Estimate Manual by Jonathan Conde
Estimate Manual by Jonathan Conde
TABLE OF CONTENTS
Page
ACTIVITY LIST FOR HIGHWAYS & BUILDINGS 4-6
Group 100 - Roadside and related features ---------- 4-5
Group 200 - Roadside features ---------- 5
Group 300 - Traffic services ---------- 5
Group 400 - Emergency works ---------- 5
Group 500 - Supervision, support & overhead ---------- 5-6
1 of 47
ESTIMATE MANUAL
2 of 47
ESTIMATE MANUAL
3 of 47
ESTIMATE MANUAL
Bituminou Pavements
111 Premix patching bituminous pavments ---------- cu.m.
112 Penetration patching bituminous pavements ---------- cu.m.
113 Sealing bituminous pavements ---------- li.
114 Replacement of bituminous pavements ---------- sq.m.
Concrete Pavements
121 Patching concrete pavaments ---------- cu.m.
122 Crack & joint sealing of concrete pavements ---------- li.
123 Replacement of concrete pavements ---------- sq.m.
4 of 47
ESTIMATE MANUAL
Unpaved Shoulder
131 Manual repair of unpaved shoulder ---------- m.
132 Manual patching unpaved shoulder ---------- cu.m.
133 Machine grading unpaved shoulder ---------- k.m.
Drainage
141 Manual ditch cleaning ---------- m.
142 Manual inlet/outlet cleaning ---------- no.
143 Culvert line cleaning ---------- no.
144 Repair / replacement of minor drainage structures ---------- no.
Bridges
151 Cleaning bridges ---------- m.
152 Patching concrete decks ---------- sq.m.
153 Repair to concrete bridges ---------- no.
154 Repair to steel bridges ---------- no.
155 Repair to bailey bridges ---------- no.
156 Repair to tomber bridges ---------- no.
157 Cleaning bridge waterways ---------- no.
Ferries
161 Ferry service ---------- hrs.
Temporary Repairs
171 Temporary patching ---------- m.
5 of 47
ESTIMATE MANUAL
6 of 47
ESTIMATE MANUAL
CONSTRUCTION DETAILS
7 of 47
ESTIMATE MANUAL
8 of 47
ESTIMATE MANUAL
Part 4 - Structures
400 Steel bridges ---------- qty of struc. stl
401 Timber detour span ---------- as unit
402 Piling ---------- l.m. of piles
403 Concrete railing ---------- l.m. along C.L. '---------- l.m. along C.L.
404 Paints or painting
405 Concrete ---------- cu.m.
406 Reinforcing steel ---------- kg.
407 Structural steel ---------- kg.
408 Welding structural steel
409 Sheet files ---------- l.m.
410 Treated & untreated timber ---------- bd.ft.
411 Timber structures
412 Stone masonry ---------- cu.m.
9 of 47
ESTIMATE MANUAL
1. BATTERBOARD
a. To estimate batterboard, first compute the area of the structure in sq.m. multiply the area by
4.85 bd.ft. for 2" x 2" lumber, 7.28 bd.ft. for 2" x 3" lumber. Then the total bd.ft. divided by
2 will give you the bd.ft. of lumber to be used as batterboard.
b. The second procedure is to compute the lineal meter of the structure location giving an allo-
wance or margin of 1.00 all around. Count also the no. of stake to be used. No. of stake multi-
ply by 1.20 ( length of stake ) to get total lineal meter. Add all the ilneal meter & change to li-
neal foot. Compute the bd.ft. by using 2" x 2" or 2" x 3" lumber.
c. For nails : divide the total bd.ft. by 1,000 then multiply by 15 to get kilos required. If keg
: divide the total bd.ft. by 2,500.
d. For # 12 guide wire to be used as guide in layout, divide the total bd.ft. by 4,000 to obtain
roll of wire.
Batterboard
Stake
Guide Wire
2. EXCAVATION
a. To estimate volume of excavation, compute the area to be excavated then multiply by the
depth
b. For cut and fill, use the Prismoidal Formula (A1 + A2)/2 x depth or length.
3. BACKFILL
a. For backfilling, use the same procedure as of the excavation no. 1, by multiply the length,
width & depth. If the backfill will be compacted add 15% for compaction.
4. CONCRETE
a. To estimate volume or cu.m. of concrete, use the same procedure in computing excavation
& backfilling.
b. To obtain bag of cement, sand and gravel, determine first the psi or class of mixture.
10 of 47
ESTIMATE MANUAL
5. RATIO OF MIXTURES
Class AAA 1:1:2 4,500-5,000 psi
Cement 13.50 bags
Sand 0.51 cu.m.
