0% found this document useful (0 votes)
26 views

PMP Chapter-7 Test - Project Cost Management

The document provides a 10 question practice exam on project cost management. It tests knowledge of concepts like cost variance, schedule performance index, basis of estimate, and how to calculate cost performance index from given metrics like budget at completion, actual cost, and schedule performance index.

Uploaded by

sddd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views

PMP Chapter-7 Test - Project Cost Management

The document provides a 10 question practice exam on project cost management. It tests knowledge of concepts like cost variance, schedule performance index, basis of estimate, and how to calculate cost performance index from given metrics like budget at completion, actual cost, and schedule performance index.

Uploaded by

sddd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

How to pass PMP Certification exam in First Attempt, contact us at

http://www.JustPMP.com/contact

Free 2 full length PMP® Practice test, visit us


http://www.JustPMP.com/pmp-practice-test

PMP Practice Exam Chapter-7 Project Cost Management


Questions:
1. Cost variance is computed by:
a. Subtracting planned value from actual cost
b. Subtracting actual cost from earned value
c. Subtracting budget at completion from earned value
d. Subtracting BAC from ETC

2. Which of the following is not needed to generate a schedule performance index (SPI)?
a. Earned value
b. Actual cost
c. Planned value
d. Basis of estimate

3. Which of the following is not needed to generate a schedule performance index (SPI)?
a. Earned value
b. Actual cost
c. Planned value
d. Basis of estimate

4. What is a basis of estimate and how does it apply to Earned Value calculations?
a. The basis of estimate is actually earned value (EV)
b. The basis of estimate is a method for determining what the project should cost based on
historical data or bottom-up estimating. It is the foundation for planned value (PV)
c. The basis of estimate is created via the use of stochastic variables and advanced mathematical
models, which will point to the most effective of the three major estimating tools for your
project: analogous, parametric, or bottom-up
d. The basis of estimate is a separate estimating function that addresses management
philosophy. It is not used in earned value calculations

5. You are having a discussion with the key stakeholder about the best estimating method to use
for the upcoming project. You argue for what provides the best team buy-in, while your
stakeholder argues for a bottom-up estimate. What is the real issue?
a. There is no issue - you are both talking about the same thing
b. The stakeholder is correct and you're just not getting it

For Instructor-led Live Online PMP Training, Please reach me [email protected]


For any latest update on PMP Training, visit us: www.JustPMP.com

PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc
c. You are correct and the stakeholder is just not getting it
d. You are both incorrect and need to explore other options

6. CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most likely reason for this
change is:
a. The project manager has not been keeping track of variances on the project to implement
corrections
b. As work packages were being executed, discovery on critical path activities caused estimates
to change drastically on several of the work packages
c. The WBS was inaccurate
d. Several key stakeholders insisted on a last-minute scope change

7. A particular project in the domain of civil construction requires that every on-site worker be
insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation
process so that the insurance cost is estimated and subsequently budgeted?
a. Enterprise Environmental Factor
b. Organizational Process Assets
c. Project Scope Statement
d. Project Management Plan

8. Management Contingency Reserve is identified in which process:


a. Estimate Activity Duration
b. Estimate Costs
c. Determine Budget
d. Estimate Activity Resources

9. Several stakeholders on the project have been questioning the effectiveness of some of the
technical team. While the work is proceeding according to plan, some of the stakeholders are
not satisfied with the work delivered to date, even though it meets requirements specifications.
You have held several meetings with the stakeholders to try to get to the root cause of the
problem. With some of the technical team present at these meetings, it becomes obvious that
some of the stakeholders have had great difficulty in describing what they want. As a result,
some of the delivered product doesn't meet stakeholder expectations. Currently your CPI is 1.3
and the SPI is .89. What is your largest concern right now?
a. Clarifying the requirements collection process
b. The schedule
c. Managing stakeholder expectations
d. An increasing probability that some technical team members may leave the project due to
high levels of frustration with stakeholders

For any latest update on PMP Training, visit us: www.JustPMP.com


PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc
10. You are three months into a six month project. Assume the budget burn rate is constant. The
budget at completion (BAC) is $120,000. AC = $65,000. The SPI = 1.2. What is the CPI of this
project? (Round to 2 decimal places)
a. 1.32
b. 1.25
c. 1.11
d. It cannot be determined from the information given

Answers:
1. B CV = EV - AC

2. B – Actual cost is part of the CPI calculation

3. B

4. B – The basis of estimate is what helps you determine the planned value for the project

5. A – Team buy-in is one of the advantages of a bottom-up estimate

6. B – Significant changes in earned value, such as the one described, usually point to some kind of
discovery on the project, especially since the product was sailing along smoothly until it
appeared to hit a bump. Answer ‘A’ is highly unlikely as is answer ‘C’. Changing scope at the last
minute would also force a change request which may cause a re-baseline of the project. This
would not necessarily change its CPI or SPI

7. C - Project Scope Statement usually contains assumptions and constraints.

8. C

9. B – The first part of the question is a red herring. With an SPI of .89 your biggest concern is the
schedule

10. C – This is a two-part calculation. You must first derive earned value from the SPI formula; SPI =
EV/PV. At this point you know SPI (1.2) and PV ($60,000). Thus solving for EV you get: EV = 1.2 *
$60,000 = $72,000. You can now compute CPI = EV/AC or $72,000/$65,000 = 1.11

For any latest update on PMP Training, visit us: www.JustPMP.com


PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc

You might also like