Earthing Functional Requirements
Earthing Functional Requirements
69
73 Interfacing electrification and system reliability
Design approach to the earthing Lightning protection 11,12 Surge arrestors: Gas plasma
of the railway: To ensure compliance discharge arrestors have a fast
Lightning strikes on or near railway
with relevant standards there is a response to transient overvoltage
equipment can generate large
requirement for a robust Quality events. This fast response and the
voltage surges that can disturb or
Assurance process including an ability to handle very high current
damage railway operations. The
Earthing Management Plan, Earthing surges effectively suppresses
various ways in which a lightning
Installation Code of Practice and transients. Low capacitance
strike can affect railways are:
Earthing Test Specification. and high insulation resistance [
(i) Direct strike to the overhead lines >Gohm] produce a low leakage
Additionally the Earthing
Management Plan must address the (ii) Direct strike to the aerial ensuring that there is virtually no
design, installation, operation, and earth wire or gantries effect on the protected system.
maintenance aspects of the railway. (iii) Nearby strike to ground Installation of surge arrestors:
[induced voltages] Surge arrestors can be installed on
AC/DC railway interfaces 14 telecommunications cables or on the
(iv) Strike to ground further
away [ground potentials]. installation equipment. Surge arrestors
An AC railway is often designed
for commercial installations are rated
in close proximity to other DC A direct strike to the lines can at typically 250V. This is normally too
light rail, metro and trams. Where generate an overvoltage surge of low for the railway environment.
there is parallel running, over several million volts. This will cause
bridges or under bridges, there a flashover across the support The surge arrestor operates when a
may be significant interactions insulators. The surge current will voltage between the line and remote
between the two electrified then find various routes to earth earth exceeds the level specified.
railway systems. The amount and depending on their surge impedance This method diverts the transient
characteristics of disturbance will be values. A lightning strike may also energy away from the line circuit
dependent on the interconnection generate a 25kV earth fault. and into the earth of the network.
of earths, traction loads, earth This is good as long as the earthed
Entry points for lightning to the system is not coupled in any way with
faults, the physical arrangement,
railway control systems are numerous the telecommunications cables. The
the electrical systems design and
and some are detailed below: design of the earth should be such
the local ground conditions.
(i) Radio masts that there is no close parallel coupling
Track circuit disturbance: DC
(ii) Electrical supply points with telecommunications cables.
traction return current flowing in
the AC traction rails can interfere (iii) Rail and track connections
Stray current corrosion
with track circuits. Similarly the AC to signalling circuits
return current can interfere with track
control (DC railways) 5,7
(iv) Signalling data, control
circuits used on DC electrified lines. and indications cables The overall control strategy is to
DC stray current: The bonds follow an approach that minimises the
(v) Ground coupling through
between the rails and metal generation of stray current, controls
circulating earth loops,
structures etc. which are necessary its ‘escape’ and maintains separation
(vi) Induction into power, signalling between the rails and associated
for electrical safety in the presence
and communications circuits. collection systems and the metro civil
of high-voltage AC railway overhead
lines will provide a path for stray Design approach on railways: structures and external structures.
DC traction return current to flow The protection of buildings, The driving force for stray
to earth, and may cause electrolytic viaducts, bridges and structures current can be minimised by:
corrosion to the structures concerned, from lightning is by the provision
• Traction power substation
as well as neighbouring buried of lightning conductors and an
design and locations;
pipes, metal-sheathed cables etc. earth electrode system. This earth
is segregated from the earth path • Rail return circuit design and
Touch and accessible voltage: bonding; and minimising the
used by signalling control and the
The impedance of the rails at longitudinal electrical conductivity
electrical and plant (E&P) systems.
50 Hz is much greater than the of supporting structures
resistance of the rails at DC. This In the case of the station roof
means that the return current structure and viaduct there is a • Maintenance of a high rail
from AC trains, and from short- requirement to provide lightning to structure insulation.
circuits on the AC overhead lines, earthing, to control earth potentials. • Construction and maintenance of
would cause significant voltage Additionally there is a requirement to stray current collection systems
drops in the rails. This would bring ensure the insulation co-ordination to provide an efficient low
a risk of electric shock if suitable and any necessary segregation resistance preferential path for
means were not employed to required for sensitive signalling and current collection and return.
limit the voltage on the rails. control systems that are located on • Maintaining an electrical
or close to the station or viaduct. separation between the collection
RAIL
70
Interfacing electrification and system reliability 73
Design approach on DC railways: The new EMC directive 2004/108/ Electromagnetic interference
This strategy is designed to EC2 includes some simplification will largely cause interference
reduce corrosion threats to the and clarification when compared from the high power circuits of
rail infrastructure and to external to the original Directive: the electrification supply and
infrastructure by minimising stray (1) Manufacturers are required to traction drive into the train control
current leakage at source and perform an EMC assessment; systems, signalling systems and
retaining this as far as practicable including the application of railway and publicly owned
within the rail system. harmonised standards telecommunication systems, remote
The design process should: control, and monitoring systems.