Gravel 1.02 cu.m.
Class AA 1 : 1½ : 3 3,500-4,000 psi
Cement 11.35 bags
Sand 0.41 cu.m.
Gravel 0.82 cu.m.
Class A 1:2:4 3,000 psi
Cement 9.50 bags
Sand 0.42 cu.m.
Gravel 0.84 cu.m.
Class B 1 : 2½ : 5 2,500 psi
Cement 8.50 bags
Sand 0.44 cu.m.
Gravel 0.87 cu.m.
Class C 1:3:6 2,000 psi
Cement 7.50 bags
Sand 0.44 cu.m.
Gravel 0.89 cu.m.
Class D 1 : 3½ : 7 1,600 psi
Cement 6.50 bags
Sand 0.45 cu.m.
Gravel 0.91 cu.m.
6. MORTAR MIXTURE
Class AA 1:1
Cement 21.0 bags
Sand 0.85 cu.m.
Class A 1:2
Cement 18.85 bags
Sand 1.0 cu.m.
Class B 1:3
Cement 13.0 bags
Sand 1.06 cu.m.
Class C 1:4
Cement 10.0 bags
Sand 1.08 cu.m.
Class D 1:5
Cement 8.0 bags
Sand 1.10 cu.m.
11 of 47
ESTIMATE MANUAL
8. ASPHALT PAVEMENT
a. To obtain asphalt for 2" thk. Asphalting : 1 metric ton of asphalt coverage of 8.75 sq.m.,
for prime coating (liquid) : total sq.m. divided by 400 = no. of drums or 1 gal. Asphalt
coverage of 64.0 sq.ft. or 6.00 sq.m..
9. CONCRETE PAVEMENT
a. To obtain bag of cement for 8" thk. pavement : total cu.m. x 8.50 = bags, or total sq.m.
x 1.90 = bags. for sand : total cu.m. x 0.47 = cu.m. of sand. for gravel : total cu.m.
x 0.94 = cu.m. of gravel. for water : cu.m. x 66.40 = gal. of water.
12 of 47
ESTIMATE MANUAL
16. CEMENT & SAND FACTOR PER CONCRETE PIPE JOINT COLLAR
Pipe Diameter Cement Sand
4" dia. NRC 0.02 0.13
6" dia. NRC 0.03 0.19
8" dia. NRC 0.05 0.26
12" dia. RCP 0.12 0.39
15" dia. RCP 0.15 0.49
18" dia. RCP 0.20 0.59
24" dia. RCP 0.35 0.79
30" dia. RCP 0.50 0.99
36" dia. RCP 0.70 1.19
42" dia. RCP 0.75 1.38
48" dia. RCP 1.20 1.58
Note : When wall is supported by buttress, estimate first the buttress stone for adobe.
estimate stone for adobe wall ( subtract width of buttress & openings ). To estimate
cross footing, estimate it as continuous footing.
13 of 47
ESTIMATE MANUAL
6" CHB using #3 @ 32" verical . & #3 @ 24" horizontal, area x 1.64 = kg.
using #4 @ 32" vertical & #4 @ 24" horizontal, area x 2.90 = kg.
8" CHB using #3 @ 32" vertical & #3 @ 24" horizontal, area x 2.00 = kg.
using #4 @ 32" vertical & #4 @ 24" horizontal, area x 3.32 = kg.
f. For tie wire #16 : for 4" CHB = area x 0.005, for 6" CHB = area x 0.008, for 8"
CHB = area x 0.009. All answer for this will be in roll of wire. Other procedure : total
kgs. Divided by 0.300 = roll of wire.
20. PLASTERING
a. To estimate mortar for plastering, compute the area & multiply 0.025 or 0.0125 to obtain
volume 1 Face = 0.0125, 2 Faces = 0.025.
b. To obtain bags of cement : vol. x 13, for sand : vol. x 1.06. Before obtaining bags of
cement & cu.m. of sand, determine first the no. of face to be plastered & class of mixtures.
c. To obtain cement : area x 0.33 = bags, for sand : area x 0.03 = cu.m. sand.
14 of 47
ESTIMATE MANUAL
23. SCAFFOLDING
a. Compute the floor area plus the area of the four elevations, then multiply by the no. of storey
for floor of the structure.
b. To obtain bd.ft.of lumber : total area x 6.75 = total bd.ft. of 2" x 3" lumber.
c. To obtain nails : divide the total bd.ft. by 2500 = keg of nails, note that I keg of nails is
equivalent to 45 kilos.
d. Other solution in obtaining nails : total bd.ft. divide by 1000 then multiply by 15 = kls.
of nails.
