Vision Built Steel Frame Building System: Systèmes Pour Constructions Bausystem
Vision Built Steel Frame Building System: Systèmes Pour Constructions Bausystem
6 Hh2 (e4)
E: www.vision-built.com
T: (091) 795505
NSAI Agrément (Irish Agrément Board) is designated by Government to carry out European Technical Assessments.
NSAI Agrément Certificates establish proof that the certified products are ‘proper materials’ suitable for their intended
use under Irish site conditions, and in accordance with the Building Regulations 1997 to 2017.
1.1
Readers are advised to check that this Certificate has not been withdrawn or superseded by a later issue by
contacting NSAI Agrément, NSAI, Santry, Dublin 9 or online at www.nsai.ie
DESIGN:
The Vision Built Steel Frame Building System is
intended for use where architect’s finalized
construction and fire strategy drawings are
available and satisfy the Building Regulations
1997 to 2017. The architect and engineer design
team of the developer (the client) is responsible
for the architectural drawings and overall building
design to comply with the Building Regulations.
The panels are fabricated from suitably coated • The bottom channel on all ground floor steel
steel coil as described in section 2.4.2 which is frame panels is additionally protected by a
formed into the required shapes by proprietary 100mm wide DPC from the floor slab.
roll-forming equipment. The frequency and size of • The rigid board insulation keeps the steel in a
the structural elements will depend on the “warmframe” environment, which, in
individual panel and truss design. The individual conjunction with the external breathable
elements manufactured are then assembled by membrane and internal air tight barrier,
trained personnel on the floor to produce the prevents the formation of condensation within
required wall or truss required with fixings as the wall structure.
specified by the structural engineer. • The metal and timber in the roof trusses is
kept free from prolonged moisture build up, by
The wall panels will also have ancillary elements means of free air circulation in the roof space,
assembled into the panel such as strap or ‘K’ using ventilation methods in accordance with
bracing, lintel trusses over openings and rigid Part F2 of TGD to Part F of the Building
insulation on the external walls which are Regulations 1997 to 2017.
described in this certificate. • Where steel is cut on site or where the coating
of the steel becomes damaged, it is protected
Typically, when it comes to traditional roofs, by the application of a zinc rich paint.
prefabricated timber roof trusses are typically • All fasteners have been assessed and tested
utilised in Vision Built structures where required. for use with the system, to ensure the
Timber Roof trusses are designed and supplied by minimum 60-year design life of the system.
others. However, there are occasions where the
roof truss is supplied as a cold rolled truss system
designed and manufactured by Vision Built. This
would be produced using the typical sections
produced by Vision Built and the fixings specified
by the structural engineer.
2.4.3 Fasteners and Connection Joints 2.4.4 Load Bearing Walls Structural
The unique design of the Vision Built Steel Frame Principles
Building System allows for no welding of joints in The perimeter walls can be the primary load
the system. The system is assembled using bearing elements of the structure and are
fasteners such as self-piercing rivets, screws or therefore designed to bear on the walls of the
bolts. All fasteners used in the steel frame system panels below, i.e. permanent and variable
are adequately protected against corrosion i.e. imposed loads are transferred by load bearing
galvanising/zinc coating and made from a suitable external wall panels and if required load bearing
metal to ensure the design life of the system is internal wall partitions where necessary.
maintained. Vision Built provide a full specification
of all fasteners, where they are to be used and The load bearing wall panels are comprised of
how they are to be installed during the vertical studs, fixed to horizontal head and bottom
construction of the system. Only system fasteners channel sections. Horizontal noggins are fitted at
approved or supplied by Vision Built may be used the mid-height of all panels where required to
with the system. It is important to ensure that provide additional strength and where particularly
protective coatings on fasteners are not removed, high vertical loads occur. Studs can interlock
i.e. to assist the fitting of a connection, as this together to form box sections as required under
would severely compromise the corrosion high concentrated loads. Typically, roof trusses
performance of the fastener. Where a building is are aligned with the vertical studs, which in turn
located within one kilometre of the coastline and are aligned above studs in the wall below. Where
has a steel roof, all fasteners at the eaves shall be windows are present or where roof trusses change
coated with a zinc rich paint to protect against centres a cold formed lintel or hot rolled section is
coastal spray or fasteners used that have the provided to allow the load to transfer to the
required salt spray test for this application. vertical wall studs. The design loads from each
level are transferred through the primary load
2.4.5 Racking
Resistance to horizontal loading (racking) is
provided by the horizontal diaphragm action of
the approved floor sheeting and roof in
conjunction with the metal diagonal cross-bracing
members on specific external inner leaf and
internal walls. All cross bracing is pre-assembled
in the factory and has the dual function of
ensuring squareness of factory produced panels in
addition to providing lateral stability for the
overall structure. Vision Built use both strap and K
Figure 12: Detail of Steel Frame Connected
bracing.
