Method Statement For Installation of MATV Distribution System
Method Statement For Installation of MATV Distribution System
TEC-274133-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for installation of MATV distribution system
Pages 1 of 7
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer coordinator contractor
Approved
By Project
Manager
3. REFERENCES
3.1. Contract documents
1. Project Specification :- Division 27, Section 274133
2. Contract Drawings :-
3.2. Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr.
Description Material Sub. No. Rev No. Date Remarks
No.
1
2
3
6. Shop Drawings
Sr.
Description Shop Drawings Rev No. Date Remarks
No.
1
2
3
4. DEFINITIONS / ABBREVIATIONS
4.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
4.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
8. MEP - Mechanical Electrical Plumbing
9. MET - Method Statement
10.MIR - Material Inspection Request
11.MSDS - Material Safety Data Sheet
12.PPE -Personal Protective Equipment
13.PQP -Project Quality Plan
14.PTW -Permit To Work ( Working at Height or enclosed spaces)
15.RA -Hazard Identification and Risk Assessment
16.RFIA - Request for Inspection and Approval
17.SPD - Shop Drawing
18.TBM - Temporary Bench Mark
5. RESPONSIBILITIES
5.1. Project Engineer
1. To ensure that all the preparation and application works are carried out according to the Contract
Specification.
2. To ensure that the progressing of works is carried out according to the planned program and as per
the approved Method Statement.
3. To ensure that all the equipment’s and materials required executing the work are available according
to the planned construction program.
4. To coordinate with the Main Contractor MEP Coordinator & Safety Officer for a safe and proper
execution of the works.
5.3. Foreman
1. The foreman will carry out his duties by maintaining continuous coordination with the Site Engineer on
daily basis and ensure proper distribution of the workforce in the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have
enough information to carry out their duties properly.
3. To ensure in consultation with the Site Engineer that the manpower involved in the works are moving
as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advice the Site Engineer of any
requirement for additional resources.
5. To control disposal of waste materials according to the instructions received from the site Engineer.
6. To ensure full coordination with the Safety Officer to maintain safe working and proper housekeeping
of the site, following the approved safety measures and further ensures that all his working team are
aware of the same to prevent accident and losses.
7. To inform the Site Engineer of the areas ready for inspection.
6.2. MATERIAL
Materials used will be as approved by the engineer and installation & routing will be as per the
approved shop drawings.
7. INSTALLATION
Adhere to drawings as closely as possible. The right is reserved to vary the runs and sizes of conduits &
Trays and to make offsets but maintain as far as possible the free area of each section, where necessary to
accommodate conditions arising at the building.
The installation will be carried out according to the approved shop drawings, site requirement and the
Engineer’s instruction at site and comply with local authorities.
7.9. Documentation
1. Prepare As Built Drawings
2. Prepare Operation & Maintenance Manual
3. Prepare Commissioning Report.
9. ATTACHMENTS
9.1. Inspection Checklists
9.2. Inspection Test Plan
9.3. Risk Assessment