15 of 47
ESTIMATE MANUAL
24. FORMWORKS
a. To estimate formworks, compute the area of the item that need form work.
b. To obtain bd.ft. of lumber, multiply the area by the corresponding factor on the conversion
table for formulas. After obtaining the total bd.ft. divide it to no. of uses.
c. To estimate ½" x 4' x 8' sht. board plywood, divide the total area by 2.88 then divide by the
no. of uses.
d. For nails : total bd.ft. divide by 2500 = keg.
e. For tie wire : total bd.ft. divide by 4000 = roll.
f. For formoil : change the area of sq.m. to sq.ft. then divide by 200 = gals. of oil.
16 of 47
ESTIMATE MANUAL
31. BASEBOARDS
a. To estimate the bd.ft. of baseboard : lm x 1.09 for 1" x 4" lumber, lm x 1.37 for 1" x 5"
lumber, lm x 1.64 for 1" x 6" lumber.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 5.5 for 1½" finishing nails.
17 of 47
ESTIMATE MANUAL
36. PURLINS
a. To estimate the total bd.ft. of purlins : make an actual counting of the purlins shown in the
roof plans or truss and rafter details. Compute the bd.ft. according to size & length.
b. Or compute the area in sq.m., then multiply : area x 3.271 for 2" x 3" lumber, area x
4.309 for 2" x 4" lumber, area x 5.321 for 2" x 5" lumber, area x 6.335 for 2" x 6" lumber.
c. For cleats : area x 3.44 for 2" x 3", area x 4.571 for 2" x 4", area x 5.458 for 2" x 5",
area x 6.50 for 2" x 6".
37. ROOFING
a. To estimate roofing by area : solve the total area in flat then add the pitch factor ( sum of
1 & 2 percentage ), the total is the slotted area of the roof.
b. Divide the slotted area by factor from the table of G.I. sheet coverage.
c. Another procedure in estimating roofing : length of spread divided by 0.67 or 27" then
multiply by the no. of lapping or row.
18 of 47
ESTIMATE MANUAL
d. To obtain metal rivet : pieces of G. I. Sheet x 0.073 = kilo of rivet, for washer : pcs
of G. I. sht x 0.146 = kilo of washer, for strap : pcs og G. I. sht x 12 or 9 = pcs of atrap,
To convert this to plain G. I. sheet, see table of strap.
e. To obtain gutter, ridge roll, valley roll, flashing : divide the total run or spread by factor
: 2.10 for ridge roll, valley roll & flashing, 2.25 for gutter & downspout, for copper ri-
vet : no of pcs of joint multiply by 8 pcs then divide by 50 = no. of box, if in kilo : no.
of pcs divided by 160 = kilo.
f. For nikolite : no. of joint x ¼ or 4 or length in foot divided by 24 = kilo
g. For muriatic acid : pcs of nikolite x 10 c.c. = total c.c. of muriatic.
19 of 47
ESTIMATE MANUAL
g.1.b. Table of Coverage - 12" end lap with 2 side corrugated lap
Size Effective Coverage
32" x 6' 27" x 5' 1.01 sq.m.
x 7' x 6' 1.21 sq.m.
x 8' x 7' 1.40 sq.m.
x 9' x 8' 1.60 sq.m.
x 10' x 9' 1.79 sq.m.
x 12' x 11' 2.21 sq.m.
x 14' x 13' 1.61 sq.m.
h. For senepa flashing : total run divided by 7' or 2.135 to estimate flashing. The same as
of gutter flashing or no. of gutter = no. of flashing for gutter
20 of 47
ESTIMATE MANUAL
21 of 47
ESTIMATE MANUAL
2. Oil Paint Flat smooth wall 1 coat 500 sq. ft. 46.25 sq.m.
2 coats 275 sq. ft. 25.55 sq.m.
3 coats 200 sq. ft. 18.50 sq.m.
plasters 1 coat 400 sq. ft. 37.00 sq.m.
2 coats 225 sq. ft. 20.81 sq.m.
3 coats 160 sq. ft. 14.86 sq.m.
stucco 1 coat 150 sq. ft. 13.94 sq.m.
2 coats 75 sq. ft. 6.97 sq.m.
3. Enamel Paint smooth with 1 coat 500 sq. ft. 46.25 sq.m.
undercoat 2 coats 250 sq. ft. 23.23 sq.m.
4. Exterior Spur smooth wood 1 coat 500 sq. ft. 46.25 sq.m.
Varnish 2 coats 275 sq. ft. 23.55 sq.m.
