PMP Chapter-7 Test - Project Cost Management
PMP Chapter-7 Test - Project Cost Management
http://www.JustPMP.com/contact
2. Which of the following is not needed to generate a schedule performance index (SPI)?
a. Earned value
b. Actual cost
c. Planned value
d. Basis of estimate
3. Which of the following is not needed to generate a schedule performance index (SPI)?
a. Earned value
b. Actual cost
c. Planned value
d. Basis of estimate
4. What is a basis of estimate and how does it apply to Earned Value calculations?
a. The basis of estimate is actually earned value (EV)
b. The basis of estimate is a method for determining what the project should cost based on
historical data or bottom-up estimating. It is the foundation for planned value (PV)
c. The basis of estimate is created via the use of stochastic variables and advanced mathematical
models, which will point to the most effective of the three major estimating tools for your
project: analogous, parametric, or bottom-up
d. The basis of estimate is a separate estimating function that addresses management
philosophy. It is not used in earned value calculations
5. You are having a discussion with the key stakeholder about the best estimating method to use
for the upcoming project. You argue for what provides the best team buy-in, while your
stakeholder argues for a bottom-up estimate. What is the real issue?
a. There is no issue - you are both talking about the same thing
b. The stakeholder is correct and you're just not getting it
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc
c. You are correct and the stakeholder is just not getting it
d. You are both incorrect and need to explore other options
6. CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most likely reason for this
change is:
a. The project manager has not been keeping track of variances on the project to implement
corrections
b. As work packages were being executed, discovery on critical path activities caused estimates
to change drastically on several of the work packages
c. The WBS was inaccurate
d. Several key stakeholders insisted on a last-minute scope change
7. A particular project in the domain of civil construction requires that every on-site worker be
insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation
process so that the insurance cost is estimated and subsequently budgeted?
a. Enterprise Environmental Factor
b. Organizational Process Assets
c. Project Scope Statement
d. Project Management Plan
9. Several stakeholders on the project have been questioning the effectiveness of some of the
technical team. While the work is proceeding according to plan, some of the stakeholders are
not satisfied with the work delivered to date, even though it meets requirements specifications.
You have held several meetings with the stakeholders to try to get to the root cause of the
problem. With some of the technical team present at these meetings, it becomes obvious that
some of the stakeholders have had great difficulty in describing what they want. As a result,
some of the delivered product doesn't meet stakeholder expectations. Currently your CPI is 1.3
and the SPI is .89. What is your largest concern right now?
a. Clarifying the requirements collection process
b. The schedule
c. Managing stakeholder expectations
d. An increasing probability that some technical team members may leave the project due to
high levels of frustration with stakeholders
Answers:
1. B CV = EV - AC
3. B
4. B – The basis of estimate is what helps you determine the planned value for the project
6. B – Significant changes in earned value, such as the one described, usually point to some kind of
discovery on the project, especially since the product was sailing along smoothly until it
appeared to hit a bump. Answer ‘A’ is highly unlikely as is answer ‘C’. Changing scope at the last
minute would also force a change request which may cause a re-baseline of the project. This
would not necessarily change its CPI or SPI
8. C
9. B – The first part of the question is a red herring. With an SPI of .89 your biggest concern is the
schedule
10. C – This is a two-part calculation. You must first derive earned value from the SPI formula; SPI =
EV/PV. At this point you know SPI (1.2) and PV ($60,000). Thus solving for EV you get: EV = 1.2 *
$60,000 = $72,000. You can now compute CPI = EV/AC or $72,000/$65,000 = 1.11