(2) Manufacturers are required to
• Assess the interfaces between produce a Technical File [TF]
the railway and other third party to demonstrate conformity
The railway authority’s
infrastructure through a Stray (3) Manufacturers may choose to responsibilities 15
Current Control Survey to identify obtain an independent conformity The railway authority has a
and assess stray current and statement from a Notified Body. responsibility to ensure that projects
corrosion risk areas. ( E&M Earths,
(4) Manufacturers are required include design specifications
Civil Structures and Utilities)
to make a Declaration of that address interfaces between
• Utilises design philosophy Conformity [DoC] electrical systems and also the
that follows the guidance management process, to ensure
(5) A Fixed Installation [FI] at a
given in BSEN 50122-2, that systems do not adversely
pre-defined location is required
BSEN50162 and UK Trams ORR interact or disturb each other.
to conform to the essential
Tramway Guidance Notes
requirement but not to follow
• Undertake modelling techniques the conformity assessment
Application of railway and
to quantify these threats and procedure and therefore does national standards
validate the control measures not have to carry the CE Mark BS EN standards are used extensively
• Provide verification processes (6) The FI will usually consist of in the specification of railway
that should be designed and equipment carrying the CE projects. The projects assume that
applied at each stage of the marking installed as specified if the standards are implemented
project to provide assurance that by the manufacturer(s) and then their design will always be
the strategy has been correctly specific equipment not otherwise adequate. The basic standard for
applied and to identify issues commercially available can be earthing railways, EN 50122-1, is
for investigation and action incorporated, accompanied by very clear on safety requirements for
• Ensure a consistent approach and documentation which indicates earthing and equipotential bonding.
awareness both across the project precautions to be taken for However, the standard is not a
and between the below ground incorporation into the FI; the practical guide to earthing a railway.
and above ground sections. installation shall follow ‘good It is a performance specification
engineering practice’ which and details what is required to be
Compatibility of electrical must be documented. undertaken by railway administration.
systems 3,6,8,9 The railway environment: contains It does not provide any detail on how
many sources of electromagnetic, installation should be undertaken.
The EEC directive 89/336 made
the requirement that all electrical electrostatic noise and electrical It should also be noted that the
apparatus must not emit disturbances; and it is a hostile European Standard EN50122-1
electromagnetic radiation that environment for low power does not specifically address
would prevent other equipment circuits i.e. remote control systems, (1) earthing arrangements for
from functioning as intended. monitoring circuits, signalling systems, lightning protection
telecommunication circuits and radio
The European EMC Directive (2) provide detail design and
networks. The complete railway
89/336/EEC as amended by 92131/ interconnection of earthed systems
electrification network requires to
EEC has been legally adopted by (3) system operability and the
be monitored in terms of emissions
UK regulations under Statutory design differences between
and susceptibility to electromagnetic
Instrument (1992) No. 2372 'The rail return, auto feeding,
interference, conductive interference
EMC Regulations' and came into force booster return, single rail and
and radio frequency interference.
in 28 October 1992. The Directive double rail return systems.
This includes electrical circuits in the
applies to virtually all electrical and
supply of traction power, the control
electronic products and systems
of traction power, the operation of
for use in the European Union.
signalling, train control circuits, the
operation of telecommunication
systems and radio communications.
RAIL
71
73 Interfacing electrification and system reliability
The complications of railway earthing Specify design interface Safety Management System 15
are significant and the specific specification The Project Safety Management
requirements for traction power,
The railway administration should System (SMS) is part of the Quality
signalling, communications, LV
be aware of the requirements Assurance process that is required
and lightning earthing all have to
for integration, and it is their to address safety of humans. In an
be addressed by the project, with
responsibility to identify and include electrified railway the topics that
potentially different requirements
these criteria within the project need to be addressed include touch
for at grade, in tunnel and on
requirements at the definition stage. and accessible potential and the
viaduct sections. It should be noted
Interface requirements must then be risks associated with the malfunction
that the IEE Wiring Regulations
included within the Particular Design of signalling, and control systems
BS7671 is pertinent to stations,
Specifications for each contract. leading to multiple fatalities.