3 coats 200 sq. ft. 18.50 sq.m.
5. Interior Spur smooth wood 1 coat 450 sq. ft. 41.81 sq.m.
Varnish 2 coats 250 sq. ft. 23.23 sq.m.
3 coats 175 sq. ft. 16.25 sq.m.
6. Shellac smooth wood 1 coat 600 sq. ft. 31.50 sq.m.
2 coats 300 sq. ft. 22.87 sq.m.
rough wood 1 coat 125 sq. ft. 11.16 sq.m.
2 coats 75 sq. ft. 6.97 sq.m.
22 of 47
ESTIMATE MANUAL
7. Shingles Satin smooth wood 1 coat 250 sq. ft. 23.23 sq.m.
Finish
8. Asphalt Rough rough 1 coat 150 sq. ft. 13.94 sq.m.
Paint smooth 1 coat 100 sq. ft. 9.29 sq.m.
9. Water Paint gold water paint - 5 lbs, powder
smooth 1 coat 300 sq. ft. 27.87 sq.m.
calsomine - 5 lbs, powder
plaster 1 coat 400 sq. ft. 37.10 sq.m.
wood 1 coat 250 sq. ft. 23.23 sq.m.
white wash - 4 to 5 lbs
brick 1 coat 200 sq. ft. 9.30 sq.m.
hydrated lime
plaster 1 coat 300 sq. ft. 27.87 sq.m.
23 of 47
ESTIMATE MANUAL
Hexagonal Tiles
4" x 4" 400.000 pcs / sq.m.
3 points hexagonal 2" size 20.000 pcs / sq.m.
4 points hexagonal 2" size 16.000 pcs / sq.m.
Cement
4" x 4" 100.000 pcs / sq.m.
6" x 6" 45.000 pcs / sq.m.
8" x 8" 25.000 pcs / sq.m.
12" x 12" 12.000 pcs / sq.m.
16" x 16" 6.250 pcs / sq.m.
Tool Finishing cement 0.150 bag /sq.m. .
sand 0.027 cu. m./sq.m.
Cuirng compound 1.000 gal/sq.m.of 7
Curb and gutter 0.740 cu m.
Cement 2.000 bags/cu.m.
Sand 0.380 cu.m.
Gravel 0.640 cu.m.
Virified Tiles mortar bed
cement 0.350 bag /cu.m.
sand 0.027 cu.m./sq.m.
24 of 47
ESTIMATE MANUAL
25 of 47
ESTIMATE MANUAL
26 of 47
ESTIMATE MANUAL
Door Jamb
Material : 2" x 6" for 3' x 7' door 18 bd.ft.
Fabrication : 1 Carpenter 18 bd.ft. / 4 hr 4.500 bd.ft./ mh
Installation : 2 Carpenters 18 bd.ft. / 3 hr 3.000 bd.ft./ mh
Door Jamb with transom of 0.30 lm
Material : 2" x 6" for 3' x 7' door = 22 bd.ft.
Fabrication : 1 Carpenter 22 bd.ft. / 5 hr 4.400 bd.ft./ mh
Installation : 2 Carpenters 22 bd.ft. / 3 hr 3.600 bd.ft./ mh
Metal Door
Steel door with #16 cladding = size 3' x 7' 21 sq. ft.
Materials : #16 cladding = 42 sq. ft.
IGSC Frame #12 = 50 l.f.
Fabrication : 2 Steelmen / 12 hr 24.000 mh / pc.
Equipment : 1 Welding machine 8.000 hrs / pc
Steel door - 18" x 14" = 253 sq. ft. (2) leaf
Materials : #16 cladding = 504 sq. ft.
C - Frame #12 = 440 l.f.
Fabrication : 4 Steelmen / 56 hrs 224.000 mh / pc.
Equipment : 1 Welding machine 40.000 hrs / pc
Tinsmitting
Corrugated G. I. Sheet - 0.685 / sq.m.
Fastener : hook bolt - 4 pcs / 1.47 sq.m. 2.520 sets /sq.m.
strap - pcs 1 sht / 792 (1/1.47) 0.015 sht /sq.m.
G. I. rivets - 8 pcs. ( 1 kg /180 ) 0.030 kg / sq.m.
( 1 kg /1.47 )
Lifting : 4 Tinsmith 0.270 mh /sq.m.
Installation : 1.570 mh /sq.m.
Ridge roll #26 x 24"
Materials : 8' sht. ( 24/36 ), ( ½ . 33 ) 1… 0.285 sht /sq.m.
Fastener : copper rivet : 8 pcs (1 kg /160), (½ . 33) 0.022 kg. / l.m.
