0% found this document useful (0 votes)
241 views2 pages

Gtu MCQ: Power Quality and Management (2180911)

This document contains a set of multiple choice questions about power quality and management. It includes questions about topics like total power factor vs displacement power factor, definitions of terms like sag, swell, surge and transient events, characteristics that define a transient, types of power system disturbances, purposes of grounding, and what electromagnetic interference refers to.

Uploaded by

Yogesh Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
241 views2 pages

Gtu MCQ: Power Quality and Management (2180911)

This document contains a set of multiple choice questions about power quality and management. It includes questions about topics like total power factor vs displacement power factor, definitions of terms like sag, swell, surge and transient events, characteristics that define a transient, types of power system disturbances, purposes of grounding, and what electromagnetic interference refers to.

Uploaded by

Yogesh Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

GTU MCQ

Power Quality and Management (2180911)  MCQs

MCQs of Introduction to Power Quality


Showing 31 to 40 out of 48 Questions   1 2 3 4 5  

31. The total power factor is greater than the displacement power factor,
(a) True
(b) False
Answer: Option (b)

32. __________ is the RMS reduction in the AC voltage at power frequency from half of a cycle to a few seconds’ duration.
(a) Surge
(b) Swell
(c) Sag
(d) Transient
Answer: Option (c)

33. Electrical transient characterized by a sharp increase in voltage or current is called as


(a) Sag
(b) Surge
(c) Swell
(d) Transient
Answer: Option (b)

34. __________ is the RMS increase in AC voltage at power frequency from half of a cycle to a few seconds’ duration
(a) Swell
(b) Sag
(c) Transient
(d) Surge

Answer: Option (a)

35. Subcycle disturbance in the AC waveform evidenced by a sharp, brief discontinuity of the waveform is known as ______________
(a) Swell
(b) Surge
(c) Sag
(d) Transient

Answer: Option (d)

36. The primary characteristics that define a transient are


(i) peak amplitude
(ii) rise time
(iii) fall time
(iv) frequency of oscillation
(a) (i), (iii), (iv)
(b) (i), (ii), (iv)
(c) (ii), (iii), (iv)
(d) (i), (ii), (iii), (iv)

Answer: Option (d)

37. ______________ are low-frequency phenomena that result in voltage sags or swells.
(a) Power frequency disturbances
(b) Power system transients
(c) Power system harmonics
(d) Electro magnetic interference

Answer: Option (a)


38. _______________ are fast, short-duration events that produce distortions such as notching, ringing, and impulse.
GTU MCQ
(a) Power frequency disturbances
(b) Power system transients
Power Quality and harmonics
(c) Power system Management (2180911)  MCQs
(d) Electro Static discharge

Answer: Option (b)

39. Grounding is done (i) for safety


(ii) to provide a low-impedance path for the flow of fault current in case of a ground fault
(iii) to create a ground reference plane for sensitive electrical
equipment
(a) Only (i)
(b) Only (ii)
(c) (i) & (ii)
(d) (i), (ii), (iii)

Answer: Option (d)

40. _________________ refers to the interaction between electric and magnetic fields and sensitive electronic circuits and devices.
(a) Radio frequency interference
(b) Power frequency disturbances
(c) Electromagnetic interference
(d) Power system harmonics

Answer: Option (c)