,448.00
8
GRAVEL BASE
Materials Aggregate Base Coarse (G1) 60.9 cu.m @ ₱ 650.00 ₱ 39,585.00

Subtotal ₱ 39,585.00

TOTAL ₱ 39,585.00
SOIL TREATMENT (RETICULATION
9
SYSTEM)

Labor and Materials 1 l.s @ ₱ 350,000.00 ₱ 350,000.00


10
FORMWORKS AND FALSEWORKS
Materials Phenolic Boards (3 uses) 400 sheets @ ₱ 1,350.00 ₱ 540,000.00

Coco Lumber (2x3x8) 2684.79 pcs @ ₱ 20.95 ₱ 56,246.35

#2 1/2 Common Wire Nail 150 kgs @ ₱ 80.00 ₱ 12,000.00

#1 Common Wire Nail 30 kgs @ ₱ 80.00 ₱ 2,400.00


#4 Common Wire Nail 1395 kgs @ ₱ 80.00 ₱ 111,600.00

Subtotal ₱ 722,246.35

Labor 1 l.s @ ₱ 216,673.91 ₱ 216,673.91

TOTAL ₱ 938,920.26
11
CONCRETE WORKS (4000 psi)
Materials Footing 166.04 cu.m ₱ 5,050.00 ₱ 838,502.00

Footing Tie Beams 95.97 cu.m ₱ 5,050.00 ₱ 484,648.50

Columns (Footing to GF) 27.004 cu.m ₱ 5,050.00 ₱ 136,370.20

Columns (GF to 2F) 25.1168 cu.m ₱ 5,050.00 ₱ 126,839.84

Columns (2F to RB) 25.1168 cu.m ₱ 5,050.00 ₱ 126,839.84

Beams (2F) 69.33 cu.m ₱ 5,050.00 ₱ 350,116.50

Beams (RB) 69.33 cu.m ₱ 5,050.00 ₱ 350,116.50

Stairs 6.6 cu.m ₱ 5,050.00 ₱ 33,330.00

Ramps 7.3 cu.m ₱ 5,050.00 ₱ 36,865.00

Slab (roof top/4000 psi) 127.05 cu.m ₱ 5,050.00 ₱ 641,602.50

Slab (2nd Floor/4000 psi) 127.05 cu.m ₱ 5,050.00 ₱ 641,602.50

Slab on Grade (3000 psi) 113.02 cu.m ₱ 5,050.00 ₱ 570,751.00

Subtotal ₱ 4,337,584.38

Labor 1 l.s ₱ 1,301,275.31 ₱ 1,301,275.31

TOTAL ₱ 5,638,859.69
STEEL REINFORCEMENTS
12
(GRADE 40)
Materials Footing 19670 kgs ₱ 47.00 ₱ 924,490.00

Footing Tie Beams 5992 kgs ₱ 47.00 ₱ 281,624.00

Columns (Footing to GF) 2106 kgs ₱ 47.00 ₱ 98,982.00

Columns (GF to 2F) 3668.6 kgs ₱ 47.00 ₱ 172,424.20

Columns (2F to RB) 3668.6 kgs ₱ 47.00 ₱ 172,424.20

Beams (2F) 9424 kgs ₱ 47.00 ₱ 442,928.00

Beams (RB) 6529.4 kgs ₱ 47.00 ₱ 306,881.80

Stairs 718 kgs ₱ 47.00 ₱ 33,746.00

Concrete Truss 472 kgs ₱ 47.00 ₱ 22,184.00

Ramps 756 kgs ₱ 47.00 ₱ 35,532.00

Slab (roof top/4000 psi) 9900 kgs ₱ 47.00 ₱ 465,300.00


Slab (2nd Floor/4000 psi) 6900 kgs ₱ 47.00 ₱ 324,300.00

Slab on Grade (3000 psi) 9980 kgs ₱ 47.00 ₱ 469,060.00


Consumables (G.I #16 tie
wires, etc.) 1 lot ₱ 100,000.00 ₱ 100,000.00

Subtotal ₱ 3,849,876.20

Labor 1 l.s ₱ 1,154,962.86 ₱ 1,154,962.86

TOTAL ₱ 5,004,839.06
STEEL REINFORCEMENTS
13
(GRADE 33)
Materials Footing 54217.5 kgs ₱ 47.00 ₱ 2,548,222.50