to Blockwork rising wall
2.5 COMPARTMENTATION
2.5.1 Separating Wall (Party Wall)
Separating walls (party walls) are constructed
using a minimum of two independent cold formed
steel framed leaves (studs at 600mm centres
max.) two layers of 15mm gypsum soundbloc or
two layers of 15mm type 5 plasterboard internal
lining on each side, fixed with the joints
Figure 13: Party wall detail (Option 1) at
staggered. This cavity is then full filled with stone
junction with external masonry wall
mineral wool batts of minimum 24kg/m3 density.
These wool batts are continuous from ground floor
to the upper floor ceiling level and provide the
required acoustic properties.
For infill panels the bottom track of the SFS infill Figure 20: Deflection Head Detail for Infill
panel is secured to the slab with holding down Panel
bolts at the specified locations identified on the
Vision Built drawings. For infill panels, brackets
with a deflection allowance will allow the studs to
face fix to the superstructure in question (Figure
20).
‘Ψ’ values for other junction outside the scope of When using air permeability values better than
this certificate should be assessed in accordance the backstop values of 7 m3/(hr.m2), a test must
with the BRE IP 1/06 and BRE Report BR 497 in be performed on each unit.
accordance with appendix D of TGD to Part L of
the Building Regulations 1997 to 2017. When air permeability values better than 5
m3/(hr.m2) are achieved, the guidance given in
4.2.2 Internal Surface condensation Clause 4.3.2 of this certificate should be
As part of the assessment carried out to considered.
determine the ψ-values, internal surface
temperatures factors (fRsi) are also checked. When The Vision Built Steel Frame Building System can
internal surface temperature are greater than be designed to provide the required project
15°C, best practice will have been adopted to safe specific airtightness requirement and can be
guard against the risk of surface condensation achieved in practice due to its offsite production
occuring under normal occupancy and humidity process, hybrid construction build up and the
class levels. quality of product produced in a factory-controlled
environment. The Vision Built Steel Frame
Building System will therefore significantly
Wall build-up:
Layer 1: Brick/masonry cladding
Layer 2: 50mm low E cavity
Layer 3: Variable PIR layer (2)(3) (see below)
Layer 4: LGS/PUR insulation (1)
Layer 5: LGS/MW insulation (1)
Layer 6: 15mm Plasterboard on AVCL
Buildings constructed using the Vision Built Steel 4.11.1 Other Investigations
Frame Building System will, when constructed in Existing data was examined to assess:
accordance with Vision Built Erection Manual and • Adequacy of weather tightness of building
the requirements of this Certificate along with all constructed using the system.
relevant codes of practice will have a minimum • Durability of the system.
design life of at least 60 years in accordance with • Requirements for maintenance.
BS 7543:2015 Guide to durability of buildings
and building elements, products and 4.11.2 Production Audits
components. Production audits were carried out at the Vision
Built factory to examine the process of structural
4.10 MAINTENANCE design, steel frame fabrication, assembly and to
Maintenance will be required at a level assess the adequacy of the methods adopted for
comparable with that for buildings of traditional quality control.
construction. The elimination of wet trades in the
construction of the inner leaf of external walls 4.11.3 Site Erection Visits
reduces drying time and can reduce the incidence Buildings under construction were visited to
of superficial cracking early in the life of the assess the practicability of construction (erection)
building. and the adequacy of Vision Built site supervision
arrangements.
As the plasterboard is screwed into the steel
structure, there is no nail popping in plasterwork,
which results in less maintenance of plasterwork,
than that of a traditionally constructed building.
5.2 The NSAI Agrément mark and 5.7 Where reference is made in this
certification number may only be used on or in Certificate to any Act of the Oireachtas,
relation to product/processes in respect of which Regulation made thereunder, Statutory
a valid Certificate exists. If the Certificate Instrument, Code of Practice, National Standards,
becomes invalid the Certificate holder must not manufacturer's instructions, or similar
use the NSAI Agrément mark and certification publication, it shall be construed as reference to
number and must remove them from the such publication in the form in which it is in force
products already marked. at the date of this Certification.