Example 2.7 Contd: 2.8 A Full Example of The Four-Stage Transportation Modelling Process
Example 2.7 Contd: 2.8 A Full Example of The Four-Stage Transportation Modelling Process
1275 1450
1 2 3
4 5 6
1450 1025
Figure 2.2 Link volumes arising from ‘all-or-nothing’ traffic assignment procedure.
Destination zone
Origin zone 1 2 3 4 5 6
Table 2.16 Trip productions and attractions for the design year (10 years after baseline year)
In order to compile the trip distribution matrix, the impedance term relating to
the resistance to travel between each pair of zones must be established. In this
case, the travel time is taken as a measure of the impedance and the zone-to-
zone times are given in Table 2.17.
Using a gravity model with the deterrence function in the following form
between zone i and zone j:
Fij = t -2ij
where tij is the time taken to travel between zone i and zone j
The interzonal trips are estimated using Equation 2.3. For example, taking the
trips from zone A to all other zones, it can be seen from Table 2.16 that 6475
38 Highway Engineering
A 10 15 15 20 25 32
B 10 7 5 10 15 22
C 15 7 8 14 16 26
D 15 5 8 6 10 18
E 20 10 14 6 16 12
F 25 15 16 10 16 12
G 32 22 26 18 12 12
PF
i ij Aj PF
i ij
A 6475 22 000
B to A 11 500 10 0.010 115.0 0.317 2053.0
C to A 17 500 15 0.004 77.78 0.214 1388.5
D to A 14 500 15 0.004 64.44 0.178 1150.5
E to A 26 500 20 0.003 66.25 0.183 1182.7
F to A 17 500 25 0.002 28.00 0.077 499.80
G to A 11 500 32 0.001 11.23 0.031 200.50
S = 362.7 S =1 S = 6475
trips were attracted to zone A. Equation 2.3 is used to estimate what propor-
tion of this total amount sets out from each of the other six zones, based on
the relative number of trips produced by each of the six zones and the time taken
to travel from each to zone A. These computations are given in Table 2.18.
When an identical set of calculations are done for the other six zones using
the gravity model, the initial trip matrix shown in Table 2.19 is obtained.
It can be seen from Table 2.19 that, while each individual column sums to
give the correct number of trips attracted for each of the seven zones, each indi-
Destination zone
vidual row does not sum to give the correct number of trips produced by each.
(It should be noted that the overall number of productions and attractions are
equal at the correct value of 121 000.)
In order to produce a final matrix where both rows and columns sum to their
correct values, a remedial procedure must be undertaken, termed the row-
column factor technique. It is a two-step process.
First, each row sum is corrected by a factor that gives the zone in question
its correct sum total (Table 2.20).
Second, because the column sums no longer give their correct summation,
these are now multiplied by a factor which returns them to their correct indi-
vidual totals (Table 2.21).
This repetitive process is continued until a final matrix is obtained where the
production and attraction value for each zone is very close to the correct row
and column totals (Table 2.22).
Destination zone
Origin Correct Row
zone A B C D E F G Total total factor
Destination zone
Origin
zone A B C D E F G Total
Destination zone
(Note, if Equation 2.2 is used within the trip distribution process, the rows
sum correctly whereas the columns do not. In this situation the row-column
factor method is again used but the two-stage process is reversed as a correc-
tion is first applied to the column totals and then to the new row totals.)
Two modes of travel are available to all trip makers within the interchange
matrix: bus and private car. In order to determine the proportion of trips under-
taken by car, the utility of each mode must be estimated. The utility functions
for the two modes are:
UCAR = 2.5 - 0.6C - 0.01T (2.19)
UBUS = 0.0 - 0.6C - 0.01T (2.20)
where
C = cost (£)
T = travel time (minutes)
For all travellers between each pair of zones:
The trip by car costs £2.00 more than by bus
The journey takes 10 minutes longer by bus than by car.
Since the model parameters for the cost and time variables are the same in
Equations 2.19 and 2.20, the relative utilities of the two modes can be easily
calculated:
U(BUS -CAR ) = (0.0 - 2.5) - 0.6(c - (c + 2)) - 0.01((t + 10) - t )
= -2.5 + 1.2 - 0.1
= -1.4
Forecasting Future Traffic Flows 41
The final stage involves assigning all the car trips in the matrix within Table 2.23
to the various links within the highway network shown in Fig. 2.3. Taking the
information on the interzonal travel times in Table 2.17 and using the ‘all-or-
nothing’ method of traffic assignment, the zone pairs contributing to the flow
along each link can be established (Table 2.24). The addition of the flows from
each pair along a given link allows its 2-way flow to be estimated. These are
shown in Fig. 2.4.
42 Highway Engineering
C F
A D G
B E
Figure 2.3 Zones and links in study area within worked example.
Network link Zone pairs contributing to flow along link Total link flow
The process of traffic forecasting lies at the very basis of highway engineering.
Modelling transport demand is normally undertaken using a four-stage sequen-
tial process starting with trip generation and distribution, followed by modal
Forecasting Future Traffic Flows 43
split and concluding with traffic assignment. Predicting flows along the links
within a highway network provides vital information for the economic and envi-
ronmental assessments required as part of the project appraisal process and
allows the scale of each individual project within the network to be determined.
Once the demand analysis and appraisal process have been completed, the
detailed junction and link design can then be undertaken.
It should be remembered, however, that the modelling process is a simplifi-
cation of reality. Predictions arising from it are broad estimates rather than
precise forecasts. The error range within which the model results are likely to
fall should accompany any data supplied to the transport planners.
2.10 References
Furness, K.P. (1965) Time function iteration. Traffic Engineering Control, 7, 458–460.
McFadden, D. (1981) Economic models and probabilistic choice. In Structural Analysis
of Discrete Data with Econometric Applications (eds Manski & McFadden). MIT Press,
Cambridge, MA, USA.
Wardrop, J.G. (1952) Some theoretical aspects of road traffic research. Proceedings of the
Institution of Civil Engineers, 1(36), 325–362.