Footing Tie Beams 7987.8 kgs ₱ 47.00 ₱ 375,426.60

Columns (Footing to GF) 3377 kgs ₱ 47.00 ₱ 158,719.00

Columns (GF to 2F) 3998.67 kgs ₱ 47.00 ₱ 187,937.49

Columns (2F to RB) 3998.67 kgs ₱ 47.00 ₱ 187,937.49

Beams (2F) 8907.6 kgs ₱ 47.00 ₱ 418,657.20

Beams (RB) 5275.01 kgs ₱ 47.00 ₱ 247,925.47

Stairs 701.2 kgs ₱ 47.00 ₱ 32,956.40

Concrete Truss 529.4 kgs ₱ 47.00 ₱ 24,881.80

Ramps 939.2 kgs ₱ 47.00 ₱ 44,142.40

Slab (2nd Floor/4000 psi) 8135 kgs ₱ 47.00 ₱ 382,345.00

Slab on Grade (3000 psi) 9842 kgs ₱ 47.00 ₱ 462,574.00

Subtotal ₱ 5,071,725.35

Labor 1 l.s ₱ 1,521,517.61 ₱ 1,521,517.61

TOTAL ₱ 6,593,242.96
14
MASONRY WORKS
Materials CHB (150mm) 993 sq.m ₱ 225.00 ₱ 223,425.00

Rebars (10mm) 875 lgths ₱ 185.00 ₱ 161,875.00

Coarse Sand 84.405 cu.m ₱ 560.00 ₱ 47,266.80

Portland Cement 1519.29 bags ₱ 260.00 ₱ 395,015.40

CHB (100mm) 697 sq.m ₱ 190.00 ₱ 132,430.00

Rebars (10mm) 581 lgths ₱ 185.00 ₱ 107,485.00

Coarse Sand 31.365 cu.m ₱ 560.00 ₱ 17,564.40

Portland Cement 550.63 bags ₱ 260.00 ₱ 143,163.80

Subtotal ₱ 1,228,225.40
Labor 1 l.s ₱ 368,467.62 ₱ 368,467.62

TOTAL ₱ 1,596,693.02
15
CONCRETE PLASTERING
Materials Portland Cement 1432.6 bags ₱ 260.00 ₱ 372,476.00

Coarse Sand 48.64 sq.m ₱ 560.00 ₱ 27,238.40

Subtotal ₱ 399,714.40

Labor 1 l.s ₱ 119,914.32 ₱ 119,914.32

TOTAL ₱ 519,628.72
16
FLOOR TOPPING AND TILES
Materials Glazed Tiles 60x60cm 1583 pcs ₱ 280.00 ₱ 443,240.00

Unglazed Tiles 60x60cm 1861 pcs ₱ 280.00 ₱ 521,080.00

Cement Mortar 60 bags ₱ 260.00 ₱ 15,600.00

Grout 350 kgs ₱ 200.00 ₱ 70,000.00

Tile Adhesive 64 bags ₱ 200.00 ₱ 12,800.00

Tile Trim 80 lgths ₱ 35.00 ₱ 2,800.00

Subtotal ₱ 1,065,520.00

Labor 1 l.s ₱ 319,656.00 ₱ 319,656.00

TOTAL ₱ 1,385,176.00
17
CEILING WORKS
Materials 4.5mm x 4ft x 8ft Hardiflex 800 shts @ ₱ 500.00 ₱ 400,000.00

