M. Schedule PLTM Lambur 2x4 MW Mechanical & Electrical - Fix
M. Schedule PLTM Lambur 2x4 MW Mechanical & Electrical - Fix
ID Task Name Duration Start Finish Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 MECHANICAL & ELECTRICAL PLTM LAMBUR 2x4 MW 224 days Fri 19/02/21 Thu 30/09/21 0%
2 Mechanical Electrical 224 days Fri 19/02/21 Thu 30/09/21 0%
3 Spare Part Fabrication 179 days Fri 19/02/21 Mon 16/08/21 0%
4 Desain Confirmation & Purchasing Order 7 days Fri 19/02/21 Thu 25/02/21 0%
5 Payment After Purchasing Order 0 days Thu 25/02/21 Thu 25/02/21 25/02
6 Payment If Spare Part Ready to Shipping 0 days Sun 23/05/21 Sun 23/05/21 23/05
7 Final Check HPU 7 days Mon 17/05/21 Sun 23/05/21 0%
8 Final Check 7 days Mon 17/05/21 Sun 23/05/21 0%
9 Shipping 85 days Mon 24/05/21 Mon 16/08/21 0%
10 Shipping by Plane 14 days Mon 24/05/21 Sun 06/06/21 0%
11 Shipping by Ship 71 days Mon 24/05/21 Mon 02/08/21 0%
12 Local transport & handling 14 days Tue 03/08/21 Mon 16/08/21 0%
13 Procurement/Fabrication Spare Part 84 days Fri 26/02/21 Thu 20/05/21 0%
14 Jumo PT100 typ:902050 49 days Fri 26/02/21 Thu 15/04/21 0%
15 Position sensor MTS-EL 35 days Fri 26/02/21 Thu 01/04/21 0%
16 Presure tanduser-Jumo Midas 35 days Fri 26/02/21 Thu 01/04/21 0%
17 Stasto E-Motor VB350 - (24 VDC) 35 days Fri 26/02/21 Thu 01/04/21 0%
18 Turbine Sealing 49 days Fri 26/02/21 Thu 15/04/21 0%
19 Hydraulic fitting/pipes/tubes 49 days Fri 26/02/21 Thu 15/04/21 0%
20 Hydraulic & Generator Oil 49 days Fri 26/02/21 Thu 15/04/21 0%
21 Piping 6_08_01/02 49 days Fri 26/02/21 Thu 15/04/21 0%
22 Hydraulic cylinder turbine 80 days Fri 26/02/21 Sun 16/05/21 0%
23 Spare Guide Vane Bearing Bushes 49 days Fri 26/02/21 Thu 15/04/21 0%
24 Water Level Measurement 56 days Fri 26/02/21 Thu 22/04/21 0%
25 Spare kit cooling system for LUB-Unit 56 days Fri 26/02/21 Thu 22/04/21 0%
26 Repait kit for One butterfly valve 35 days Fri 26/02/21 Thu 01/04/21 0%
27 Hydraulic Power Unit 84 days Fri 26/02/21 Thu 20/05/21 0%
28 Rubber Compenstor DN50/DN80 49 days Fri 26/02/21 Thu 15/04/21 0%
29 Preparation Electrical Mechanical 116 days Tue 01/06/21 Fri 24/09/21 0%
30 Erection Mechanical Unit 1 42 days Tue 01/06/21 Mon 12/07/21
31 Setting coordinate 1 day Tue 01/06/21 Tue 01/06/21 0%
32 Setting Spiral Case 6 days Wed 02/06/21 Mon 07/06/21 0%
33 Expantion Join Installation 6 days Wed 02/06/21 Mon 07/06/21 0%
34 Main inlet valve installation (MIV) 1 day Tue 08/06/21 Tue 08/06/21 0%
35 Base frame installation 5 days Wed 09/06/21 Sun 13/06/21 0%
36 Mounting by Pass 3 days Mon 14/06/21 Wed 16/06/21 0%
37 Prepare for Secondary Concrete Works Drafttube 1 day Thu 17/06/21 Thu 17/06/21 0%
Critical Split Task Progress Duration-only Baseline Split Manual Summary Inactive Task Critical
Critical Progress Manual Task Path Predecessor Milestone Task Milestone Project Summary Inactive Milestone
Task Start-only Path Predecessor Summary Task Summary Progress External Tasks Inactive Summary
Split Finish-only Path Predecessor Normal Task Summary External Milestone Deadline