Nicolite : (24/36)(½ . 33) 1.300 bend /l.m.
Labor : bending 3 bend 8(½ . 33) 1.300 bend /l.m.
Installation : 2.430 cu.m./ lm
27 of 47
ESTIMATE MANUAL
28 of 47
ESTIMATE MANUAL
Finishing
1. Plain cement plastering 1.330 mh /sq.m
2. Colored cement finish 1.400 mh /sq.m
3. Pebble washout 2.860 mh /sq.m
4. Granolithic tile finish 2.860 mh /sq.m
5. Marble tiles 2.860 mh /sq.m
6. Vinyl tiles 1.670 mh /sq.m
7. Unglazed tiles 3.000 mh /sq.m
8. Glazed tile 0.170 mh /sq.m
9. Asphalt tiles 1.670 mh /sq.m
Carpentry works
1. Partition including framing
- ¼" thk plywood single wall 0.230 mh /sq.m
- ¼" thk plywood double wall 0.314 mh /sq.m
- wooden louver 314.000 mh /sq.m
- #10 cyclone wire 0.029 mh /sq.m
Doors ( excluding finish hardware )
1. FHC door 0.200 mh /sq.ft
2. FSC door 0.286 mh /sq.ft
3. Steel sliding door 0.860 mh /sq.ft
4. Steel single door 0.715 mh /sq.ft
5. Roll up aluminum door - manual 0.715 mh /sq.ft
6. Cyclone wire sliding door 0.715 mh /sq.ft
Windows
1. Fixed glass on steel frame 0.286 mh /sq.ft
2. Fixed G. I. Louver 0.429 mh /sq.ft
Fixed asbestos louver 0.429 mh /sq.ft
4. Metal louver 0.286 mh /sq.ft
29 of 47
ESTIMATE MANUAL
30 of 47
ESTIMATE MANUAL
31 of 47
ESTIMATE MANUAL
32 of 47
ESTIMATE MANUAL
33 of 47
ESTIMATE MANUAL
Placing concrete
Slab on fill 0.200 sq.m./ mh
Slip form 0.040 sq.m./ mh
Floor finish - unhardened 1.000 sq.m./ mh
Concrete finish - hardened 0.700 sq.m./ mh
Installation of pre - moulded expansion joint 1.000 sq.m./ mh
Installation of water stop 1.500 l.m. / mh
Caulking of slab joint 5.000 l.m. / mh
Walls, beams, columns 1.300 sq.m./ mh
Slab 1.700 sq.m./ mh
Asphalting 1.250 sq.m./ mh
Masonry work
4" CHB laying 1.250 sq.m./ mh
6" CHB laying 1.250 sq.m./ mh
8" CHB laying 1.250 sq.m./ mh
Coating & tool finish plaster 0.600 sq.m./ mh
Plain cement plastering finish - synthetic & pebbles 0.700 sq.m./ mh
Marble slab installation 0.500 sq.m./ mh
¼" x 2" x 8" red bricks 0.200 sq.m./ mh
Ceramic glazed tiles 0.190 sq.m./ mh
Unglazed tiles 0.230 sq.m./ mh
Formwokrs installation
Nails on ground 1.000 sq.m./ mh
Nails above 10' 0.850 sq.m./ mh
Boxes 0.650 sq.m./ mh
Columns 0.850 sq.m./ mh
Suspended slabs
4" - 18" 1.200 sq.m./ mh
18" - 36" 0.800 sq.m./ mh
36" - up 0.600 sq.m./ mh
Formwork fabrication 1.860 sq.m./ mh
34 of 47
ESTIMATE MANUAL
Stripping of formwork
Nail on ground 8.000 sq.m./ mh
Nails above 10' 1.550 sq.m./ mh
Boxes 1.950 sq.m./ mh
Columns 2.350 sq.m./ mh
Suspended slabs
0 - 18" 3.600 sq.m./ mh
18" - 36" 2.400 sq.m./ mh
36" - up 1.850 sq.m./ mh
General stripping 4.080 sq.m./ mh
Reinforcing bars
Fabrication & installation 10.000 kgs / mh
Metal work
Structural steel 10.000 kgs / mh
Miscellaneous metal
Fabricstion of anchor bolt 10.000 kgs / mh
Installation of anchor bolt 3.000 kgs / mh