concourses and other buildings;
however, track, platforms, railway They should also make all System All potential safety hazards associated
traction equipment, rolling stock and Wide Contractors responsible for with the operation of the railway
signalling equipment are excluded. identifying interfaces, hazards and including the earthed infrastructure
for participating in the integration of the railway network should be
It is normal practice therefore for a methodology of the project. identified. The hazards associated
railway administration to produce an
If they fail to include this within with electrification supply points,
accompanying installation guideline
the particular specification, then overhead lines, traction return paths,
for contractors and maintainers.
the contractors will not be obliged operation of traction and rolling
Without such a code it is inevitable
to ensure that this integration stock, effects in depots and station
that earthing disturbances will
happens. The outcome of this can be stops etc need to be addressed.
occur. Examples of Company Code
of Practice are; Network Rail NR/ disastrous for the project programme To achieve this, experts in the fields
SP/ELP/21085, Channel Tunnel Rail and the railway administration, of electrification, earthing, signalling
Link 000-GDS-LCEEN-10041-05; which may be powerless to ensure and rolling stock are required to
Indian Railways AC Traction Manual that their multi-million pound be brought together to assess the
Appendix 11 code for bonding investment operates as intended. system behaviour under normal train
and earthing for 25kV AC 50Hz operation, under system faults and
single phase traction system.
Management of electrical systems all degraded modes of operation
The railway authority should specify of the electrification and signalling
Risk (commercial, the requirement for Management systems and the rolling stock.
operational, safety) Plans to address quality assurance
process and installation Codes of Design interface specifications
It has become the norm for railway
Practice. This is to ensure compliance Where there are known interfaces
contracts to be based along
with railway and national electrical these should be recorded in an
traditional engineering disciplines
and safety standards. This normally interface matrix and a specification
and interfaces; for example, wheel
becomes the responsibility of prepared between the two
to rail and pantograph interfaces.
the design and build contractor disciplines or contractors. Such
Railway authorities sometimes fail to
and has been addressed in more interfaces could also include the
recognise the complexity of electrical
detail later in this article. co-location of several different
interfaces and provide a solution to
manage the integration between railways at an interchange station.
different engineering disciplines. Design management An example of this is London,
The major cost element of a new responsibilities where various lines on the London
railway is the civils discipline; the Underground DC metro railway are
The preliminary and detailed design
electrical systems are a relatively small in close proximity to the 25 kV AC
stages of project management plans
portion when compared to the civil main line infrastructure. The interface
should be prepared to address the
infrastructure costs. However, failure specification should identify all of
above system interfaces. The following
to integrate the electrical systems the systems that may be affected.
are examples of management
will probably mean disruption to the plans that should be incorporated It is necessary that the responsibilities
whole project during commissioning within the overall systems for the identified hazards in the
and delay early operational service. engineering management plan. project are assigned an owner (and
Major Rail Projects are largely run accepted) and that the designer then
This is normally the responsibility of
by the Civil Engineering Discipline. mitigates any potential disturbance.
the Design and Build Contractors.
Rail Authorities often fail to provide It should also be remembered
adequate project management effort that utilities and neighbours must
to integrate the systems, placing the be considered when addressing
whole project programme at risk. interface specifications within
the railway environment.
RAIL
72
Interfacing electrification and system reliability 73
73
73 Interfacing electrification and system reliability
References
1. R D White. “The Challenges of Integrating an Electrified Railway”,
International Railway Journal, Sept 2006, pp 94-95;
2. IET Seminar on EMC in Railways 28 Sept 2006 ‘The new EMC Directive 2004/108/EC’ C Marshman;
3. BS EN50121 Parts 1-5 Title: Railway applications - electromagnetic compatibility;
4. BS EN50122-1 Railway applications, fixed installations, protective
provisions relating to electrical safety and earthing;
5. BS EN50122-2 Railway applications, fixed installations, protective provisions
against the effects of stray currents by D.C. traction Systems;
6. BS EN61000-5 Title: Electromagnetic Compatibility (EMC) - Part 5: Installation and mitigation guidelines;
7. BS EN50162 Railway Applications - protection against corrosion by stray current from DC systems;
8. BS EN61000 Electromagnetic Compatibility (EMC) Limits, Testing;
9. BS EN50238 Railway applications - Compatibility between rolling stock and train detection systems;
10. BS 7671 The Wiring Regulations;
11. BS EN 50124-1:2001 Railway applications - Insulation coordination;
12. BS EN62305 Protection against lightning
13. BS EN61140 Protection against electric shock - Common aspects for installation and equipment
14. prEN50122-3 Railway applications - Fixed installations - Electrical safety, earthing and
the return circuit - Part 3: Mutual Interaction of a.c. and d.c. traction Systems.
15. ROGS The Railways and Other Guided Transport Systems (Safety) Regulations 2006
RAIL
74