0.40mm thick Double Furring 1040 lgths @ ₱ 120.00 ₱ 124,800.00

Concrete Nails 50 kgs @ ₱ 120.00 ₱ 6,000.00

Blind Rivets 30 boxes @ ₱ 250.00 ₱ 7,500.00


Rod suspension hanger with
adjustment spring 900 set @ ₱ 65.00 ₱ 58,500.00

W-Clip 50 roll @ ₱ 350.00 ₱ 17,500.00


0.2mm thk-20mm x 20mm x
2.44m Wall Angle 420 lgths @ ₱ 60.00 ₱ 25,200.00

Subtotal ₱ 639,500.00

Labor 1 l.s @ ₱ 191,850.00 ₱ 191,850.00

TOTAL ₱ 831,350.00
FABRICATED MATERIALS AND
18
HARDWARES

Doors 1 lot @ ₱ 500,000.00 ₱ 500,000.00

Windows 1 lot @ ₱ 700,000.00 ₱ 700,000.00


Subtotal ₱ 1,200,000.00

Labor 1 l.s @ ₱ 300,000.00 ₱ 300,000.00

TOTAL ₱ 1,500,000.00
BOOK SHEELVES AND OTHER
19
FURNITURES

Labor and Materials 1 l.s @ ₱ 1,500,000.00 ₱ 1,500,000.00


20
RAILINGS

Labor and Materials 1 l.s @ ₱ 400,000.00 ₱ 400,000.00


21
PAINTING WORKS

Labor and Materials 1 l.s @ ₱ 830,785.29 ₱ 830,785.29


22
ELECTRICAL WORKS

Labor and Materials 1 l.s @ ₱ 3,500,000.00 ₱ 3,500,000.00


23
PLUMBING WORKS

Labor and Materials 1 l.s @ ₱ 501,717.29 ₱ 501,717.29


FIRE DETECTION AND ALARM
24
SYSTEM

Labor and Materials 1 l.s @ ₱ 400,000.00 ₱ 400,000.00

SUMMARY

ITEM
NO.
1 MOBILIZATION AND DEMOBILIZATION INCL. EQUIPMENT
₱ 640,000.00
2 GOVERNMENT FEES
₱ 300,000.00
3 TEMPORARY FACILITIES
₱ 130,000.00
4 OCCUPATIONAL SAFETY AND HEALTH PROGRAM
₱ 282,950.00
5 SITE CLEARING AND LAY-OUTING
₱ 579,500.00
6 EXCAVATION AND DISPOSAL
₱ 544,857.60
7 BACKFILLING AND COMPACTION
₱ 773,448.00
8 GRAVEL BASE
₱ 39,585.00
9 SOIL TREATMENT (RETICULATION SYSTEM)
₱ 350,000.00
10 FORMWORKS AND FALSEWORKS
₱ 938,920.26
11 CONCRETE WOKRS (4000 psi)
₱ 5,638,859.69
12 STEEL REINFORCEMENTS (GRADE 40)
₱ 5,004,839.06
13 STEEL REINFORCEMENTS (GRADE 33)
₱ 6,593,242.96
14 MASONRY WORKS
₱ 1,596,693.02
15 CONCRETE PLASTERING
₱ 519,628.72
16 FLOOR TOPPING AND TILES
₱ 1,385,176.00
17 CEILING WORKS
₱ 831,350.00
18 FABRICATED MATERIALS AND HARDWARES
₱ 1,500,000.00
19 BOOK SHEELVES AND OTHER FURNITURES
₱ 1,500,000.00
20 RAILINGS
₱ 400,000.00
21 PAINTING WORKS
₱ 830,785.29
22 ELECTRICAL WORKS
₱ 3,500,000.00
23 PLUMBING WORKS
₱ 501,717.29
24 FIRE DETECTION AND ALARM SYSTEM
₱ 400,000.00

DIRECT COST ₱ 34,781,552.88

INDIRECT COST

TAX (10%) ₱ 3,478,155.29

OCM (5%) ₱ 1,739,077.64

TOTAL PROJECT COST ₱ 40,000,000.00

Prepared by:

LIEZEL S. DIAZ
PMMO-Staff

Reviewed by:

ELEUTERIO D. MARIÑO, III, C.E.


OIC - DIRECTOR / PMMO

Recommended by:

MARC ALEXEI CAESAR B. BADAJOS, PAE, Ph.D.


VICE PRESIDENT FOR ADMINISTRATION AND FINANCE

Funds Available:

VICENTE M. TRIO, JR.


Budget Officer

Approved by:

ALADINO C. MORACA, Ph.D.


SUC PRESIDENT