Fabrication of embedded item 7.000 kgs / mh
Laying of RCP - 8 men one team
24" ø 16 pcs 2.000 l.m. / mh
36" ø 10 pcs 1.250 l.m. / mh
48" ø 6 pcs 0.750 l.m. / mh
Underground drainage piping laying
6" ø concrete pipe 0.400 l.m. / mh
12" ø concrete pipe 0.250 l.m. / mh
15" ø concrete pipe 0.230 l.m. / mh
18" ø concrete pipe 0.220 l.m. / mh
30" ø concrete pipe 0.120 l.m. / mh
35 of 47
ESTIMATE MANUAL
Carpentry works
Plywood partition 0.930 sq.m./ mh
Plywood ceiling 0.700 sq.m./ mh
T&G flooring & siding 14.000 bd.ft. / mh
Ceiling framing 5.500 bd.ft. / mh
Siding framing 7.500 bd.ft. / mh
Roof framing 4.130 bd.ft. / mh
Floor framing 9.380 bd.ft. / mh
Wood post 8.750 bd.ft. / mh
Truss fabrication 5.750 bd.ft. / mh
Truss erection 5.000 bd.ft. / mh
Girts 9.380 bd.ft. / mh
Plates 15.000 bd.ft. / mh
Purlins 7.500 bd.ft. / mh
Fascia board 4.380 bd.ft. / mh
Cabinets
Framing 7.500 bd.ft. / mh
boarding 10.000 bd.ft. / mh
Plywood sheeting 1.740 bd.ft. / mh
door 0.930 bd.ft. / mh
Painting works
Anay paint 3.480 sq.m./ mh
Varnishing 2.320 sq.m./ mh
Metal works
G. I. roofing 1.220 sq.m./ mh
G. I. gutter cut & shape 6.250 l.m. / mh
G. I. gutter installation 2.250 l.m. / mh
Downspout cut & shape 3.380 l.m. / mh
Downspout installation 7.500 l.m. / mh
Backfilling & waterproofing 2.250 sq.m./ mh
Painting structural steel framing 20.000 mh/m ton
36 of 47
ESTIMATE MANUAL
37 of 47
ESTIMATE MANUAL
38 of 47
ESTIMATE MANUAL
Note : 490 is a factor for pounds as to obtain kilo, divide then sum by 2.20 & the answer is in
kilo.
39 of 47
ESTIMATE MANUAL
40 of 47
ESTIMATE MANUAL
41 of 47
ESTIMATE MANUAL
42 of 47
ESTIMATE MANUAL
DECORS
kgs. / ft. kgs / 20'
150 x 50 x 2.30 mm 1.52 31.24
150 x 50 x 3.20 mm 2.06 41.20
100 x 75 x 3.20 mm 2.856 56.52
CHANNELS
kgs. / ft. kgs / 20'
3/4.4 1.364 37.28
4/5.4 2.500 50.00
5/6.7 3.145 60.90
6/3.2 5.721 74.54
7/12.25 5.570 111.40
10/15.50 6.955 139.10
ANGLES
kgs. / ft. kgs / 20'
1" x 1" x 1/8" 0.364 1.20
1" x 1" x 3/16" 0.530 10.60
1" x 1" x ¼" 0.680 13.60
1¼" x 1¼" x ¼" 0.870 17.40
1¼" x 1¼" x 3/16" 0.670 13.40
1¼" x 1¼" x 1" 0.460 9.20
1½" x 1½" x ¼" 1.060 21.20
1½" x 1½" x 3/16" 0.820 16.40
1½" x 1½" x 1/8" 0.560 11.20
1¾" x 1¾" x ¼" 1.260 25.20
1¾" x 1¾" x 3/16" 0.960 19.20
1¾" x 1¾" x 1/8" 0.150 3.90
2" x 2" x 3/8" 2.140 42.80
2" x 2" x 5/16" 1.780 35.60
2" x 2" x ¼" 1.460 29.20
2" x 2" x 3/16" 1.110 22.20
2" x 2" x 1/8" 0.750 15.00
2½" x 2½" x ½" 3.500 70.00
2½" x 2½" x 3/8" 2.680 53.60
2½" x 2½" x 5/16" 2.270 45.40
2½" x 2½" x ¼" 1.865 37.30
2½" x 2½" x 3/16" 1.400 28.00
43 of 47
ESTIMATE MANUAL
UNEQUAL ANGLES
kgs. / ft. kgs / 20'
1¾" x 1¼" x ¼" 1.060 21.20
1¾" x 1¼" x 3/16" 0.820 16.40
1¾" x 1¼" x 1/8" 0.560 11.20
2" x 1¼" x ¼" 1.160 23.20
2" x 1¼" x 3/16" 0.890 17.80
2" x 1½" x ¼" 1.280 25.20
2" x 1½" x 3/16" 0.960 19.20
2" x 1½" x 1/8" 0.650 13.00