Page 1
Schedule Mechanical & Electrical Lambur 2x4 MW for EOT 06
ID Task Name Duration Start Finish Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
69 Erection Kabel Tray 5 days Tue 01/06/21 Sat 05/06/21 0%
70 Pooling Cable 5 days Tue 01/06/21 Sat 05/06/21 0%
71 Panel - Panel installation 12 days Tue 01/06/21 Sat 12/06/21 0%
72 Batterai installation 2 days Tue 01/06/21 Wed 02/06/21 0%
73 Transformer installation 3 days Sun 06/06/21 Tue 08/06/21 0%
74 NGR dan NGT installation 3 days Wed 09/06/21 Fri 11/06/21 0%
75 EDG installation 2 days Sat 12/06/21 Sun 13/06/21 0%
76 Power cable installation 7 days Mon 14/06/21 Sun 20/06/21 0%
77 Control cable installation 7 days Mon 21/06/21 Sun 27/06/21 0%
78 Termination/Connection 7 days Mon 28/06/21 Sun 04/07/21 0%
79 Setting dan Commissioning 24 days Wed 01/09/21 Fri 24/09/21 0%
80 Pekerjaan Setting & Programing (Lokal) 7 days Wed 01/09/21 Tue 07/09/21 0%
81 Pekerjaan Setting & Programing (Asing) 20 days Wed 01/09/21 Mon 20/09/21 0%
82 Unit 1 10 days Wed 01/09/21 Fri 10/09/21 0%
83 Dry Test 2 days Wed 01/09/21 Thu 02/09/21 0%
84 Wet Test ( No Load ) 4 days Fri 03/09/21 Mon 06/09/21 0%
85 Load Test 4 days Tue 07/09/21 Fri 10/09/21 0%
86 Unit 2 10 days Sat 11/09/21 Mon 20/09/21 0%
87 Dry Test 2 days Sat 11/09/21 Sun 12/09/21 0%
88 Wet Test ( No Load ) 4 days Mon 13/09/21 Thu 16/09/21 0%
89 Load Test 4 days Fri 17/09/21 Mon 20/09/21 0%
90 Both Unit Together 4 days Tue 21/09/21 Fri 24/09/21 0%
91 Load Test 4 days Tue 21/09/21 Fri 24/09/21 0%
92 Sertifikat Laik Operasi 95 days Mon 28/06/21 Thu 30/09/21 0%
93 Pekerjaan SLO Mechanical Electrical 95 days Mon 28/06/21 Thu 30/09/21 0%
94 Pemeriksaan dokumen 3 days Mon 28/06/21 Wed 30/06/21 0%
95 Pemeriksaan desain 3 days Mon 28/06/21 Wed 30/06/21 0%
96 Pemeriksaan visual 2 days Mon 28/06/21 Tue 29/06/21 0%
97 Pengujian Sistem 15 days Wed 01/09/21 Wed 15/09/21 0%
98 Evaluasi hasil uji komissioning 6 days Sat 25/09/21 Thu 30/09/21 0%
99 Pemeriksaan Dampak Lingkungan 3 days Mon 28/06/21 Wed 30/06/21 0%
100 Pemeriksaan Proteksi Katodik 7 days Mon 28/06/21 Sun 04/07/21 0%
101 Pekerjaan SLO Jaringan Tegangan Menengah 16 days Mon 05/07/21 Tue 20/07/21 0%
102 Pemeriksaan dokumen 3 days Mon 05/07/21 Wed 07/07/21 0%
103 Pemeriksaan desain 3 days Mon 05/07/21 Wed 07/07/21 0%
104 Pemeriksaan visual 2 days Mon 05/07/21 Tue 06/07/21 0%
105 Pengujian Sistem 7 days Wed 07/07/21 Tue 13/07/21 0%
106 Evaluasi hasil uji komissioning 7 days Wed 14/07/21 Tue 20/07/21 0%
107 Pemeriksaan Dampak Lingkungan 3 days Mon 05/07/21 Wed 07/07/21 0%
108 Pemeriksaan Proteksi Katodik 7 days Mon 05/07/21 Sun 11/07/21 0%
Critical Split Task Progress Duration-only Baseline Split Manual Summary Inactive Task Critical
Critical Progress Manual Task Path Predecessor Milestone Task Milestone Project Summary Inactive Milestone
Task Start-only Path Predecessor Summary Task Summary Progress External Tasks Inactive Summary
Split Finish-only Path Predecessor Normal Task Summary External Milestone Deadline
Page 2