2" x 1½" x 5/16" 1.780 35.60
2" x 1½" x ¼" 1.450 29.00
2¼" x 1½" x 3/16" 1.110 22.20
2¼" x 2" x 3/8" 2.410 48.20
2¼" x 2" x 5/16" 2.050 47.00
2¼" x 2" x ¼" 1.650 33.00
2¼" x 2" x 3/16" 1.250 23.00
3" x 2½" x ½" 3.860 77.20
3" x 2½" x 7/16" 3.850 69.00
3" x 2½" x 3/8" 3.000 60.00
3" x 2½" x 5/16" 2.550 51.00
3" x 2½" x ¼" 2.050 41.00
3½" x 2½" x ½" 4.270 85.40
3½" x 2½" x 7/16" 3.770 75.40
3½" x 2½" x 3/8" 3.220 65.40
3½" x 2½" x 5/16" 2.770 55.40
3½" x 2½" x ¼" 2.227 44.54
3" x 2" x 1/20" 3.500 70.00
3" x 2" x 7/16" 3.100 62.00
3" x 2" x 3/8" 2.680 53.60
3" x 2" x 5/16" 2.270 45.40
3" x 2" x ¼" 1.860 37.20
44 of 47
ESTIMATE MANUAL
CARPENTRY WORKS
Type of work Material Coverage
Columns form lumber 33 bd.ft /.sq.m.
Batterboard form lumber 6.50 bd.ft. / sq.m.
Pedestal form lumber 9.0 bd.ft. / sq.m.
Beam form lumber 34.0 bd.ft. / sq.m.
Concrete wall form lumber 19.0 bd.ft. / sq.m.
Slab form lumber 25.0 bd.ft. / sq.m.
Scaffolding form lumber 8.50 bd.ft. / sq.m.
Curb & gutter form lumber 36.0 bd.ft. / sq.m.
Coneslab form lumber 18.0 bd.ft. / sq.m.
Sill & lintel good lumber 1.0 bd.ft. / sq.m.
Baseboard good lumber 1.25 bd.ft. / sq.m.
Flooring 1" x 3" T&G 16.66 pcs. / l.m.
1" x 4" T&G 11.77 pcs. / l.m.
1" x 6" T&G 7.87 pcs. / l.m.
1" x 8" T&G 5.34 pcs. / l.m.
Sidings 1" x 3" S - cut 20.00 pcs. / l.m.
1" x 4" S - cut 13.16 pcs. / l.m.
1" x 6" S - cut 7.87 pcs. / l.m.
1" x 8" S - cut 5.95 pcs. / l.m.
45 of 47
ESTIMATE MANUAL
46 of 47
ESTIMATE MANUAL
2. DRAINAGE DITCHES
Equipment Unit Condition
Ditching machine - wheel type 1.50 cu.yd. sandy soil
1.25 cu.yd. common earth
75.0 cu.yd. hard / frozen earth
Ditching machine - ladder type 50 cu.yd. sandy soil
45 cu.yd. common earth
Shoe dragline 34 cu.yd. 45 cu.yd. hard digging
75 cu.yd. basing digging
Motorized grader 450 cu.yd. "V" ditches
sandy soil
300 cu.yd. "V" ditches
common earth
Grader towed type 300 cu.yd. common earth
Shovel at dragline 2 - cu.yd. 125 cu.yd. hard digging
200 cu.yd. easy digging
47 of 47
ESTIMATE MANUAL
3. EXCAVATION
Equipment Unit Condition
Tractor 70 to 90 dbhp with single dozer 130.0 cu.yd. 50 ft. level haul, common
earth
80 cu.yd. 100 ft. level haul, common
earth
50 cu.yd. 200 ft. level haul, common
earth
Scraper Towed 8 cu.yd. With single dozer 95.0 cu.yd. 500 ft. level haul, common
earth
80 cu.yd. 600 ft. level haul, common
earth
60 cu.yd. 800 ft. level haul, common
earth
Motorized scraper 12 cu.yd. With tractor 87.93 cu.m.
70 to 90 dbhp 115 cu.yd. 80 ft. level haul, common
earth
Pusher 68.81 cu.m. 90 cu.yd. 1000 ft. level haul, common
earth
57.30 cu.m. 75 cu.yd. 2000 ft. level haul, common
34.41 cu.m. earth
Shovel or dragline ¾ cu.m. 45 cu.yd. hard digging
57.35 cu.m. 75 cu.yd. easy digging
Shovel or dragline 2 cu.yd. 125 cu.yd. hard digging 95.58 cu.m.
152.92 cu.m. 200 cu.yd. easy digging
4. EMBANKMENT
Equipment Unit Condition
Tractor 70 to 90 dghp with single dozer 300 cu.yd. spreading material
229.38 cu.m.
Rolller, sheepsfoot 2 drum 250 cu.yd. 9" loose layers
191.15 cu.m. 8 passes
In - line, towed by tractor 200 cu.yd. 9" loose layers
152.92 cu.m. 10 passes
70 to 90 dbhp 150 cu.yd. 9" loose layers
114.69 cu.m. 12 passes
Pump, troiler, med., water distributor 350cpm moisture varies with
materials
Towed type grader 400 sq.yd. scarify & shape
Motorized grader 400 sq.yd. scarify & shape
Roller, sheepsfoot 2 drum in-line towed 650 sq.yd. 60" layer, 8 passes
by tractor
70 to 90 dbhp 540 sq.yd. 60" layer, 10 passes
450 sq.yd. 60" layer, 12 passes
Roller, road, tandem 5 to 8 tons 1,000 sq.yd. 3 mph, 5 passes
Rubberized roller with tractor 30 dbhp 3,000 sq.yd. 3 mph, 5 passes
Rotary tiller, tractor 30 dbhp 1,750 sq.yd. 6" depth, 3 mph,
6 passes
Pump trailer, mounted water distributor 350 gpm moisture varies with
48 of 47
ESTIMATE MANUAL
materials
49 of 47
ESTIMATE MANUAL
6. SURFACE TREATMENT
Equipment Unit Condition
Tractor sweeper 30 dbhp 2,500 sq. yd. sweeping, compact base
2,500 sq. yd. 0.10gal / sq.yd. 24 ft.
spray
Trailer mounted distributor 1,250 sq.yd. 0.10 gal / sq.yd. 24 ft.
spray
Concrete spreader 20 to 25 ft. 200 l.ft. capacity depnds on payer
Aggregate spreader, traction powered 5,000 sq.yd. spreading coned aggregates
Roller, road tnadem 5 to 8 tons 3,000 sq.yd. rolling aggregate 3 mph
3 passes
Rubber-tired tractor roller 30dbhp 3,000 sq.yd. rolling aggregate 5 mph
5 passes
Trailer mounted distributor 1,250 sq.yd. 0.20 gal / sq.yd. 24 ft.
spray
Motorized grader 150 sq.yd. mixed in place, 2 in
bituminous materials
Rotary tiller tractor 30dbhp 100 cu.yd. mixing bituminous mat'l
Travel -plant asphalt mixer 120 tons mixed in place by travel
plant
Roller, road tandem 6 to 8 tons 1,500 sq.yd. rolling pavement, 3 mph
6 passes
Rubber-tired tractor roller 3,000 sq.yd. rolling pavement, 5 mph
5 passes
Concrete mixer 14 cu.ft. 20 cu.yd 1 batch every 3 minutes
10 cu.yd 1 batch every 3 minutes
34 cu.ft. 40 cu.yd 1 batch every 1.75 min
Asphalt finisher 12 ft. 100 ton ft. finishing plant mix mat'l
Concrete finisher 20 to 25 ft. 200 l.ft. capacity depends on payer
50 of 47
ESTIMATE MANUAL
7. AGGREGATE PRODUCTION
Equipment Rate & unit/hour Unit Condition
Crusher 2 units 25 tons / hr 15 tons 1" screened aggregate
20 tons 1½" screened aggregate
30 tons 1½" screened aggregate
crusher 9 units 150 tons / hr 60 tons 1" aggregate screened
mashed
100 tons 1½" aggregate screened
mashed
240 tons 3" aggregate screened
mashed
Compressor 105 cfm 105 cfm at sea level
90 cfm 5,000 ft. above sea level
Drill, rock 350 lbs. class 20 l.ft. 1¾" hole mix 16 ft. deep
requires 40 to 60 cfm of
air
45 lbs. class 30 l.ft. 1¾" hole mix 16 ft. deep
requires 70 to 90 cfm of
air
Bucket type leader type 150 cu.yd. from stock pile
8. SUBGRADE PREPARATION
Equipment Rate & unit/hour Unit Condition
Grader - scarify & shape 334.40 sq.m. / hr 2.60 days 7.0 surface / k.m.
3.20 days 9.0 surface / k.m.
Road roller 5 - 8 tons 83.16 sq.m. / hr 100 sq.yd. 7-9 surface / k.m, 3 mph
1.10 days 6 passes
51 of 47
ESTIMATE MANUAL
52 of 47
ESTIMATE MANUAL
53 of 47